Thursday 3 September 2020 6:00pm Council Chamber 37 Ayr Street Ohakune

Page created by Edith Butler
 
CONTINUE READING
Thursday 3 September 2020 6:00pm Council Chamber 37 Ayr Street Ohakune
Thursday
3 September 2020
         6:00pm

Council Chamber
   37 Ayr Street
        Ohakune
Thursday 3 September 2020 6:00pm Council Chamber 37 Ayr Street Ohakune
WAIMARINO-WAIOURU COMMUNITY BOARD

                             NOTICE OF MEETING

A MEETING OF WAIMARINO-WAIOURU COMMUNITY BOARD WILL BE HELD AT THE
              COUNCIL CHAMBER, 37 AYR STREET, OHAKUNE
               ON THURSDAY 3 SEPTEMBER 2020, AT 6:00PM

Members

Chairperson:                John (Luigi) Hotter
Board Members:              Allan Whale
                            Cynthia Dowsett
Councillors:                Rabbit Nottage
                            Vivienne Hoeta
Councillors (non-voting):   Ben Goddard
                            Elijah Pue
Mayor (non-voting):         Don Cameron

Clive Manley
CHIEF EXECUTIVE
Thursday 3 September 2020 6:00pm Council Chamber 37 Ayr Street Ohakune
Roles and Powers of Community Boards

The Community Board has already been delegated the task of co-ordinating rural reserves and hall
committees. It also has a major input into the development of Council’s Long Term Plan.

The Community Board’s prime objective is to be the interface between Council and the ratepayers
and public of the Ward.

Role of Community Boards
The role of a Community Board is to (Section 52 Local Government Act 2002 [LGA]):

(a)    Represent and act as an advocate for the interests of the community.
(b)    Consider and report on all matters referred to it by the territorial authority, or any other
       matter of interest or concern to the community board.
(c)    Maintain an overview of services provided by the territorial authority within the community.
(d)    Prepare an annual submission to the territorial authority for expenditure within the
       community.
(e)    Communicate with community organisations and special interest groups within the
       community.
(f)    Undertake any other responsibilities that are delegated to it by the territorial authority.

Powers of Community Boards
A Community Board shall perform such functions and duties and exercise such powers as are
delegated to it by Council from time to time.

Powers of Community Boards (Section 53 – LGA):
1     A community board has the powers that are:
      (a) Delegated to it by the relevant territorial authority in accordance with Clause 43 of
           Schedule 7 of the LGA.
      (b) Prescribed by the Order in Council constituting its community.
2     The powers of a Community Board prescribed by Order in Council expire at the close of six
      years after the Order comes into force.
3     Despite subsection (1), a community board may not:
       (a) Acquire, hold or dispose of property.
       (b) Appoint, suspend or remove staff.

Powers Delegated to the Community Board by Council
• The co-ordination of rural reserves and hall committees.
• To allocate the approved budget for the following activities in the area:
   Footpaths programme;
   Parks and Reserves discretionary spend;
   Public information signage.
• To approve:
   Temporary road closures for events (subject to administrative imperatives);
   Street names;
   Parades, collections and special uses of the roads;
   Changes to speed restrictions on local roads (subject to NZTA rules);
   Road closures.
Thursday 3 September 2020 6:00pm Council Chamber 37 Ayr Street Ohakune
WAIMARINO-WAIOURU COMMUNITY BOARD
                                         ORDER PAPER

A MEETING OF WAIMARINO-WAIOURU COMMUNITY BOARD WILL BE HELD AT THE
              COUNCIL CHAMBER, 37 AYR STREET, OHAKUNE
               ON THURSDAY 3 SEPTEMBER 2020, AT 6.00PM

                                       PUBLIC BUSINESS

                                                                             Page

1   Apologies

2   Declarations of Interest:
    Notification from Elected Members of:
    2.1 Any interests that may create a conflict with their role as an
    elected member relating to the items of business for this meeting;
    and
    2.2 Any interests in items in which they have a direct or indirect
    pecuniary interest as provided for in the Local Authorities (Members’
    Interests) Act 1968

3   Public Forum: Temporary Suspension and Reinstatement                         5
    of Standing Orders

4   Confirmation of Minutes: 6 August 2020                                   6 - 10

5   Long Term Plan 2021-2031 Progress Report                                11 - 12

6   Capital Works and Members Request for Information                       13 - 26

    PUBLIC EXCLUDED BUSINESS

7   Resolution to Exclude the Public for Consideration of                       27
    Board Business
Thursday 3 September 2020 6:00pm Council Chamber 37 Ayr Street Ohakune
5

 Report to: Waimarino-Waiouru Community Board

 Meeting Date:    3 September 2020

 Subject:         Public Forum: Temporary Suspension and
                  Reinstatement of Standing Orders

Purpose of Report
1.1    The purpose of this Report is to enable the Board to temporarily suspend Standing Orders
       in their entirety to allow Members and the Public to address the Board.

Significance and Engagement

2.1   There is nothing in this Report that triggers the Significance and Engagement Policy.

Public Forum Guidelines
3.1    The Community Board has adopted the following Public Forum Guidelines:
       (a) Five minutes speaking time will apply to each speaker or group.
       (b) Members of the public wishing to speak must advise the Community Board of the
            reasons and subject he/she wishes to address the Board a minimum of two clear
            working days prior to the meeting.
       (c) The Chair may refuse applications which are repetitious or offensive and may
            terminate a speaker in progress where the subject matter is disrespectful or offensive.
       (d) There are not to be criticisms of individual Board members or individual staff
            members.
       (e) The Public Forums are designed for people to speak about matters of interest to them
            to the Community Board. It is not intended that people should be questioning Board
            members on these occasions. However, Board members may ask questions of
            speakers to clarify their statements.

Suggested Resolution(s)
1     That the Report on Public Forum: Temporary Suspension and Reinstatement of Standing
      Orders be received.

2     That, pursuant to Section 27(4) Schedule 7 of the Local Government Act 2002, the Board
      temporarily suspends Standing Orders in their entirety to allow Members and the public to
      address the Board.

      The Board received addresses as follows:

      RESOLVED

      That, pursuant to Section 27(4) Schedule 7 of the Local Government Act 2002, the Board
      reinstates Standing Orders in their entirety for consideration of the agenda.

Liana Mua
GOVERNANCE OFFICER
Thursday 3 September 2020 6:00pm Council Chamber 37 Ayr Street Ohakune
Unconfirmed                                    6                       Unconfirmed

             WAIMARINO-WAIOURU COMMUNITY BOARD
                                          MINUTES

    A MEETING OF WAIMARINO-WAIOURU COMMUNITY BOARD HELD AT THE
             RAETIHI CHAMBERS, 44 SEDDON STREET, RAETIHI
                 ON THURSDAY 6 AUGUST 2020, AT 6.00PM

                                       PUBLIC BUSINESS

Present

Board Members: John (Luigi) Hotter
               Cynthia Dowsett
               Allan Whale

Councillors:       Vivienne Hoeta
                   Rabbit Nottage

Councillors:       Ben Goddard
(Non-voting)       Elijah Pue

Mayor:             Don Cameron
(Non-voting)

Staff:             Pauline Welch         Group Manager, Customer Services
                   Warren Furner         Economic Development Manager
                   Stuart Watson         Projects, Environmental Services
                   Liana Mua             Governance Officer

In attendance:       Trevor Carswell
                     Alistair Barber
                     Daniel Schlumpf

1        Apologies

         No apologies were received.

2        Declarations of Interest

         Councillor Nottage declared an interest in items 6 and 8.
Thursday 3 September 2020 6:00pm Council Chamber 37 Ayr Street Ohakune
Unconfirmed                              7                           Unconfirmed

3   Public Forum: Temporary Suspension and Reinstatement of Standing Orders

    The Board Temporarily suspended Standing Orders in their entirety to allow Members
    and the public to address the Board.

    RESOLVED
    Moved: Whale
    Seconded: Cr Hoeta

    1       That the Report on Public Forum: Temporary Suspension and Reinstatement
            of Standing Orders be received.

    2       That pursuant to section 21(4) Schedule 7 of the Local Government Act 2002,
            the Board temporarily suspends Standing Orders in their entirety to allow
            Members and the public to address the Community Board.

    Received addresses as follows:

        •   Geoff Anderson:
               o Updated members on the Raetihi Promotions Charitable Trust.
               o Commended Warren Furner’s efforts in securing funding for the Raetihi
                   Information Centre and thanked the Mayor and Councilor Goddard.
               o Expressed his enthusiasm in contributing to the Long Term Plan and
                   receiving a report on the Raetihi Swimming Pool and Security Cameras.
               o Spoke about the Christmas parade and encouraged volunteers to come
                   forward.

        •   Daniel Schlumpf:
               o Presented the Petition for Reducing Speed limit to 50KM for the
                   Mangawhero River Road to members.

        •   Cr Goddard:
               o Updated members on the recent meeting held in Waiouru with Bruce
                  Francis where they flew a drone to identify a safe passage crossing on
                  SH1.

        •   Mayor Cameron:
               o Updated members on the reinstatement of the Northern Explorer which
                  will be heavily subsidized.

        •   Cr Nottage:
               o Expressed his concerns around rubbish remaining on the roads as
                   Envirowaste do not pick anything up once it falls from their trucks.
               o Requested information on street sweeping and the levels of service for
                   drain clearing.

    RESOLVED
    Moved: Whale
    Seconded: Dowsett

    That, pursuant to Section 27 (4) Schedule 7 of the Local Government Act 2002, the
    Board reinstates Standing Orders in their entirety for consideration of the Agenda.
Unconfirmed                              8                            Unconfirmed

4   Deputation: Trevor Carswell and Victoria Main, Club Targa Incorporated

    Trevor Carswell from Club Targa Incorporated dialed in to speak about the Silver Fern
    Rally and answer any queries and or concerns that members had.

    RESOLVED
    Moved: Whale
    Seconded: Cr Hoeta

    That the report on Deputation: Trevor Carswell and Victoria Main, Club Targa
    Incorporated be received.

5   Confirmation of Minutes: 2 July 2020

    RESOLVED
    Moved: Dowsett
    Seconded: Whale

    That the minutes dated 2 July 2020 be confirmed as a true and correct record.

6   Ohakune to Raetihi Walk and Cycle Way Proposal

    Members considered a report seeking their endorsement of the Ohakune 2000
    proposed Walk & Cycle Way Ohakune-Raetihi, to enable it to be submitted to Council
    as a part of the Long Term Plan 2021-2031. It was agreed that key interest groups
    such as Raetihi Promotions Charitable Trust, Uenuku and Ngāti Rangi should be
    consulted before the proposal is taken any further.

    RESOLVED
    Moved: Dowsett
    Seconded: Cr Hoeta

    1      That the report on Ohakune to Raetihi Walk and Cycle Way Proposal be
           received.

    RESOLVED
    Moved: Cr Hoeta
    Seconded: Dowsett

    2      That the Waimarino-Waiouru Community Board supports this plan in principle,
           subject to further detailed design and landowner consent.
Unconfirmed                              9                           Unconfirmed

7   Ohakune Mardi Gras 2020: Proposed Road closure update

    Members received a report on the progress of the proposed Road Closure application
    for the Ohakune Mardi Gras 2020. Alistair Barber from Audiology was in attendance to
    answer any questions or queries members had.

    RESOLVED
    Moved: Dowsett
    Seconded: Whale

    That the report on Ohakune Mardi Gras 2020 – Proposed Road closure update be
    received.

8   Annual Tree Programme South 2020/21

    Members were informed of planned tree work in Raetihi and Ohakune for the
    2020/21 financial year and worked their way through the tree programme with staff.

    RESOLVED
    Moved: Whale
    Seconded: Dowsett

    1      That the Report on Annual Tree Programme South 2020/21 be received.

    RESOLVED
    Moved: Whale
    Seconded: Dowsett

    2      That the Waimarino-Waiouru Community Board approves the 2020/21 planned
           tree work for Raetihi and Ohakune, as amended, including Christie Park as
           discussed, pending documentation from Council.

9   Waimarino-Waiouru Citizens Award 2020

    Members received a report informing them on the process for receiving nominations
    from organisations and individuals for selecting a citizen whom has made an
    outstanding contribution to the general well-being of the area.

    RESOLVED
    Moved: Dowsett
    Seconded: Whale

    That the report on the Waimarino-Waiouru Citizens Award be received.
Unconfirmed                                10                            Unconfirmed

10     Capital Works and Members’ Requests for Information

       Members considered a report on Capital Works and Members’ Requests for
       Information. Relevant staff spoke to the report and answered members’ questions
       around a number of items.

          •   It was agreed that Managers would be asked to remove any items that have
              been completed and to include specific completion dates.
          •   R4 - Ruapehu Road Rail Overbridge – landowners will be sent a reminder letter
              around the weight restrictions.
          •   Members have requested an update to O3 - Security Cameras.
          •   A request was made for investigation/information on the heavy truck parking in
              Waiouru and a possible dedicated truck park area working with NZ Rail.
          •   A request was made for investigation/information on the rubbish at the BP
              Truck Stop and back streets of Waiouru.

      RESOLVED
      Moved: Whale
      Seconded: Dowsett

      That the Report on Capital Works and Members Requests for Information be received.

11     Resolution to Exclude the Public for Consideration of Committee Business

       It was agreed that there was no need to enter into Public-Excluded Business and
       therefore this item was not taken.

There being no further business, the meeting concluded at 8:14PM.

Dated at Ohakune this 3rd day of September 2020.

John Hotter
CHAIRPERSON
11

 Report to: Waimarino – Waiouru Community Board

 Meeting Date:     03 September 2020

 Subject:          Long Term Plan 2021-31 Progress Report

Purpose of Report
1.1     The purpose of this report is to update the Waimarino - Waiouru Community Board (WWCB)
        on the progress of the Long Term Plan 2021-31.

Significance and Engagement, Social Impact
2.1     SIGNIFICANCE
        This report does not trigger the Significance and Engagement Policy.

2.2     SOCIAL IMPACT
        This report does not trigger the Social Policy.

Background
3.1     Every three years Council reviews its Long Term Plan (LTP), as per the Local Government
        Act 2002 (LGA).

3.2     Reviewing the LTP every three years gives Council the opportunity to review their strategic
        direction and to assess whether they are satisfied with the current direction or if change is
        needed.

3.3.    It also provides the same opportunity to Councils community members to give feedback on
        the direction of the district, and in particular their communities.

Discussion
4.1     Council staff have been working on developing the LTP and other planning documents as
        part of the process, e.g. Asset Management Plans (AMPs) and reviewing financial policies.

4.2     Currently, council staff have been holding workshops with elected members and community
        board members to discuss the core business functions of Council and to decide the strategic
        direction elected members would like to focus on.

4.3     Pre-engagement with community members has also been taking place via public meetings
        and online. This is an opportunity for community members to give feedback, possible
        projects and ideas on what they would like to see council focus on in their communities.
        Community members are encouraged to provide feedback with any idea, big or small.

4.3.1   This pre engagement feedback will be collated and submitted to elected members for
        consideration.

4.4     Once workshops are completed, council staff will collate all the information to create first
        AMPs, reviewed financial policies, the LTP and the Infrastructure and Financial Strategies.
12

4.4.1   Through this process Council will also identify the key issues, ideas or projects that will need
        to be incorporated into the consultation document.

4.4.2   The above documents mentioned in 4.4.1 and 4.4.2 will all be collated and adopted through
        Council for formal consultation. Other strategies or policies may also need to be created for
        consultation.

4.5     Community board members are able to give feedback and input at the workshops.

4.5.1   WWCB will be presented with the pre-engagement information that is related to their
        communities.

4.5.2   WWCB is able to submit to the pre-engagement phase of the process on behalf of its
        communities as well as the formal consultation process.

4.6     WWCB will be informed and kept updated on the progress of the LTP.

Suggested Resolution(s)
That the Long Term Plan Progress report be received.

Candice McNaught
TEAM LEADER POLICY

Email address for point of contact: Pauline.Welch@ruapehudc.govt.nz
13

 Report to: Waimarino-Waiouru Community Board

 Meeting Date:      3 September 2020

 Subject:           Capital Works and Members' Requests for Information

Purpose of Report
1.1      The purpose of this Report is to provide an update on the planned capital works and other
         items of interest in the Waimarino-Waiouru Community Board area in 2020/21.

Significance and Engagement
2.1     This report does not trigger the Significance and Engagement Policy.

Discussion
3.1      WORKS

3.1.1    The list is a combination of contracted items and other items that Members have displayed
         an interest in. Other items can be added to the list on request.

3.2      ROADING

                  Subject          Action taken                                                  Target
                                                                                                 Completion
          R1      Mangateitei      Design underway, Kiwi Rail approval in principle has           June 2022
                  Railway Over     been received. Land owner agreement achieved for
                  Bridge           proposed alignment.
                                   We applied to do this work under the Low cost low risk
                                   category in the 2018/21 Block. NZ Transport Agency
                                   advised in late June 2018 that the project did not
                                   receive funding in the Block, but that we have the
                                   option to reallocate our existing LCLR budget for it. We
                                   re-inspected the bridge and found it is suitable for work
                                   to be deferred until 21/22.
                                   Any opportunity to advance the project using unspent
                                   funding elsewhere in our NZTA region will be pursued,
                                   but this has a low likelihood of success.
                                   In the meantime, Kiwirail permission to work around
                                   the lines is being sought through a Grant of Right
                                   application. This was submitted in October 2019 and
                                   we are actively chasing it up.
                                   This has been included in the Crown Infrastructure
                                   Fund Shovel ready application.
          R2      Pavement         Rimu Street seal extension: Earthworks for Rimu                June 2021
                  Rehabilitation   Street seal extension will be carried out in this financial
                                   year, after being deferred from 2019/20.
14

     Subject          Action taken                                                Target
                                                                                  Completion
                      Ohakune Mountain Road RP 13km: The hairpin                    February
                      grade realignment on Ohakune Mountain Road has                  2021
                      been completed with a temporary seal, due to Covid-
                      Level 4. This will be completed permanently when the
                      weather allows between December 2020 and February
                      2021.

R3   Wilding          Council will be carrying out some tree removal with the      June 2021
     Vegetation       Worker redeployment funding approved from the
                      Provincial Development Unit throughout the District.

R4   Ruapehu          Deferred till 2021/22. Funding will be applied for in the    June 2022
     Road Rail        next Waka Kotahi New Zealand Transport Agency
     Overbridge       funding block. It was included in our Crown
                      Infrastructure Fund shovel ready application.
                      Bridge is being regularly inspected.
                      As per requested at August meeting, a letter drop is
                      being carried out to remind landowners of the current
                      weight restriction.
R5   Matahiwi         16 T GVM suspension requires upgrading for Atihau             On Hold
     Bridge           forest harvest. Investigation beginning to secure
                      advanced funding for the project as a regional
                      improvement project. Awaiting funding approval from
                      NZ Transport Agency. Funding not approved by NZ
                      Transport Agency in late June 2019. Project on hold
                      while alternative funding sources are sought.
                      Negotiation between NZTA and Atihau now
                      progressed as part of SH 4 realignment options. This
                      project has been included in the Crown Infrastructure
                      Fund shovel ready project application.
R6   Minor            Clyde’s Access and Makino Road intersection and              June 2021
     Improvements     bridge approach to be sealed over summer.
R7   Crossing         Following on from the drone flight over State Highway        Meeting –
     points, State    1, four potential crossing points were identified. These     September
     Highway 1,       have been forwarded to Waka Kotahi for                         2020
     Waiouru          consideration. The meeting with the Safety Manager
                      will take place later in September. Initial feedback is
                      that two sites would be the ideal number.

                      The lockdowns are affecting income for Waka Kotahi
                      as road user charges and petrol tax income have
                      dropped significantly. This has meant that the Low
                      Cost low risk programme is reduced significantly,
                      affecting this work.

R8   Speed limits –   Ohakune                                                      Consultation
     Waiouru and      Extension of 50km/hr speed limit on SH49 east of            for Waiouru –
     Ohakune          Ohakune to the Carrot Park is high on Waka Kotahi’s           likely to be
                      priority list.                                              early in 2021

                      Waiouru
                      Waiouru speed limit on State Highway 1 through the
                      town area is also high on Waka Kotahi’s priority list and
                      is likely to be put out for consultation early next year.
R9   Pipiriki Speed   Item requested by members at July meeting. Speed             September
     bump             counters have been in place and we are awaiting a              2020
                      report recommending a course of action.
15

              Subject         Action taken                                                 Target
                                                                                           Completion
      R10     Waiouru         Member’s request to consider providing for trucks that         Funding
              Truck Parking   park in Waiouru off Rangipo Street. Officers are               request –
                              considering the idea of including this as a project in the    June 2021.
                              Long Term Plan 2021/31, with investigation funding in
                              2021/22. Project would likely need to be funded with a
                              partner.

3.3   ENVIRONMENTAL

            Subject           Action taken                                                    Target
                                                                                              Completion
      E1    Flood Modelling   Horizons Regional Council have commenced their meeting          June 2021
            River Works       with key stakeholders. Council and Horizons have agreed
                              to have a regular meeting around drainage issues to look
                              at opportunities to collate our responses. Two such
                              meetings have been held between Council. Awaiting
                              response from Horizons. Waters Manager has a site
                              meeting with Horizons 22 June 2020.
      E2    Government        RDC has submitted an application to the new Government          June 2021
            Freshwater        Freshwater Improvement Fund for the upgrade of Ohakune
            Improvement       and Raetihi Wastewater Treatment Plants (WWTPs), and
            Fund              for support of the Whangaehu Catchment Accord (a group
                              established to protect and enhance the Whangaehu water
                              catchment). RDC is one of many applicants from around
                              the country. The catchment was successful at getting
                              some funding through the Regional Council. The Nga Wai
                              Ora O Te Whangaehu Freshwater Improvement project will
                              cost $1.68 million, with $590,000 secured Freshwater
                              Improvement Funding from MFE over three years: for 60
                              km fencing to prevent stock access, riparian planting of
                              12,000 native plants, five fish pass repairs and 10
                              community-led restoration projects. Horizons have signed
                              with the government to uplift the money and spend it over
                              the next three years. The Government agreement requires
                              a governance group and Mayor Don Cameron is council’s
                              representative on this group. The quality of the project was
                              very high and they had some ambitious goals. The
                              governance group met and allocated funding to community
                              groups against their criteria. The first governance reports
                              have been submitted to MFE and expected targets have
                              been met. Ruapehu continues to co-ordinate the wider
                              Whangaehu Catchment group and are gathering
                              information around works being undertaken in the
                              catchment. A Governance meeting which covered the
                              actions against targets for Riparian fencing, planting, fish
                              pass improvements and community projects. Projects goal
                              appear to be on track. The work programmed has been
                              split across three years so there remain opportunities for
                              more work across all the categories so please spread the
                              word to those who might wish to participate. In general the
                              works programme is being delivered to budget.
      E3    Visitor           Council has sought funding for a feasibility study of a joint   June 2021
            Infrastructure    wastewater treatment plant between Ohakune and Raetihi
            Funding           with Land passage. This will provide for the increasing
                              environmental requirements being signalled by the
                              Government. The feasibility study funding has been
                              accepted by Government. At this stage, funding has been
                              allocated for GHD to undertake a feasibility study for a
                              combined WWTP for Raetihi and Ohakune.
16

           Subject         Action taken                                                    Target
                                                                                           Completion
      E4   Ohakune Water   Council is seeking new money to fund increase in capacity       June 2021
           Intake          which is out for public consultation. Also Council has
                           applied to the Tourism Infrastructure Fund for the funding
                           part of the plant. Council has secured funding and has
                           consulted with the Community as part of the requirements.
                           The first stage of planning for the upgrade of the Ohakune
                           Water Treatment Plant has commenced with GHD drawing
                           up a procurement plan. Veolia to develop and design. A
                           site visit to the Ohakune raw water intake site was planned
                           for 30 April with Iwi representatives however this has been
                           changed to an online meeting. Construction has not
                           started. Site visit this month (May 2020) to Ohakune Water
                           Intake with Council, Iwi and GHD. Adhering to social
                           distancing guidelines with group size restricted to 10, no
                           shared food and separate vehicles. Comments made in
                           the Environmental Assessment indicate the design and
                           location of the raw water line requires further understanding
                           of the significance that Tongariro National Park is a world
                           heritage site. Next Project Steering Group meeting
                           scheduled for 4 August with progress report #2 due to MBIE
                           on 31 August.
      E5   New Zealand     The New Zealand Defence Force in Waiouru is also                June 2021
           Defence Force   working toward a new Water Safety Plan and Council has
                           been invited to assess its risk matrix development,
                           providing input around the Waiouru township reticulation
                           works. Council attended a meeting in December to further
                           the water safety plan and discuss general works between
                           the organisations. High-level discussions around levels of
                           service for the whole community of Waiouru (public and
                           army) were held. NZDF are in the process of seeking a
                           new resource consent for the abstraction of water. Council
                           is providing assistance with this process. Pattle Delamore
                           Partners are working with NZ Defence Force on upgrades
                           to the water supply network and water treatment plant at
                           the Waiouru Military Base. The work is in the preliminary
                           design stage and includes a second outflow from the base
                           water treatment plant to the township that increase
                           redundancy and security of supply. A replacement water
                           meter to be installed on the outflow of the WTP. The NZDF
                           also intend to upgrade their WWTP.

3.4   COMMUNITY PROPERTY
            Subject        Action taken                                                    Target
                                                                                           Completion
      C1    Re-pile        Soil test shows that re-piling will require much deeper         July 2022
            Ohakune        foundations than existing, work will now consist of subfloor
            Railway        bracing and fireplace removal or strengthening in line with
            Station        earthquake assessment recommendations.             Awaiting
                           advice from Heritage New Zealand. Cost to do the work is
                           more than the budget, report to go to Council to make a
                           decision on the work required. Further information is being
                           sought regarding work required to bring building up to 34%
                           New Building Standards (NBS) or 67% NBS to inform
                           report. A proposal by AECOM for a detailed seismic
                           investigation to be carried out on the Railway Building has
                           been received for consideration. It is proposed to seek
                           feedback from the community on the future of the building
                           due to the indicative high cost of remedial work and seek a
17

Subject   Action taken                                                  Target
                                                                        Completion
          recommendation to Council from the Board at its August
          meeting. A report will be presented at the August WWCB
          meeting for a recommendation to Council as to whether the
          Community Board wish to see the building upgraded to
          meet new building standards as defined by the Building Act.
          The community has been made aware of the issues facing
          the Ohakune Railway Station Building on Council
          Facebook page. Report went to Council on 12 September
          to request funds be spent on detailed seismic assessment.
          Council resolved to seek approval from Heritage NZ for the
          permanent removal of the chimneys. Letter to Heritage NZ
          has been sent. A detailed seismic assessment was also
          approved to be undertaken. This will be requested once a
          response from Heritage NZ is received around the
          chimneys.       Heritage NZ has responded with a
          recommendation for the chimneys to remain and be
          strengthened. Council will now arrange for a detailed
          seismic assessment to be undertaken. Engineering firm to
          undertake site inspection before end of November.
          Engineering staff from Miyamoto International NZ Ltd have
          inspected the site and are in the process of undertaking a
          Detailed Seismic Assessment (DSA). DSA report received
          from Miyamoto. Some points to be clarified before
          progressing further. Awaiting clarification from Miyomoto.
          Response received from Miyomoto and Council
          considering information and next step. Miyomoto
          proceeding with estimate of costs for concept
          strengthening design. Quote received for detailed design
          however will await costs for strengthening before
          proceeding. Strengthening estimate received and being
          taken to management to consider next steps. Following
          Miyomoto checking status of platform canopy connections
          and piles in the first week of September a report will be
          prepared to update WWCB. Miyomoto has reported that the
          existing connections between the platform canopy and
          main building are satisfactory however may require some
          minor maintenance. The building piles, in their opinion, do
          not require any replacement however connections do need
          to be put in place between the piles and the bearers.
          Council awaits an updated strengthening price estimate
          based on the above observations. Advised that cost for
          connection of piles will have minimal effect on
          strengthening price estimate. Report to be provided at
          future meeting to update WWCB on findings. Miyamoto
          have submitted revised DSA and updated strengthening
          price estimate. Working through final queries with
          Miyamoto with aim to have report to WWCB in June. The
          DSA has been passed on to Heritage NZ for comment.
          Communication to KiwiRail has requested whether they will
          contribute to costs of strengthening the rail platform
          canopy, which is owned by them. Miyamoto have been
          asked for costs for an alternative option to lightweight
          replicas to complete information on strengthening options
          for the chimneys. Council has delayed the report to WWCB
          until these parties have responded. Heritage NZ has
          recommended Council engage the services of a
          Conservation Architect to work with Miyamoto on a suitable
          method for strengthening the chimneys. A Conservation
          Architect has been contacted and a cost estimate to get to
18

     Subject          Action taken                                                   Target
                                                                                     Completion
                      the detailed design phase provided. Contact has been
                      established with KiwiRail. Architect has completed a review
                      of the station building and now working with Miyomoto on a
                      strengthening concept in line with the heritage values for
                      the building. Site visit arranged for beginning of August.
                      Site visit by Miyomoto has found spiral chimney
                      strengthened following fire in 2006 does not meet
                      earthquake standards and therefore will require further
                      strengthening work. Variation provided to Council for
                      additional cost for this work.
C2   Raetihi          Contact is being made with all known interest groups with      July 2023
     Revitalisation   a request for information on projects that have either been
     Project          identified but yet to be funded and progressed, or that have
                      been started. This will provide a better understanding of
                      who is doing what and where assistance from
                      Council/Community Board can be delivered to support
                      these community initiatives.
C3   Ohakune          Budget of $30,000 for either seed funding for bigger           July 2025
     Swimming         community project or an upgrade of existing facilities.
     Pool Ablutions   Report to be brought to WWCB in future months. WWCB
     Block            approved use of budget as seed funding for larger upgrade
                      to Ohakune pool complex on 7 March 2019. Decisions for
                      what this will include awaiting outcome of Ohakune town
                      assessment. Ohakune 2000 Inc. meeting with Council mid-
                      June to engage in Town Assessment. Council contracted
                      pool operators, Community Leisure Management (CLM),
                      have offered to meet with both Ohakune and Raetihi
                      community representatives and develop concept plan for
                      both pools. CLM met on site with both Raetihi and
                      Ohakune community groups and are in the process of
                      putting together a feasibility plan for development of both
                      pools. CLM are making good progress with the
                      development of proposals for the future of the Ohakune &
                      Raetihi pools. There has been extensive consultation with
                      interests in both towns including community, business and
                      iwi groups as well as the immediate neighbours in
                      Ohakune. Some clear ideas about the future of each facility
                      have been developed, which now need to be aligned with
                      other proposals, (in Raetihi), and expressed in concept
                      form. Elements of a draft feasibility have been prepared,
                      but preliminary design and costing work is required to
                      complete this. Lines Company replacement of old power
                      meter has highlighted issue with safety of wiring in
                      switchboard. Electrical quote being sought to replace
                      switchboard.
C4   Parapara         Budget available of $10,000 to be allocated by WWCB after      July 2021
     Road Reserve     discussions with community.             Raetihi Promotions
     Development      presented WWCB with a project proposal for using
                      available funding for a cultural gateway entrance to the
                      Makotuku Walkway. The proposal was approved subject
                      to a plan being provided to WWCB for funding required to
                      complete the project. Seeking further information from
                      Raetihi Promotions to inform report to enable final decision
                      prior to end of financial year. Council has agreed to carry
                      over funds to next financial year to enable more time for
                      further funding to be found and proposal to be confirmed.
C5   Tangiwai         Budget of $15,000 for the ongoing development of the           July 2023
     Reserve          reserve, as required by the Tangiwai Committee. A series
     Development      of meetings have been held to discuss landscape designs.
19

     Subject          Action taken                                                         Target
                                                                                           Completion
C6   Park Ave         There is an opportunity to develop a stormwater retention            July 2021
     Reserve          area on the Park Avenue Reserve area. This will be
                      developed in conjunction with HRC flood evaluation works,
                      stormwater models and engagement of what the
                      community wish to see around stormwater. A report will
                      then be brought to Community Board and Council. Council
                      has requested information from Horizons on this project.
C7   Raetihi          Site meeting held on 17 July 2019 to go over complaints              July 2021
     Holiday Park     and outstanding issues from the construction. List of issues
     Ablution Block   being worked through by staff. Fortnightly meetings set to
                      progress number of actions being addressed. Plumber and
                      Builder engaged to address number of smaller issues
                      around door handles and taps. The taps in the public toilets
                      have been changed to timer taps to ensure taps are not left
                      running using the hot water and causing additional
                      expense. Toilet consumable units in the Holiday Park
                      ablution block have been fastened to the wall with screws
                      to ensure they remain in place. Having the gas setup made
                      compliant has been prioritised and a quote has been
                      received to undertake this work. Quote accepted for
                      reinstatement of electricity to caravan sites, installation of
                      heating in shower cubicles and to fit time to control heating
                      unit in drying room. Electrical work completed and working
                      well. Pipework for water supply to building has been
                      upgraded to larger diameter which has improved water
                      pressure considerably. Guests have been very
                      complimentary. Gas has been signed off as being
                      compliant by Envirohaz. Arrangements being made with
                      supplier to install one 120kg and one 45kg gas cylinder for
                      insitu filling. Gas cylinders for insitu filling are installed and
                      in use. Stormwater disposal, landscaping and upgrade to
                      car parks will be carried out in next financial year due to
                      significant cost. Remaining to be completed are stormwater
                      disposal works, landscaping and upgrade of the car park
                      area and addressing an issue with the drying room door
                      which was hung incorrectly. The suppliers and building
                      contractor are in discussion as to who is responsible for
                      fixing this. The stormwater and car park works have been
                      delayed until next financial year due to the significant cost.
                      A contractor has been scheduled to undertake Stormwater
                      works around the new Ablution Block.
C8   Recycling Bins   Staff have been working in background to source external             July 2020
                      funding for recycling bins through the Glass Packaging               Completed
                      Forum (Love NZ) and solar compacting bins from the
                      Tourism Infrastructure Fund (TIF). Both applications have
                      been successful for bins which will be installed throughout
                      the District. Installation of bins will be taking place over the
                      coming months with final locations to be determined (one
                      of which will be located in the Makotuku Reserve near the
                      new BBQ area). The community needs to advise the
                      Community Property Team where there is a perceived
                      requirement for additional bins in their community. The
                      decisions are made based on advice from the litter
                      collection contractor. Side by side recycling bins have
                      arrived and scheduled for installation at Pitt St Reserve and
                      outside Angel Louise café on Seddon St, Raetihi. Contract
                      received from TIF for signing for solar compacting bins.
                      These to be installed outside I-Site, the Junction, Goldfinch
                      Street (outside New World) & at the Carrot Park in
20

     Subject      Action taken                                                    Target
                                                                                  Completion
                  Ohakune, at Tangiwai Memorial Site & outside the public
                  toilets in Waiouru (replacing the existing one which is
                  leased). TIF solar compacting bins to be installed in March
                  following delivery. Delivery of bins into New Zealand has
                  been delayed and a variation lodged with MBIE for a new
                  completion date of the end of April.
                  Bins have arrived in Auckland and await lifting of COVID-
                  19 restrictions so that they can be delivered to the Ruapehu
                  District for installation. The bins have been delivered to
                  Taumarunui and work to install them will be scheduled with
                  a contractor. Bins installed at Carrot Park, Clyde Street,
                  Ohakune CBD, Tangiwai and Waiouru. Contractor
                  scheduled to complete installation of final bin on
                  Mangawhero Terrace. Installation of bin on Mangawhero
                  Terrace completed.
C9   Accessible   New funding allocation for 2019/20 of 21,420. Report to be      June 2020
     Walkway      provided. Report requesting decision for allocation of funds    Completed
                  provided at this meeting. WWCB has approved $17,000 be
                  allocated to Raetihi Promotions to complete the concreting
                  of the Makotuku Walkway. Ohakune 2000 Inc. has been
                  allocated $4,000 to complete the pathway to the picnic
                  plaza. Further funding of approximately $16,000 to cover
                  the cost of building the causeway (required following the
                  installation of the footbridge) and connecting the footbridge
                  to the existing footpath on State Highway 49 will be
                  allocated to Ohakune 2000 Inc. from funds available for
                  footpaths through the Roading Team. Council invoiced and
                  funds to be paid to Ohakune 2000 Inc. this month. Raetihi
                  Inc. awaiting completion of work by contractor who will
                  invoice Council directly. One invoice received by Raetihi
                  Inc. Continuation of walkway awaiting removal of conifer
                  trees alongside Raetihi swimming pool to be carried out by
                  PowerCo Lines Co. Scheduled for end of January.
                  Treescape have removed conifers and left mulch for use on
                  Makotuku Walkway. Removal of conifers means that work
                  to complete walkway exit onto SH49 can now be scheduled
                  with contractor.       COVID-19 restrictions have delayed
                  progress on completion of the walkway. Approx 30m of
                  walkway from SH4 across the edge of reserve where the
                  pool is situated remains to be excavated and concreted.
                  Awaiting contractor to become available for excavation
                  before concreting can be started. Fence panels at the
                  Raetihi swimming pool have been removed and the
                  walkway excavated to the State Highway ready for
                  concrete to be poured in the coming weeks. Removal of the
                  fence panels means that the outdoor grass area of the pool
                  will not be secure from the general public when the doors
                  at the North end of the pool are opened, however this will
                  be remedied through rerouting of the fence in future. Art
                  panels of native birds, funded by the Creative Art Grant,
                  have been erected along the walkway. Work to complete
                  footpath through swimming pool area to State Highway has
                  been delayed by weather. Footpath through swimming pool
                  area completed thus 2019/20 budget allocated has been
                  exhausted. Any further work to accessible pathways will
                  require an application to the 2020/21 Accessible Walkway
                  budget for the South of the District.
21

      Subject          Action taken                                                   Target
                                                                                      Completion
C10   Ohakune          New project 2019/20. Report to WWCB meeting held 1             October 2020
      Cemetery         August 2019. Resolved to create extension at top of hill
      Extension        near existing cemetery. Consulted with both Ngāti Rangi
                       and Uenuku with approval received. Earthworks
                       completed. Farm fence, knee-breaker fencing and
                       landscaping underway.           The farm fence has been
                       completed and the knee breaker posts are in place and now
                       require iron rope to complete. Installation of two berms and
                       a concrete path are underway. COVID-19 restrictions have
                       delayed progress on completion of the cemetery extension.
                       Awaiting new financial year for budget to complete
                       installation of wire rope on fencing, excavate and pour
                       concrete berms and path. Contractor quoting to complete
                       wire rope fencing, concrete berms and create footpath.
C11   Raetihi          New project 2019/20. Locations for a new site are being        July 2020
      Cemetery         explored and expected to have some direction by July
      Extension        2020. Suitability of use of section of Reserve alongside
                       existing cemetery on State Highway being investigated.
C12   Ruatiti Domain   New project 2019/20 (budget $81,600). Site visit to be         December
      Toilet Upgrade   arranged for November 2019. Site confirmed. Awaiting           2021
                       plans of cycleway toilets to compare with other options.
                       Quotes have been received.
C13   Waiouru          New project 2019/20, need to discuss with community:           2020
      Playground       location, budget ($30,600) and timeframes. Meeting to be
                       arranged with representatives of community to discuss site
                       (during May). Meeting for input from community held 23
                       July.
C14   Raetihi          Added by request of WWCB. CLM are developing a                 July 2025
      swimming pool    proposal for the future of the Raetihi pool and a draft
                       feasibility study is in the process of being prepared. Quote
                       sought to fence off outdoor area of pool which has been
                       opened up to enable the Makotuku Walkway to be
                       completed.
R14   Ohakune          Safety for walkers exiting Mangawhero Walkway onto Old         September
C15   Junction         Station Road is an issue, along with vehicle speeds            2020
                       heading towards the Junction – site visit held on 26 May
                       2020.
                       Issue moved to Community Property section.
                       Decision made to realign the entrance to the walkway to
                       allow for safer crossing. Staff to work with the Walkway
                       Committee to complete the work.
                       Sightlines at Railway Row – vegetation has been removed,
                       however could come back another few metres to further
                       improve sightlines.
C16   Accessible       Proposals requested from Ohakune Inc and Raetihi               June 2021
      Walkway          Promotions for use of funds for report to WWCB 1 Oct
      2020/21          Meeting.
C17   Ohakune          $10,000 available in 2020/21 Financial year.                   June 2021
      Drinking
      Fountains
C18   Seal Ohakune     Quote being sought to seal driveway of Moore Street            June 2021
      Flats Driveway   Flats.
22

3.5     OTHER ITEMS

                Subject             Action Taken                                                 Target
                                                                                                 Completion
          O1    Future         of   Actions over June have been finalising food waste bin and    Work ongoing
                Taumarunui          compostable liner purchasing. Target delivery is liners in   to prepare for
                Landfill            August with bins now scheduled for first week in             landfill closure
                                    September after which roll out to householders on            October 2020
                                    kerbside collection. Still awaiting to hear from funding
                                    application for hot composting unit from Ministry of
                                    Environment but preparations for construction in
                                    progress. Information on changes in service being
                                    prepared for brochure distribution and communication
                                    through all channels over August and September.
                                    New contracts on track to commence 5 October with
                                    closure of landfill 4 October. Information on new services
                                    will be in an information brochure to be dropped in all
                                    letterboxes mid September.
          O2    Ore Ore Slip        In November 2017, Whanganui District Council was             Ongoing
                                    contacted by a local landholder about a slip threatening
                                    to block the Mangawhero River at Matahiwi. A webcam
                                    was installed by Horizons so real-time monitoring could
                                    occur. Horizons installed a low flow-monitoring device at
                                    the Matahiwi Track bridge so if the slip was to come down
                                    the monitoring device would trigger.           The device
                                    automatically warns Council, police, upstream and
                                    downstream property owners via cell or landline. The
                                    major threat would be the YMCA camp downstream and
                                    plans are in place for the camp. It is now a wait and see
                                    situation. This has slowly failed but is letting water
                                    through. The state highway 4 slip is monitored separately
                                    through NZTA.
          O3    Security            The CCTV project Phase 1 was completed the first week        Ongoing
                Cameras             in December 2019 and went live. Systems were upgraded
                                    in BP, TCD and iSite. Also a new monitoring PC was
                                    installed at the Ohakune Police station.
                                    We are still waiting on a quote for Phase 2 to be
                                    completed and submitted. This also requires a quote for
                                    the power supply to the Northern and Southern entrances
                                    from a power installation company.
                                    Staff have followed up with supplier.
                                    The IT manager has been into contact with Alpine
                                    Security and is compiling a report on the current system
                                    for consideration on any upgrade requirements. Further
                                    information has been attached to this report.
          O4    Proposed            Preparing for roll out of communications and community       2025
                Raetihi             engagement and consultation.
                Community Hub

Suggested Resolution(s)
That the Report on Capital Works and Members’ Requests for Information be received.

Clive Manley
CHIEF EXECUTIVE
Attachment                                       23

Raetihi Public CCTV
Background
The Raetihi Community raised funds and engaged with the NZ Police for guidance on the placement
of town CCTV cameras.

At the request of the Councilors, it was agreed that Ruapehu District Council (RDC) would take over
management of the system. Subsequently Stuart Campbell, RDC’s IT manager has engaged with Alpine
Security and the Police to investigate the current setup and state of the cameras.

This is with the view of Councilors assessing the current setup and discussing if there is a requirement
to add extra cameras, reposition these or upgrade the current solution.

Below are the current cameras and their locations.
Attachment   24
Attachment   25
Attachment   26
27

 Report to: Waimarino-Waiouru Community Board

 Meeting Date:       3 September 2020

 Subject:            Resolution to Exclude the Public for Consideration of
                     Board Business

Purpose of Report
1.1   Section 48 of the Local Government Official Information and Meetings Act 1987 gives the
      Board the right by resolution to exclude the public from the whole or any part of the
      proceedings of any meeting on one or more of the grounds contained within that Section.

Significance and Engagement

2.1   Nothing in this report triggers the Significance and Engagement Policy.

Suggested Resolutions
1     That the report on Resolution to Exclude the Public for Consideration of Board Business be
      received.
2     That the public is excluded from the following part of the proceedings of the meeting.
3     That the general subject of each matter to be discussed while the public is excluded, the
      reason for passing the resolution in relation to each matter and the specific grounds under
      Section 48(1) of the Local Government Official Information and Meetings Act 1987 for the
      passing of this resolution are as follows:
                                                                                                       Ground(s)
       General Subject of                                                                              under
       each matter to be     Reason for passing this resolution in relation to each matter             S48(1) for
       considered                                                                                      passing this
                                                                                                       resolution
       C1: Update:           Enable any local authority holding the information to carry on, without
       Waimarino             prejudice or disadvantage, negotiations (including commercial and
       Resthome              industrial negotiations). To maintain the effective conduct of public
                             affairs through the free and frank expressions of opinions by, or
       C3: Confidential      between, or to members of or officers or employees of any local
       Briefing              authority, or any persons to whom Section 2(5) of the Local
                             Government Official Information and Meetings Act 1987 applies, in the
                             course of their duty. To protect the privacy of natural persons.
       C2: Confirmation of   The reason(s) for excluding the public is/are recorded in the Public        48(1)(a)
       Public Excluded       Business Minutes of the meeting.
       Minutes: 2 July
       2020

      This resolution is made in reliance on Section 48(1)(a) of the Local Government Official
      Information and Meetings Act 1987 and the particular interest or interests protected by
      Section 6 or Section 7 of that Act or Section 6 or Section 7 or Section 9 of the Official
      Information Act 1982 as the case may require are listed above.

Liana Mua
GOVERNANCE OFFICER
You can also read