UPPER ST CLAIR SCHOOL DISTRICT BOARD OF SCHOOL DIRECTORS Mr. Patrick A. Hewitt, President• Mr. Phillip J. Elias, Vice President• Mrs. Amy L Billerbeck Mrs. Barbara L. Bolas • Mrs. Jennifer L. Bowen• Dr. Daphna Gans• Mr. Louis P. Mafrice, Jr. Mrs. Angela B. Petersen• Mrs. Jennifer A. Schnore Dr. John T. Rozzo, Superintendent Mrs. Jocelyn P. Kramer, Solicitor SCHOOL BOARD MEETING MINUTES Monday, January 11, 2021 @ 7:00pm Executive Session @ 6:15pm (Litigation and Personnel) District Administration Building Board Room Notice having been advertised and posted and members duly notified, a special Board meeting of the Board of School Directors was held on January 11, 2021 in the District Administration Board Room. School Board Members in Attendance: Mr. Patrick Hewitt President (in-person) Mr. Mr. Phillip J. Elias, Vice President (in-person) Mrs. Amy Billerbeck (virtual) Mrs. Barbara L. Bolas (in-person) Mrs. Jennifer L. Bowen (virtual) Dr. Daphna Gans (virtual) Mr. Louis P. Mafrice Jr. (virtual) Mrs. Angela Petersen (in-person) Mrs. Jennifer Schnore (virtual) School Personnel in Attendance: Dr. John T. Rozzo, Superintendent (in-person) Dr. Sharon K. Suritsky, Assistant/Deputy Superintendent (virtual) Mrs. Amy Pfender, Assistant to the Superintendent (virtual) Mr. Ray Carson, Senior Director of Operations & Administrative Services (virtual) Mr. Scott Burchill, Director of Business & Finance (in-person) Dr. Lou Angelo, Director of Facilities and Operations (virtual) Mr. Raymond Berrott, Director of Technology (in-person) Dr. Judith Bulazo, Director of Curriculum and Development (virtual) Mrs. Cassandra Doggrell, Director of Student Support Services (virtual) Mrs. Lauren Madia, Assistant Director of Student Support Services (in-person) Mr. Bradley Wilson, Director of Strategic Initiatives (virtual) Upper St Clair School District School Board Meeting Minutes January 11, 2021
Mrs. Jocelyn Kramer, Solicitor (in-person) Mrs. Sarah MacDonald, Board Stenographer (virtual) Karsen Damon – Student Board Representative (virtual) R.J. Shontz – Student Board Representative (virtual) Call to Order (Hewitt, School Board President) Mr. Hewitt called the meeting to order at approximately 7:17pm. Resident’s Comments - (Regarding Agenda Items Only) Link to Online Form Note: As per Guidelines for Resident's Comments, please state your name and address and limit your comments to three minutes. Social distancing and mask guidelines will also be adhered to during Resident's Comments. In light of continued health and safety concerns, the Board will offer an additional option for submitting Residents’ Comments via online form (link above) or by phone in advance of the meeting. You can submit a comment via phone by contacting the Board Stenographer at 412-833-1600 x2218 by Monday, January 11, 2021 any time before 2pm. Comments submitted in advance regarding agenda items will be shared with the Board prior to the meeting and summarized at this time. There were no Resident’s Comments at this time. Approval of Agenda (Hewitt, School Board President) MOTION: By Bolas: I move that the Board approve the Agenda, as presented. Seconded by Elias and carried by unanimous voice vote. Superintendent’s Report a. Presentation Regarding Truxton Hillside Embankment Reconstruction Project (Angelo, Director of Operations & Facilities) ATTACHED Dr. Angelo presented a proposed reconstruction project of the Truxton Hillside Embankment. The Truxton hillside has slid and is in need of repair. The hillside is currently a safety concern. Engineering site work has been completed to determine the best options for repair. Currently, the hillside belongs to the Upper St. Clair Township, however upon completion of the project the property will be transferred to the Upper St. Clair School District. The Township will share the cost 50/50 with the District, and the Township will oversee the project. Upper St Clair School District School Board Meeting Minutes January 11, 2021
b. Authorization to enter into an Intergovernmental Cooperation Agreement between the Upper St. Clair School District and the Upper St. Clair Township regarding the Truxton Hillside Embankment Reconstruction Project (Angelo, Director of Operations & Facilities) ATTACHED Dr. Angelo reviewed the presentation and stated why it is important to enter into the Agreement with the Township. Dr. Rozzo noted that the property is adjacent to the High School Stadium and that over time the District has noticed significant deterioration. He also advised that the District and Township have a great relationship and he would like to acknowledge the Township’s commitment to resolving this matter. MOTION: By Bolas: I move that the Board approve the following Resolution: Resolved, that the Board authorize the Superintendent to enter into an Intergovernmental Cooperation Agreement between the Upper St. Clair School District and the Upper St. Clair Township regarding the Truxton Hillside Embankment Reconstruction Project, subject to final terms and conditions approved by the Superintendent and Solicitor. Seconded by Petersen and carried by unanimous voice vote. c. Approval of Personnel Listings (Carson, Sr. Director of Operations & Administrative Services) ATTACHED Mr. Carson reviewed the Personnel Listings. MOTION: By Schnore: I move that the Board approve the Personnel Listings, as attached. Seconded by Bolas and carried by unanimous voice vote. Adjournment (Hewitt, School Board President) The meeting was adjourned at approximately 7:27pm. Upper St Clair School District School Board Meeting Minutes January 11, 2021
Patrick A. Hewitt, President BOARD OF SCHOOL DIRECTORS Scott P. Burchill, Secretary BOARD OF SCHOOL DIRECTORS Submitted by: Sarah MacDonald School Board Stenographer Upper St Clair School District School Board Meeting Minutes January 11, 2021
● The Truxton Drive hillside property has long been assumed to have belonged to the Upper St. Clair School District. ● Originally owned by the Upper St. Clair Township, the property was intended to be transferred to the School District during the 1980s. However, the transfer process was never completed. ● In June of 2018, the Truxton hillside slid during a rainstorm ● The Truxton hillside is a safety concern that is in need of repair ● Engineering site work has been completed to determine best options 2
● Drive Soldier Pile and Lagging Retaining Wall ○ Approximate Dimensions: 200 ft. long, 15 ft. high ○ Useful life: 50-60 years ○ Textured finish ● 50/50 cost sharing with the Township ● Township will oversee the project ● Property will be transferred from the Township to USCSD at the completion of the project ● Value added engineering option provides $450K - $500K savings 5
Drive lane: 15ft. Approximate loss of (Highway lane 12ft) parking lot: 20ft 6
7
Construction Costs $1,079,852.55 Engineering to date $21,000.00 Engineering Final Design and Bid Package $12,500.00 Construction Management/Administration $100,000 Property Transfer $10,000 Estimated Total Project Costs $1,223,352.55 Approximate USCSD Project Costs (50%) $611,676.28 (Costs may vary based on final accepted bid) 8
December/ January/ March May June August January February Review Project and Finalize Construction Upper St. Clair Construction begins Hillside USCSD Board Details Township approves bid from upper stadium lot Construction continues construction ends. Approval of March 1 from Truxton Drive Intergovernmental Gateway Engineers Transfer Truxton Cooperation advertise for RFP hillside property Agreement Jan. 11 Bid Opening Feb. 16 Gateway Engineers prepare bid Bid Finalization specifications Feb. 19 Bid Approval by USCSD Board Feb. 22 9
USC SCHOOL DISTRICT Memo To: Mr. Ray Carson From: Dr. Lou Angelo Date: December 8, 2020 RE: Truxton Hillside Project and Intergovernmental Cooperation Agreement This memo serves as a recommendation to approve the intergovernmental cooperation agreement between the Upper St. Clair School District and the Township of Upper St. Clair as part of our partnership to complete the Truxton hillside embankment reconstruction project during the summer of 2021. History: The Truxton hillside is property that has long been assumed to have belonged to the Upper St. Clair School District. Originally owned by the Upper St. Clair Township, the property was intended to be transferred to the School District during the 1980s. However, the paperwork to complete the transfer was never formally signed and processed; therefore, although the School District was assumed to have taken ownership of the Truxton hillside since the 1980’s, the property is actually owned by the Township. Current Circumstances: During a heavy rain in June 2018, a significant portion of the Truxton hillside slid toward and onto the sidewalk and roadway and has become a safety concern. The Township secured Gateway Engineers Inc. to conduct a geotechnical investigation and assess the stability of the hillside. After reviewing the site location and conditions, conducting geological reconnaissance, and boring for subsurface exploration, the results indicated a portion of the embankment east of Truxton Drive has been experiencing long-term creep movement. Consequently, the Truxton hillside is distressed and embankment reconstruction is recommended. Additionally, we are working with the Township to formally transfer the Truxton hillside property ownership to the District after the completion of the project. Consequently, we should ensure a sustainable solution to the distressed hillside that will provide the maximum years of stability and safety. Lastly, the Township will manage the project while, if approved, we are completing the paving project for the High School campus. The two projects will be coordinated so as to not interfere with one another. Proposed Remediation: The Upper St. Clair Township officials hired Gateway Engineering and collaborated with the District to determine the best possible solution. After reviewing several options, ● Page 1
deliberating costs, projected useful life, value added engineering capabilities and aesthetics, we have tentatively agreed to following solution: ● Soldier Pile and Lagging Retaining Wall ● Textured concrete finish ● Approximate dimensions: 200 ft long, 15 feet high ● Approximate useful life: 50 – 60 years ● Value added engineering will necessitate excavation to our current Truxton end-zone parking lot, but the lot will retain functionality. This option will save approximately $450K-$500K to the overall project costs. Estimated Costs: As part of the understanding with the Township, each party will contribute 50% of the costs for completing the project. An agreement will be drawn up detailing the responsibilities/obligations of each party. The District’s portion to fund this initiative will be secured/included as part of a proposed loan to complete the High School paving project. Construction Costs (details attached) $1,079,852.55 Engineering to date $21,000.00 Engineering Final Design and Bid Package $12,500.00 Construction Management/Administration $100,000.00 Property Transfer $10,000.00 Estimated Total Project Costs $1,223,352.55 Approximate USCSD Project Costs (50%) $611,676.28 Attached: ● Pictures of the Truxton Drive hillside ● Site drawing ● Picture of sample wall ● Project Timeline ● Page 2
© Gateway Engineers Inc. All Rights Reserved Full-Service Civil Engineering & Surveying 855-634-9284 ® FENCE TO MATCH EXISTING (OPTION TO WELD TO TOP PLATE) The Gateway Engineers, Inc. PE Pittsburgh, PA R 3/8" STEEL TOP PLATE UP WELD ON TOP OF SOLDIER UN R S PE BEAMS, USE 1/4" FILLET WELDS FL DE T. O ON BOTH SIDES OF PILE WEB GUARD RAIL TO MOUNT TO PILES RG UT gatewayengineers.com :1 RO CLA 00 4.0 UN IR + /- ( D CON PE CRE FL LD C T: : 10 RE) FIE TE OR KNO UT TOW UN SID 10 UUTNK E IN OR ILNO R PR 0+/- EWA IG W N OR PO P 12 6.0 LK CON IG IW IL NS CRE WP 4775 IN MH . UP TE L 40 IPS T IG CUR INTNY 0 O TOP OF WALL UN R S UT 65 S /T 3 B IT HI P DIP 1 PE GU /T EXTEND MIN 3' I ER 3 D DE T . IL IE P N/ UNKN ER LI MI Y- NUS ABOVE GRADE MI RG IT 8" GH NU S TE OW TCP TO FL S WI S RO CLA Y 1 RM N P RE 2 UN I R PO 0+00 " RCPFL 99 94.7 IN IN 65' TO D 9 9. LE U LE P UT TOW T 1 STEEL PILE PER PLAN (TYP.) OR KNO IL N S 00 ' UN IN 82' 99 IG WN 0. 74' IT H I LE IN 3. EXISTING SOILS AASHTO #57 LIMESTONE T /T IE P 1000 ER BACKFILL RCP TR S SA P 99 987 .69 12" MI EE TO IN FL OUT N FL NU 24" 30'-0" MAX 30 MH RCP ENGINEERED FILL COMPACTED TO VARIES S " CONCRETE CURB 4 95% PROCTOR WITH NO . CONCRETE 64 43' UN 24" SIDEWALK CLAYS OR ORGANICS 98 MI ILIT " RCP ' UT 8" TR . 7 SC DE 1010 TR TC 1010 P EE ST RE EL EE (B RG LA BOX TR OUS OR CO 8" Y TEMPORARY WOOD 10 Y NE EE TE OU M 1010 1010 LAGGING AS NEEDED LE 8" 12 MH D) ND 101 (DESIGN BY CONTRACTOR) PH 2 10 ON 8" TCP R 101 14 E/ EL 4 10 1020 1020 84 TR CO 10 6" PERFORATED SLCCP DRAIN 16 LF O EE EC M 16 TR MU 10 F2 DAYLIGHT @ 40' O.C. SA P 10 4.38 EE TO 100 10 NI 4" TR LA RP L SC 18 FL N 10 SL PROPOSED GRADE " CA 18 0 8" MH 17.0 ' 1 CC ND A IC (SEE PLAN) TI 10 P ELEVATION BOTTOM OF WALL 20 20 ON SL INE 10 1030 S 10 LI ID PR 1048 040 22 REVISION RECORD 1 030 6' 22 LI T: IN: 1 10 FL E 10 NE NE MH .0+ .8 24 ELEVATION BEDROCK VARIES 24 10 S 10 26 26 CO ECT 10 EL UN /- 2+2 EL 10 NC 28 EC 1040 28 D 10 30 LF O 16.00' RE IC 8 LA ARP ER 10 TR 1040 30 SC TE 30 TW ELEV: CO ND 10 IC R 10 4 G 32 NC 0+0 OU SL LINE 32 1046' 10 6 10 RE PA0 X DRILLED SHAFT TO BE FILLED WITH CONCRETE 2+0 4 BO 3 3 ID TE 10 8 1+00 N 0+0 10 BO EL F TO BOTTOM OF WALL ELEVATION AFTER D/ 36 0 2+00 X X X 3 D 10 40 E 10 PA 24" SLC 38 EC 0 1+00 X SOLDIER PILE IS INSTALLED. 3 2+04 CONCRETE SIDEWALK 10 42 D 10 EL 40 TR X 10 42 10 X EC IC 10 X X X TR X 10'-0" MIN X ME NEL CP X 1+00 X PA IC X TE X X X X X X X X X X X X X R X X X X X X X X LI X X X X 24.00' NE 1+23 112.00' CCP TW ELEV: " SL 24.00' S TW ELEV: 1050' F 24 CI 21.00' BI 1046' O BR F TW ELEV: 66 L TU RC KER E MI 1048' GA A UI EL X FE N 01 - 02 - - - - - - - 24.92' BO OU TE CH (TY T NC EC S No 03 04 05 06 07 08 AI E TR PA NL P.) PO BI DRILLED SHAFT SHALL EXTEND V PR 048 040.8 IN IC TU EM ST T: IN: 1 A MINIMUM OF 22'-0" BELOW TOE OF WALL. K FL 16.00' GA MI EN MH .0+/ 1 NO T ME TW ELEV: TE Date US END OF CAISSON TE - - - - - - - - 1048' GR PA PO PR 048 042.0 .5 R - n© AV T: IN: 1 104 VE FL OUT S TE UN MH .0+/ EL 1 FL ME T NT 36" Ø LE DE AR BI SOLDIER PILES SHALL BE EA TU PH RG : - PLACED IN BOTTOM OF CONC. MI ON OU NO FILLED DRILLED SHAFTS (FI 1 U EL E ND S DC PA VA VE EL OR M UL EN E) EC T T/ 202 TR EL IC SCALE: NTS EC SCALE: 1" = 20' 3 TR LI TYPICAL WALL SECTION 1 C600 IC NE SITE PLAN C600 S TOWNSHIP OF UPPER ST. CLAIR BO 0M X 1060 Path & Filename=G:\Projects\85000 Upper St Clair\85411 Truxton Drive Slide\-0002 Wall Design\Dwg\02-Sheet\Wall plan and details_Option 2.dwg 24.00' 16.00' 112.00' 24.00' 16.00' TW ELEV: 1046' TW ELEV: 1048' TW ELEV: 1050' TW ELEV: 1048' TW ELEV: 1046' axa 1050 r© PROPOSED FINISHED GRADE FRONT OF WALL TRUXTON WALL 1040 CN Save Date=12/4/2020 11:07 AM 1820 MCLAUGHLIN ROAD PITTSBURGH, PA 15241 PITTSBURGH, PA 15241 1030 ES TRUXTON DRIVE PREPARED FOR: 1020 ( 202 1010 APPROXIMATE Plot Date=12/4/2020 11:38 AM Addie L. Jack BEDROCK WALL PLAN AND ELEVATION ELEVATION 0) Project Number: C-85411-0003 1000 Drawing Scale: ViewportScale REVISED WALL - 60% DESIGN Date Issued: -- Index Number: -- NOT FOR CONSTRUCTION Dis Drawn By: ALJ SCALE: 1/2" = 1'-0" Checked By: AJD 2 WALL ELEVATION 2020/12/04 Project Manager: KMN C600 C600 trib 18.02
GATEWAY ENGINEERS 100 McMORRIS ROAD PITTSBURGH, PA 15205 412-921-4030 PHONE 412-921-9960 FAX www.gatewayengineers.com PROJECT SCHEDULE USC TRUXTON DRIVE WALL December 4, 2020 Milestones 1. Design Documents Complete and Ready for bid January 4, 2021 2. Documents provided to Township and District for authorization to solicit bid January 4, 2021 3. Anticipated approval from Township and District to Bid January 12, 2021 o District Board meeting January 11, 2021 4. Public Advertisement Date January 22, 2021 5. Bid Due Date February 9, 2021 6. Bid Review Complete and Recommendation to Township and District February 15, 2021 7. Anticipated acceptance of bids from Township and District March 3, 2021 o Township discussion meeting February 22, 2021 o Township regular meeting March 1, 2021 o District Board meeting February 22, 2021 8. Contracts Executed March 22, 2021 9. Contractor Notice to Proceed March 23, 2021 10. Materials delivered (approx. 8-week lead time) May 21, 2021 11. Construction Start May 24, 2021 12. Construction Complete August 22, 2021
Personnel List Board Meeting - Interim Approval (Dr. John Rozzo, Superintendent) January 11, 2021 ELECTION Staff Name Location New Assignment New Effective Date Assignment Status Assad, Andrew Substitute Custodian Substitute 01-12-21 Brown, Natalie Streams AWS Teacher Substitute 01-11-2021 through 06-09-2021 Cejer, Brittany Ft. Couch 1.0 Special Ed Teacher (LTS for A. LTS 02-09-21 through LDTR Neely through 4-7-21 & extended SE position) Holzworth, Cynthia Substitute Substitute Nutrition Center Worker Substitute 01-05-20 Hughes, Emily Ft. Couch AWS Teacher Substitute 01-06-2021 through 06-09-2021 Long, Maria Boyce /Ft Couch 1.0 Music Teacher (0.6 Boyce/0.4 FC) LTS TBD through LDTR (LTS for S. Shoemaker) Mayfield, Alice Substitute ETC Substitute Teacher Substitute 01-11-21 Nicolette-Fantin, Emily Boyce 1.0 Music Teacher (LTS for J. Schetley) LTS 01-19-21 through LDTR O'Brien, Lauren Substitute Substitute Nurse Substitute 01-04-21 Sargent, Robert Bus Garage Bus Attendant PT 01-04-21 Taylor, Elizabeth Substitute Substitute Teacher Aide Substitute 12-17-20 Williams, Hallie Boyce AWS Teacher Substitute 01-19-21 through 06-09-21 Zader, Avis Ft. Couch Substitute Nutrition Center Worker Substitute 01-04-21 CHANGE OF STATUS Staff Name Location Current Assignment Current New Assignment New Effective Date Assignment Assignment Status Status Jones, Holly Boyce Day-to-Day Substitute Substitute AWS Teacher Substitute 01-25-21 through 06-09-21 Young, Lindsey Streams AWS Teacher Substitute 1.0 Elementary Teacher LTS 02-04-21 through (LTS for C. Fortson) 05-12-21 (includes overlap) RESIGNATION Staff Name Location Current Assignment Current Effective Date Assignment Status LaPradd, Emily Ft. Couch AWS Teacher Substitute 12-23-20 OTHER EE#3061 5 day suspension & LCA (12-17 through 12-23)