GMARG Teleconference Thursday 18th January 2018 - Gas Networks Ireland

Page created by Kirk Malone
 
CONTINUE READING
GMARG Teleconference Thursday 18th January 2018 - Gas Networks Ireland
GMARG Teleconference

Thursday 18th January 2018
Today’s Agenda
       Item     Description                                             Time
       Number                                                           Allotted
       1        Introduction/confirmation of attendees                  5 mins
       2        Review of Previous Minutes and Actions                  15 mins
       3        Incident Management Plan                                5 mins
       4        GNI Complaints Process                                  5 mins
       5        Schema Release 2018                                     10 mins
       6        Prepayment Meter Refunds                                10 mins
       7        Revenue Protection update including DR                  5 mins
       8        GNI Verbal Updates:                                     15 mins
                     Eircode project update
                     Vulnerable and Priority Customer reconciliation
                     Lock Moratorium results
       9        CER Verbal Update                                       5 mins
       10       AOB                                                     5 mins

2
2. Review of Previous Minutes & Actions
                               14 December 2017
Action   Status    Overview                                                                       Responsible
Number

G121     Open      Data Processing Agreement. – GNI had issued revised DPA, GNI to write to       GNI/CRU/ Shippers
                   CRU to clarify timeline for Eligibility List circulation. Shippers to return
                   comments on the DPA by 31/01
G 175    Open      GNI to maintain watching brief on Eircodes, communicate go-live project        GNI/CRU
                   plan, now Q4. CRU to confirm date for introduction in Electricity.
G 185    Open      High level impact assessment of introducing supplier locks on PAYG meters      GNI IT
                   –
                   GNI to issue;- 2. BGES DR: GNI to issue note and to clarify implementation
                   date/MPD status/clarify capability to download Debt. 3. Lock/Read matrix
                   to be produced. 4. Closed: DR Details recirculated

3
2. Review of Previous Minutes & Actions
                           14 December 2017 (continued)
Action   Status     Overview                                                                             Responsible
Number

G 190    Open       Review MPD2 re reflect change of mind provisions GNI to organise workshop            GNI/FG
                    FG to develop TOR
G 202    Open       Vulnerable Customers: GNI to consider DR to cease Priority flag removal after CoS,   GNI/Shippers
                    clarify Schema.
                    Shippers to consider updating GPRN records with mobile details.
G 203    Open       Misdirected Payments - GNI to investigate front office adjustment process.           GNI

G 206    Open       CRU to provide update and issue final version of GMARG ToR including revised         CRU
                    CR/DDR timelines, present to GMARG and IIG by end of Q1
G 207    Propose    PPM Slots – CRU has written to GNI on PPM slots                                      CRU/Shippers
         to Close

  4
2. Review of Previous Minutes & Actions
                            14 December 2017 (continued)
Action   Status     Overview                                                                           Responsible
Number
G 208    Open       Long-term PPM solution – Suppliers to consider position post 2019.                 Shippers

G 218    Open       Schema Date All agreed June 2018 subject to technical complexity, Shippers & GNI   All
                    to rank the priority items in matrix and Shippers to revert with any new changes
                    required.
G 221    Open       Call centre warm transfers: GNI to finalise document by next GMARG.                GNI/Shippers

G 223    Open       Incident management Plan - Shippers to Nominate contacts for Incidents, GNI to     Shippers/GNI
                    consider impact on other procedures.
G 224    Propose    Misdirected Payments - GNI to consider potential approach. Refer G203              Shippers/GNI
         to Close

  5
2. Review of Previous Minutes & Actions
                            14 December 2017 (continued)
Action   Status     Overview                                                                         Responsible
Number
G 225    Open       GNI Complaints Process: Shippers invited to comment on GNI’s proposals. GNI to   Shippers/GNI
                    develop MPD.
G 226    Propose    Revenue Protection RP: Shippers comment were received                            Shippers
         to Close
G 227    Open       PPM User guides: PPM User Guide to be developed by GNI by end of Q1 of 2018.     GNI

G 228    New        GNI to consider using Skype meetings for future GMARG conference calls           GNI

  6
Retail Gas Market Incident
Management Plan

Con O’Donnell

18th January 2018
Feedback Received
ID   Feedback                                                  GNI Response
1.   Update the Scope, Section 1.2, to define and              Section 1.2 updated and GNI will update the NGEM, in
     distinguish any overlap between this plan and the         H1 2018, to reference this plan and it’s role if the
     NGEP.                                                     emergency impacts the retail market. The DRAFT text for
                                                               inclusion in the NGEP is as follows “GNI may use the
                                                               Retail Market Incident Management Plan to co-ordinate
                                                               the interface and communications with gas suppliers and
                                                               the NDM market. This plan will be activated by the
                                                               Regulatory Operations Manager.
2.   Update Section 4, Activation of the plan, to state that   Section 4 updated accordingly.
     GNI are responsible for activating this plan and a
     supplier may request them to do so. If this request is
     rejected, a supplier may escalate to the CRU.
3.   Update Section 4, Activation of the plan, to state that  Section 4 updated accordingly.
     GNI will seek to implement the plan within two
     business days of becoming aware of the first instance of
     the issue.

 8
Next Steps

• On the basis of the feedback received, which has been reviewed, discussed at this forum
    and incorporated into the plan where relevant, GNI are seeking approval to finalise this
    document.

9
GNI Complaints Processing

Con O’Donnell
18th January 2018
1. Complaint definition
• CRU Decision: GNI need to align our definition of a complaint to that in the CRU
  Electricity and Natural Gas Supplier Handbook:
   ‒ “The expression (through various possible channels, letter, email, phone call, physical
      claim) of a customer’s dissatisfaction and his/her explicit expectation for a response or
      resolution.”
GNI Action                                                                    Status
Update the “Customer Complaint Handling Procedure” leaflet to reflect         Complete - CRU approved and
the CRU definition of a complaint.                                            updated document now live on
                                                                              GNI website.
Update the “Complaints training module” document with the CRU                 Complete
definition of a complaint.
Refresher training to all call-centre staff on what constitutes a complaint   Complete - 1 to 1 training
based on the new definition and the updated training module document.         undertaken.

11
2. Complaint processing
• No written feedback received from suppliers on the High-Level principles presented at the
  GMARG in December.
• As a result, GNI have proceeded to develop a Market Process Definition (MPD) based on
  the high-level principles and this has been circulated to all stakeholders.

Next Steps
• Suppliers to review the MPD and revert to GNI with feedback by the 31st of January.
• GNI to review feedback, update MPD and revert at the February GMARG.

12
5. Schema Release

Con O’Donnell
14th December 2017
6. PPM Contractual
Arrangements
7. Revenue Protection update including DR

15
8. GNI updates

 Eircode project update
 Vulnerable and Priority Customers
 Lock Moratorium results

16
Eircode Project Update

• Verbal Update

17
Vulnerable Customers

18
Lock Moratorium outcome

19
9. CRU Updates

• CRU

20
10. GMARG Proposed Meetings

     Day (all 10:30 am starts      Meeting/       Date
     unless otherwise advised)     Call

     Thursday                      Meeting                15/02/2018
     Thursday                      Call                   15/03/2018
     Thursday                      Meeting                19/04/2018
     Thursday                      Call                   17/05/2018
     Thursday                      Meeting                21/06/2018
     Thursday                      Call                   19/07/2018
     Thursday                      Meeting                16/08/2018
     Thursday                      Call                   20/09/2018
     Thursday                      Meeting                18/10/2018
     Thursday                      Call                   15/11/2018
     Thursday                      Meeting                13/12/2018

21
     * Conference Call slots subject to agreement at previous physical GMARG
11. A.O.B.

22
T21 Issue – IBM Recommendations
No    Recommendation                                                                                                                                                                            Status

     A report be developed by GNI on the ‘open field text’ User interface by GNI field staff to establish key issues and trends emerging.                                                       In progress
     In this instance of the T21 issue, the error code T21 was entered into the open field text on the User, Interface by the GNI Field Engineers, therefore there must be a report run and
1
     developed by GNI to report on meter problems and open field texts to see if there are trends emerging on any given meter

     Technical governance should be included in the agenda of the quarterly service review meetings with Payzone and Siemens.                                                                   Complete
     It is recommended that the agenda of the quarterly meetings held with GNI, Siemens and Payzone should also include any open issues, planned technical changes or roll outs and any
2
     impacts this may have across GNI, Payzone and Siemens. There should be an IT presence from all parties attending this quarterly meeting.

     Introduce service requests and open queries into monthly reports                                                                                                                           Complete
     In the monthly report developed by Payzone and provided to GNI, there is currently no section documenting any open queries, service request and or defects. The reason for It is
3    recommended to include a section in the monthly report from Payzone detailing any open queries, service requests, incidents and or defects.
     A set of incident management guidelines should be agreed upon                                                                                                                              In progress
4    There is currently no structured incident management procedure in place.
     The test environment should be improved and maintained regularly.                                                                                                                          Complete
     A key issue of the T21 incident relates to test coverage with both Siemens and Payzone. It is recommended that both parties have coverage of each side of the technical ecosystem.
5    (Terminals/Meters etc)
     The Payzone Patch 2 on the Ingenico terminals should be tested in a controlled environment.                                                                                                In progress
6    Similar to the Cross Participant in place for planned or ad hoc releases by Payzone or Siemens. It is recommended that the required testing for Patch 2 should be included in the
     upcoming market assurance exercise and does not need to include all market participants.
     Release notes should be provided by Payzone with any change on the front office solution.                                                                                                  In progress
     In conjunction with the introduction of a formal testing procedure, it is recommended that technical release note documentation should be documented and distributed by Payzone to
7
     GNI and Siemens with any major patch releases or software upgrades.

     Payzone should provide confirmation of testing and results of any changes on their terminals.                                                                                              In progress
8    With the dynamic nature of the market in which Payzone operate, there are continuous product and service developments, therefore Payzone should formalise and inform GNI of their
     regression testing scope and results for any of these related changes.
     Payzone to refresh its support team’s knowledge on the GNI prepayment solution                                                                                                             Complete
9    As Payzone had some initial issues pinpointing the root cause of the issue, training is recommended to the Payzone support team to improve their knowledge specifically in relation to
     the GNI prepayment solution
                                                                                        * Where appropriate, recommendations for the Front Office Provider will be implemented across all Front Office Providers