Blackberry Lane Sewer Pump Station Improvements Project - Pre-Construction Neighborhood Meeting Thursday, March 11, 2021

Page created by Terrance Cruz
 
CONTINUE READING
Blackberry Lane Sewer Pump Station Improvements Project - Pre-Construction Neighborhood Meeting Thursday, March 11, 2021
Blackberry Lane Sewer Pump Station
Improvements Project
Pre-Construction Neighborhood Meeting
Thursday, March 11, 2021
Blackberry Lane Sewer Pump Station Improvements Project - Pre-Construction Neighborhood Meeting Thursday, March 11, 2021
Meeting Agenda
• Project Team Introductions
• Project Overview
• Anticipated Impacts
• Timeline
• Questions From Public
Blackberry Lane Sewer Pump Station Improvements Project - Pre-Construction Neighborhood Meeting Thursday, March 11, 2021
Introductions
Department of Public Works Capital Program
 Alison Eliot, PE, Senior Project Manager
 William Sedewitz, PE, Chief Engineer
 Allyssa Jewell, Senior Communications Project Manager
Weston & Sampson (consultant)
 Justin Gould, PE, Senior Project Manager
 David Meier, Resident Engineer
RJV Construction (contractor)
Blackberry Lane Sewer Pump Station Improvements Project - Pre-Construction Neighborhood Meeting Thursday, March 11, 2021
Existing Conditions
Blackberry Lane Sewer Pump Station Improvements Project - Pre-Construction Neighborhood Meeting Thursday, March 11, 2021
Need for an upgrade
A larger sewer pumping station is replacing the
existing station to accommodate the increased
wastewater flows
resulting from the
new development
at 175 Millwood St.
Blackberry Lane Sewer Pump Station Improvements Project - Pre-Construction Neighborhood Meeting Thursday, March 11, 2021
Project Location

               WORK          4 Blackberry
                                 Lane
               ZONE
                                                 5 Blackberry
                                                     Lane
         2 Blackberry
             Lane
                                  3 Blackberry
                                      Lane

              1 Blackberry
                  Lane
Blackberry Lane Sewer Pump Station Improvements Project - Pre-Construction Neighborhood Meeting Thursday, March 11, 2021
Project Scope                    4 Blackberry
                                     Lane
   2 Blackberry
       Lane

                                                3 Blackberry
                                                      V
                                                    Lane

                  1 Blackberry
                      Lane
Blackberry Lane Sewer Pump Station Improvements Project - Pre-Construction Neighborhood Meeting Thursday, March 11, 2021
Project Scope
• Existing dry pit to be abandoned
Blackberry Lane Sewer Pump Station Improvements Project - Pre-Construction Neighborhood Meeting Thursday, March 11, 2021
Project Scope
• Valve chamber
• Wet well
• Submersible pump system
Project Scope
• Upgrade electrical cabinet
Project Scope
• Relocation of approximately 60’ of water main
Project Scope
• Relocation of approximately 300’ drainage
• Pavement restoration
Anticipated Impacts
• Construction work hours – 7 AM to 4 PM, Monday-Friday.
• A road closure and detour will be in effect during construction hours.
• Property access for residents and emergency vehicles will be maintained.
• Water and sewer disruptions are not anticipated unless emergency.
• The City will distribute notices in advance of any significant interruptions.
Anticipated Impacts

                WORK          4 Blackberry
                                  Lane
                ZONE                              5 Blackberry
                                                      Lane
          2 Blackberry
              Lane
                                   3 Blackberry
                                       Lane

               1 Blackberry
                   Lane
Detour Route
Anticipated Construction Schedule
• March 2021: Public meeting
• May 2021: Mobilize
• August 2021: Substantially complete except for final paving
• Fall 2021: Project complete
Other Potential Construction
The currently permitted sewer connection from the 175
Millwood Street development will require sewer improvements
through private property and along Blackberry Lane. Alternative
connections are being considered. That work would be
managed privately and is separate from the pump station
replacement.
Summary of What’s Next
• Respond to unanswered questions within 5 business days.

• Video recording of the meeting and a copy of tonight’s
 presentation will be available on BuildingFramingham.com
 within 5 business days.

• Construction anticipated to start in May.
Questions
Q: After upgrade, how will service be impacted during power failure? In the past there have
been backup/flooding issues.
A: The intent of the project is to mitigate backup issues by increasing size of station and will
provide more robust alarm features to allow adequate response time.

Q: What are the chances and impact of the upgrade not being sufficient to handle added
sewage demands?
A: An evaluation and modeling was completed to analyze existing sewer conditions with
recommendations for upgrades.

Q: During the upgrade, will there be times when sewer usage is interrupted or restricted?
A: Sewer interruptions and restrictions are not anticipated. Should an interruption or
restriction be required, residents will be given as much notice as possible.
Questions
Q: During the upgrade, will there be times when water usage is interrupted?
A: Water outages are not anticipated unless emergency. Should an interruption be required,
residents will be given as much notice as possible.

Q: During the upgrade, will there be times when electrical service is interrupted?
A: We do not anticipate electrical outages due to this project. However, unexpected outages
may occur.

Q: What impact will abandonment of the dry well have on the service?
A: Construction will be sequenced to install the new station first and make it operational prior
to abandoning the existing dry well. Abandonment is not expected to have an affect on sewer
service.
Questions
Q: How will pedestrian access/passage be impacted?
A: Pedestrian access will be maintained. Detail officers will be present during construction.
Pedestrians are reminded to be cautious near construction zones.

Q: My child has a bus stop at Blackberry Lane and Millwood Street. How will we be affected?
A: City staff is coordinating with the Schools and transportation team. Detail officers will be
present during construction and can assist pedestrian traffic.

Q: What is the project duration?
A: Approximately 4 months of active construction, followed by a settling period before final
paving.
FOR FUTURE PROJECT UPDATES AND TO STAY CONNECTED
   WITH FRAMINGHAM PUBLIC WORKS, PLEASE VISIT:

              City Website:
       www.BuildingFramingham.com   If you need assistance or have questions
                                        about the project, please contact:

                                    Alison Eliot, P.E., Senior Project Manager:
              Facebook:                    aeliot@framinghamma.gov
        @FraminghamPublicWorks
                                    For immediate assistance, please call the
                                        Capital Projects 24/7 Phone Line:
                                                  508-532-6040

               Twitter:
            @DPWFramingham
HOW TO PARTICIPATE ON ZOOM                               PUBLIC PARTICIPATION
                                                            GROUND RULES
      If you are watching the meeting via Zoom      • Questions submitted prior to the meeting will
     on your computer, mobile device, or tablet       be discussed first
     and wish to speak, please raise your digital
                        hand.                       • You will have 3 minutes to speak

      Please do not use the chat function.          • Participants will not be able to speak more than
                                                      once until everyone has had an opportunity for
                                                      their voice to be heard
Dial by phone:
+1-301-715-8592 or +1-312-626-6799 or               • Inappropriate language and/or offensive
+1-646-558-8656 or +1-253-215-8782 or                 comments will NOT be tolerated
+1-346-248-7799 or +1-669-900-9128
                                                    • For follow-up questions that cannot be
Webinar ID# 884 7150 4214                             answered tonight, we will post a Q&A sheet on
                                                      the City website 5 business days after the
Press *9 to speak                                     meeting

                                                    • Hard stop at 8 p.m.
You can also read