Esso Bass Strait 2020 Jack Up Rig Campaign - Update 2 March 2020 - Seahorse / Tarwhine P&A programme - ExxonMobil

Page created by Alicia Castro
 
CONTINUE READING
Esso Bass Strait 2020 Jack Up Rig Campaign - Update 2 March 2020 - Seahorse / Tarwhine P&A programme - ExxonMobil
Campaign Sheet #4 – March 2020

Esso Bass Strait 2020 Jack Up Rig
Campaign – Update 2
March 2020

Seahorse / Tarwhine P&A programme

Issue Date: March 2020              Page 1 of 6
Esso Bass Strait 2020 Jack Up Rig Campaign - Update 2 March 2020 - Seahorse / Tarwhine P&A programme - ExxonMobil
Campaign Sheet #4 – March 2020 – Seahorse / Tarwhine Campaign

Esso Australia is planning to undertake a number
of offshore activities within the Gippsland Basin
off the Victorian coastline collectively called the
2020 Jack Up Rig Campaign as advised in 2Q19.
This programme includes:

    Drilling
     o    Two subsea gas production wells in the
          West Barracouta field (BTW)

     o    Two subsea gas production wells in the
          Kipper field

    Well Plug and Abandonment (P&A)
     o    Subsea wells, Seahorse -1 and Tarwhine
          – 1 (SHA/TWA)

     o    Whiting platform                            Noble Tom Prosser Jack-Up Drilling Rig (Image courtesy of
                                                      Noble Corporation)
     o    Mulloway / Whiptail

     o    Perch / Dolphin
                                                      The Tom Prosser does not have any propulsion
There will be no seismic activity as part of this     capability and will be towed into position, then
campaign.                                             the legs lowered onto the seabed and the rig
Drilling activities began at Barracouta (BTA) in      elevated above the sea surface.
January 2020 using the jack-up drilling rig “Tom      Following the BTW drilling activities the Tom
Prosser”, which is known as a jack-up offshore        Prosser will move to the Whiting platform and
drilling rig (JUR). The Tom Prosser was built in      then to Seahorse / Tarwhine to begin the plug
2014 and operates to the latest international         and abandonment programme of the wells.
safety and environmental standards. The drilling
rig will be supported by up to three support          This information sheet provides additional
vessels.                                              information on the Seahorse/Tarwhine Plug and
                                                      Abandonment (SHA/TWA P&A) programme.

Issue Date: March 2020                                                                                 Page 2 of 6
Esso Bass Strait 2020 Jack Up Rig Campaign - Update 2 March 2020 - Seahorse / Tarwhine P&A programme - ExxonMobil
Campaign Sheet #4 – March 2020 – Seahorse / Tarwhine Campaign

Activity Description                                 Impacts and Risks

Well Abandonment                                     Impacts and risks from the JUR activities have
                                                     been outlined in the campaign sheet sent out in
The SHA subsea well was plugged with solids in
                                                     2Q19.
2014 and the wellbore was circulated to replace
its contents with inhibited water.

The TWA chemical and hydraulic cores of the
umbilical were also flushed with inhibited
seawater prior to severing it at the BTA platform
end in 2018.

Once the JUR is positioned over the wellhead, the
tree cap will be removed and barrier testing will
be completed.

For all wells, a Blowout Preventer (BOP) will be
used to prevent the release of hydrocarbons
during the plugging of the wells. Tubing and
associated instruments and control valves will be
removed, and permanent cement plugs / barriers
installed to provide multiple physical barriers to
prevent the release of any hydrocarbons that
remain in the reservoir.

The well casing and conductors will be cut at a
depth of ~ 3 m below the mudline and removed
and the severed wellhead will be retrieved.

Activity Location

The Seahorse and Tarwhine wells are located 15
and 23 km off the Gippsland coastline
respectively, south of Lakes Entrance in a water
depth of ~43m.

The BTA platform lies in-between the two subsea
wells, ~11km from SHA and ~17km from TWA.

SHA activities will occur within the Bass Strait
Area To Be Avoided (ATBA) for commercial
shipping while TWA lies immediately outside the
ATBA. Neither the existing subsea facilities nor
the existing routes of the flexible flowline and
control umbilical from BTA to SHA/TWA are
located within any established or proposed
Commonwealth or State Marine Protected Areas,
Critical Habitats or Threatened Ecological
Communities. It is recognised that the activities
will overlap with existing fisheries.

Issue Date: March 2020                                                                      Page 3 of 6
Esso Bass Strait 2020 Jack Up Rig Campaign - Update 2 March 2020 - Seahorse / Tarwhine P&A programme - ExxonMobil
Campaign Sheet #4 – March 2020 – Seahorse / Tarwhine Campaign

Well Locations                             Licence Area      Latitude/Longitude     Activity Type   Water depth (m)

Kipper Subsea Facility                                              38°10' 53" S
                                               VIC/L25                                  Drilling          95
(KPA-A1, KPA-A3)                                                   148° 35' 35” E
West Barracouta Drill Centres                                      38° 19’ 06” S
                                                VIC/L1                                  Drilling          46
(BTW-W1, BTW-W2)                                                   147° 36’ 53” E
                                                                   38° 24’ 12” S
Tarwhine (TWA-1)                                VIC/L1                                    P&A             42
                                                                   147° 31’ 46” E
                                                                   38° 11’ 42” S
Seahorse (SHA-1)                               VIC/L18                                    P&A             42
                                                                   147° 40’ 27” E
                                                                   38° 14’ 29” S
Whiting platform (WTA) (5 wells)                VIC/L2                                    P&A             54
                                                                   147° 72’ 20” E

                         Whiptail &
                         Mulloway

  Esso Bass Strait 2020 Jack Up Rig Campaign Activity Locations as circled

Issue Date: March 2020                                                                                         Page 4 of 6
Esso Bass Strait 2020 Jack Up Rig Campaign - Update 2 March 2020 - Seahorse / Tarwhine P&A programme - ExxonMobil
Campaign Sheet #4 – March 2020 – Seahorse / Tarwhine Campaign

Activity Timing                                       The timing of the activity may vary and is
The following shows an indicative campaign            contingent on regulatory approvals, joint venture
timetable only.                                       approvals, and weather and rig/vessel schedules.

Activities will be conducted 24 hours per day,
seven days per week. It is expected to take ~30
days to plug and abandon each well.

                                                        West Barracouta Drilling
                           January 2020
                                                        Commences

                                                        Whiting Plug & Abandonment
                               April 2020
                                                        Commences

                                                        Seahorse / Tarwhine Plug &
                               July 2020                Abandonment Commences

                         September 2020                 Kipper Drilling Commences

                                                        Mulloway / Whiptail Plug & Abandonment
                         December 2020                  Commences (to be confirmed)

                                                        Perch / Dolphin Plug & Abandonment
                             March 2021                 Commences (to be confirmed)

  Indicative Jack Up Rig Campaign Activity Timeline

Issue Date: March 2020                                                                           Page 5 of 6
Esso Bass Strait 2020 Jack Up Rig Campaign - Update 2 March 2020 - Seahorse / Tarwhine P&A programme - ExxonMobil
Campaign Sheet #4 – March 2020 – Seahorse / Tarwhine Campaign

Petroleum Safety Zones                                (ALARP) and meet Esso Australia’s acceptability
                                                      criteria.
Seahorse / Tarwhine is located within existing
500m Petroleum Safety Zones (PSZ). The exact          Consultation
location of the drill rig while at location will be
                                                      Esso Australia is committed to engaging with the
communicated to other marine vessels via a
                                                      communities where we operate and helping our
Notice to Mariners issued by the Australian
                                                      stakeholders to understand our business.
Hydrographic Service (AHS) and AUSCOAST
warnings issued by AMSA.                              Esso has been consulting with stakeholders
                                                      potentially affected by this campaign through a
Interaction with Commercial Fishing
                                                      number of different channels.
Seahorse / Tarwhine is located within existing
                                                      While some community consultations have
designated Commonwealth and State fisheries
                                                      occurred, Esso welcomes the opportunity for
that may be used by commercial fishers. The
                                                      more face-to-face meetings and will continue to
500m PSZ will be communicated to South East
                                                      keep interested stakeholders informed of the
Trawl Fishing Industry Association (SETFIA) as it
                                                      proposed activities throughout the planning
is a legal requirement that the area should be
                                                      phase and into operational phase.
avoided during the P&A Activities.
                                                      We will address questions and consider feedback
Environment Plans
                                                      from stakeholders throughout this campaign.
Under the Offshore Petroleum and Greenhouse
                                                      If you have any specific questions or feedback
Gas Storage Act 2006, before any petroleum
                                                      about any of these activities please contact Esso
related activities in Commonwealth waters can
                                                      at consultation@exxonmobil.com or call 03 9261
commence, an Environment Plan (EP) must be
                                                      0788.
accepted by the National Offshore Petroleum
Safety    and      Environmental Management
Authority (NOPSEMA).

In the course of preparing an EP, Esso Australia
must consult with relevant authorities, persons
and organisations whose functions, interests or
activities may be affected by the proposed
activities (i.e. a relevant person) and provide the
opportunity for any issues or concerns to be
raised.

Separate Environment Plans (EPs) are being
developed for these different activities, however,
to improve efficiencies for stakeholders, a single
consultation process is being undertaken.

The EP is a comprehensive document that
describes the existing environment, including
stakeholders, and how Esso Australia will
undertake the activities to avoid, minimise or
manage potential environmental impacts to the
“As Low As Reasonable Practicable” standard

Issue Date: March 2020                                                                         Page 6 of 6
You can also read