Construction update North Melbourne November 2020 - Metro Tunnel

Page created by Deborah Gonzalez
 
CONTINUE READING
Construction update North Melbourne November 2020 - Metro Tunnel
Construction update
North Melbourne
November 2020

Major construction of the Metro Tunnel is continuing at and around the
Arden Station site. This update provides an outline of current and
upcoming works in your area throughout November.

Construction snapshot                                     When are we working?
Work at and around the Arden Station site during
November involves:                                                    Normal construction hours
— Tunnelling support                                                  7am to 6pm, Monday to Friday
— Station box construction, including concreting of                   7am to 1pm, Saturdays.
  the station’s internal walls and roof, and removal
  of struts
                                                                      Out of hours
— Cross passage construction
                                                                      Some works are required to
— North Melbourne electrical substation
                                                                      take place out of normal
  construction
                                                                      construction hours.
— Utility investigations on Arden, Laurens, Barwise
  and Queensberry streets
— Slurry treatment plant, water treatment plant                       24 hours
  and concrete batching plant operation
                                                                      24 hour works are sometimes
— Out of hours oversize deliveries to and from site                   required during peak
                                                                      construction activities.
— Surveying, and sampling and testing of
  groundwater and soil
— Transporting concrete from the concrete
  batching plant to other Metro Tunnel Project
  construction sites.
Further information on these works can be
found overleaf or at metrotunnel.vic.gov.au.

                           Construction partner:

                                           Design &
                                           Construction
Construction update North Melbourne November 2020 - Metro Tunnel
Works in your area                                    — At times, these activities may need to be
                                                        undertaken at night and are expected to
                                                        generate low to medium levels of noise

                                                                                                                                                                                                                                M
                                                                                                                                                                                                                                 ac
Tunnelling support

                                                                                                                                                                                                                                   au
                                                                                                                                                                                                                                     la
                                                      — Concrete pouring activities may commence                                                                                Arden S

                                                                                                                                                                                                                                                                    St
                                                                                                                                                                                                                                       y
                                                                                                                                                                                       t
Arden Station site

                                                                                                                                                                                                                                       Rd
                                                                                                                        Moone ek
                                                        before 7am and extend beyond 6pm, Monday

                                                                                                                                                                                                                                                            Lothian
Ongoing until mid-late 2021                            to Saturday. This may include the early arrival

                                                                                                                           Cre
                                                                                                                             e Pond
                                                        of concrete trucks to site and operation of the                                                                         Barwise
— Tunnelling between Arden and Parkville is now         concrete batching plant                                                                                                         St

                                                                                                                                                                                                                                             h St
  complete

                                                                                                                                   s

                                                                                                                                                                                                                          ace

                                                                                                                                                                                                                                      Dryburg
                                                      — Oversized deliveries will occur at night, when                                      Slurry nt

                                                                                                                                                                                                                      Terr
— The Arden Station site will provide TBM and           roads are quieter, and are subject to permit                                             e
                                                                                                                                          treatmnt
                                                                                                                                             pla

                                                                                                                                                                                                                 ster
  tunnelling support for the duration of tunnelling     conditions                                                                                                        box
  to the CBD. This involves delivery of tunnel                                                                                                                    Station

                                                                                                                                                                                                              Mun
  lining segments, operation of the slurry and        — Unless otherwise notified, construction
  water treatment plants and transportation of          vehicles will enter and exit the site via Arden
  excavated material 24 hours a day, seven days         Street after 6pm.
                                                                                                                                                                        Site fac
  a week                                                                                                                                                                        ilities

— The project team will continue to undertake         Site maintenance activities                                                                                                                                                                   Queensb
                                                                                                                                                                                                                                                           erry St
  survey and monitoring activities at ground level    Arden Station site                                                                                      Site fac
                                                                                                                                                                      ilities
  along the tunnel alignment.                         Ongoing                                                                                                                                            Legend

                                                                                                                                                                                                     St
                                                                                                                                                                                                                    Construction site

                                                                                                                                                                                             Laurens
                                                                                                                  ink
                                                                                                                                                                                 Concrete
                                                                                                                                                                                 batchin                            Site gate
                                                      — Ongoing site maintenance activities including

                                                                                                                yL
Cross passage construction                                                                                                                                                              g

                                                                                                             Cit
                                                                                                                                                                                  plant                             Internal road network
                                                        modifications to laydown areas and
North Melbourne to Parkville                            existing gates and hoarding on Laurens
                                                                                                                                                                                                                    Intermittent single lane closures
                                                                                                                                                                                                                    and pedestrian detours
Ongoing until mid-2021                                 and Arden streets                                                                                                                                           Substation worksite
                                                                                                                                                                                                                    Vehicle access route
— Installing work platforms and steel bracing         — Survey, and sampling and testing of groundwater
                                                                                                                                                                                                                    Intermittent short traffic holds
  frames inside the completed sections of tunnel        and soil

— Geotechnical probe drilling to collect samples      — Testing and maintenance of site equipment
  and confirm ground conditions in each cross           and plant.                                         Arden Station construction site. Indicative only
  passage location
— Cutting through the tunnel walls using a wall saw   Utility investigation works
                                                                                                           North Melbourne electrical substation                                       Traffic and transport impacts
— Using a small excavator to mine between the         Arden, Laurens, Barwise and Queensberry
                                                      streets, North Melbourne                             North Melbourne                                                             — Up to 200 trucks per day are expected to
  tunnels, and spraying concrete (shotcrete) to                                                            Ongoing until mid-2021                                                       travel to and from site. Construction vehicles
  support the ground                                  Ongoing until late 2020 
                                                                                                                                                                                         and trucks will access the site via Laurens
— Installing waterproofing membrane and               — Service investigations will be undertaken          — Service investigations using NDD trucks to                                  and Arden streets
  lining the cross passage tunnels using steel          intermittently in Arden, Laurens, Barwise and        locate underground services will be required
                                                                                                                                                                                       — All trucks carrying excavated materials will
  reinforcement and concrete                            Queensberry streets                                  intermittently as construction progresses
                                                                                                                                                                                         be covered, and water carts and street
— Each cross passage is expected to take              — This involves the use of non-destructive digging   — Ongoing site investigations and monitoring                                  sweepers will be used frequently to minimise
  approximately six months to construct. Works          (NDD) trucks to locate underground services          activities including survey and soil sampling                               the spread of dust
  will occur concurrently at different cross            and then reinstating the road surface and          — Installing steel reinforcement and formwork, and                          — Rumble grids and a wheel wash have been
  passage sites                                         line marking                                         pouring concrete to create the foundations of the                           installed on site to remove debris from the
— All works will be completed from within the         — These activities are expected to generate            substation structure                                                        wheels and carriages of vehicles to minimise
  completed section of tunnels and are expected         periods of medium to loud noise                                                                                                  the spread of dirt on local roads.
                                                                                                           — Short holds of traffic on the Moonee Ponds Creek
  to generate low levels of noise at surface level                                                           Trail will be required intermittently while large                         Utility investigation works
                                                      — Service investigations in the westbound lane
— Further information about cross passages can          on Arden Street, between the Arden Street            construction vehicles travel along the narrow                             — Utility investigations will involve the
  be found at metrotunnel.vic.gov.au.                   bridge and the Upfield rail line crossing, will      section of the existing access track near Arden                             intermittent short-term closure of one
                                                        be completed at night to minimise disruption         Street. Traffic controllers will be in place to direct                      lane on Arden, Laurens, Barwise and
                                                        to traffic. Works in all other locations will be     cyclists and pedestrians                                                    Queensberry streets. Traffic will be
Station box construction
                                                        undertaken during regular construction hours       — For more information on the North Melbourne                                 maintained in both directions via a
Arden Station site                                                                                                                                                                       shuttle flow arrangement
                                                      — These works may include intermittent impacts         substation visit metrotunnel.vic.gov.au.
Ongoing
                                                        to traffic, footpaths and on-street parking.                                                                                   — Some on-street parking spaces may be
— Removing steel struts from within the station         See the ‘traffic and transport impacts’ section                                                                                  temporarily impacted on Arden, Barwise,
  box using hand tools and cranes                       for further information.                                                                                                         Queensberry and Laurens streets

— Constructing the internal walls and station                                                                                                                                          — Sections of footpath adjacent to works may
  roof using cranes, concrete trucks and pumps                                                                                                                                           be temporarily closed, with local pedestrian
                                                                                                                                                                                         diversions in place
                                                                                                                                                                                       — Access to businesses will be maintained
                                                                                                                                                                                         at all times
                                                                                                                                                                                       — Signage and traffic controllers will be
                                                                                                                                                                                         in place to direct vehicles, cyclists and
                                                                                                                                                                                         pedestrians around the work area.
Construction update North Melbourne November 2020 - Metro Tunnel
Look ahead for 2020-2021
                                              November        December               January              February

   Station box construction

   Utility investigation works

   Tunnelling support

   Cross passage construction

   North Melbourne electrical
   substation construction

Program is indicative and subject to change

   Health and safety                                         Business support
   Metro Tunnel Project works are progressing                While the new Arden Station will be a
   safely under the current Third Step                       significant boost for the local area,
   restrictions in metropolitan Melbourne.                   construction activities can impact
                                                             local businesses.
   You may notice an increase of workers on
   Victoria’s Big Build projects as restrictions on          In response to this, our Business Support
   construction sites start to ease. Large-scale             Team assists businesses through the
   public infrastructure projects are critical and           disruption and any permanent changes
   strict COVIDsafe Plans are in place on all                that will take place.
   project sites across Victoria.
                                                             Please see the offer in this notification from
   The health and safety of our workforce and                The Complete Basketcase, located at
   community remains our top priority. Workers               71 Bakehouse Rd, Kensington VIC 3031.
   on all of Victoria’s Big Build sites are required
   to wear face masks unless they meet any of                We look forward to promoting more local
   the criteria for exception – such as a medical            businesses as the project progresses.
   condition for Occupational Health and Safety
   guidelines. Physical distancing measures are in
   place as well as increased hygiene practices.
   For more information and advice about
   the coronavirus (COVID-19), please visit
   coronavirus.vic.gov.au.

More information
To find out more about the Metro Tunnel Project:
   metrotunnel.vic.gov.au
   1800 105 105 (24 hours a day, 7 days a week)         It should be noted that this information is current at the time of
                                                         printing, however due to unforeseen circumstances, changes
Rail Projects Victoria                                   may occur. Please visit railprojects.vic.gov.au for
                                                                                                                              CYP-WN00409

PO Box 4509, Melbourne, VIC 3001                         the latest updates.
Construction update North Melbourne November 2020 - Metro Tunnel
Construction update North Melbourne November 2020 - Metro Tunnel
CYP-BS00189

71 Bakehouse Road, Kensington VIC 3031
1300 733 933
                                         www.thebasketcase.com.au
Construction update North Melbourne November 2020 - Metro Tunnel Construction update North Melbourne November 2020 - Metro Tunnel Construction update North Melbourne November 2020 - Metro Tunnel Construction update North Melbourne November 2020 - Metro Tunnel Construction update North Melbourne November 2020 - Metro Tunnel
You can also read