CHICAGO DEPARTMENT OF AVIATION PROCUREMENT OPPORTUNITIES GUIDE - 3Q 2021 - 4Q 2023

Page created by Herbert Brewer
 
CONTINUE READING
CHICAGO DEPARTMENT OF AVIATION PROCUREMENT OPPORTUNITIES GUIDE - 3Q 2021 - 4Q 2023
OPPORTUNITIES TO WORK AND PARTNER WITH THE
     CHICAGO DEPARTMENT OF AVIATION

               PROCUREMENT OPPORTUNITIES
                        GUIDE

                                3Q 2021 – 4Q 2023

Version 10 Effective 08/05/21
CHICAGO DEPARTMENT OF AVIATION PROCUREMENT OPPORTUNITIES GUIDE - 3Q 2021 - 4Q 2023
CHICAGO DEPARTMENT OF AVIATION PROCUREMENT OPPORTUNITIES GUIDE - 3Q 2021 - 4Q 2023
Commissioner’s Statement
On behalf of Mayor Lori E. Lightfoot and the Chicago Department of Aviation (CDA), I want to thank you
for your continued partnership as we embark on one of the biggest and most exciting projects in our City’s
history: O’Hare 21.

The CDA is focused not only on what we are building but who will be doing the building. No one knows
and appreciates the power of procurement to drive meaningful change, transform communities and provide
opportunities better than Mayor Lori Lightfoot, and her vision of a City that is more equitable and inclusive
are the principles that guide the work we do here at the airport.

By working together to deliver O’Hare 21, the CDA and its contract partners can continue to offer economic
opportunities for our communities while furthering the momentum behind Chicago as a global leader in
air travel. The $8.5 billion program is critical to O’Hare International Airport’s long-term viability, not to
mention Chicago’s standing as a destination and hub for commerce and tourism. This program represents
an unprecedented opportunity for local participation, including contracting opportunities at all levels and
tens of thousands of jobs.

The CDA is leveraging the scale and scope of this historic project so that businesses throughout Chicago and
the Chicagoland area have the opportunity to participate in and benefit from O’Hare 21 and Midway’s ongoing
capital improvements. This emphasis on inclusion and empowering communities will foster economic
growth in the region for years to come.

As I look back at the growth and resilience our airport community has displayed over recent months, I cannot
overstate how proud I am of what we have all accomplished together. O’Hare and Midway are catalysts for
growth and opportunity for Chicago’s 77 communities and the entire Chicagoland area. I am hopeful that our
partnerships will only continue to grow as we reconnect the world to Chicago and Chicago to the world, and
I am confident that we will continue to work in the same spirit throughout the rest of 2021 and beyond.

Sincerely,

Jamie L. Rhee

Commissioner

Chicago Department of Aviation
CHICAGO DEPARTMENT OF AVIATION PROCUREMENT OPPORTUNITIES GUIDE - 3Q 2021 - 4Q 2023
DEFINITIONS
(DPS)		            Department of Procurement Services
(SBA)		            Small Business Administration
(SBI)		            Small Business Initiative
(SBI-I)            Small Business Initiative for projects estimated between $2M and $3M
(SBI-II)		         Small Business Initiative for projects estimated below $2M
(MBI)		            Mid-Size Business Initiative
(MBI-1)		          Mid-Size Business Initiative for projects estimated between $10M and $20M
(MBI-2)		          Mid-Size Business Initiative for projects estimated between $3M and $10M

Small Business Initiative (SBI)
•       Exclusive to small businesses and limited to construction projects that are under $3 million in total cost.
•       Divided into two tiers:
        SBI-I –	projects that are between $2 million and $3 million in total cost. In order to be eligible to bid on an SBI I
                  project, firms must be:
        (1)       no larger than the SBA size standards per NAICS code, and
        (2)	at least 51% owned by one or more individuals whose personal net worth does not the limits set forth in
                  Section 2-92-670 of the Municipal Code of Chicago (MCC).
        SBI-II – 	projects that are less than $2 million in total cost. In order to be eligible to bid on an SBI II project, firms
                  must be:
        (1)       no larger than ½ the SBA size standards per NAICS code, and
        (2)	at least 51% owned by one or more individuals whose personal net worth is not more than 1/2 the limits
                  set forth in Section 2-92-670 of the MCC.

Mid-Size Business Initiative (MBI)
•	Exclusive to small and mid-sized local (six counties) businesses and limited to construction projects that are
        between $3-20 million.
•       Divided into two tiers:
        MBI-1 – 	projects between $10-20 million in total cost. In order to be eligible to bid on an MBI-1 project, firms
                 must be:
        (1)      no larger than two times the SBA size standards per NAICS code, and
        (2)	at least 51% owned by one or more individuals whose personal net worth is not more than two times
                 the limits set forth in Section 2-92-670 of the MCC.
        MBI-2 – 	projects between $3-10 million in total cost. In order to in total cost. In order to be eligible to bid on an
                 MBI-1 project, firms must be:
        (1)      no larger than 1½ times the SBA size standards per NAICS code, and
        (2)	at least 51% owned by one or more individuals whose personal net worth is not more than 1½ times the
                 limits set forth in Section 2-92-670 of the MCC.

Target Market Program
•	Target Market was created to offer exclusive opportunities for MBE/WBEs on non-construction contracts,
        including contracts for professional services, such as Architecture, Engineers, or IT, work services, such as
        janitorial services and landscaping services, and commodities.
•        Allows prime level opportunities for MBE and WBEs.
Table of Contents

Summary of Construction Opportunities ............................................................. 1
Summary of Professional Services Opportunities ............................................... 3
Summary of Work Services and Commodities Opportunities .............................. 5
Detail of Construction Opportunities ................................................................... 7
Detail of Professional Services Opportunities ................................................... 13
Detail of Work Services and Commodities Opportunities .................................. 17
Construction Opportunities Offered by Construction Managers at Risk ............. 23

                    All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                            visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                    and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
SUMMARY OF CONSTRUCTION
    OPPORTUNITIES
ESTIMATED             SBI/MBI
                                                                                                                                                         ANTICIPATED
PAGE #                     PROJECT NAME                                     CONTRACT TYPE                      ESTIMATED VALUE                    TERM               TARGET
                                                                                                                                                           AD DATE
                                                                                                                                                (MONTHS)             MARKET

         Chicago Department of Aviation JOC Rehabilitation
  7                                                                                  JOC                             $10M - $20M                     36      3Q 2021
         of Airport Facilities

         O'Hare Residential Sound Insulation Program
  7                                                                             Construction                         $5M - $10M                      24      3Q 2021
         Phase 18B (175 Homes)

         O'Hare Residential Sound Insulation Program
  7                                                                             Construction                         $5M - $10M                      24      4Q 2021
         Phase 19A (250 Homes)

         O'Hare Residential Sound Insulation Program
  7                                                                             Construction                         $5M - $10M                      24      4Q 2021
         Phase 19B (250 Homes)

  8      Terminal Building ADA                                                  Construction                          $2M - $3M                      12      1Q 2022    SBI-I / JOC

  8      T5 Building ADA Improvements                                           Construction                         $500K - $1M                      6      1Q 2022        SBI-II

  8      Combined Heat Exchanger Projects                                       Construction                         $5M - $10M                      12      2Q 2022        MBI-2

         Restroom Modernization Program - International -
  8                                                                             Construction                          $3M - $5M                       6      1Q 2022        MBI-2
         Phase I

  9      90" JAWA Relocation                                                    Construction                          Over $20M                      12      3Q 2022

  9      Perimeter Fence Replacement in Southeast Airfield                      Construction                          $3M - $5M                       6      3Q 2022

  9      Ring Tunnel Exhaust System                                             Construction                         $10M - $20M                     24      3Q 2022        MBI-1

  9      Ring Tunnel Electrical and Lighting Infrastructure                     Construction                         $5M - $10M                      18      4Q 2022

  10     Taxiway LL Phase II Extension                                          Construction                          Over $20M                      18      4Q 2022

  10     Spine Road Airside Relocation                                          Construction                         $5M - $10M                      12      4Q 2022        MBI-2

  10     Airport Maintenance Center Building Renovations                        Construction                         $10M - $20M                     18      3Q 2023        MBI-1

  10     Fire Hydrant & Backflow Prevention Improvements                        Construction                          $2M - $3M                       6      4Q 2023        SBI-I

  11     Water Main Automatic Meter Readers                                     Construction                          $2M - $3M                       6      4Q 2023        SBI-I

  11     Terminal 5 Apron Level Exterior Repairs                                Construction                          $1M - $2M                       6      4Q 2023        SBI-II

         Terminal 1 B and C Terminal Apron Level Exterior
  11                                                                            Construction                          $1M - $2M                       6      4Q 2024        SBI-II
         Repairs

         Terminal Apron Level Overhead Roll-Up Door
  11                                                                            Construction                          $1M - $2M                       6      4Q 2024        SBI-II
         Replacement Terminal 1 B and C

         Terminal Core Upper Level Expansion Joints
  12                                                                            Construction                         $5M - $10M                      18      1Q 2025
         and Sidewalks

  12     Runway 10L-28R Rehabilitation                                          Construction                          Over $20M                      24      1Q 2026

                                                                                                                                                                       Updated July 2021
                                                                                            1
                                 All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                         visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                                 and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
2
All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
        visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
SUMMARY OF PROFESSIONAL
 SERVICES OPPORTUNITIES
ESTIMATED             SBI/MBI
                                                                                                                                                         ANTICIPATED
PAGE #                     PROJECT NAME                                     CONTRACT TYPE                      ESTIMATED VALUE                    TERM               TARGET
                                                                                                                                                           AD DATE
                                                                                                                                                (MONTHS)             MARKET

         Designated Aviation Channeling (DAC) Services at
  13                                                                       Professional Services                      $3M - $5M                      60      3Q 2021
         O'Hare and Midway International Airports

         Management of Public Parking Facilities and Ground
  13                                                                       Professional Services                     $10M - $20M                     60      3Q 2021
         Transportation at Chicago Midway International Airport

  13     On-Call Noise Management Consulting Services                      Professional Services                     $10M - $20M                     60      3Q 2021

         On-Call Sustainability and Energy Management
  13                                                                       Professional Services                     $5M - $10M                      60      3Q 2021
         Consulting Services

         Program Management/Construction Management
  14                                                                       Professional Services                      Over $20M                      60      3Q 2021
         Services for the Residential Sound Insulation Program

         Emergency Mass Notification/Alert System for
  14     O'Hare and Midway International Airports and                      Professional Services                     250K - 500K                     60      3Q 2021
         Department of Streets and Sanitation

         Property Management Services for                                                                                                                                 TARGET
  14                                                                       Professional Services                      Over $20M                      60      3Q 2021
         Midway International Airport (Target Market)                                                                                                                     MARKET

         Target Market Architecture and Engineering
                                                                                                                                                                          TARGET
  14     Services for Terminal 5 Landside Improvements and                 Professional Services                     $10M - $20M                     60      3Q 2021
                                                                                                                                                                          MARKET
         Repurposing Project at O’Hare International Airport

         On-Call Environmental Compliance and Industrial
  15                                                                       Professional Services                     $5M - $10M                      60      4Q 2021
         Hygiene Consulting Services

  15     Developer Services Permit Review                                  Professional Services                     $5M - $10M                      60      4Q 2021

  15     Hilton O'Hare Hotel Renovation and Design Services                Professional Services                     $5M - $10M                      12      4Q 2021

         O'Hare International Airport Terminal 5 Property                                                                                                                 TARGET
  15                                                                       Professional Services                      Over $20M                      60      1Q 2022
         Management (Target Market)                                                                                                                                       MARKET

                                                                                                                                                                       Updated July 2021
                                                                                            3
                                 All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                         visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                                 and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
4
All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
        visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
SUMMARY OF WORK
SERVICES AND COMMODITIES
      OPPORTUNITIES
ESTIMATED             SBI/MBI
                                                                                                                                                          ANTICIPATED
PAGE #                      PROJECT NAME                                     CONTRACT TYPE                      ESTIMATED VALUE                    TERM               TARGET
                                                                                                                                                            AD DATE
                                                                                                                                                 (MONTHS)             MARKET

         Inspection, Preventative Maintenance, Repair,
  17     Replacement and New Installation of Variable                           Work Services                          $1M - $2M                      60      3Q 2021
         Frequency Pumps and Fans

         Installation, Repair and Replacement of Various
         Electrical, Lighting, Traffic Control, Security, Audio-
  17                                                                            Work Services                          Over $20M                      60      3Q 2021
         Video and Public Address Systems Infrastructure at
         Chicago O'Hare and Midway International Airports

         Maintenance, Repair, Installation and Data Services
  17     for Runway/Roadway Weather Information Systems                         Work Services                          $3M - $5M                      60      3Q 2021
         (RWIS)

         On-Call Warranty Services for the Airport Residential
  17                                                                            Work Services                         $5M - $10M                      36      3Q 2021
         Sound Insulation Program

  18     Shuttle Bus Services for Midway International Airport                  Work Services                         $5M - $10M                      60      3Q 2021

         Structural Bridge Repair at
  18     O'Hare and Midway International Airports                               Work Services                          Over $20M                      60      3Q 2021
         (Landside and Airside)
         Purchase of Industrial Equipment, Tools, Attachments,
  18     Various Fasteners, Supplies and Accessories                             Commodities                          $5M - $10M                      36      3Q 2021
         (Groups - A, O, S, and CC)
         Installation, Maintenance, Repair, Replacement
  18     and New Installation of Various HVAC Systems                           Work Services                         $5M - $10M                      60      4Q 2021
         and Equipment

         Purchase, Calibration, Maintenance, Repair, Parts and
  19                                                                            Work Services                        $250K - $500K                    60      4Q 2021
         Training for Runway Friction Testing Equipment

         Purchase of Water Treatment Chemicals for
  19                                                                             Commodities                           $3M - $5M                      60      4Q 2021
         HVAC Systems

         Repair, Replacement and Fabrication of Signage
  19                                                                            Work Services                         $5M - $10M                      60      1Q 2022
         Systems for O'Hare and Midway International Airports

         Waste Disposal, Recycling Services and Rental of
  19                                                                            Work Services                         $5M - $10M                      60      1Q 2022
         Related Equipment

         Maintenance and Repair of Diesel
  20     Electric Generators and Fire Pumps at                                  Work Services                          $1M - $2M                      60      2Q 2022
         O'Hare and Midway International Airports
         Pick-Up, Launder and Deliver Blankets, Mop Heads
  20                                                                            Work Services                        $50K - $100K                     60      2Q 2022
         and Bonnets to O'Hare International Airport
         Servicing and Supplying of Activated
  20     Charcoal Filter Cells for Air Handling Units for                       Work Services                          $3M - $5M                      60      2Q 2022
         Chicago O'Hare International Airport

         Reflective Sheeting for
  20                                                                             Commodities                           $500 - $1M                     60      2Q 2022
         O'Hare and Midway International Airports

         Decorating Services for Seasonal Display and
  21                                                                            Work Services                          $2M - $3M                      60      3Q 2022
         Special Events

         Inspection, Cleaning, Maintenance and Repair of
  21     Interior and Exterior Horizontal and Vertical Metal                    Work Services                         $10M - $20M                     60      3Q 2022
         Expansion Joints

         Maintenance, Repair and Installation of Various
  21                                                                            Work Services                         $10M - $20M                     60      3Q 2022
         Fencing, Guardrail and Related Equipment

         Roofing Inspection, Maintenance, Repair and
  21     Replacement for O'Hare and Midway International                        Work Services                         $5M - $10M                      60      4Q 2022
         Airports and Various City Locations (Roofing Services)

         Snow Removal Services (Landside) at Chicago
  22                                                                            Work Services                          $3M - $5M                      60      4Q 2022
         O'Hare International Airport

  22     Maintenance, Repair and Installation of Terrazzo                       Work Services                         $10M - $20M                     60      3Q 2023

                                                                                                                                                                        Updated July 2021
                                                                                             5
                                  All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                          visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                                  and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
6
All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
        visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
DETAIL OF CONSTRUCTION
    OPPORTUNITIES
Chicago Department of Aviation JOC Rehabilitation of Airport Facilities
Contract Type: JOC                                                                                                                       Delivery Method: Request for Proposal

                                  Management, work, materials, supplies, parts (to include system components), transportation,
                                  plant, supervision, labor and equipment, except when specified as City of Chicago furnished,
                                  needed to perform the necessary work. This contract may be used to perform any work on
                                  facilities under the jurisdiction of the Chicago Department of Aviation. The work of this contract
                                  will be set forth in the Detailed Scopes of Work referenced in the individual Job Orders. Upon
                                  receipt of a Blanket Release, the Vendor is required to complete each Detailed Scope of Work
                                  for the Job Order Price within the Job Order completion time.

                      2021                                                             2022                                                           2023
                                                                                                                               Estimated Contract Amount: $10M - $20M

O’Hare Residential Sound Insulation Program Phase 18B (175 Homes)
Contract Type: Construction                                                                                                                    Delivery Method: Competitive Bid

                                  Alterations and modifications of approximately one hundred and seventy five (175) dwelling
                                  units in the area surrounding O’Hare (“Homes”). The majority of the Homes in this contract will
                                  be single-family and multi-family homes located in Chicago and Park Ridge. There may also
                                  be single-family and multi-family homes in other communities.

                      2021                                                             2022                                                           2023
                                                                                                                                 Estimated Contract Amount: $5M - $10M

O’Hare Residential Sound Insulation Program Phase 19A (250 Homes)
Contract Type: Construction                                                                                                                    Delivery Method: Competitive Bid

                                  Alterations and modifications of approximately two hundred and fifty (250) dwelling units in
                                  the area surrounding O’Hare (“Homes”). The majority of the homes in this contract will be
                                  single- family and multi-family homes located in Chicago and Park Ridge. There may also be
                                  single- family and multi-family homes in other communities.

                      2021                                                             2022                                                           2023
                                                                                                                                 Estimated Contract Amount: $5M - $10M

O’Hare Residential Sound Insulation Program Phase 19B (250 Homes)
Contract Type: Construction                                                                                                                    Delivery Method: Competitive Bid

                                  Alterations and modifications of approximately two hundred and fifty (250) dwelling units in
                                  the area surrounding O’Hare (“Homes”). The majority of the homes in this contract will be
                                  single- family and multi-family homes located in Chicago and Park Ridge. There may also be
                                  single- family and multi-family homes in other communities.

                      2021                                                             2022                                                           2023
                                                                                                                                 Estimated Contract Amount: $5M - $10M
                                                                                         7
                              All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                      visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                              and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
Terminal Building ADA
Contract Type: Construction                                                                                                            Delivery Method: Design-Bid-Build / JOC

                                  ADA improvements in and adjacent to the terminal buildings to incorporate current compliance
                                  measures as identified by FAA and the ADA standards for accessible design.

                      2021                                                             2022                                                           2023
                                                                                                                                   Estimated Contract Amount: $2M - $3M

T5 Building ADA Improvements
Contract Type: Construction                                                                                                                   Delivery Method: Design-Bid-Build

                                  ADA improvements in and adjacent to the terminal building to incorporate current compliance
                                  measures as identified by FAA and the ADA standards for accessible design.

                      2021                                                             2022                                                           2023
                                                                                                                                Estimated Contract Amount: $500K - $1M

Combined Heat Exchanger Projects
Contract Type: Construction                                                                                                                   Delivery Method: Design-Bid-Build

                                  The project consists of upgrading current heat exchangers in Terminals 2, 3, and the Rotunda.
                                  The designer will evaluate the existing conditions of Heat Exchangers to provide detailed
                                  design documents.

                      2021                                                             2022                                                           2023
                                                                                                                                 Estimated Contract Amount: $5M - $10M

Restroom Modernization Program - International - Phase I
Contract Type: Construction                                                                                                                   Delivery Method: Design-Bid-Build

                                  This project includes the modernization of four restrooms located in Terminal 5 at
                                  O’Hare International Airport (ORD). Two of the four restrooms will integrate a family restroom.
                                  The design shall incorporate the latest airport restroom standards while achieving compliance
                                  with Americans with Disabilities Act (ADA) requirements and all applicable codes and
                                  ordinances. Construction will be performed in two phases.

                      2021                                                             2022                                                           2023
                                                                                                                                   Estimated Contract Amount: $3M - $5M
                                                                                         8
                              All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                      visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                              and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
90” JAWA Relocation
Contract Type: Construction                                                                                                                   Delivery Method: Design-Bid-Build

                                  Installation of a by-pass 48-inch water main, new 48-inch Chicago Department of Water
                                  Management water main, new 90-inch Joint Action Water Agency (JAWA) water main, two
                                  90-inch hot taps, and other associated water main infrastructure along I-90.

                      2021                                                             2022                                                           2023
                                                                                                                                   Estimated Contract Amount: Over $20M

Perimeter Fence Replacement in Southeast Airfield
Contract Type: Construction                                                                                                                   Delivery Method: Design-Bid-Build

                                  Design and construction of 7,800 feet of AOA fence in the southeast airfield. The new fence is
                                  to include a wildlife deterrent barrier and 10’ vegetative free zone on either side of the newly
                                  aligned fence.

                      2021                                                             2022                                                           2023
                                                                                                                                   Estimated Contract Amount: $3M - $5M

Ring Tunnel Exhaust System
Contract Type: Construction                                                                                                                   Delivery Method: Design-Bid-Build

                                  Upgrades to the existing exhaust fan system in the ring utility tunnel.

                      2021                                                             2022                                                           2023
                                                                                                                               Estimated Contract Amount: $10M - $20M

Ring Tunnel Electrical and Lighting Infrastructure
Contract Type: Construction                                                                                                              Delivery Method: Request for Proposal

                                  The project work scope includes the replacement of approximately fifty (50) percent of the
                                  existing electrical and lighting infrastructure in the Ring Tunnel inclusive of cost saving LED
                                  lighting. The work will include the removal and replacement of conduit, wiring/cable, fixtures
                                  and Life Safety Improvements in approximately 196,000 SF of the entire 392,000 SF tunnel.

                      2021                                                             2022                                                           2023
                                                                                                                                 Estimated Contract Amount: $5M - $10M
                                                                                         9
                              All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                      visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                              and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
Taxiway LL Phase II Extension
Contract Type: Construction                                                                                                   Delivery Method: Construction Manager-at-Risk

                                  New pavement to extend Taxiway LL between Taxiway EE and Taxiway Y; demolition of
                                  existing Taxiway N pavement and its relocation to previously constructed pavement to the
                                  South; installation of new airfield lighting and markings; and construction of new shoulders
                                  where necessary.

                      2021                                                             2022                                                           2023
                                                                                                                                   Estimated Contract Amount: Over $20M

Spine Road Airside Relocation
Contract Type: Construction                                                                                                                   Delivery Method: Design-Bid-Build

                                  Upgrades and conversion of a section of Spine Road to an airside roadway, which will include
                                  improvement of the traffic patterns along the Eastern perimeter of the airfield, a widened travel
                                  way, and a larger area for snow removal equipment storage. Scope includes replacement
                                  of sections of deficient pavement and relocation a section of the existing AOA fence to an
                                  alignment East of Spine Road.

                      2021                                                             2022                                                           2023
                                                                                                                                 Estimated Contract Amount: $5M - $10M

Airport Maintenance Center Building Renovations
Contract Type: Construction                                                                                                                   Delivery Method: Design-Bid-Build

                                  Renovations to the existing Airport Maintenance Center building to ensure current code
                                  compliance. Items to be addressed include carbon monoxide sensors, exhaust fans and
                                  dampers, oil and hazmat storage upgrades, battery room upgrades, and other building code
                                  compliance throughout the facility.

                      2021                                                             2022                                                           2023
                                                                                                                               Estimated Contract Amount: $10M - $20M

Fire Hydrant & Backflow Prevention Improvements
Contract Type: Construction                                                                                                                   Delivery Method: Design-Bid-Build

                                  Reduction in the lengths of stagnant water lines leading to fire hydrants, both landside and
                                  airside, including removal, relocation of lopping back existing hydrants into the main. Work
                                  may include new fire main and backflow prevention.

                      2021                                                             2022                                                           2023
                                                                                                                                   Estimated Contract Amount: $2M - $3M
                                                                                         10
                              All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                      visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                              and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
Water Main Automatic Meter Readers
Contract Type: Construction                                                                                                                   Delivery Method: Design-Bid-Build

                                  Installation or replacement of automatic water main meter reader systems at all water main
                                  connections that serve O’Hare terminals and facilities. Updated meter reading systems will
                                  match demands with current water main infrastructure and provide a standard requirement for
                                  future upgrades.

                      2021                                                             2022                                                           2023
                                                                                                                                   Estimated Contract Amount: $2M - $3M

Terminal 5 Apron Level Exterior Repairs
Contract Type: Construction                                                                                                                   Delivery Method: Design-Bid-Build

                                  Masonry repairs including tuckpointing, partial and full brick repair/replacement along the
                                  exterior LL walls of Terminal 5 concourse M. The estimated cost is based on 4,320 LF of wall.

                      2021                                                             2022                                                           2023
                                                                                                                                   Estimated Contract Amount: $1M - $2M

Terminal 1 B and C Terminal Apron Level Exterior Repairs
Contract Type: Construction                                                                                                                   Delivery Method: Design-Bid-Build

                                  Masonry repairs including tuckpointing, partial and full brick repair/replacement along the
                                  exterior LL walls of Terminal 1 Concourses B and C.

         2021                          2022                            2023                            2024                           2025                       2026
                                                                                                                                   Estimated Contract Amount: $1M - $2M

Terminal Apron Level Overhead Roll-Up Door Replacement Terminal 1 B and C
Contract Type: Construction                                                                                                                   Delivery Method: Design-Bid-Build

                                  Removal of the existing Overhead Roll-Up Doors and the replacement with high-speed,
                                  insulated, high wind resistant, metal coiling doors inclusive of all electrical work and controls.

         2021                          2022                            2023                            2024                           2025                       2026
                                                                                                                                   Estimated Contract Amount: $1M - $2M
                                                                                         11
                              All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                      visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                              and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
Terminal Core Upper Level Expansion Joints and Sidewalks
Contract Type: Construction                                                                                                                   Delivery Method: Design-Bid-Build

                                  Replace the inner bridge expansion joints and sidewalks in the upper level roadway consisting
                                  of the inner roadway lanes and sidewalk in front of Terminals 1, 2, and 3.

         2021                          2022                            2023                            2024                           2025                       2026
                                                                                                                                 Estimated Contract Amount: $5M - $10M

Runway 10L-28R Rehabilitation
Contract Type: Construction                                                                                                                   Delivery Method: Design-Bid-Build

                                  Milling, asphalt overlay, pavement grooving, lighting adjustments, and markings of
                                  approximately 188,000 square yards of Runway 10L-28R and taxiways within the Runway
                                  Safety Area. Work will be restricted to bituminous asphalt pavements. Construction work will
                                  be scheduled to comply with airfield operational requirements.

         2021                          2022                            2023                            2024                           2025                       2026
                                                                                                                                   Estimated Contract Amount: Over $20M

                                                                                         12
                              All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                      visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                              and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
DETAIL OF PROFESSIONAL
SERVICES OPPORTUNITIES
Designated Aviation Channeling (DAC) Services at O’Hare and Midway International Airports
Contract Type: Professional Services                                                                                                   Delivery Method: Request for Proposal

Provide certified and accredited Designated Aviation Channeling (“DAC”) Services (“Services”) to Transportation
Security Administration (TSA). The selected Respondent (the “Contractor”) will process required background checks
including but not limited to fingerprint-based Criminal History Record Checks (CHRC) and Security Threat Assessments
(STA) at Chicago O’Hare (ORD) and Midway (MDW) International Airports (“Airports”).

                       2021                                                          2022                                                           2023
                                                                                                                                 Estimated Contract Amount: $3M - $5M

Management of Public Parking Facilities and Ground Transportation at Chicago Midway International Airport
Contract Type: Professional Services                                                                                                   Delivery Method: Request for Proposal

Manage and maintain the parking and ground transportation infrastructure, grow revenues and elevate the customer
experience. Work with the department’s new parking services including Premium Parking Services to use technology
to enhance customer experience and increase revenue.

                       2021                                                          2022                                                           2023
                                                                                                                             Estimated Contract Amount: $10M - $20M

On-Call Noise Management Consulting Services
Contract Type: Professional Services                                                                                                   Delivery Method: Request for Proposal

On-Call Noise Management Services, as specified.

                       2021                                                          2022                                                           2023
                                                                                                                             Estimated Contract Amount: $10M - $20M

On-Call Sustainability and Energy Management Consulting Services
Contract Type: Professional Services                                                                                                   Delivery Method: Request for Proposal

On-Call Sustainability and Energy Management Consulting Services to the Chicago Department of Aviation, as required.

                       2021                                                          2022                                                           2023
                                                                                                                               Estimated Contract Amount: $5M - $10M
                                                                                       13
                            All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                    visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                            and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
Program Management/Construction Management Services for the Residential Sound Insulation Program
Contract Type: Professional Services                                                                                                   Delivery Method: Request for Proposal

Program Management and Construction Management (PM/CM) Consulting Services for the Residential Sound
Insulation Program (RSIP), as specified.

                       2021                                                          2022                                                           2023
                                                                                                                                 Estimated Contract Amount: Over $20M

Emergency Mass Notification/Alert System for O’Hare and Midway International Airports and Department of Streets and Sanitation
Contract Type: Professional Services                                                                                                   Delivery Method: Request for Proposal

The City seeks a secure, robust, reliable and certified Department of Homeland Security (DHS) Level 3 (or higher)
Telecommunications Service Provider (TSP) Certification Airport Mass Notification and Emergency Response
Management System. This system shall be virtual, (i.e., web-based), hosted (off site) by the Vendor, and provided as
a bundle of services, provided by subscription, that are fully compatible with the systems, procedures, and protocols
at the Airports and Chicago Department of Streets and Sanitation facilities. The Vendor will perform the work tasks/
services assumed necessary for the proper implementation and maintenance of the mass notification system at the
Chicago Department of Aviation and the Chicago Department of Streets and Sanitation.

                       2021                                                          2022                                                           2023
                                                                                                                               Estimated Contract Amount: 250K - 500K

Property Management Services for Midway International Airport (Target Market)
Contract Type: Professional Services                                                                                                   Delivery Method: Request for Proposal

Facility maintenance and repair services and property management services for the following facilities at Midway International
Airport “Midway”: Terminal, H&R Plant, AMC, Airfield Lighting Building, Security /ID Badging Office, Butler Building, Sand & Salt
Building, Construction trailer, Guard Booths, Central Field Office Building, Airport Terminal Building Front Exterior Roadway Upper
and Lower Level sidewalks, Lower Level Terminal Building Rear Side, CTA Walkway and Airport City-controlled gates and Hold
Room spaces. The Property Manager will be required to provide the services described in this Scope of Services (the “Services”)
on a 24 hour, 365 day basis. Midway’s peak passenger volume occurs between the hours of 4:30 a.m. and 11:00 p.m. The Property
Manager will assume responsibility TARGET for performing and managing these Services under the supervision of the department.
                                                                                                                                                           TARGET
                                                                                                                                                           MARKET

                       2021                                                          2022                                                           2023
                                                                                                                                 Estimated Contract Amount: Over $20M

Target Market Architecture and Engineering Services for Terminal 5 Landside Improvements and Repurposing Project at O’Hare International Airport

Contract Type: Professional Services                                                                                             Delivery Method: Request for Qualifications

The Scope of Professional Services in this RFQ includes validation, final planning, programming, design, and construction phase
support services for landside upgrades to Terminal 5 (T5). The project includes upgrades to the terminal, roadway and site civil
improvements, and a pedestrian bridge. Terminal Improvements consist of landside vertical circulation infrastructure, building
extension between the current building facade and the curbside, and wayfinding to accommodate improvements. The roadway
and site civil improvements include widening and extension of exit roadways on a new alignment, modifications to the curbside and
associated roadway to accommodate terminal upgrades, required to connections to I-190, utilities, drainage, and ADA improvements.
The pedestrian bridge is a conditioned structure to connect the T5 Parking Garage to T5.
                                                                                                                                                           TARGET
                                                                                                                                                           MARKET

                       2021                                                          2022                                                           2023
                                                                                                                             Estimated Contract Amount: $10M - $20M
                                                                                       14
                            All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                    visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                            and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
On-Call Environmental Compliance and Industrial Hygiene Consulting Services
Contract Type: Professional Services                                                                                                   Delivery Method: Request for Proposal

Manage an Environmental Compliance Program to maintain full compliance with all environmental regulations and
laws including, but not limited to, Air Quality, Land and Waste Management, Water Quality, Storage Tanks and
Industrial Hygiene.

                       2021                                                          2022                                                           2023
                                                                                                                               Estimated Contract Amount: $5M - $10M

Developer Services Permit Review
Contract Type: Professional Services                                                                                             Delivery Method: Request for Qualifications

The City of Chicago, Department of Aviation and Department of Buildings (“City”) seeks Architectural and Engineering
firms to provide municipal code compliance review and associated project review services by examination of project
plans for various small to large/complex Chicago Department of Aviation (CDA) projects located throughout at O’Hare
& Midway Airport. The city is outsourcing the permit review services, in order to streamline the City’s permit approval
process and provide CDA and/or his/her design professional with a consistent and timely permit process.

                       2021                                                          2022                                                           2023
                                                                                                                               Estimated Contract Amount: $5M - $10M

Hilton O’Hare Hotel Renovation and Design Services
Contract Type: Professional Services                                                                                             Delivery Method: Request for Qualifications

The Hilton Chicago O’Hare Hotel is a unique on-airport hotel within the terminal core area at O’Hare International
Airport. Owned by the City of Chicago Department of Aviation and managed by Hilton Hotels LLC, this landside
hotel has 860 guest rooms, approximately 40,000 square feet of meeting space, 4 food and beverage outlets, and
key amenities including an indoor pool and fitness center. The Scope of Services for the Project includes planning,
programming, validation, design, and construction phase support services for the Hotel Renovation. All improvements
will be in accordance with Hilton Brand Standards and will provide contemporary finishes that define each space.

                       2021                                                          2022                                                           2023
                                                                                                                               Estimated Contract Amount: $5M - $10M

O’Hare International Airport Terminal 5 Property Management (Target Market)
Contract Type: Professional Services                                                                                                   Delivery Method: Request for Proposal

Facilities and Property Management for the International Passenger Terminal and immediate surrounding structures
(“Terminal 5”) at O’Hare (“Services”). The Vendor is also referred to herein as the Property Manager and will assume
responsibility for the Services under the supervision of the Chicago Department of Aviation (“CDA”). The Services
include, but are not limited to, preservation, maintenance, cleanliness, safe and efficient operation, physical upkeep,
and management of all assets and systems of Terminal 5 and associated structural/physical features including all
personnel and equipment necessary to perform these tasks and services.
                                                                                                                                                           TARGET
                                                                                                                                                           MARKET

                       2021                                                          2022                                                           2023
                                                                                                                                 Estimated Contract Amount: Over $20M
                                                                                       15
                            All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                    visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                            and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
DETAIL OF WORK SERVICES
   AND COMMODITIES
    OPPORTUNITIES
Inspection, Preventative Maintenance, Repair, Replacement and New Installation of Variable Frequency Pumps and Fans
Contract Type: Work Services                                                                                                               Delivery Method: Competitive Bid

 Furnishing of all labor, equipment, materials, tools, services and all necessary supervision required for the inspection,
 preventative maintenance, repair, replacement and new installation of Variable Frequency Drive (VFD) pumps and
 fans located at O’Hare International Airport, as specified.

                      2021                                                         2022                                                           2023
                                                                                                                               Estimated Contract Amount: $1M - $2M
Installation, Repair and Replacement of Various Electrical, Lighting, Traffic Control, Security, Audio-Video and Public Address Systems
Infrastructure at Chicago O’Hare and Midway International Airports
Contract Type: Work Services                                                                                                               Delivery Method: Competitive Bid

 Furnish and deliver Freight on Board, to the Chicago Department of Aviation and various using Departments
 Replacement Parts, Components, and Accessories for the Installation, Repair, and Replacement of Various Electrical,
 Lighting, Traffic Control Systems, Security Monitoring Systems, Audio and Video Systems, and Public Address Systems
 infrastructures located at various City of Chicago locations, as specified.

                      2021                                                         2022                                                           2023
                                                                                                                               Estimated Contract Amount: Over $20M

Maintenance, Repair, Installation and Data Services for Runway/Roadway Weather Information Systems (RWIS)
Contract Type: Work Services                                                                                                               Delivery Method: Competitive Bid

 The Contractor will provide year-round weather forecasting and Runway/Roadway Weather Information (RWIS)
 Maintenance and Data Hosting Services for the Department of Aviation and Department of Streets and Sanitation.
 When directed by the City, the Contractor will also add the service to additional RWIS sites as required by the City.
 The Contractor must be a Vaisala Service Certified Partner at time of bid submittal and provide written certification of
 same with their bid. After award, on an annual basis throughout the term of the contract and any extensions thereof,
 the Contractor must continue to provide written documentation from Vaisala of their current status as a Vaisala Service
 Certified Partner.

                      2021                                                         2022                                                           2023
                                                                                                                               Estimated Contract Amount: $3M - $5M

On-Call Warranty Services for the Airport Residential Sound Insulation Program
Contract Type: Work Services                                                                                                               Delivery Method: Competitive Bid

 Repair of windows and doors in homes surrounding Chicago O’Hare and Midway International Airports that were
 installed in prior years as part of the Residential Sound Insulation Program. Services will be required on an on-call
 basis in response to homeowner requests for warranty services.

                      2021                                                         2022                                                           2023
                                                                                                                             Estimated Contract Amount: $5M - $10M
                                                                                     17
                          All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                  visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                          and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
Shuttle Bus Services for Midway International Airport
Contract Type: Work Services                                                                                                               Delivery Method: Competitive Bid

 Furnish all trained labor, drivers, dispatchers, mechanics, administrators, etc., equipment, vehicles (buses), materials,
 tools, repair/maintenance facilities, operations and services (dispatching, inventory control, administration, maintenance,
 etc.) required to provide comprehensive passenger transport and related services at Midway International Airport
 between the terminals and parking lots, as specified.

                      2021                                                         2022                                                           2023
                                                                                                                             Estimated Contract Amount: $5M - $10M

Structural Bridge Repair at O’Hare and Midway International Airports (Landside and Airside)
Contract Type: Work Services                                                                                                               Delivery Method: Competitive Bid

 Furnish all labor, materials, equipment, tools and traffic protection required for structural, tunnel and bridge repairs both
 structural and non-structural where directed at O’Hare and Midway International Airports.

                      2021                                                         2022                                                           2023
                                                                                                                               Estimated Contract Amount: Over $20M

Purchase of Industrial Equipment, Tools, Attachments, Various Fasteners, Supplies and Accessories (Groups - A, O, S, and CC)
Contract Type: Commodities                                                                                                                 Delivery Method: Competitive Bid

 The Contractor must furnish and deliver F.O.B., to the Chicago Department of Aviation, and various Using
 Departments Industrial Equipment, Tools, Attachments, Various Fasteners, Supplies, and Accessories at various
 City of Chicago locations; all in accordance with the General Conditions, Special Conditions, and Detailed
 Specifications of this Contract.

                      2021                                                         2022                                                           2023
                                                                                                                             Estimated Contract Amount: $5M - $10M

Installation, Maintenance, Repair, Replacement and New Installation of Various HVAC Systems and Equipment
Contract Type: Work Services                                                                                                               Delivery Method: Competitive Bid

 Furnish all supervision, labor, equipment, parts, materials, tools, services, and transportation for inspection,
 maintenance, repair, replacement and new installation of various HVAC systems and equipment.

                      2021                                                         2022                                                           2023
                                                                                                                             Estimated Contract Amount: $5M - $10M
                                                                                     18
                          All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                  visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                          and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
Purchase, Calibration, Maintenance, Repair, Parts and Training for Runway Friction Testing Equipment
Contract Type: Work Services                                                                                                               Delivery Method: Competitive Bid

Inspection, calibration, repair and training on four existing City of Chicago-owned Dynatest 6875 Friction Tester units
to the Department of Aviation, Airport Maintenance Complex (AMC) Building, 10000 W. Montrose, Chicago, Illinois
60666 and at Airport Maintenance Complex (AMC) Building, 6201 S. Laramie Ave., Chicago, IL 60638, as specified.

                      2021                                                         2022                                                           2023
                                                                                                                          Estimated Contract Amount: $250K - $500K

Purchase of Water Treatment Chemicals for HVAC Systems
Contract Type: Commodities                                                                                                                 Delivery Method: Competitive Bid

The Contractor must furnish and deliver F.O.B., to the Chicago Department of Aviation Water Treatment Chemicals
for HVAC Systems as described in the Detailed Specifications all in accordance with the General Conditions, Special
Conditions, and Detailed Specifications of the Contract.

                      2021                                                         2022                                                           2023
                                                                                                                               Estimated Contract Amount: $3M - $5M

Repair, Replacement and Fabrication of Signage Systems for O’Hare and Midway International Airports
Contract Type: Work Services                                                                                                         Delivery Method: Request for Proposal

Furnish and deliver signage repair, replacement and fabrication in accordance with all the terms and conditions of
this specification. The Vendor will provide the materials, labor, tools, equipment, traffic control and any and all other
items necessary to repair, replace and fabricate the various types of signage systems. The Contract will be utilized for
repairs, fabrication, replacement and maintenance of various signage systems and components as directed by the City
and will be used to supplement the City’s own work force to effect repairs on an as-needed basis.

                      2021                                                         2022                                                           2023
                                                                                                                             Estimated Contract Amount: $5M - $10M

Waste Disposal, Recycling Services and Rental of Related Equipment
Contract Type: Work Services                                                                                                               Delivery Method: Competitive Bid

Collection, transport, recycling and environmentally safe removal and disposal of all waste from the Chicago Airport
System (Group A) and at designated City facilities (Group B).

                      2021                                                         2022                                                           2023
                                                                                                                             Estimated Contract Amount: $5M - $10M
                                                                                     19
                          All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                  visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                          and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
Maintenance and Repair of Diesel Electric Generators and Fire Pumps at O’Hare and Midway International Airports
Contract Type: Work Services                                                                                                               Delivery Method: Competitive Bid

 Furnish all supervision, labor, equipment, parts, materials, tools, services, and transportation for testing, repair and/or
 maintenance of Diesel Driven Electric Generators and Fire Pumps.

                      2021                                                         2022                                                           2023
                                                                                                                               Estimated Contract Amount: $1M - $2M

Pick-Up, Launder and Deliver Blankets, Mop Heads and Bonnets to O’Hare International Airport
Contract Type: Work Services                                                                                                               Delivery Method: Competitive Bid

 Laundering of Bonnet Pads and Dust Mops used for floor cleaning at Chicago O’Hare International Airport. The Vendor
 must furnish all labor, material, transportation, and equipment for laundering, conditioning, drying, and folding of
 washable blankets for the Passenger Assistance Programs (PAP) at O’Hare International Airport and of bonnet heads
 and dust mops for floor cleaning.

                      2021                                                         2022                                                           2023
                                                                                                                           Estimated Contract Amount: $50K - $100K

Servicing and Supplying of Activated Charcoal Filter Cells for Air Handling Units for Chicago O’Hare International Airport
Contract Type: Work Services                                                                                                               Delivery Method: Competitive Bid

 Furnish and deliver Freight on Board Air Filter products and perform servicing, which includes, but not limited to,
 activation of charcoal, repairing and/or replacing of the cells, cleaning and painting of the cells, regular testing of the
 carbon, and/or partial replacement of carbon. Furnishing all necessary labor, materials, products, tools, equipment,
 transportation and disposal services for removing, reconditioning, refilling and replacing activated charcoal filter cells
 on air handling units at O’Hare International Airport.

                      2021                                                         2022                                                           2023
                                                                                                                               Estimated Contract Amount: $3M - $5M

Reflective Sheeting for O’Hare and Midway International Airports
Contract Type: Commodities                                                                                                                 Delivery Method: Competitive Bid

 The Contractor must furnish and deliver F.O.B., to the Chicago Department of Aviation Reflective Sheeting as
 described in the Detailed Specifications all in accordance with the General Conditions, Special Conditions, and
 Detailed Specifications of the Contract.

                      2021                                                         2022                                                           2023
                                                                                                                              Estimated Contract Amount: $500 - $1M
                                                                                     20
                          All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                  visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                          and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
Decorating Services for Seasonal Display and Special Events
Contract Type: Work Services                                                                                                               Delivery Method: Competitive Bid

 When directed by the Commissioner, the Contractor must furnish and deliver Seasonal Decorations including design,
 fabrication, provision, replacement, refurbishment, installation, takedown, and storage of materials for the Chicago
 Airport System and other Departments throughout the City of Chicago in accordance with all terms and conditions of
 this Specification. The Contractor will provide the required materials, labor, tools, equipment, traffic control, implement
 safety and security requirements and any and all items necessary to install, takedown, refurbish, replace and fabricate
 various different types of seasonal decorations for the Chicago Airport System and other Departments throughout the
 City of Chicago.

                      2021                                                         2022                                                           2023
                                                                                                                               Estimated Contract Amount: $2M - $3M

Inspection, Cleaning, Maintenance and Repair of Interior and Exterior Horizontal and Vertical Metal Expansion Joints
Contract Type: Work Services                                                                                                               Delivery Method: Competitive Bid

 The Contractor must furnish all labor, supervision, materials, barricades and equipment to inspect, repair and/or
 replace metal Horizontal and Vertical Expansion Joints including but not limited to those located in the Terminals,
 ATS Train Stations, Concourse and Pedestrian Tunnels, Exterior Upper Level Sidewalks, and Outlying Buildings at
 Chicago O’Hare lnternational Airport and Chicago Midway lnternational Airport on as needed basis as directed by
 the Commissioner of the Chicago Department of Aviation (CDA), all in accordance with the terms and conditions of
 these specifications.

                      2021                                                         2022                                                           2023
                                                                                                                           Estimated Contract Amount: $10M - $20M

Maintenance, Repair and Installation of Various Fencing, Guardrail and Related Equipment
Contract Type: Work Services                                                                                                               Delivery Method: Competitive Bid

 Furnishing of all supervision, labor, traffic control, equipment, materials, tools, and services required for the preventive
 maintenance, repairs, replacement of parts, new installations and rehabilitation of fencing system.

                      2021                                                         2022                                                           2023
                                                                                                                           Estimated Contract Amount: $10M - $20M

Roofing Inspection, Maintenance, Repair and Replacement for O’Hare and Midway International Airports and Various City Locations (Roofing Services)

Contract Type: Work Services                                                                                                               Delivery Method: Competitive Bid

 Furnishing all labor, equipment, incidentals, materials and supervision required to perform inspections, maintenance,
 replacement and repairs of roofing systems for O’Hare and Midway International Airports and various city locations
 (Roofing Services), as specified.

                      2021                                                         2022                                                           2023
                                                                                                                             Estimated Contract Amount: $5M - $10M
                                                                                     21
                          All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                  visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                          and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
Snow Removal Services (Landside) at Chicago O’Hare International Airport
Contract Type: Work Services                                                                                                               Delivery Method: Competitive Bid

Furnish all supervision, labor, equipment and services required for providing full snow removal services landside
24 hours per day, 7 days per week including all holidays at O’Hare International Airport.

                      2021                                                         2022                                                           2023
                                                                                                                               Estimated Contract Amount: $3M - $5M

Maintenance, Repair and Installation of Terrazzo
Contract Type: Work Services                                                                                                         Delivery Method: Request for Proposal

Furnishing, Freight on Board all labor, equipment, materials, incidentals, and supervision required to perform Terrazzo
Maintenance, repair and refinishing services for the Chicago Department of Aviation and the Chicago Department of
Water Management.

                      2021                                                         2022                                                           2023
                                                                                                                           Estimated Contract Amount: $10M - $20M

                                                                                     22
                          All information in this guide is for planning purposes only and is subject to frequent change. For current opportunities,
                                  visit https://www.chicago.gov/city/en/depts/dps/provdrs/contract/svcs/current_bid_opportunities.html
                          and sign up for CDA bid alerts through https://www.flychicago.com/business/contact/Pages/web-alert-sign-up.aspx.
CONSTRUCTION OPPORTUNITIES OFFERED BY
              CONSTRUCTION MANAGERS AT RISK
                        The Chicago Department of Aviation has implemented the Construction Manager at Risk
                                  delivery method to build select projects in the O’Hare 21 program.

    WHAT IS O’HARE 21?                                        WHAT IS THE CMR DELIVERY M
                                                                                       ​ ETHOD?
   O’Hare 21 is an $8.5 billion capital                 The Construction Manager at Risk (CMR) Delivery Method is a construction delivery
   modernization program comprised                      method. Unlike traditional Design-Bid-Build projects where a general contractor is
   of the Terminal 5 Gate Expansion, the                selected based on a low bid, the CMR Delivery Method engages the builder during
   Airport’s 15-year capital improvement                the design stage for input on schedule, budget, and constructability. The CMR
   program, and the Terminal Area Plan                  procures the work of subcontractors via bid packages and holds the contracts with
   (TAP) which includes the replacement                 its subcontractors. It manages the subcontractors and acts as the construction
   of Terminal 2 with a new O’Hare                      manager to provide expedited field direction, on-site safety programs and quality
   Global Terminal and two new satellite                assurance, and acts as a general contractor ensuring the subcontractors are
   concourses west of Terminal 1. These                 building in accordance with plans and specifications. The CMRs release packages
   projects, combined with the soon-to-be               that are specific in their scopes and sizing to provide opportunities for firms to
   finished O’Hare Modernization Program,               successfully work at the airport and increase their capabilities and range. The
   will enhance O’Hare’s continued                      unbundling of the trade packages that might otherwise be bid out as larger packages
   international reputation as a world class            allows for important growth for small to medium sized Chicago businesses in the
                                                        O’Hare 21 Program.
   aviation hub well into the 21st century.

                                WHO ARE THE CMRS? The CDA has engaged three CMRs:

      APP’s work includes construction of               TPAP’s current efforts focus on the              AHCB’s projects include the rehabilitation
      a 10-gate extension to the existing               realignment of the major taxiway network         of Runway 4R-22L, the Lower Level Utility
      International Terminal (T5), installation of      immediately south of Terminals 1 and             and Pavement Reconstruction work in
      a new baggage system that will serve the          2. Work includes realigning portions of
                                                        Taxiways A and B in preparation for the          front of Terminals 1, 2, and 3 which will
      entire expanded terminal, and completion                                                           replace 60 year old water mains and
                                                        construction of the new O’Hare Global
      of numerous capital improvements in
                                                        Terminal and new concourse satellites.           electrical duct banks, rehabilitation of the
      and adjacent to the existing terminal.            Work includes relocation of a significant        Airport’s Elevated Parking Structure, and
      These projects will increase numerous             number of underground utilities, earthwork,
      terminal functions and significantly                                                               the construction of the Terminal 5 Parking
                                                        paving, and the installation airfield lighting
      improve the passenger experience with             and signage. A major challenge for TPAP          Garage. This project will be a six level,
      amenities such as new airline lounges             is the coordination of construction with         cast-in-place structure with helical ramps
      and concessions.                                  aircraft movements.                              at each end of the garage.

                                  HOW ARE BIDS SUBMITTED TO THE CMRS?
   If you are interested on working with the CMRs, you should first contact each CMR.
   For APP, visit www.austinpowerpartners.com
   For TPAP, visit www.tpapord.com
   For AHC, visit www.ahcjv.com
   The CMRs will discuss opportunities available on their projects and walk you through the next steps for prequalification, or
   connect you with a first-tier subcontractor.

                                                            FOR MORE INFORMATION
Version 1 August 2021        Visit ord21.com for a current list of upcoming opportunities and more information on O’Hare 21.