PETROPAVLOVSK PLC Investor Presentation April 2019

Page created by Adam Snyder
 
CONTINUE READING
PETROPAVLOVSK PLC Investor Presentation April 2019
PETROPAVLOVSK PLC
Investor Presentation
April 2019
PETROPAVLOVSK PLC Investor Presentation April 2019
Cautionary and Forward-looking Statements

— Some statements contained in this presentation or in documents referred to in it are or may be forward-looking statements, including
  references to guidance. Such statements reflect the Company’s current views with respect to future events and are subject to risks,
  assumptions, uncertainties and other factors beyond the Company’s control that could cause actual results to differ from those
  expressed in such statements. Although the Company believes that such forward-looking statements, which speak only as of the date
  of this presentation, are reasonable, no assurance can be given that they will prove to be correct. Therefore, you should not place
  undue reliance on these statements
— There can be no assurance that the results and events contemplated by the forward-looking statements contained in this presentation
  will, in fact, occur. The Company will not undertake any obligation to release publicly any revisions to these forward-looking
  statements to reflect events, circumstances or unanticipated events occurring after the date of this presentation, except as required by
  law or by any appropriate regulatory authority. Nothing in this presentation or in documents referred to in it should be considered as a
  profit forecast.
— The past performance of the Company and its securities is not, and should not be relied on as, a guide to the future performance of
  the Company and its securities
— This presentation does not constitute, or form part of or contain any invitation, recommendation or offer to any person to underwrite,
  subscribe for, buy, sell, otherwise acquire, exchange or dispose of any shares or securities in the Company or advise persons to do
  so in any jurisdiction, including, but not limited to, the Russian Federation, nor shall it, or any part of it, form the basis of or be relied on
  in any connection with or act as an inducement to enter into any contract or commitment therefore or engage in any other investment
  activity. In particular, this presentation and the information contained herein are not an offer of securities for sale in the United States.
  This presentation does not constitute an advertisement of any securities in the Russian Federation
— No reliance may be placed for any purpose whatsoever on the information or opinions contained in this presentation or on its
  completeness and no liability whatsoever is accepted for any loss howsoever arising from any use of this presentation or its contents
  or otherwise in connection therewith.
— The development and production plans and estimates set out herein represent the current views of the Company's management. The
  Company’s Board reviews the production estimates on an ongoing basis. All planning is subject, inter alia, to available funding and
  capital allocation decisions

— English law and English courts will have exclusive jurisdiction over any disputes arising from or connected with this presentation

                                                                                                                                               2
PETROPAVLOVSK PLC Investor Presentation April 2019
Introduction

3
PETROPAVLOVSK PLC Investor Presentation April 2019
qwas
Top 5 Russian Gold Miner With One Of Only Two Pressure Oxidation Plants
Vertically integrated gold mining business, operating throughout the entire mining cycle

                                             3 x gold mines, mix of open pit + underground, c.7.1Moz of gold produced to
                                             date(1)

                              8.21Moz of JORC Reserves, 20.52Moz of JORC Resources(2)

                    c.14Mtpa of RIP processing capacity

               FY2019F gold production c.450-500Koz, with growing contribution from refractory
               ore treatment

               Pressure Oxidation (POX) Hub successfully commissioned in Q4 2018

                    Experienced management team + skilled workforce

                                Significant untapped exploration potential, with combined licence area
                                c.2,600km2

                                             31% equity interest in low cost Hong Kong listed iron ore producer IRC Ltd.
                                             (US$153m market cap)(3)

                (1) As at 31 Dec 2018, incl. historical production from our alluvial operations and JVs (2) As at 31 Dec 2018, in accordance with the JORC Code.
                Resources (M,I&I) are incl. of Reserves (3) IRC market capitalisation as at close 26 April 2019 (US$153m, source: Bloomberg) x Petropavlovsk’s     4
                equity interest (31.1%) = US$48m
PETROPAVLOVSK PLC Investor Presentation April 2019
Company Snapshot (1/2)
Proven track record of execution from exploration and development to mining and processing
Brief Overview                                                                                                 FY 2018 Russian Gold Mine Production
—   Petropavlovsk is one of Russia’s major gold mining companies with assets located in the
    Amur region, the Russian Far East
                                                                                                                                                               Polymetal, 14%
—   Founded in 1994, accounted for c.6% of Russia’s total gold production in 2018                           Polyus, 35%
—   Total JORC Resources 20.5Moz(1) including 8.2Moz of Reserves                                                                                                 Kinross Gold, 7%
—   Petropavlovsk has 4 production sites, including the technically advanced Pressure Oxidation
    (POX) Hub, launched Q4 2018                                                                                                                                  Uzhuralzoloto, 7%
—   In 2018, produced 422Koz of gold, generating US$500m of revenue and US$143m of EBITDA
—   The company holds 31% share in IRC Ltd, a Hong Kong listed premium grade iron ore                           Other, 32%                                       Petropavlovsk, 6%
    producer
—   After listing on AIM in 2002, Petropavlovsk moved to the Main Market of the LSE in 2009

                                   Mining + Production Facilities                                                                                  JORC Resources(1)
               —    One of the largest gold mines in Russia in terms of mineral resources(2)
               —    Acquired as a greenfield in 2003. Licence area of c.75km2
Malomir        —    RIP plant throughput: 3.0Mtpa, commissioned 2010                                                   Ca tegor y 1
                                                                                                                                                         97%                3%     6.9Moz
               —    Flotation plant with current stage I capacity of 3.6Mtpa launched H2 2018
               —    Stage 2 will increase capacity to 5.4Mtpa via addition of third 1.8Mtpa line

               —    One of Russia’s largest gold mines in terms of processing capacity
               —    Acquired as a greenfield in 2001. Licence area of c.1,300km2
Pioneer        —    Expected >15 year life of mine
                                                                                                                        Ca tegor y 1
                                                                                                                                                  76%               24%      5.9Moz
               —    RIP plant throughput: 6.7Mtpa, commissioned 2007

               —    The Group’s newest mine with an expected >15 year mine life
Albyn          —    Acquired 2005 as a greenfield. Licence area of 1,053km2                                                 Ca tegor y 1
                                                                                                                                           21%           79%              5.4Moz
               —    RIP plant throughput: 4.7Mtpa, commissioned 2011

               —    The Group’s oldest mine, now closed, and which has been converted to host the Pressure
Pokrovskiy                                                                                                                                                     Refractory Resources
                    Oxidation (POX) Hub and supporting infrastructure                                                       Ca tegor y 1
                                                                                                                                           100% 0.9Moz
               —    Historically has produced c.2.0Moz of gold                                                                                                 Non-Refractory Resources

                          (1)Total JORC Resources as at 31 Dec 2018, in accordance with JORC Code. Resources (M,I&I) are inclusive of Reserves. For full details and asset
                          by asset breakdown please refer to the 2018 Petropavlovsk annual report                                                                                     5
                          (2) Based on management estimates
Company Snapshot (2/2)
Gold mining business supported by a range of complementary in-house service companies

                                        Operating mine                    Analytical labs
                                        Underground mine                   R&D
                                        POX                               Offices           Mining assets
London                                                                                      Pioneer
Petropavlovsk Plc
Corporate headquarters     St Petersburg                                                    Albyn
                           RDC
                           Hydrometallurgy                                                  Malomir
                                                                                            Pokrovskiy

                         Moscow
                         Petropavlovsk Moscow
                         PHM Engineering
                                                                Blagoveschensk (Amur region)
                                                                Regis Exploration
                                                                Kapstroi Construction

                                                         Irkutsk
                                                         Irgiredmet Institute

                                                                                IRC Ltd. (associate company)

                                                                                                               6
Investment Highlights

 1
                  One of the major gold mining companies in Russia

 2
     Experienced management team + skilled workforce, in-house technical expertise
                               and R&D facilities

 3
                      Efficient mining + processing operations

 4
           Potential to grow production via refractory ore processing at the
                            Pressure Oxidation (POX) Hub

 5
       Strong track record of mine development, expansion + asset optimisation

 6
                Strategic location + access to developed infrastructure

 7
      Exploitable + long life mineral resource base with high expansion potential

                                                                                     7
FY 2018 Highlights
2018 Highlights
Restoring leadership and progressing growth ambitions

Commissioning of the POX Hub + Malomir flotation plant              Improved operating performance

— Unlocks value embedded in c.5.3Moz of refractory reserves         — H2 2018 operational turnaround enabled FY 2018 targets to be
                                                                      met: production in line with guidance, costs reduced
— Significantly increases optionality of the Group to process own
  refractory ores or treat 3rd party material                       — IRC: ongoing ramp-up of K&S

— Production growth to resume in 2019, from higher grades +
  material contribution from POX

Balance sheet de-risking                                            Board and management teams strengthened
— New US$240m facility signed between Gazprombank and IRC,          — Leadership restored: return of Dr Pavel Maslovskiy as CEO
  payment schedule aligned with K&S ramp-up
                                                                    — Additions of Sir Roderic Lyne (Non-Executive Chairman),
— New gold sales agreement for c.175Koz signed                        Robert Jenkins, James Cameron Jr , Damien Hackett, Harry
                                                                      Kenyon-Slaney (Independent Non-Executive Directors) + Bektas
— Ongoing de-leveraging / reduction in net debt                       Mukazhanov (Non-Executive Director)
                                                                    — Board fully compliant with UK Corporate Governance Code

                                                                                                                                  9
Key Achievements in 2018
Following a disappointing H1 2018, recovery is underway with strong H2 2018 under new
leadership

                       — Production of 422Koz Au (incl. 52Koz of gold in high-grade refractory concentrate), in line
 Production + Costs      with guidance
                       — H2 2018 TCC of US$650/oz, down 28% vs. H1 2018 (US$899/oz)

                       — Malomir: following flotation plant commissioning in July, c.46Kt of high-grade refractory
                         concentrate produced (c.36g/t), for POX processing
                           — Material improvement in flotation flowsheet à c.50% increase in concentrate grade
 Malomir Flotation +           vs. initial design and 50% – 60% decrease in concentrate yield
     POX Hub
                       — POX Hub: autoclaves 1 + 2 commissioned Q4 2018, ahead of schedule
                           — Smooth ramp-up, first gold poured Dec 2018
                           — 3rd party refractory concentrate being acquired

                       — Resources of 20.5Moz Au with Reserves of 8.2Moz Au
    Exploration        — Reserves increased by 0.6Moz despite depletion to 8.2Moz due to new discoveries at
                         Pioneer + Malomir

                       — Net Debt reduced by US$17m to US$568m
       Other
                       — IRC: increased production volumes + higher EBITDA

                                                                                                                   10
FY 2018 Financials
FY 2018 Financial Results
Performance impacted by scheduled inventory build and sub-optimal H1 2018

                                                                                                     Units               2018         2017     Change

Gold production                                                                                       Koz                422.3 (1)   439.6      (4%)
Gold sold                                                                                             Koz                369.6       439.8     (16%)
Avg. realised gold price                                                                            US$/oz               1,263       1,262      0%
Group revenue                                                                                        US$m                499.8       587.4     (15%)

Total cash costs (TCC)                                                                              US$/oz                786         741       +6%
All-in sustaining costs (AISC)                                                                      US$/oz               1,117        963      +16%

Underlying EBITDA                                                                                   US$m                 143.0       196.8     (27%)
Operating profit                                                                                     US$m                126.6       100.4     +26%
Profit before tax                                                                                    US$m                 82.4        48.9     +69%
Profit for the period                                                                                US$m                 25.9        37.1     (30%)

Net cash from operating activities                                                                   US$m                217.2       124.0     +75%

Net debt (as at 31 Dec)                                                                             US$m                 (568.0)     (585.1)    (3%)

Development capex                                                                                   US$m                 112.8        66.2     +70%
Exploration capex                                                                                    US$m                 21.6        21.9      (1%)

Note: (1) Incl. c.52Koz of gold contained in high-grade refractory concentrate produced by the Malomir flotation plant

                                                                                                                                                       12
FY 2018 Total Cash Costs (TCC)
TCC within guided range of US$750/oz – US$800/oz, despite difficult H1 2018

US$/oz                               48                                      0.2
                                                           3                                         91
                     123                                                                                             39

     741                                                               +6%                                                786
      TCC FY2017

                                                                                                                          TCC FY2018
                                    Deferred stripping

                                                                             Co-product effect

                                                                                                 Changes in grades
                                                         Other taxes
                     Higher costs

                                                                                                                     FX
                                                                                                   / recoveries
— TCC affected by inflation of some RUB denominated costs, higher volumes of stripping + suboptimal organisation of
  mining works in H1 2018, partially mitigated by higher processed grades (Pioneer, Malomir), higher recoveries (Pioneer,
  Albyn, Malomir) + effect of RUB depreciation

                                                                                                                                       13
Precious metals operating cash expenses 2018 vs. 2017
Cash expenses -3% yoy as inflation of certain RUB denominated costs (electricity, diesel) was
somewhat offset by the effect of RUB depreciation
                                                Precious Metals Operating Cash Expenses Structure

                                    FY2017                                                                                         FY2018

Consumables                                                                                         Consumables
     +                                                                                                   +
   Other                               Labour                                                                                       Labour
                                                                                                       Other
  Materials                             23%                                                                                          22%
                                                                                                      Materials
   34%                                                                                                 31%
                                                                                                                                                 Fuel
                                                            Fuel                                                                                 15%
                                   Total                    14%                                                                     Total
                                US$313.4m(1)                                                                                     US$302.7m(2)
  Consumables +                                         Other                                                                                     Other
      Other                                              7%                                                                                        8%
    Materials
       37%                                    Electricity                                                                               Electricity
                                                10%                                                                                        9%

        External Services                                                                                    External Services
              12%                                                                                                  15%

                                                                                        2018             2017          Change
                                         Avg. RUB/US$ FX                                62.7             58.3           +7%
                                         Avg. Gold PM Fix US$/oz                       1,269            1,257           +1%

Note: (1) Before movement in ore stockpiles, GIC and bullion in process of US$19.2m;
      (2) Before movement in ore stockpiles, GIC, flotation concentrate and bullion in process of US$55.6m

                                                                                                                                                          14
FY 2018 Development and Exploration Spend
FY 2018 exploration + development capex totalled US$134.4m

          FY2018 Development US$112.8m                                      FY2018 Exploration US$21.6m

           Active development continued ahead
             of scheduled Q4 commissioning

   61.5

                           Flotation,
                    tailings, underground
                          development
                                                  Tailings, underground
                                                development, machinery /                    Pioneer US$10.0m
                                                        equipment                           Malomir US$5.5m
                                                                                             Albyn US$5.0m
                                                                                             Other US$1.1m
                                                  Tailings, access road

                                                                                                 21.6
                  19.3                19.1

                                                 10.5

                                                                      2.4

   POX          Malomir             Pioneer     Albyn          PPE Upgrade                   Exploration

                                                                                                               15
US$m
                    As at 1 Jan 2018

                                        585.1
                Capital expenditure

                 Bridge loans to IRC             134.4
                                                         57.0

     Interest accrued on borrowings
                                                                                                                                                                          2018 Change in Net Debt

                                                                  55.5

     Transaction costs in connection
                                                                   9.0

       with bank loans and notes

     Interest paid on prepayment on
                                        -3%
                                                                   6.8

          gold sale agreements

                    Income tax paid
                                                                   5.0
                                                                   1.9

                               Other

                     Increase in w/c
                                                          160.3

         Net cash generated by
      operating activities before w/c
                                                122.6

                 changes

                  As at 31 Dec 2018
                                        568.0
                                                                                Net Debt down c.3% to US$568m due to an increase in cash + cash equivalents of c.US$15m

16
Debt Profile
Net Debt at historical low for the last 7 years - a major part being long term

Debt Repayment Schedule                                     FY 2018 Debt Composition (Nominal)

                                            US$500m notes
                                             maturing Nov         Convertible Bond
                                                2022                   17%

                                                                                              Total Debt
                US$100m
                                                                                              US$600m
            convertible bond
             issue maturing                       500
                Mar 2020                                                                                   Guaranteed
                                                                                                             Notes
                                                                                                              83%
     –           100                –

    2019         2020              2021           2022

                               2020 Convertible Bond                2022 Guaranteed Notes

                    — Principal amount: US$100m             — Principal amount: US$500m
                    — Coupon: 9%                            — Coupon: 8.125%
                    — Maturity: Mar 2020                    — Maturity: Nov 2022
                    — Exchange price: US$0.1253             — Rating: S&P = B-, Fitch = CCC

                                                                                                                    17
Petropavlovsk’s Guarantee of IRC’s New Debt Facilities
A key milestone in de-risking the Group’s finances

                The Gazprombank Debt Facility                                                                            Petropavlovsk Guarantee Structure
— In Dec 2018, K&S (a subsidiary of IRC) entered into a                                           — Comprised of 5 guarantees which fluctuate over life of loan
  US$240m facility with Gazprombank
                                                                                                  — The current guarantee amount is US$160m comprising a
— Replaces an earlier facility with ICBC on more favourable terms:                                  Corporate and Fixed Term Guarantee

       — Extended repayment period through to 2026                                                — The Corporate Guarantee will be removed subject to certain
                                                                                                    operational conditions at the K&S project being met(1)
       — Principal repayment skewed to the latter part of the loan
         term

       — Amortisation schedule better aligned to the ramp-up of                                                                     Corporate             Fixed Term
         the K&S iron ore mine                                                                                                      Guarantee             Guarantee

                                                                                                                 2019
                                                                                                                                                            $40m
                                                                                                                 2020                   $120m
                                                                                                                 2021
                                                                                                                                                            $40m
                                                                                                                 2022
                                                                                                                 2023
                                                                                                                                                            $40m
                                                                                                                 2024
                                                                                                                 2025
                                                                                                                                                            $120m
                                                                                                                 2026

                         (1)These conditions are considered to be ‘base case’ and the Company expects these will be achieved within a 3 year time-frame
                                                                                                                                                                       18
Q1 2019 Update
Q1 2019 Production Update
 A healthy start to 2019 with c.25% of output attributable to the processing our own refractory ore

    Production in line        — Production / sales of 108Koz - with 28Koz of refractory gold processed at the POX Hub
       with target            — Strong contribution from Malomir underground with grades in excess of 8g/t

     Malomir flotation        — Successful test work carried out on concentrate from lower grade ores: 87% recovery with
  continues to produces
                                better than design concentrate yields (2.8% vs. 5.5%) à lower TCC
refractory concentrate with
   improved parameters        — c.29Kt of concentrate at 28g/t containing 26Koz of gold stockpiled for processing

   POX: Q1 recoveries         — c.32Kt of high-grade concentrate at 32g/t processed via POX Hub
      reached 91%,            — POX recoveries reached 91% in March, targeting 94% in H2 2019
autoclaves 3 + 4 ready for    — Autoclaves 3 + 4 tested + shown to be fully-functioning. Ready to begin operating at full
         launch                 capacity once supply of 3rd party concentrate secured

   Acquisition / trial of
 3rd party concentrate to     — Concentrate successfully trialled from two different sources
 optimise POX utilisation     — 2 x batches of concentrate secured, incl. 17Kt at 65g/t – 75g/t + 20Kt at 40g/t – 60g/t
           rates

     IRC: successful          — New loan facility with Gazprombank on better terms
   refinancing of ICBC        — Petropavlovsk has received c.US$57m as full repayment for 2 x bridge loans advanced to
  project finance facility      IRC in 2018

                                                                                                                            20
Q1 2019 Operations Review
Strong performance let down by water issues at Pioneer(2) – remain on track to meet 2019
guidance
        Q1 2019 Au Production by Mine(1)                                                         Q1 2019 Production Highlights

                                                                             Malomir production above budget
                                                                             — Non-refractory ore via RIP: gold recoveries exceeded
                                                                               budget by 6.2Koz due to larger quantity of high-grade ore
                Malomir (incl. POX)                                            mined from underground + higher recoveries
                  45Koz (41%)
                                                                             — Flotation: 25Kt of concentrate produced at avg. grade of
                                                                               23g/t
                                                                             — POX Hub: 32Kt of concentrate processed at avg. grade of
                     Total                                                     32g/t, with 2.8Koz of metal produced above quarterly
                  production                                                   budget
                                               Pioneer
                    108Koz                     22Koz                         Albyn production above budget
                                                (20%)
                                                                             — c.200Kt of ore at 1.2g/t was mined above budget, resulting
              Albyn                                                            in 4.3Koz of production above plan
           41Koz (38%)
                                                                             Pioneer production below budget

                                                                             — Underground delays caused by persistence of water inflow
                                                                               + lower grade material from open pit(2)

                                                                             — Production 6.7Koz below budget
                                                                             Company remains on course to meet FY2019 guidance

                 (1)   Percentages may not add up due to rounding
                 (2)   At Pioneer, all water has been pumped out of mine, cement backfill has been implemented and pump size increased   21
2019 Outlook

               22
2019 Outlook
Guidance has improved following successful commissioning of POX Hub

                               — Targeting 450Koz – 500Koz Au, an increase vs. 2018 due to contribution from POX Hub facility (incl.
                                 gold in concentrate stockpiles from FY 2018), but excluding potential upside from 3rd party concentrate
      Gold                       processing
   production                  — c.125Kt – 145Kt of refractory concentrate expected to be produced by Malomir flotation plant at 29gt –
                                 32g/t
                               — c.155Kt – 175Kt of refractory gold concentrate at 30g/t – 31g/t to be treated at POX Hub

                               — TCC FY 2019: US$850 – 950/oz, based on a RUB:US$ FX of 66, reflecting additional POX Hub
                                 ramp-up costs
     Costs
                               — Once POX is operating at full production from 2020, TCC expected to normalise at c.15% below 2019
                                 guidance

     Capex                     — US$45m – US$55m, consisting of sustaining, exploration + remaining POX capex

                               — Autoclaves 3 + 4 to begin operating at full capacity once supplies of 3rd party concentrate secured
  Development                  — Management + Board are considering benefits of accelerating construction of additional flotation lines
                                 at Pioneer / Malomir

  De-leveraging                — Net debt to continue to fall in line with ramp-up of production + increase in free cash flow(1)

                  (1)   Net debt (unaudited) as of 31 March 2019 reduced to c.US$550m
                                                                                                                                    23
Malomir Flotation Plant

                               24
24
Malomir Flotation Plant
 Production rates expected to increase from Q2 2019 once the Malomir flotation plant begins
 processing higher grade material to produce higher grade concentrate
Background                                                            Stage 2 flotation plant expansion

— Malomir flotation plant is a two-stage development                  — Stage 2 will expand Malomir flotation to 5.4Mtpa by adding a
                                                                        third 1.8Mtpa line to the existing two
— Stage 1: 3.6Mtpa capacity across 2 x 1.8Mtpa processing lines
  (line 1 launched Jul, line 2 Oct 2018)                              — Management considering fast-tracking expansion to maximise
                                                                        utilisation of POX Hub capacity (currently 2020)
— With both lines ramped-up, the flotation plant produced c.46Kt of
  high-grade refractory concentrate with grades of up to 36g/t in
  2018

Flotation process flowsheet improvements

— Gold losses reduced: more efficient flotation reagent to suppress
  carbon has eliminated need for carbon flotation stage

— c.50% improvement in concentrate grade vs. original design
  parameters (c.24g/t vs. c.36g/t – 40g/t)

— Concentrate mass pull improved from 5.5% to c.2.8% (using
  lower grade ores), reducing volume of material transported

Tests work has produced 25Kt of concentrate from low grade
material

— Low grade trial material (c.0.7g/t), stripped ahead of accessing
  main ore body was processed, achieving concentrate grades of
  22g/t – 24g/t at 87% recovery

— Resulting concentrate yield of c.2.8% significantly better vs.
                                                                                   Flotation cells at the Malomir flotation plant
  5.5% long-term plan, reducing transport volumes / costs

                                                                                                                                    25
The Pokrovskiy POX Hub
Our New Pressure Oxidation (POX) Hub Presents Growth Opportunities
Commissioned in Q4 2018, the POX plant is the result of almost a decade of work by our in-house
group of scientific experts + engineers
                                                                                  §     Over 50% of Russia’s defined gold resources are refractory or partially
                                                                                        refractory
                                                                                  §     Extraction of gold from refractory ore requires additional stages eg.
                                                                                        flotation, then pressure oxidation (POX) to extract gold from flotation
                                                                                        concentrate
                                                                                  §     POX is a globally recognised process for treating refractory ore and
                                                                                        flotation concentrate
                                                                                  §     The POX Hub repositions the Group as a technological + operational
                                                                                        leader, within Russia + in a global context
                                                                                  §     Optionality / growth: treatment of 3rd party concentrate, acquisition of
                                                                                        refractory deposits

          External view of the POX Hub complex                                          We expect to unlock c.60% of our R&R via the POX Hub

                                                                                           JORC Resources(1)                           JORC Reserves(1)

                                                                                                Refractory                                  Refractory
                                                                                              60% / 12.3Moz                                65% / 5.3Moz

                                                                                                     20.5                                        8.2
                                                                                                     Moz                                         Moz

                                                                                              Non-refractory                              Non-refractory
                                                                                              40% / 8.2Moz                                35% / 2.9Moz
                        Autoclaves

                  (1) In accordance with the JORC Code, as at 31 Dec 2018. Resources (M,I&I) are inclusive of Reserves. For full details and asset by asset breakdown
                  please refer to the 2018 Petropavlovsk annual report                                                                                                27
Refractory Gold – the Journey from Mined Ore to Doré
Process flowsheet and parameters

                                                       28
POX Hub: Successfully Commissioned End of 2018
 Total installed capacity of 400Ktpa – 500Ktpa(1)

                                                                                          2019 plans
       Autoclaves 1 + 2                           Autoclaves 3 + 4
                                                                                          — Lines 1 + 2 at POX expected to treat 155Kt – 175Kt of
  – Commissioned Q4 2018                   – Tested in Q1 2019 à fully-                     refractory concentrate in 2019 at 30g/t – 31g/t
                                             functioning
  – 32Kt of concentrate                                                                   — This includes:
    processed at avg. c.32g/t              – Ready to start once 3rd
                                                                                                   — 125Kt –145Kt at 29g/t – 32g/t representing
    in Q1 2019                               party concentrate secured
                                                                                                     material mined in 2019
                                                                                                   — 29Kt at 28.2g/t representing material mined in
                                                                                                     2018 and stockpiled
100 - 125Ktpa(1) 100 - 125Ktpa(1)       100 - 125Ktpa(1) 100 - 125Ktpa(1)
                                                                                                   — 37Kt at 40-75g/t of 3rd party concentrate

                        40%                                                               2020 onwards
                                                                                          — Once additional flotation lines have been installed at
                                                                                            Malomir + Pioneer, POX will be able to treat up to:
    100%                                        100%                   100%
                        30%                                                                        — 200Ktpa of concentrate from Malomir (at 27%
                                                                                                     sulphur) from 2020
                                                                                                   — 240Ktpa from Pioneer (at 23% sulphur) from 2023
                        30%

 Autoclave 1         Autoclave 2          Autoclave 3             Autoclave 4

     Mined in 2019            Mined in 2018 and stockpiled                   3rd party concentrate

                              (1)POX capacity determined by sulphur levels, hence capacity shown here as ranges which depend on specific qualities of   29
                              source material (lower sulphur = higher POX plant capacity)
R&R / Exploration
Track Record of Resource Growth
As at 31 Dec 2018, Group Reserves & Resources totalled 20.5Moz Au, with Reserves of 8.2Moz
Au
— Following successful commissioning of POX, some transitional Resources and Reserves suitable for either RIP or refractory processing,
  were reclassified from non-refractory to refractory.
— As a result, and due to the success of 2018 exploration campaign, total refractory Resources increased by 2.7Moz to 12.3Moz
— There was a corresponding decrease in non-refractory Resources from 11.2Moz to 8.2Moz (this change also reflects mine depletion and
  disposals)

                            10.1        12.3         11.7         13.8
                                                                              14.0         14.4                                   8.2
                                                                                                        10.4         11.2

   2.1         6.0
                            13.0        12.8         12.1         12.0                                                           12.3
                                                                               9.3          9.3          9.3           9.6
   6.8         5.2
   1.4         1.9          2.4          3.8          5.1         5.9          6.6          7.2
                                                                                                        11.2         11.7        12.5

  2008        2009         2010         2011         2012        2013         2014         2015        2016         2017         2018
                     Refractory Resources              Non-Refractory Resources                Depletion + Disposals

                                                                                                                                    31
Mine by Mine JORC Resource Breakdown
New Resources at Pioneer, Albyn, Malomir and Pokrovskiy

                                                                Total JORC Resources (as at 31/12/2018)                                            Non-Refractory Resources
                                                                                                                                                      Refractory Resources
                                                                                                                                                          New Resources -
                                                                                                                                                            Explanation
                                                              8.2Moz                   20.5Moz                   12.3Moz
                                                               40%                                                 60%

                    Malomir                                      Pioneer                                       Albyn                                    Pokrovskiy
                    6.7Moz                                       4.5Moz                                       4.2Moz
                     97%                                          76%                                          79%

                    6.9Moz                                       5.9Moz                                      5.3Moz                                        0.9Moz
                                                                                                                          1.1Moz
                                                          1.4Moz                                                           21%
                                                           24%                                                                                              0.9Moz
                       0.2Moz                                                                                                                                100%
                         3%

                RIP tailings for                                                                                                                     Decrease due to
                                                                   Katrin
               reprocessing via                                                                     Albyn main ore body +                               disposals +
                                                                Nikolaevskya
             flotation + POX and                                                                      Unglichikanskoye                              sterilisation due at
                                                                Ulunginskaya
                Quartzitovoye                                                                                                                           POX facility

                                                                                                                                                                                32
Note: Tokur, not shown above, contains non-refractory Resources of 1.4Moz. For full details and asset by asset breakdown please refer to the 2018 Petropavlovsk annual report
IRC Limited

              33
IRC Limited (1029.HK)
Petropavlovsk has a 31.1% equity share in Hong Kong-listed iron ore producer IRC

                                   Who are IRC?                                                                          POG Equity Interest In IRC

A developer + producer of industrial commodities, principally                                Petropavlovsk is a 31.1% shareholder

iron ore                                                                                     — IRC is accounted for as an associate
— Based in the Russian Far East, IRC benefits from low                                       — Market value of US$46m as at 21 May 2018(1)

      production costs and proximity to China                                                — Petropavlovsk is assessing the best way to realise the value of its

— IRC was part of Petropavlovsk’s Non-Precious Metals Division,                                    interest in IRC
      before listing on the Hong Kong Stock Exchange in 2010                                 Petropavlovsk acts as a guarantor in relation to a US$240m

IRC’s key mining assets include:                                                             Gazprombank facility entered into by K&S (an IRC subsidiary) in
— K&S: a producing iron ore(1) mine with a 20 year mine life                                 Dec 2018

           — Located in the Jewish Autonomous Region, Russian                                — This new facility supersedes / replaces the US$340m facility

                Far East                                                                           entered into between IRC and the Industrial and Commercial Bank
           — Produces premium quality high grade 65% Fe iron ore                                   of China (ICBC) in 2010, enabling IRC to construct / develop the

           — Ramping up to phase I design capacity of 3.2Mtpa, with                                K&S mine
                option to increase to 4.6Mtpa (K&S Phase 1.5) and                            — New facility matures 2026 and is on better terms, with payments

                6.3Mtpa (K&S Phase II)                                                             aligned with the ramp-up and cash flows expected from production

— Kuranakh: on care + maintenance since Q1 2016                                                    at K&S
— Garinskoye: project is at an early stage of exploration

(1)   IRC market capitalisation as at close 25 April 2019 (US$149m, source: Bloomberg) x Petropavlovsk’s equity interest (31.1%) = US$46m

                                                                                                                                                                34
FY 2018 IRC Results
Strong FY performance due to successful continuation of K&S ramp-up + refinancing of ICBC project
finance facility

                        — Total revenue +39% to US$152m (vs. US$ 109m in 2017) due to increased K&S output
                        — EBITDA +42% to US$29m (vs. US$20m in 2017) due to stronger revenues + stricter cost-control
    Financials
                        — Net profit of US$68m (vs. US$113m in 2017)
                        — Impairment reversal of US$91m

                        — Iron ore concentrate production +43% to 2,235Kt (vs. 1,563Kt in 2017)
                        — Iron ore concentrate sales + 44% to 2,224Kt (vs. 1,539Kt in 2017)
                        — Avg. selling price of US$68/t (vs. US$70/t in 2017)
    Operations
                        — In Dec 2018, K&S achieved a record-breaking monthly production by operating at an average capacity
                          of c.84%
                        — Care + maintenance at Kuranakh mine remains satisfactory

                        — K&S (a subsidiary of IRC), entered into a new loan facility agreement with Gazprombank to refinance
    Corporate             existing ICBC loan, with principal repayments better aligned with ramp-up of K&S
                        — Mr Peter Hambro appointed as Non-Executive Chairman of IRC

                        — Russian + Chinese sections of Amur river bridge successfully connected
   Amur bridge          — The bridge is expected to be operational in Sep 2019 once customs checkpoints + other ancillary
                          infrastructure are in place

                                                                                                                            35
Appendix

                36
36
Corporate Structure + Overview

                                                                           Shareholder Structure (as at 31 March 2019)
                                                                                                                   Kenges Rakishev
                                                                                                                 (via Fincraft Holdings
                                                                                                                    Ltd & VTB Bank)
                                                                                     Other                               22.4%
                                                                                     36.7%

                                                                                                                         Sothic Capital
                                                                                                                            10.9%

                                                                                                                   Prosperity Capital
                                                                                  Everest Alliance                      8.3%
                                                                                       4.6%
                                                                                                           DE Shaw & Co
                                                                                               Slevin          7.8%
                                                                                               4.6% RCB Bank
                                                                                                      4.7%

                 Share Price, Gold Price, FX(1)                                  Share Price and Trading Volumes(1)

 Price (GBP, pence)                          8.3p             9.0p                                                                        50m
                                                                                             Price               Vols
 52 Week Range                            5.2p – 8.4p         8.5p
 Avg. Daily Vol (12m)                     3,644,578                                                                                       40m
                                                              8.0p
 Shares outstanding                     3,307,151,712
 Market Cap.                          £274m (US$356m)         7.5p                                                                        30m
 EV                                   £711m (US$924m)         7.0p
                                                              6.5p                                                                        20m
 Gold PM Fix                              $1,284/oz
 52 Week Range                    US$1,178/oz - US$1,344/oz   6.0p
                                                                                                                                          10m
                                                              5.5p
 USD:RUB FX                                  64.8
 52 Week Range                            61.2 – 70.5         5.0p                                                                        0m
                                                                     (1) Data as at market close 26 April 2019

                                                                                                                                          37
FY 2018 Operations Overview
Production summary

Mining                         Units   FY 2018   FY 2017
Total material moved          m3 000   44,383    57,539
Ore mined                      t 000   10,294    17,990
Average grade                   g/t      1.2       0.9
Processing
RIP
Total milled                  t 000    13,595    16,620
Average grade                  g/t       1.0       0.8
Gold content                   Koz      417       448
Recovery rate                   %       84%       80%
Gold recovered                 Koz      351       360
Heap Leach
Ore stacked                   t 000     701       1,250
Average grade                  g/t      0.5        0.4
Gold content                   Koz       11         18
Recovery rate                   %       54%        50%
Gold recovered                 Koz        6          9
Gold in concentrate – POX      Koz       52          -
TOTAL gold production          Koz      422        440
Gold sales                     Koz      370        440
Costs
TCC                           US$/oz     786      741
AISC                          US$/oz    1,117     963

                                                           38
You can also read