GODDARD-PLUMVILLE 138 KV - Generation Interconnection Revised Impact Study Report for Queue Project AE1-144 80.2 MW Capacity / 120 MW Energy ...

Page created by Charlie Hudson
 
CONTINUE READING
GODDARD-PLUMVILLE 138 KV - Generation Interconnection Revised Impact Study Report for Queue Project AE1-144 80.2 MW Capacity / 120 MW Energy ...
Generation Interconnection
   Revised Impact Study Report
               for
      Queue Project AE1-144
   GODDARD-PLUMVILLE 138 KV
80.2 MW Capacity / 120 MW Energy

                                   January 2021
Table of Contents
1     Preface ................................................................................................................................................................................................................ 3
2     General ............................................................................................................................................................................................................... 4
    2.1        Point of Interconnection ................................................................................................................................................................... 5
    2.2        Cost Summary........................................................................................................................................................................................ 5
3     Transmission Owner Scope of Work ..................................................................................................................................................... 6
4     Attachment Facilities ................................................................................................................................................................................... 6
5     Direct Connection Cost Estimate ............................................................................................................................................................. 6
6     Non-Direct Connection Cost Estimate................................................................................................................................................... 6
7     Incremental Capacity Transfer Rights (ICTRs) ................................................................................................................................. 7
8     Interconnection Customer Requirements ........................................................................................................................................... 8
9     Revenue Metering and SCADA Requirements ................................................................................................................................... 9
    9.1        PJM Requirements ............................................................................................................................................................................... 9
    9.2        EKPC Requirements ............................................................................................................................................................................ 9
10         Network Impacts.....................................................................................................................................................................................10
11         Generation Deliverability ....................................................................................................................................................................12
12         Multiple Facility Contingency ............................................................................................................................................................12
13         Contribution to Previously Identified Overloads ......................................................................................................................12
14         Potential Congestion due to Local Energy Deliverability .......................................................................................................12
15         System Reinforcements ........................................................................................................................................................................13
16         Steady-State Voltage Requirements ................................................................................................................................................13
17         Light Load Analysis ................................................................................................................................................................................13
18         Stability and Reactive Power Requirement for Low Voltage Ride Through ..................................................................13
    18.1       Flow Gate Details................................................................................................................................................................................16
      18.1.1            Index 1 ..........................................................................................................................................................................................17
    18.2       Queue Dependencies ........................................................................................................................................................................18
    18.3       Contingency Descriptions ...............................................................................................................................................................19
19         Affected Systems .....................................................................................................................................................................................21
    19.1       TVA ...........................................................................................................................................................................................................21
    19.2       Duke Energy Progress ......................................................................................................................................................................21
    19.3       MISO ........................................................................................................................................................................................................21
    19.4       LG&E ........................................................................................................................................................................................................21
20         Short Circuit ..............................................................................................................................................................................................23

© PJM Interconnection 2021. All rights                                                                       2
reserved                                                                                                                                                     AE1-144: GODDARD-PLUMVILLE 138 KV
21      Attachment 1. Single Line Diagram .................................................................................................................................................24

1    Preface
The intent of the System Impact Study is to determine a plan, with approximate cost and construction time
estimates, to connect the subject generation interconnection project to the PJM network at a location
specified by the Interconnection Customer. As a requirement for interconnection, the Interconnection
Customer may be responsible for the cost of constructing: Network Upgrades, which are facility additions, or
upgrades to existing facilities, that are needed to maintain the reliability of the PJM system. All facilities
required for interconnection of a generation interconnection project must be designed to meet the technical
specifications (on PJM web site) for the appropriate transmission owner.

In some instances an Interconnection Customer may not be responsible for 100% of the identified network
upgrade cost because other transmission network uses, e.g. another generation interconnection or merchant
transmission upgrade, may also contribute to the need for the same network reinforcement. The possibility of
sharing the reinforcement costs with other projects may be identified in the Feasibility Study, but the actual
allocation will be deferred until the System Impact Study is performed.

The System Impact Study estimates do not include the feasibility, cost, or time required to obtain property
rights and permits for construction of the required facilities. The project developer is responsible for the right
of way, real estate, and construction permit issues. For properties currently owned by Transmission Owners,
the costs may be included in the study.

The Interconnection Customer seeking to interconnect a wind or solar generation facility shall maintain
meteorological data facilities as well as provide that meteorological data which is required per Schedule H to
the Interconnection Service Agreement and Section 8 of Manual 14D.

An Interconnection Customer with a proposed new Customer Facility that has a Maximum Facility Output
equal to or greater than 100 MW shall install and maintain, at its expense, phasor measurement units (PMUs).
See Section 8.5.3 of Appendix 2 to the Interconnection Service Agreement as well as section 4.3 of PJM
Manual 14D for additional information.

© PJM Interconnection 2021. All rights                                                     3
reserved                                                                                                                            AE1-144: GODDARD-PLUMVILLE 138 KV
2    General
The Interconnection Customer (IC), has proposed a solar / battery storage generating facility located in
Flemingsburg, KY. The installed facilities will have a total capability of 120 MW with 80.2 MW of this output
being recognized by PJM as capacity. The capacity & energy rights are associated with the solar generating
facility only. The proposed in-service date for this project is June 1, 2022. This study does not imply a EKPC
commitment to this in-service date.

                       Queue Number                                          AE1-144
                        Project Name                                 GODDARD-PLUMVILLE 138 KV
                            State                                                KY
                           County                                            Fleming
                     Transmission Owner                                        EKPC
                            MFO                                                 120
                            MWE                                                 120
                            MWC                                                80.2
                             Fuel                                         Solar; Storage
                     Basecase Study Year                                       2022

© PJM Interconnection 2021. All rights                  4
reserved                                                                        AE1-144: GODDARD-PLUMVILLE 138 KV
2.1 Point of Interconnection
AE1-144 will interconnect with the EKPC transmission system along the Goddard - Plumville 138kV line.

2.2 Cost Summary
The AE1-144 project will be responsible for the following costs:

 Description                                               Total Cost
 Attachment Facilities                                     $250,000
 Direct Connection Network Upgrade                         $4,320,000
 Non Direct Connection Network Upgrades                    $800,000
 Allocation for New System Upgrades                        $0
 Contribution for Previously Identified Upgrades           $15,040,000
 Total Costs                                               $20,410,000

© PJM Interconnection 2021. All rights                 5
reserved                                                                    AE1-144: GODDARD-PLUMVILLE 138 KV
3    Transmission Owner Scope of Work

4    Attachment Facilities
The total preliminary cost estimate for the Attachment work is given in the table below. These costs do not
include CIAC Tax Gross-up.

 Description                                                           Total Cost
 Install a 138 kV switch structure at the point of demarcation,        $250,000
 revenue metering, and attachment facility line/bus and
 associated hardware to accept the Interconnection Customer
 generator lead line/bus terminating at the AE1-144
 Interconnection switching station.
 Total Attachment Facility Costs                                       $250,000

5    Direct Connection Cost Estimate
The total preliminary cost estimate for the Direct Connection work is given in the table below. These costs do
not include CIAC Tax Gross-up.

 Description                                                           Total Cost
 Build 138kv switching station near Mt. Carmel, KY including           $4,320,000
 associated transmission line work.
 Estimated Time to Construct: 24 months
 Total Direct Connection Facility Costs                                $4,320,000

6    Non-Direct Connection Cost Estimate
The total preliminary cost estimate for the Non-Direct Connection work is given in the table below. These
costs do not include CIAC Tax Gross-up.

 Description                                                           Total Cost
 Goddard - Plumville 138kV line: Install a line loop to the            $700,000
 proposed AE1-144 interconnection switching station.
 Adjust remote, relaying, and metering settings at the Goddard         $50,000
 138 kV switchyard
 Adjust remote, relaying, and metering settings at the Plumville       $50,000
 138 kV switchyard
 Total Non-Direct Connection Facility Costs                            $800,000

© PJM Interconnection 2021. All rights                             6
reserved                                                                            AE1-144: GODDARD-PLUMVILLE 138 KV
7    Incremental Capacity Transfer Rights (ICTRs)
Will be determined at a later study phase

© PJM Interconnection 2021. All rights         7
reserved                                            AE1-144: GODDARD-PLUMVILLE 138 KV
8    Interconnection Customer Requirements

    1. An Interconnection Customer entering the New Services Queue on or after October 1, 2012 with a
       proposed new Customer Facility that has a Maximum Facility Output equal to or greater than 100 MW
       shall install and maintain, at its expense, phasor measurement units (PMUs). See Section 8.5.3 of
       Appendix 2 to the Interconnection Service Agreement as well as section 4.3 of PJM Manual 14D for
       additional information.

    2. The Interconnection Customer may be required to install and/or pay for metering as necessary to
       properly track real time output of the facility as well as installing metering which shall be used for
       billing purposes. See Section 8 of Appendix 2 to the Interconnection Service Agreement as well as
       Section 4 of PJM Manual 14D for additional information.

    3. The Interconnection Customer seeking to interconnect a wind generation facility shall maintain
       meteorological data facilities as well as provide that meteorological data which is required per item
       5.iv. of Schedule H to the Interconnection Service Agreement.

© PJM Interconnection 2021. All rights                  8
reserved                                                                         AE1-144: GODDARD-PLUMVILLE 138 KV
9    Revenue Metering and SCADA Requirements

9.1 PJM Requirements
The Interconnection Customer will be required to install equipment necessary to provide Revenue Metering
(KWH, KVARH) and real time data (KW, KVAR) for IC's generating Resource. See PJM Manuals M-01 and M-
14D, and PJM Tariff Section 8 of Attachment O.

9.2 EKPC Requirements
The Interconnection Customer will be required to comply with all EKPC Revenue Metering Requirements for
Generation Interconnection Customers. The Revenue Metering Requirements may be found within the “EKPC
Facility Connection Requirements” document located at the following link:

http://www.pjm.com/planning/design-engineering/to-tech-standards/ekpc.aspx

© PJM Interconnection 2021. All rights                9
reserved                                                                     AE1-144: GODDARD-PLUMVILLE 138 KV
10 Network Impacts
The Queue Project AE1-144 was evaluated as a 120.0 MW (Capacity 80.2 MW) injection into a tap of the
Goddard – Plumville 138 kV line in the EKPC area. Project AE1-144 was evaluated for compliance with
applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission
Owners). Project AE1-144 was studied with a commercial probability of 1.00. Potential network impacts were
as follows:

© PJM Interconnection 2021. All rights              10
reserved                                                                   AE1-144: GODDARD-PLUMVILLE 138 KV
Summer Peak Load Flow

© PJM Interconnection 2021. All rights   11
reserved                                             AE1-144: GODDARD-PLUMVILLE 138 KV
11 Generation Deliverability
(Single or N-1 contingencies for the Capacity portion only of the interconnection)

None

12 Multiple Facility Contingency
(Double Circuit Tower Line, Fault with a Stuck Breaker, and Bus Fault contingencies for the full energy output)

None

13 Contribution to Previously Identified Overloads
(This project contributes to the following contingency overloads, i.e. "Network Impacts", identified for earlier
generation or transmission interconnection projects in the PJM Queue)
  ID     FRO      FROM      kV      FRO     TO      TO       kV       TO         CK              CONT NAME              Type     Rati    PRE         POST      AC|     MW
          M        BUS               M     BUS#     BUS               BUS         T                                               ng    PROJE       PROJE      DC     IMPA
         BUS#                       BUS                               ARE        ID                                              MV       CT          CT               CT
                                    ARE                                A                                                          A     LOADI       LOADI
                                     A                                                                                                  NG %        NG %
 4275    2469     05WLD     138     AEP    2430    05HILL    138      AEP        1          DAY_P4_STUART_HH            break    185.   111.66      115.31     AC     7.95
  61      46       CAT       .0             19       SB       .0                                                          er      0
 4287    2469     05WLD     138     AEP    2430    05HILL    138      AEP        1          DEO&K-DAY-EKPC.C5           towe     185.   135.19      140.54     AC     11.66
  96      46       CAT       .0             19       SB       .0                       4541MELDAHLSPRLCKSTUARTSPUR        r       0
                                                                                                LOCKDPLEK

14 Potential Congestion due to Local Energy Deliverability
PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified
below are likely to result in operational restrictions to the project under study. The developer can proceed
with network upgrades to eliminate the operational restriction at their discretion by submitting a Merchant
Transmission Interconnection request.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of
energy for this project by fixing only the conditions listed in this section. With a Transmission Interconnection
Request, a subsequent analysis will be performed which shall study all overload conditions associated with the
overloaded element(s) identified.
   ID     FROM       FROM         kV      FRO      TO       TO BUS          kV        TO    CK      CONT       Type      Ratin      PRE       POST           AC|D     MW
          BUS#        BUS                  M      BUS#                                BUS    T      NAME                   g      PROJECT    PROJECT          C      IMPAC
                                          BUS                                         ARE   ID                           MVA      LOADIN     LOADIN                    T
                                          AREA                                         A                                            G%         G%
 42838    24694    05WLDCA        138.    AEP     24301     05HILLS     138.          AEP    1     EKPC_P1   operatio    185.0     111.11        114.77      AC      7.97
   3        6         T            0                9          B         0                            -         n
                                                                                                   2_SPUR-
                                                                                                   STU345

© PJM Interconnection 2021. All rights                                                 12
reserved                                                                                                                 AE1-144: GODDARD-PLUMVILLE 138 KV
15 System Reinforcements
                                              Upgrade Description                                                          Cost
                                                                                                                        Allocated   Upgrade
        ID           Idx         Facility                                                                    Cost
                                                                                                                         to AE1-    Number
                                                                                                                           144
                                              A sag check will be required for the ACSR ~ 477 ~
                                              26/7 ~ HAWK - Conductor Section 1 to determine if
                                              the line section can be operated above its emergency
                                              rating of 185 MVA. The sag study results show that a
                                              distribution circuit crossing underneath structures
                                              37-58 and 37-59 will need to be relocated to allow
                                              the line to be operated at its MOT. An approximate
                                              time for the sag study is 6 to 12 months after signing
                                              an interconnection agreement. Estimated Cost is
                                              $186K. AC1-089 is responsible for this cost. The
                                              new expected SE rating following the sag study will
                               05WLDCAT       be 256 MVA SE.
                               138.0 kV -
  428796,427561       1                       Note 1: AE1-144 presently does not receive cost                $186K         $0       N5472
                             05HILLSB 138.0
                                              allocation for this upgrade.
                                kV Ckt 1
                                              As changes to the interconnection process occur,
                                              such as prior queued projects withdrawing from the
                                              queue, reducing in size, etc, AE1-144 could receive
                                              cost allocation.

                                              Note 2: Although AE1-144 may not have cost
                                              responsibility for this upgrade, AE1-144 may need
                                              this upgrade in-service to be deliverable to the PJM
                                              system. If AE1-144 comes into service prior to
                                              completion of the upgrade, AE1-144 will need an
                                              interim study.

                                              Reconductor/rebuild 10.03 miles’ section of ACSR ~
                                              477 ~ 26/7 ~ HAWK Conductor section 1. An
                               05WLDCAT       approximate construction would be 24- 36 months
                               138.0 kV -     after signing an Interconnection agreement.
  428796,427561       1                                                                                     $15.04M     $15.04 M    N5857
                             05HILLSB 138.0
                                kV Ckt 1      AE1-144 is responsible for this cost as the loading is
                                              pushed over the 256 MVA SE rating.

16 Steady-State Voltage Requirements
(Summary of the VAR requirements based upon the results of the steady-state voltage studies)

None

17 Light Load Analysis
No violation

18 Stability and Reactive Power Requirement for Low Voltage Ride Through
(Summary of the VAR requirements based upon the results of the dynamic studies)

Executive Summary

© PJM Interconnection 2021. All rights                              13
reserved                                                                                             AE1-144: GODDARD-PLUMVILLE 138 KV
Generator Interconnection Request AE1-144 is for a 120 MW Maximum Facility Output (MFO) solar/battery
storage generating facility, which consists of 41 Power Electronics FS3225 Solar Inverters. The batteries are
solely charged by the solar arrays (DC coupled). The AE1-144 solar generating facility will be located in Fleming
County, Kentucky.
To interconnect the AE1-144 solar generating facility, a new 138 kV switching substation with main and
transfer bus configuration will be constructed by tapping the Goddard – Plumville 138 kV line in the East
Kentucky Power Cooperative (EKPC) transmission system. The new substation will be approximately 9.90 miles
from Goddard substation and 7.00 miles from Plumville substation and adjacent to the 138 kV line. Project
AE1-144 will connect to the new substation via approximately 0.2 miles 138 kV transmission line. The Point of
Interconnection (POI) will be at the terminal frame of the disconnect switch on the Interconnection Customer
side.
This report describes a dynamic simulation analysis of AE1-144 as part of the overall system impact study. The
load flow scenario for the analysis was based on the RTEP 2022 peak load case, modified to include applicable
queue projects. AE1-144 has been dispatched online at maximum power output, with unity power factor and
approximately 1.0 pu voltage at the generator terminals.
AE1-144 was tested for compliance with NERC, PJM, Transmission Owner, and other applicable criteria. 113
contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to
any events). Studied faults included:
    a) Steady state operation (Category P0);
    b) Three phase faults with normal clearing time on the intact network (Category P1);
    c) Single phase to ground faults with delayed clearing due to a stuck breaker (Category P4);
    d) Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the
       fault due to primary communications/relay failure (Category P5);
    e) Single phase to ground faults with normal clearing for common structure (Category P7).
For all 113 fault contingencies tested on the 2022 peak load case:
    a) AE1-144 was able to ride through the faults (except for faults where protective action trips a
       generator(s)).
    b) Post-contingency oscillations were positively damped with a damping margin of at least 3%.
    c) Following fault clearing, all bus voltages recover to a minimum of 0.7 per unit after 2.5 seconds (except
       where protective action isolates that bus).
    d) No transmission element trips, other than those either directly connected or designed to trip as a
       consequence of that fault.
No mitigations were found to be required.
Please also note that the project AE1-144 meets the 0.95 leading and lagging reactive power requirement at
the high side of facility main transformer.

© PJM Interconnection 2021. All rights                 14
reserved                                                                        AE1-144: GODDARD-PLUMVILLE 138 KV
© PJM Interconnection 2021. All rights   15
reserved                                      AE1-144: GODDARD-PLUMVILLE 138 KV
18.1 Flow Gate Details
The following indices contain additional information about each facility presented in the body of the report.
For each index, a description of the flowgate and its contingency was included for convenience. The intent of
the indices is to provide more details on which projects/generators have contributions to the flowgate in
question. All New Service Queue Requests, through the end of the Queue under study, that are contributors
to a flowgate will be listed in the indices. Please note that there may be contributors that are subsequently
queued after the queue under study that are not listed in the indices. Although this information is not used "as
is" for cost allocation purposes, it can be used to gage the impact of other projects/generators. It should be
noted the project/generator MW contributions presented in the body of the report are Full MW Impact
contributions which are also noted in the indices column named "Full MW Impact", whereas the loading
percentages reported in the body of the report, take into consideration the PJM Generator Deliverability Test
rules such as commercial probability of each project as well as the ramping impact of "Adder" contributions.
The MW Impact found and used in the analysis is shown in the indices column named "Gendeliv MW Impact".

© PJM Interconnection 2021. All rights                 16
reserved                                                                       AE1-144: GODDARD-PLUMVILLE 138 KV
18.1.1 Index 1

   ID    FROM       FROM   FRO    TO     TO BUS    TO    CK                CONT NAME             Type    Ratin     PRE     POST    AC|D    MW
         BUS#        BUS    M    BUS#              BUS    T                                                g     PROJEC   PROJEC    C     IMPAC
                           BUS                     ARE   ID                                              MVA        T        T              T
                           ARE                      A                                                            LOADIN   LOADIN
                            A                                                                                      G%       G%
 42879   24694   05WLDC    AEP   24301   05HILLS   AEP   1            DEO&K-DAY-EKPC.C5          towe    185.0   135.19   140.54    AC     11.66
   6       6       AT              9        B                  4541MELDAHLSPRLCKSTUARTSPURLOCK     r
                                                                            DPLEK

            Bus #                      Bus                    Gendeliv MW Impact                Type                      Full MW Impact
           916272                   Z1-080 E                        0.5617               Merchant Transmission                  0.5617
           918802                  AA1-099 E                        0.3745               Merchant Transmission                  0.3745
           925981                 AC1-074 C O1                      2.7384                      Adder                            3.22
           925982                 AC1-074 E O1                      1.1736                      Adder                            1.38
           926101                 AC1-089 C O1                     38.8312                      50/50                          38.8312
                                  (Suspended)
           926102                 AC1-089 E O1                     63.3562                       50/50                         63.3562
                                  (Suspended)
           932551                  AC2-075 C                       0.6504                       Adder                           0.77
           932552                  AC2-075 E                       0.3276                       Adder                           0.39
           936381                  AD2-048 C                       3.3999                       Adder                            4.0
           936382                  AD2-048 E                       1.6963                       Adder                            2.0
           939141                 AE1-144 C O1                     6.6214                       Adder                           7.79
           939142                 AE1-144 E O1                     3.2859                       Adder                           3.87
            LGEE                      LGEE                         1.1281                    Confirmed LTF                     1.1281
             CIN                       CIN                         1.3034                    Confirmed LTF                     1.3034
            CPLE                      CPLE                         0.1402                    Confirmed LTF                     0.1402
             IPL                       IPL                         0.7308                    Confirmed LTF                     0.7308
          CBM-W2                    CBM-W2                         13.3463                   Confirmed LTF                     13.3463
          CBM-W1                    CBM-W1                         0.9438                    Confirmed LTF                     0.9438
            WEC                       WEC                          0.1450                    Confirmed LTF                     0.1450
            O-066                    O-066                         0.8816                    Confirmed LTF                     0.8816
           CBM-S2                   CBM-S2                         0.5133                    Confirmed LTF                     0.5133
            CARR                     CARR                          0.0526                    Confirmed LTF                     0.0526
           CBM-S1                   CBM-S1                         2.9366                    Confirmed LTF                     2.9366
            G-007                    G-007                         0.1365                    Confirmed LTF                     0.1365
            MEC                       MEC                          1.6355                    Confirmed LTF                     1.6355
         RENSSELAER               RENSSELAER                       0.0415                    Confirmed LTF                     0.0415

© PJM Interconnection 2021. All rights                                17
reserved                                                                                                AE1-144: GODDARD-PLUMVILLE 138 KV
18.2 Queue Dependencies

The Queue Projects below are listed in one or more indices for the overloads identified in your report. These
projects contribute to the loading of the overloaded facilities identified in your report. The percent overload
of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the
action of these earlier projects. The status of each project at the time of the analysis is presented in the table.
This list may change as earlier projects withdraw or modify their requests.

               Queue Number                           Project Name                             Status
                 AA1-099                           Clinton Co. 34.5kV                        In Service
                 AC1-074                      Jacksonville-Renaker 138kV I                     Active
                 AC1-089                        Hillsboro-Wildcat 138kV                     Suspended
                 AC2-075                         Great Blue Heron Solar                        Active
                 AD2-048                      Cynthia-Headquarters 69 kV                       Active
                  AE1-144                      Goddard-Plumville 138 kV                        Active
                   Z1-080                        Clinton County 34.5kV                       In Service

© PJM Interconnection 2021. All rights                    18
reserved                                                                         AE1-144: GODDARD-PLUMVILLE 138 KV
18.3 Contingency Descriptions

 Contingency Name                        Contingency Definition

                                         CONTINGENCY 'DAY_P4_STUART_HH'
                                          OPEN LINE FROM BUS 253077 TO BUS 342838 CKT 1       / 253077 09STUART 345
                                         342838 7SPURLOCK 345 1
 DAY_P4_STUART_HH
                                          OPEN LINE FROM BUS 253077 TO BUS 253076 CKT 1       / 253077 09STUART 345
                                         253076 09STUART 138 1
                                         END

                                         CONTINGENCY 'DEO&K-DAY-EKPC.C5 4541MELDAHLSPRLCKSTUARTSPURLOCKDPLEK'
 DEO&K-DAY-EKPC.C5
                                          OPEN BRANCH FROM BUS 342838 TO BUS 249581 CKT 1
 4541MELDAHLSPRLCKSTUARTSPUR
                                          OPEN BRANCH FROM BUS 253077 TO BUS 342838 CKT 1
 LOCKDPLEK
                                         END

                                         CONTINGENCY 'EKPC_P1-2_SPUR-STU345'                /* SPURLOCK - STUART
                                          OPEN BRANCH FROM BUS 253077 TO BUS 342838 CKT 1         /* 253077 09STUART
 EKPC_P1-2_SPUR-STU345
                                         345.00 342838 7SPURLOCK 345.00
                                         END

© PJM Interconnection 2021. All rights                              19
reserved                                                                                      AE1-144: GODDARD-PLUMVILLE 138 KV
Affected Systems

© PJM Interconnection 2021. All rights   20
reserved                                       AE1-144: GODDARD-PLUMVILLE 138 KV
19 Affected Systems

19.1 TVA
None

19.2 Duke Energy Progress
None

19.3 MISO
None

19.4 LG&E
A LG&E Affected System Study will be required for AE1-144. The AE1-144 customer will need to sign onto a
LG&E Affected System Study Agreement.

© PJM Interconnection 2021. All rights              21
reserved                                                                   AE1-144: GODDARD-PLUMVILLE 138 KV
Short Circuit

© PJM Interconnection 2021. All rights   22
reserved                                      AE1-144: GODDARD-PLUMVILLE 138 KV
20 Short Circuit
The following Breakers are overduty

None.

© PJM Interconnection 2021. All rights   23
reserved                                      AE1-144: GODDARD-PLUMVILLE 138 KV
21 Attachment 1. Single Line Diagram

© PJM Interconnection 2021. All rights   24
reserved                                      AE1-144: GODDARD-PLUMVILLE 138 KV
You can also read