Procurement Strategy for Transport - A strategy to outline the procurement by Porirua City Council for Roading and Transport activities
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Procurement Strategy for Transport A strategy to outline the procurement by Porirua City Council for Roading and Transport activities Final October 2019
VERSION HISTORY Version Date Description Owner Revision Due 1 12/9/2014 Manager Roading 2016/17 2 01/09/2018 Transport Manager 2021/22 3 2 September 2019 Major rewrite in Transport Manager 2022/23 advance of tender round for Network Maintenance 3.1 16 Sept 2019 Edits Transport Manager 2022/23 3.2 16 Oct 2019 Edit post NZTA Transport Manager 2022/23 feedback PS Final 18 Oct 2019 Finalisation Transport Manager 2022/23 Roading Procurement Strategy October 2019 2
; CONTENTS PAGE 1. Executive Summary ........................................................................................... 4 1.1 Overview ..................................................................................................... 4 1.2 Recommendations ...................................................................................... 5 1.3 Council Endorsement .................................................................................. 5 2. Context .............................................................................................................. 6 2.1 Strategic Objectives .................................................................................... 6 2.1.1 Council’s Overall Strategic Objectives .................................................. 6 2.1.2 Growth in Porirua ................................................................................. 6 2.1.3 Specific Transport Enhancements ........................................................ 8 2.1.4 Asset Valuation and Condition ............................................................. 8 2.1.5 Overall Financial Strategy .................................................................... 9 2.2 Outcomes and objectives for the Transport Procurement Strategy ............ 10 2.3 NZTA’s Procurement Requirements .......................................................... 11 2.4 Other Factors affecting Procurement......................................................... 11 2.4.1 Organisation-wide Procurement Policy............................................... 11 2.4.2 Regional Procurement ....................................................................... 12 2.4.3 Public Private Partnership model in Porirua City ................................ 12 2.4.4 Other Strategic Documents ................................................................ 12 3. Procurement environment ................................................................................ 13 3.1 Analysis of Supplier Market ....................................................................... 13 3.1.1 s17A and Delivery Strategy. ............................................................... 13 3.1.2 Professional Services Providers ......................................................... 13 3.1.3 Physical Works Contractor Market ..................................................... 14 3.2 What do we need to buy? - Analysis of planned spend ............................. 15 3.3 Impact of Council Procurement on others.................................................. 17 4. Procurement Programme ................................................................................. 18 4.1 Procurement Programme .......................................................................... 18 4.1.1 Contracting Strategy .......................................................................... 18 4.1.2 Detailed programme and procurement approach ............................... 19 4.1.3 Simplified Programme timeline ........................................................... 23 4.2 Unusual/Advanced procurement ............................................................... 23 5. Implementation................................................................................................. 24 5.1 Capability and Capacity - general.............................................................. 24 5.2 Internal Procurement Processes ............................................................... 24 5.3 Performance Measurement and Monitoring............................................... 25 5.4 Communication Plan ................................................................................. 25 Appendix 1 – Council Transport Structure ............................................................... 26 Roading Procurement Strategy October 2019 3
1. EXECUTIVE SUMMARY 1.1 Overview Porirua is experiencing and planning for additional considerable growth. Annual residential growth is over twice the historical average, and there are major investments in the region such as the Eastern Porirua Regeneration Project, Porirua Adventure Park, Kenepuru Landing, Plimmerton Farms etc. This growth, and the completion of major projects such as Transmission Gully will increase the pressure on our roading and transport network. Porirua City Council (Council) has undertaken significant long-term planning with a Growth Strategy 2018 to 2048 and a Long-Term Infrastructure Strategy 2018 to 2038. To accompany these and Council’s other planning initiatives, this procurement strategy outlines how Council will plan and procure the delivery of projects and services to support the transport network. Historically, the investment in the transport network has been less than ideal. Council had other infrastructure and funding priorities so adopted a ‘high risk’ investment profile and capped funding in transport for a period; but is now moving to a medium- risk profile. In addition, our contracting strategies and internal management processes to monitor these have not always resulted in the desired levels of service and/or outputs. The following diagram summarises the issues/challenges and how these are addressed in this procurement strategy. Issues/Challenges Addressed in this Procurement Increasing Growth in Porirua strategy Specific transport initiatives (TG Increased investment – from high risk impacts) strategy to medium risk strategy for LTP funding Prior under-investment in roading infrastructure Specific projects to address TG linkages and impacts Backlog of maintenance Unbundling contracts to get greater focus Asset condition deficits on maintenance activity and good value for money Market conditions Increased focus on RAMM data quality in Under capability/capacity within new contracts Council Council change in structure to ensure it has capability/capacity Roading Procurement Strategy October 2019 4
1.2 Recommendations Council recommends: a) the New Zealand Transport Agency (NZTA) endorse this strategy and the programme described within it; and b) continued approval by NZTA under s26 of the Land Transport Management Act for the use of in-house professional services. Council also notes that three are no advanced components or variations to the NZTA Procurement Manual. If approval of the full Procurement Strategy is delayed then approval of the Roading Maintenance Contract procurement component is sought ASAP to allow this to go to the market in Q4 2019. 1.3 Council Endorsement Procurement Strategy Owner: Transport Manager Once endorsed this strategy will apply to all procurement involving NZTA funding and will be owned by Council’s Executive Leadership Team, specifically managed by the Transport Team, and overseen by the Procurement Committee. This is not a standard alone document but is to be read in conjunction with the Transport Activity Management Plan 2018-21. The Procurement Strategy will be reviewed on an on-going basis as part of the Management Plan Review. A full review will occur at least every three years or when a major change in funding policy or process occurs. Next review date is 2022/23. Roading Procurement Strategy October 2019 5
2. CONTEXT 2.1 Strategic Objectives Council’s Overall Strategic Objectives The transportation activity fits within Council’s strategic priorities as set out in the Long Term Plan 2018 to 2038 of; • a growing prosperous and regionally connected city • a great village and city experience –ensuring that our city’s infrastructure is resilient and fit-for-purpose, connecting our city through walking, cycling and road networks. Our transport network plays a big part in this as it helps us connect safely and efficiently. We want an integrated network to ensure that our drivers, pedestrians, cyclists and public transport users can travel safely and conveniently around and through our city. Growth in Porirua Council has developed a Growth Strategy 2018 to 2048. The Growth Strategy is in response to, and to influence future growth pressures in Porirua. These include: • Residential growth is currently running at 2.2% per annum – a significant increase on the historical 1% per annum • Porirua may get as many as 29,000 extra people by 2048 • There is significant urban development planned and underway. There is $1.5 billion of investment in Eastern Porirua through the regeneration strategy. There are a number of other urban developments – both greenfield and increasing intensification of residential areas. The growth principles included are (highlight added): • A diverse and inclusive city • A harbour-centred city • A compact and liveable city • A connected and active city • A city of opportunities and prosperity • A resilient city The principles of “Compact and liveable”, “connected and active” and “a resilient city” have clear implications for transport networks. The effect of growth will be an increased pressure on the roading network. In Porirua, 57% of residents use a car to get to work with 12% using public transport (2013 census). In addition, in the Wellington region, cars represent 68% of all trips and 81% of distance covered (Ministry of Transport, Household Travel Survey 2015-18). The following spatial layout from the Growth Strategy indicates the 30 Year Growth Horizon and expected intensification of development, including some major transport routes: Roading Procurement Strategy October 2019 6
Spatial Layout from Council’s 2018-2048 Growth Strategy: Roading Procurement Strategy October 2019 7
Specific Transport Enhancements Transmission Gully (TG) is a significant investment in the region and should improve overall resilience. Council is contributing around $40m for its Link Roads due for completion by July 2020. These changes will have a significant effect on the way traffic flows through, and within, the Porirua City region. In addition, due to the direct linkage with TG, the Kenepuru Corridor is expected to see significant changes of use. For example, the southern section is expected to incur increased vehicle usage by about 4,000 plus vehicles per day (a 20+% increase). Asset Valuation and Condition The transport assets in Porirua have a total replacement cost of $332 million (as at December 2018 as follows: Depreciated Replacement Replacement Annual Cumulative Asset Group Cost Cost Depreciation Depreciation Formation $ 69,273,453 $ 69,273,453 $- $- Subbase $ 31,897,872 $ 29,993,867 $39,681 $ 1,904,005 Basecourse $ 39,407,108 $ 18,327,236 $440,001 $ 21,079,872 First Coat Seals $ 12,458,627 $ 5,052,709 $154,700 $ 7,405,918 Surface $ 17,116,771 $ 5,856,046 $969,319 $ 11,260,725 Carparks $960,001 $472,239 $23,231 $487,762 Bridges & Large Culverts $ 27,199,009 $ 17,251,378 $291,978 $ 9,947,631 Drainage $ 16,769,503 $ 6,096,291 $277,671 $ 10,673,212 Footpath $ 46,902,766 $ 21,562,427 $613,692 $ 25,340,338 Islands $928,967 $429,121 $13,991 $499,846 Minor Structures $890 $415 $59 $474 Railings Railings $ 1,406,331 $519,075 $65,269 $887,257 Retaining Walls $ 13,892,447 $ 6,493,471 $232,114 $ 7,398,976 Signs $ 1,777,541 $613,366 $118,503 $ 1,164,174 Street Lights $ 16,985,410 $ 9,976,734 $566,181 $ 7,008,676 Surface Water Channel $ 35,379,932 $ 17,618,349 $472,522 $ 17,761,582 Traffic Signals $127,636 $ 25,527 $ 8,509 $102,109 Total $ 332,484,263 $ 209,561,704 $ 4,287,422 $ 122,922,560 Roading Procurement Strategy October 2019 8
The following are the performance measures reported through our LTP/Annual Report processes: Measure Result 2018/19 Target 2018/19 Response to service requests: Percentage of customer service requests relating to roads and footpaths responded to within the More than 85% within agreed timeframes 64% agreed timeframes Road safety: Number of fatalities and serious injury crashes on the local road network (expressed as a Contribute to a reducing number) 17 trend over 5 years Road condition: The average quality of ride on sealed local roads More than 75% quality of (smooth travel exposure by NZTA) 79% ride Road maintenance: Percentage of sealed local road network that is 9% resurfaced (external resurfaced 3.7% contractor) Footpaths: Percentage of footpaths that are in average or better More than 97% in better condition 97.4% or average condition Resident satisfaction with the More than 70% condition of: satisfaction 47% (a) local roads More than 70% (b) local footpaths 51% satisfaction In addition, some of our Road Assessment and Maintenance Management (RAMM) database data is not as reliable as we desire and we are investing to insure we continually improve the quality of our RAMM information. Overall Financial Strategy In addition to the Growth Strategy, Council has developed its Long Term Plan 2018 – 2038. Rather than a 10 year view we are now taking a 20 year view of financing and funding. Included in this is a specific Infrastructure Strategy, linked to the LTP and the Asset Management Plans: Roading Procurement Strategy October 2019 9
The financial strategy indicates forecast 4.98% rates increases for the next two years of the Long Term plan. A significant amount of this increase is just to address the historical underfunding of depreciation across Council and is not for additional service levels. The funding in the Infrastructure Strategy aims to address the following: • The backlog of maintenance to be addressed in the next 2-3 years (however funding is constrained on 2019/20). • Large capital to address capacity issues and alleviate congestion points. The Long Term Plan is moving to a more targeted funding of transport projects over the next ten years. This will include capital projects, improvement and maintenance that have longer term impacts on the City’s networks, both for vehicle movements and the movement of the people around the City by cycle or foot • In the last few years the Council has moved from a high risk strategy to a medium risk strategy, with the objective of bringing much of the network up to a fit for purpose condition and providing a network that delivers value for Council and all the users of the Transport system. 2.2 Outcomes and objectives for the Transport Procurement Strategy A key outcome is to deliver value for money and a coherent response to the challenges and opportunities that present themselves to Council in the next three years (and beyond). Investing in the transport network is part of the critical infrastructure to promote and support economic growth. Council is a significant user of public money, and that the expenditure of this money has a significant impact on the local and domestic economy and the overall performance of the Council. Every action undertaken to spend these funds is publicly discoverable and the use should reflect the practice of good governance and financial management. To this end the Transport team uses the Council and NZTA procurement processes and frame works to deliver value for money on the transport programme and for the wider council. This strategy aims to be consistent with the Porirua City Council Procurement Policy (#969114), the One Network Roading Classification (ONRC) requirements and the NZTA Procurement Manual. NZTA are a significant funder and partner of Council transport infrastructure. This procurement strategy is to align with NZTA requirements. Roading Procurement Strategy October 2019 10
2.3 NZTA’s Procurement Requirements The NZTA’s procurement requirements are: • Value for money • Competitive and efficient markets • Fair competition among suppliers The proposed contracting strategy in the following sections has taking that into account with the contracting strategy and programme. Council has based its procurement policy on the Government Procurement Rules. The NZTA Procurement Manual is used to drive the transport programme and its related programmes. Council is driving improved procurement practices across the Transport Team and the entire organisation including ensuring: • Each procurement decision is driven by the principles of ‘best value over whole of life’, having due regard to propriety • Using the Government Procurement Rules and guidance to inform and direct Council’s procurement policy • Promote open and effective competition including full and fair opportunity for all suppliers • Promote awareness of its Sustainable Procurement Policy among Transport staff involved in the procurement of infrastructure and services • Establish organisational targets and measure associated progress to support continued improvement in procurement practices. Council also aligns its procurement activity with NZTA requirements. Council’s Procurement Policy states that ”any officer engaged in any NZTA subsidised work should have a clear understanding of the NZTA procurement manual, its requirements and principles”. It also states that ”All procurement projects for NZTA subsidised work shall follow the procedures set out in the NZTA Procurement manual. The tender evaluation procedure must be specified in the Conditions to tendering and the method specified must be adhered to”. 2.4 Other Factors affecting Procurement Organisation-wide Procurement Policy This Transport Procurement Strategy fits within Council’s Procurement Policy of July 2018. The purpose of the Procurement Policy is to provide guidance to staff and suppliers to achieve our Long-Term Plan objectives. It defines how Council will undertake procurement decisions, the processes involved and provides clarity to suppliers and the community on what Council will consider in procurement and the guiding procurement principles. The Scope of Council’s Procurement Policy applies as follows: • All Council staff with responsibility for procuring goods and services do so in accordance with the Financial Delegations Policy • Consultants or contractors used to advise on, arrange or manage a procurement process for Council Roading Procurement Strategy October 2019 11
• Any Officer engaged in any NZTA subsidised work should have a clear understanding of the NZTA procurement manual and its requirements as well as the principals in this policy. Regional Procurement There are no immediate plans to secure wholesale regional procurement of Transport services at the current time. Currently Council does secure traffic signal maintenance and operation via a regional procurement process. However, the Transport team is aware of the procurement strategies, contracts and contractors working on road assets in adjacent authority areas. For example, the One Network Road Classification (ONRC) involves categorising roads based on the functions they perform as part of a national network. These classifications will assist local government and NZTA to plan, invest in, and maintain and operate a transport network in a more strategic, consistent and affordable way throughout the country. Council may investigate the potential of joint procurement of some further transport asset services at a future date, if it is deemed to deliver value for money and is not inconsistent with the procurement strategy or procedures in operation at that time. At this stage, regional procurement is not expected to realise tangible value as there is no one contractor who could service more than one council in any real and efficient fashion. Public Private Partnership model in Porirua City The TG programme involves Council in the construction of the two Link Roads (connecting to/from Waitangirua and Whitby) associated with the development. Construction of TG began in 2015/2016. The Council Link Roads are being procured using a separate, standard, Design and Construct contract procured via the TG Public Private Partnership (PPP). Under this procurement process, Council has contracted directly with the principal construction subcontractor as part of the PPP Consortium. This work is now current and ongoing with practical completion programmed to occur prior to July 2020. Other Strategic Documents Key planning documents that inform the transport programme and the development of this procurement strategy include: • Land Transport Management Act 2003 • Local Government Act 2002 • Porirua City Council District Plan • Porirua City Council Long Term Plan • Porirua City Council Growth Strategy 2018 to 2048 • Porirua Long-Term Infrastructure Strategy 2018 to 2038 • Porirua City Council Transport Asset Management Plan 2018 • Government Procurement Rules • NZTA Procurement Manual • Wellington Regional Land Transport Plan 2015 • Wellington Regional Land Transport Strategy: 2010-2040 • Making Cycling Safer and More Attractive The NZ Transport Agency’s cycling safety action plan 2015 • Safer Journeys - NZ’s Road Safety Strategy 2010-2020 These documents are available on request from the relevant authority. Roading Procurement Strategy October 2019 12
3. PROCUREMENT ENVIRONMENT 3.1 Analysis of Supplier Market s17A and Delivery Strategy. Councils are required to determine the cost-effectiveness of different funding, governance and service delivery options under s17A of the Local Government Act 2002. A review of roading and transport activities under s17a confirms the overall contracting out of the physical works and retention of in-house of governance and management capability. Council retains an in-house team to plan and manage the delivery of the transport projects with its major purchases being professional services and physical works. Council continues to provide some professional services in-house to improve the effectiveness of strategic alignment and delivery e.g. the preparation of funding applications and the design of small / low risk transportation and safety improvement projects, while outsourcing specialised professional services and when additional capacity is required. The following table summarises the delivery mechanisms: Activity Delivery mechanism Asset Management In House / Contracted Specialist technical and asset management advice In House / Contracted Community safety In House Structures inspections and management In House / Contracted Associated road strategy and maintenance issues In House / Contracted Physical works contract management In House / Contracted Operational aspects of managing Porirua roads In House (overweight permits, corridor access requests CARS temporary traffic management plans etc.) Maintenance physical works Contracted Physical renewals and improvements Contracted Professional Services Providers Council currently uses a professional service provider to deliver Roading Asset Management Professional Services. The scope of the work includes but is not limited to: • Pavement Testing and Analysis • Condition Rating • Development of Maintenance Strategy • Pavement Performance Modelling (dTIMS) • Road Asset Valuation. Specialised professional services will continue to be sourced from external providers where no internal expertise and/or capacity exists. Roading Procurement Strategy October 2019 13
Physical Works Contractor Market There are ongoing macro-economic considerations for the physical works market: • Cost of capital is generally low, with historically low interest rates, but there are uncertainties about future global economic demand, the effects of climate change and climate change policies on roading/transport projects etc. • Cost of labour is increasing with a generally low unemployment rate and forecast rises to the minimum wage having a knock-on effect to the next tier of workers • Cost of inputs increasing and variable, with oil prices and exchange rates increasing, and supply of materials such as aggregates sometimes uncertain • The impact of increased focus on Health & Safety and traffic management plan requirements which are necessary and appropriate but do sometimes constrain capacity, flexibility, and increase costs. The contracting market in the region is notable for: • Three (3) major contractors dominating the major capital and long term transportation maintenance contracts, being Fulton Hogan, Higgins, and Downer with all being major national providers • Minor contractors available for small works, often subcontracting to one or more of the aforementioned major contractors. The contracting market is in a period of heightened uncertainty as: • TG as a major project which is tying up considerable resources of equipment and labour with a revised, stated, completion date of ‘sometime’ in 2020 although there is the potential for this to be delayed. • The Otaki Expressway is also a significant project which is programmed to continue through to 2021 • Challenges for local councils to deliver on their chip resealing and renewal activities • Uncertain commitment to the next tranche of major physical transportation projects. Many Roads of National Significance (RONS) projects are on hold or postponed. The above factors transpire into an observed increase in civil construction costs with indications that roading unit rates have increased significantly in the lower North Island. Contractors appear to be ensuring that all tenders are appropriately profitable, and in some cases are not tendering if they do not immediately have sufficient resource and/or certainty of making a minimum financial return. There is no indication that contractors are securing long term work for certainty at reduced profitability. This uncertainty in the contractor market is expected to last through the next 2-5 years (which is also the timeframe when the major regional projects such as TG and the Otaki Expressway are completed) and this needs to be taken into consideration in procurement planning. To ensure reliability of supply of emergency works, the primary response is included in the Roading Maintenance Contract. Roading Procurement Strategy October 2019 14
3.2 What do we need to buy? - Analysis of planned spend Council has allocated additional subsidies from NZTA (being the increased Funding Assistance Rate (FAR) to 56% and new subsidies on footpath work) particularly to areas that have fallen behind, such as sealed pavement maintenance, sealed road resurfacing, sealed pavement rehabilitation and footpath renewals. Where possible drainage renewals and structures maintenance have also received additional budget allocations compared to historical spend, to start catching up on previous underspend and to finance particular projects. Intersection upgrade projects are programmed for areas of growth and change due to TG. There is a significant expenditure envisaged for revocation and/or TG Integration planning work, the cost of which is estimated by Council but not yet approved by NZTA due to NZTA not progressing their Revocation business case. Walking and cycling projects are the other major capital expenditure projects. There is also known slip, seawall and erosion work to be managed. These projects have been submitted via Transport Investment Online (TIO) and into the Regional Land Transport Programme (RLTP). The budget below sets out the annual profile of spend on physical assets for Transport. The programme includes physical works for all Transport activities (subsidised and un-subsidised). 2019-22 2018/19 2019/20 2020/21 2021/22 (3 years) $000 $000 $000 $000 $000 LTP LTP Project Description Budget Yr2 Yr3 LTP Yr4 Total Roading & Safety Maintenance 111 - Sealed Pavement Maintenance 408 421 450 464 1,335 113 - Routine Drainage Maintenance 359 370 390 402 1,162 114 - Structures Maintenance 326 334 355 366 1,056 121 - Environmental Maintenance 454 468 493 508 1,469 122 - Traffic Service Maintenance 211 219 240 248 706 123 - Operational Traffic Maintenance 5 5 5 5 16 124 - Cycle Path Maintenance 51 53 55 57 165 131 - Level Crossing Warning Device 5 5 5 5 15 151 - Network & Asset Management 431 440 459 468 1,367 Minor Events Emergency works 107 110 114 117 341 NZTA 003 - Activity Management Plans 51 52 53 54 159 Traffic Services Maintenance - Streetlighting Power 519 530 541 553 1,624 - Accessways 61 63 64 65 192 Asset Management 20 21 22 22 65 CAR Management 247 250 253 256 759 CBD Canopies & Walkways 219 223 68 70 361 Footpath Maintenance 68 71 73 75 219 Footpath RAMM 15 16 16 17 49 Footpath Vegetation 77 79 82 84 245 432 - Road Safety Promotion 183 189 194 200 583 Maintenance subtotal 3,817 3,920 3,932 4,037 11,889 Roading Procurement Strategy October 2019 15
2019-22 2018/19 2019/20 2020/21 2021/22 (3 years) $000 $000 $000 $000 $000 LTP LTP Project Description Budget Yr2 Yr3 LTP Yr4 Total 212 - Sealed Road Resurfacing 1,248 1,288 1,329 871 3,488 213 - Drainage Renewals 511 159 80 83 322 214 - Sealed Road Pavement Rehabilitation 408 421 435 449 1,305 215 - Structures Component Replacements 61 63 65 67 195 222 - Traffic Services Renewals 382 395 408 421 1,224 321 - New Traffic Management Facilities 20 5 5 5 15 Sealed Pavement Mtce - Reseal Preparation Work 331 342 353 365 1,060 Footpath Renewals 537 211 217 127 555 Capital subtotal 3,499 2,884 2,892 2,388 8,163 Offstreet Parking 68 71 73 75 219 Street Furniture 56 57 59 60 176 Transport (non-subsidised) Assert Management 133 137 141 146 424 Unsubsidised subtotal 257 265 273 281 819 Roading & Safety Maintenance subtotal 7,573 7,068 7,097 6,706 20,871 Capital Projects 141 - Emergency Works 765 365 373 381 1,119 323 - Transmission Gully 12,787 6,014 - - 6,014 341 - Minor Improvements 245 250 266 272 788 Albatross Close slip repair work 1,500 - - - - Conversion of all Streetlights to LED 606 - - - - Intersection Upgrades 746 2,304 1,182 1,291 4,777 LTP - New Road Connections, Eskdale 25 730 - 218 948 LTP - Roading Bridge Upgrade, Kenepuru Culvert - - 501 - 501 Walking and Cycling Pathway Priorities 306 297 517 - 814 Seawalls - 146 490 354 990 SH1 & SH58 Revocation Project 180 210 102 275 587 Wineera to CBD Pathway 918 - - - - Wineera to Onepoto Walkway & Cycleway 408 2,710 - - 2,710 18,486 13,026 3,431 2,791 19,248 Total 26,059 20,094 10,528 9,497 40,119 Excluding Council’s TG Link Roads, it plans to spend $40m on its transport network in the three year funding period 2019/20 to 2021/22. The Long Term Plan (LTP) reports Council’s aim to restrict rates increases to 5% for the 2018/19 year and beyond. This restriction of rates increases requires an overall budget reduction in conjunction with improved reprioritisation of funding allocation. Roading Procurement Strategy October 2019 16
The 2015/25 LTP determined to move from the high-risk scenario to a planned medium-risk scenario. This means that an additional $12.8m is expected to be required over the next ten years. This investment would take the transport network to a 30% likelihood of significant failure of an asset resulting in a loss of service. At this stage, we are two (2) years into a six (6) year progression to achieve 30% likelihood of loss of service. A purposeful progression towards reduced threat of failure and sustained prioritised investment is considered appropriate for Council, given the competing financial demands on the city’s infrastructure. 3.3 Impact of Council Procurement on others The Council considers the impact of its procurement on other approved organisations. Currently, with the contracting strategy outlined in section 4.1.1 we are focusing on our own organisation’s procurement activities and foresee limited impact on other approved organisations, or opportunities for collaboration (beyond ongoing collegial/professional dialogue). This procurement strategy will be published on Council’s website and communicated directly to regional stakeholders. Roading Procurement Strategy October 2019 17
4. PROCUREMENT PROGRAMME 4.1 Procurement Programme Contracting Strategy Historically our contracting approach for transport contracts has been: • Tendering for major capital projects • A major Network Maintenance Contract (NMC) bundling roading maintenance, renewals/reseals, vegetation control, lighting maintenance and ancillary services. Contract. Council’s latest iteration of the NMC, AM000046, started in May 2015 and has been contracted to Downers. The current NMC has been challenging and has not met its expectations. This is related to: • Ongoing under-investment in asset renewals leading to lower than desirable asset condition • RAMM data quality not increasing appreciatively • Insufficient contract monitoring by Client to ensure service levels are being met. Our contracting strategy for the medium term aims to address this by significantly changing our contract philosophy. We will carry out the following: • Unbundling contracts. We will unbundle AM00046 services including: o Split ‘core’ maintenance activities from renewals/rehabilitations/reseals. Maintenance activity will be let on a medium term contract (3+1+1) to lock in a maintenance provider (see table below). o Renewals and reseals will be let by annual programme to give Council flexibility, and also enable competitive bidding as major projects such TG are completed in the region. o Split out street lighting as this is generally a subcontracted service or a discrete business unit within some roading companies. With the change to LED’s there is also a changing work profile to this activity. o Vegetation Control will be let as a standalone contract. o Remove other minor ancillary services that are often subcontracted (e.g. traffic counting). • Greater financial control within contracts. We will increase use of ‘unit rates’ within contracts and reduce ‘lump sums’ so that there is greater transparency in the delivery of services enabling payments to be more closely linked to delivery of quality outcomes. • Increasing Contract Management. We have increased resources and capability within the Transport team to match both the increased internal management required for unbundled contracts and to improve monitoring to ensure the service output levels are being achieved. • Ensuring our procurement processes adequately account for non-price attributes. The overall unbundling should also support competitive markets – different contractors may pick up portions of the work – rather than having one Contractor dominate. This unbundling and greater financial control de-risks the contract pricing for both the Council and Contractors and should provide greater transparency. Our approach also has been to take into account NZTA’s objectives of obtaining best value for money, obtained by fair competition and encouraging competitive and efficient markets. Roading Procurement Strategy October 2019 18
Detailed programme and procurement approach Based on the contracting strategy above, the following table summarises the procurement project by segment, the nature of the activities, bundling of contracts, delivery models and selection methods, and the impact on NZTA objectives. Roading Procurement Strategy October 2019 19
Contracted Works Segments Inclusions Existing Procurement basis Selection & Contracting Meeting NZTA Procurement and value1 Contracts Approach Objectives Major capital Link roads, traffic Let by Project Delivery model – Generally NZTA Price Open tendering achieving good value (circa $6m in safety mostly staged2. Some Quality Method. and fair competition. the next 2 enhancements etc. Contract value generally smaller years following varies from year projects let as design Small (
Contracted Works Segments Inclusions Existing Procurement basis Selection & Contracting Meeting NZTA Procurement and value1 Contracts Approach Objectives Road Footpath and Current Contract Delivery model staged. NZTA Price Quality Method Achieving good value by providing maintenance pavement repairs, expires June (PQM), incorporating an certainty for a contractor and working (circa $2m Drainage 2020 By Medium term Engineers Estimate, and a through integration with Council annually) maintenance Contract (3+1+1) Schedule of Prices (SoP) for processes/asset information and a transparency. focus on maintenance outcomes. NZS3917: 2013 as a base document. Reference to all appropriate NZTA technical standards with a technical and performance specification developed from good practice. Professional A Professional Professional Delivery model mostly Will retender with a Achieving good value by reducing services Services Contract Services Contract staged for technical weighted attribute model. transaction cost of each service (circa $0.6m provides the basis for three years support. In-house appointment being tendered. annually but for the majority of runs through to expertise maintained Ongoing direct appointment Transparency through the higher with this professional 30 September for planning and for specific technical advice. Professional Services Contract. design works) support. 2020 with a decision-making, possible contract management ACENZ contract form will For small works avoid cost of Additional low value extension of 2 etc. as per current. generally be used. tendering through direct appointment. specific works (e.g. further years. design works) may Will retender the be procured directly Professional Services from the Contract either at the Professional end of the term of the Services Contract or extension period. from providers directly. May also appoint technical professional services directly as per the NZTA procurement manual and in Roading Procurement Strategy October 2019 21
Contracted Works Segments Inclusions Existing Procurement basis Selection & Contracting Meeting NZTA Procurement and value1 Contracts Approach Objectives accordance with Council’s procurement policies. Ancillary Vegetation Control, Most expire June Delivery model staged. Generally weighted Transparency as these are usually services Street light 2020 attributes delivered by specialist (Circa $0.5m maintenance, traffic Each service by subcontractors. annually) counting etc. Vegetation medium term contract NZS3917: 2013 or bespoke control – generally open service-based contracts. value less than market (smaller $200k contracts less than $200k may be through closed contest) Traffic signals Porirua is a party Tendered regionally as NZTA methodologies Competitive markets by retaining two operations & to a Wellington a staged delivery different contractors in the market. maintenance Regional model at the same Transparency through a regional Services Contract time as WCC – with agreement. with NZTA and different contractors other regional for each portfolio. TA’s bar WCC. Minor value Roading Procurement Strategy October 2019 22
Simplified Programme timeline The following shows the simplified timeline for procurement, with considerable activity in Q4 of 2019 and early in 2020 to implement new contracts. 2019 2020 2021 2022 Simplified Programme Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Current Maintenance and Reseals Contract Roading Maintenance Contract Tender period and award Tender Contract New Contract Ongoing -> 2023 + 1 +1 Renewals & reseals Programme Tender Tender Tender Y2 Tender Y3 Programme of works Year 1 Year 2 Annual Capital Tender period and award Contract Various dates Various dates Vegetation Control Tender Contract Ongoing -> 2023 + 1 +1 Streetlight maintenance Tender Contract Ongoing -> 2023 + 1 +1 Professional Services Current Contract Current Contract Extension period New Contract Tender 4.2 Unusual/Advanced procurement No unusual procurement or advanced procurement activity is planned at this stage. Roading Procurement Strategy October 2019 23
5. IMPLEMENTATION 5.1 Capability and Capacity - general Council has recently reviewed and refreshed its staffing structure. There have been improvements in the oversight and staffing of the transport group to give better focus and continuity to the overall transport program. Appendix 1 outlines the new structure. This structure should provide sufficient capability and capacity to ensure Council can implement the procurement programme in conformance with NZTA requirements. 5.2 Internal Procurement Processes Council has a comprehensive procurement policy aligned with the Government Procurement Rules and uses GETS extensively. The Procurement Committee is the internal governance group accountable for the procurement policies and processes. It oversees all procurement plans and all procurement over the value of $100,000 as high risk procurement. All of these must go to the Procurement committee to be vetted and signed off for publishing and then for the contract to be signed. This is to mitigate any unforeseen risks in these larger, and/or higher risk, contracts and projects. Council’s procurement team provide the overall framework for procurement with the Transport Team providing the specific transport technical knowledge and evaluative expertise. Each teams’ accountabilities and responsibilities are summarised below: Procurement Team Transport Team Accountabilities • Procurement • Overall Transport Framework Procurement activity • Ensure Procurement • Funding arrangements with Committee oversight. NZTA • Procurement in accordance with NZTA. Responsibilities • Project management • Specific technical expertise support where required for projects • GETS coordination • NZTA approved procurement • Monitoring and plans Reporting procurement • NZTA approved evaluator/s. activities • Contract Register. Following from the NZTA audit in late 2019, Council ensures that it has NZTA approved evaluators on all evaluation panels and is using current versions of all NZTA documents for evaluation purposes. Roading Procurement Strategy October 2019 24
5.3 Performance Measurement and Monitoring The following will be undertaken to measure and monitor this procurement strategy: • Performance measures as listed in section 2.1.4 will be annually reviewed and reported. • Each major procurement exercise is monitored by the Procurement Committee through its procurement plan through to reported results to ensure fair competition, and value for money and competitive markets. • This Procurement Strategy is reviewed every three years. 5.4 Communication Plan The procurement strategy will be communicated through the following media: • On the intranet for internal stakeholders • On the internet for external stakeholders • GETS • Direct email to neighbouring territorial Local Authorities and NZTA • As part of the Activity Management Plan process. Roading Procurement Strategy October 2019 25
APPENDIX 1 – COUNCIL TRANSPORT STRUCTURE Roading Procurement Strategy October 2019 26