STAGE 2 LRT CONSTRUCTION INFORMATION SESSION WITH WESTBORO, MCKELLAR PARK AND CARLINGWOOD COMMUNITY ASSOCIATIONS - APRIL 29, 2021 7:30 - 9:00 P.M ...

Page created by Jacob Dixon
 
CONTINUE READING
STAGE 2 LRT CONSTRUCTION INFORMATION SESSION WITH WESTBORO, MCKELLAR PARK AND CARLINGWOOD COMMUNITY ASSOCIATIONS - APRIL 29, 2021 7:30 - 9:00 P.M ...
Stage 2 LRT Construction
          Information Session
 with Westboro, McKellar Park and
Carlingwood Community Associations
              April 29, 2021
             7:30 – 9:00 p.m.
STAGE 2 LRT CONSTRUCTION INFORMATION SESSION WITH WESTBORO, MCKELLAR PARK AND CARLINGWOOD COMMUNITY ASSOCIATIONS - APRIL 29, 2021 7:30 - 9:00 P.M ...
AGENDA
➢Public art brief
➢Key construction milestones for 2021
➢Station construction and design overview
➢Connectivity review update
➢Questions and Answers

                                            2
STAGE 2 LRT CONSTRUCTION INFORMATION SESSION WITH WESTBORO, MCKELLAR PARK AND CARLINGWOOD COMMUNITY ASSOCIATIONS - APRIL 29, 2021 7:30 - 9:00 P.M ...
2021 KEY MILESTONES

                      3
STAGE 2 LRT CONSTRUCTION INFORMATION SESSION WITH WESTBORO, MCKELLAR PARK AND CARLINGWOOD COMMUNITY ASSOCIATIONS - APRIL 29, 2021 7:30 - 9:00 P.M ...
4
STAGE 2 LRT CONSTRUCTION INFORMATION SESSION WITH WESTBORO, MCKELLAR PARK AND CARLINGWOOD COMMUNITY ASSOCIATIONS - APRIL 29, 2021 7:30 - 9:00 P.M ...
SCOTT STREET DETOUR
➢ Buses will move onto Scott St from
  Transitway in April 2022.
➢ Widening of Scott St, west of Tunney’s
  Pasture, to accommodate additional bus
  traffic
➢ MUPs and traffic signals will be relocated
  during the detour
➢ Fencing will be in place around work
  zones
➢ Construction of a transit-only bridge at
  Roosevelt Ave

                                               5
STAGE 2 LRT CONSTRUCTION INFORMATION SESSION WITH WESTBORO, MCKELLAR PARK AND CARLINGWOOD COMMUNITY ASSOCIATIONS - APRIL 29, 2021 7:30 - 9:00 P.M ...
SCOTT ST. DETOUR - ROOSEVELT PEDESTRIAN BRIDGE AT DOMINION AVE.

                                  ➢ Utilities relocation work is
                                    currently ongoing prior to
                                    bridge removal later this
                                    spring
                                  ➢ Summer installation of
                                    temporary new bridge for
                                    buses     to    cross    over
                                    Transitway
                                  ➢ Sound      buffering    echo
                                    barriers will be installed
                                    near residential area at
                                    Workman/Dominion
                                  ➢ This is to allow construction
                                    of the station and guideway
                                    in Transitway trench while
                                    maintaining bus routes
                                                                    6
STAGE 2 LRT CONSTRUCTION INFORMATION SESSION WITH WESTBORO, MCKELLAR PARK AND CARLINGWOOD COMMUNITY ASSOCIATIONS - APRIL 29, 2021 7:30 - 9:00 P.M ...
NEW BRIDGE AT ROOSEVELT & DOMINION - WORKMAN AVENUES

                                                       7
               Graphic depiction only
STAGE 2 LRT CONSTRUCTION INFORMATION SESSION WITH WESTBORO, MCKELLAR PARK AND CARLINGWOOD COMMUNITY ASSOCIATIONS - APRIL 29, 2021 7:30 - 9:00 P.M ...
KÌCHÌ SÌBÌ STATION SITE (DOMINION STATION)

                                             8
STAGE 2 LRT CONSTRUCTION INFORMATION SESSION WITH WESTBORO, MCKELLAR PARK AND CARLINGWOOD COMMUNITY ASSOCIATIONS - APRIL 29, 2021 7:30 - 9:00 P.M ...
KITCHISSIPPI LOOKOUT AND SJAM

                       ➢ Utilities relocation between Atlantis Ave and
                         SJAM, to Kitchissippi Lookout: May to July
                       ➢ Work at Atlantis Avenue requires a temporary
                         road closure May-June 2021
                       ➢ Boreholes to determine locations of rock
                         underway through May

                                                              9
STAGE 2 LRT CONSTRUCTION INFORMATION SESSION WITH WESTBORO, MCKELLAR PARK AND CARLINGWOOD COMMUNITY ASSOCIATIONS - APRIL 29, 2021 7:30 - 9:00 P.M ...
KÌCHÌ SÌBÌ STATION AREA – ALIGNMENT

                                      10
SLURRY PLANT AT SJAM

                       11
SLURRY PLANT OPERATIONS ALONG SJAM

                                     12
CLEARY AVENUE

                ➢Cleary and Richmond area
                 utilities work is ongoing with
                 manholes and West Nepean
                 Collector excavation
                ➢New watermain installation
                 this summer

                                          13
CLEARY AVENUE

                14
SHERBOURNE STATION AREA

                          ➢ Relocation of utilities is
                            ongoing, anticipated to be
                            completed this summer.
                          ➢ Drilling of soldier piles
                            ongoing for the excavation
                            of the tunnel
                          ➢ Excavation work within
                            Byron Linear Park is
                            expected to begin in late
                            June

                                                15
OVERVIEW – BYRON LINEAR PARK

1. Tunnel work is progressing well across 6.   Echo Barriers will be installed in more
   the Parkway tunnel                          areas as concrete barriers with wire
2. Utilities relocation work is making         fencing get placed following
   progress with work continuing in some       advancement of activities
   areas                                  7.   Rock breaking is making progress
3. Asphalt paving on Byron Avenue has          across the tunnel zone
   started and will progress in May       8.   13-day closure of Woodroffe at
4. Contractor to install and relocate          Richmond end of May for structure
   barriers                                    installation
5. Concrete pouring of tunnel walls       9.   Truck hauling on arterial roads only
   throughout spring-summer from Byron
   Ave

                                                                                   16
BYRON LINEAR PARK – CUT AND COVER TUNNEL

   ➢The Cut and Cover tunnel
    in Byron Linear Park is
    being excavated to an
    approximate depth of 10.5
    metres.
   ➢Cut        and       Cover
    construction    operations
    are now underway and will
    continue until 2023.
   ➢Rock breaking is required
    to excavate for the tunnel
    between Hartleigh Avenue
    and Sherbourne Road.

                                 17
BYRON LINEAR PARK – AERIAL VIEWS OF PROGRESS & ROCK BREAKING

                                                               18
WOODROFFE AVENUE AT RICHMOND ROAD – 13-DAY CLOSURE

                           ➢ Construction of a temporary road
                             bridge crossing Woodroffe will
                             begin on May 28 for 13 days.
                           ➢ This temporary closure is
                             required to maintain traffic flow
                             while tunnel excavation occurs
                             underneath.
                           ➢ Preparations start early May
                             followed by a 13-day road closure
                             with daytime and nighttime work
                             scheduled starting May 28.

                                                         19
PARKWAY GUIDEWAY – EXCAVATION
WITH CONSTRUCTION ZONES

                                                                                   Zone 13
                                                Zone 9, 10, 11
                      Zone 5, 6, 7,
        Zone 1 & 3

                                      ZONE                       START DATE                  QUANTITY (2021)
                                      1&3                               MAY 2021             18,000 m3
                                      5, 6, 7                           OCT 2020             66,000 m3
                                      9, 10 & 11                        NOV 2020             53,000 m3
                                      13a, 13b, 13c                     APR 2021             42,000 m3
                                      Total                                                  179,000 m3
                                                                                             25,000 loads
                                                                                                               20
PARKWAY GUIDEWAY - STRUCTURES

                                21
STATIONS

           22
WESTBORO STATION
                      •     St
                            art            Finish
                               June 2022        September 2023

                   Facts:

                            Westboro Station

                   Number of Entrances 2

                   Bus Connections          Yes

                   Elevators                2

                   Bike Parking Spaces      40

                   Benches                  1

                   Fare Gates               10

                                                      23
KICHI SIBI STATION
                              Start          Finish
                                 July 2022        March 2023

                     Facts:

                               Kichi Sibi Station

                     Number of Entrances 2

                     Bus Connections          Yes

                     Elevators                2

                     Bike Parking Spaces      60

                     Benches                  3

                     Fare Gates               5

                                                        24
SHERBOURNE STATION
                        •     St
                              art            Finish
                                 June 2022        November 2023

                     Facts:

                              Sherbourne Station

                     Number of Entrances 1

                     Bus Connections          Yes

                     Elevators                1

                     Bike Parking Spaces      20

                     Benches                  1

                     Fare Gates               5

                                                       25
COMMUNITY ENGAGEMENT

                       26
COMMUNITY IMPACTS

• Majority of the work will occur from 7:00 am to 6:00 pm, Monday to Friday.

• There will be intermittent overnight and weekend work. Weekend work will
  begin at 8am on Saturdays, 9am on Sundays.

• Construction is permitted to occur between 6:00 am to 10:00 pm 7
  days/week.
   o All construction work in Ottawa is permitted to work 7 days a week;
   o In Ottawa there are NO mechanisms to prevent 7 days a week work;
   o During COVID-19, Province of Ontario superseded Ottawa’s by laws
     allowing work to begin at 6:00 a.m. until 10:00 p.m. Monday to Sunday;
   o In Ottawa, affected ward Councillors’ play a role in the issuance of Noise
     By-law Exemption permits for night work.

                                                                          27
COMMUNITY IMPACTS

• Noise and vibration from trucks and heavy equipment should be expected.

• Noise and vibration levels are continuously monitored and reported to the City to ensure they are within
  the limits established for the Project.

• Dust suppression and street sweeping will be ongoing. Site lighting for overnight work will be required,
  which will be directed away from residences.

• All pedestrian, cycling, bus, and vehicular movements will generally be maintained during construction
  apart from highway ramp closures. Pedestrians and cyclists should use extra caution when localized
  detours are in place.

• Motorists should adhere to detours, traffic control signage, posted speed limits, and use extra caution as
  traffic patterns change. Motorists should use caution and allow for added travel time when moving
  through active construction corridors.

                                                                                                        28
STAKEHOLDER RELATIONS

Stage 2 is committed to providing:
   • Rapid response to public inquires
   • Proactive communications through newsletters, online articles, videos, social
      media updates, public notices
   • Providing dedicated presentations to affected groups and residents
   • Dedicated contact with City’s Rail Construction Program

       For Ward 15 residents: Jessica Maxwell
       Stakeholder Relations, Rail Construction Program, City of Ottawa
       Jessica.Maxwell@ottawa.ca

       For Ward 7 residents: Damon Berlin
       Stakeholder Relations, Rail Construction Program, City of Ottawa
       Damon.Berlin@ottawa.ca

       ottawa.ca/Stage2connect - to sign up for e-newsletter               29
Questions?