Strategic Spares Warehouses - Inverness - August 2021 - SSEN Transmission
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
www.ssen-transmission.co.uk/projects/strategic-spares-warehouses
02
www.ssen-transmission.co.uk/projects/strategic-spares-warehouseswww.ssen-transmission.co.uk/projects/strategic-spares-warehouses
Who we are
We are Scottish and Southern Electricity Networks Transmission (SSEN Transmission),
operating under licence as Scottish Hydro Electric Transmission Plc (SHE
Transmission) for the transmission of electricity in the north of Scotland.
What is the difference between
Transmission and Distribution?
Electricity Transmission is the transportation of electricity from
generating plants to where it is required at centres of demand.The
Electricity Transmission network, or grid, transports electricity at
very high voltages through overhead lines, underground cables
and subsea cables. Our transmission network connects large scale
generation, primarily renewables, to central and southern Scotland
and the rest of Great Britain. It also helps secure supply by providing
reliable connection to the wider network of generation plans.
The Electricity Distribution network is connected into the
Transmission network but the voltage is lowered by transformers at
electricity substations, and the power is then distributed to homes
and businesses through overhead lines or underground cables.
Overview of Transmission Projects
In total we maintain about 5,000km of overhead lines and
underground cables – easily enough to stretch across the
Atlantic from John O’Groats all the way to Boston in the USA.
Our network crosses some of the UK’s most challenging
terrain – including circuits that are buried under the seabed,
are located over 750m above sea level and up to 250km long.
The landscape and environment that contribute to the
challenges we face also give the area a rich resource for
renewable energy generation. There is a high demand to
connect from new wind, hydro and marine generators which
rely on Scottish and Southern Electricity Networks to provide a
physical link between the new sources of power and electricity
users. Scottish and Southern Electricity Networks is delivering a
major programme of investment to ensure that the network is
ready to meet the needs of our customers in the future.
Our responsibilities
We have a licence for the transmission of electricity in the
north of Scotland and we are closely regulated by the energy
regulator Ofgem.
Our licence stipulates that we must develop and maintain
an efficient, co-ordinated and economical system of
electricity transmission.
03
www.ssen-transmission.co.uk/projects/strategic-spares-warehouseswww.ssen-transmission.co.uk/projects/strategic-spares-warehouses
Coronavirus: Covid-19 pandemic
As transmission network operator in the work that is essential to the safe and reliable supply of electricity
in the medium term, which includes meeting our regulatory
north of Scotland, we play a vital role in obligations until the end of the coming winter. In conducting
powering the country, providing a safe and this critical work, there will be the need to be active on certain
reliable supply of electricity at local, regional construction sites. We will continue to engage constructively
with all relevant authorities, adapting our advice in line with what
and national level, on which the people and is clearly an evolving situation.
organisations whose work is critical to the
Coronavirus response depend. Whilst we are still present at some sites, all staff that can work
remotely are now working from home, actively reducing
Our employees are working 24/7 to keep the network running, the number of staff onsite. We are mindful of the current
providing an essential service transporting energy to where it is environment and our numbers and activities are much reduced
needed. Working in some of the remotest parts of the UK, our as a consequence of this. For those based at site, increased
employees and supporting contractors need to be able hygiene and social distancing measures are being adhered
to move around the UK to ensure this work continues. to as per Scottish Government guidelines.
The Covid-19 outbreak and the necessary social measures We also deem it critical to ensure that we continue to submit
introduced by government are unprecedented in recent times planning applications for future developments which are
and we know that for the customers and the communities we deemed essential to operating the transmission network in a
serve, this may lead to concerns about the essential services we safe and secure manner for the future.
all rely on. Since the outbreak we have been collaborating daily
with UK and Scottish Governments and local authorities across We are committed to continuing quality engagement with all
our network to ensure the continued safe and reliable supply our stakeholders as we all respond to the challenges facing us in
of electricity. the weeks and months ahead. You have our commitment that
we will keep you up to date on what this means for our
In the absence of specific guidance and with companies customers, communities and stakeholders.
understandably expected to use their judgement on what is
critical, we are currently deeming critical activity to include
04
www.ssen-transmission.co.uk/projects/strategic-spares-warehouseswww.ssen-transmission.co.uk/projects/strategic-spares-warehouses
Project overview
SSEN Transmission has a need for improved materials management and warehousing capabilities.
This relates to the need to improve overall electricity network infrastructure performance
through reliability, availability and maintainability of asset and spares’ inventory.
Existing facilities for the storage of network materials are in unsuitable locations and require updating. The Government’s drive to
‘net zero’ means that there will be expansion of the electricity network and in short there is a greater need for improved reliability and
system resilience overall.
Much of the SSEN transmission network is designed to be highly resilient to asset failures. However, if lead times are significant then
this can lead to increased risk to the remainder of the network. It is therefore critical, for SSEN Transmission to obtain, store and
manage a certain level of spare materials and allow for dispatch from a key strategic locations. The overall benefits of the strategic
spares warehouses can be summarised as follows:
• The provision of modern, safe, secure and efficient working environment with managed and controlled stock.
• Reduced customer restoration times in the event of a network failure.
• Overall system security increased as able to facilitate outages in short order.
Project timeline
Autumn Winter Spring Summer Winter
2021 2021 2022 2022 2024
Planning Construction
Planning Appoint Final
Application works
submission contractor commissioning
granted commence
05
www.ssen-transmission.co.uk/projects/strategic-spares-warehouseswww.ssen-transmission.co.uk/projects/strategic-spares-warehouses
Our proposed solution
Our proposal is to construct a 7500m2 strategic spares warehouse at the established Inverness
Airport Business Park (IABP) development adjacent to Inverness Airport. This facility will
incorporate heavy lifting facilities, bunded areas for oil filled plant, bespoke storage areas
and office and welfare areas for staff. In line with SSEN Transmission’s core value of net zero,
Electric Vehicle (EV) charging points will be installed and photovoltaics (PV) installations will be
considered if practical.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A1 LIST OF ALL RELEVANT DRAWINGS OR DOCUMENTS THAT DIRECTLY RELATE TO
A THE CURRENT REVISION OF THE DRAWING A
DOCUMENT REFERENCE:
NOTES:-
1. ALL DIMENSIONS GIVEN IN MILLIMETRES (mm) U.N.O.
Electricity
Distribution Site
B LEGEND:- B
PROPOSED SITE BOUNDARY 19,915sqm (EXISTING SITE C &
5260sqm ACQUIRED OF SITE B)
AREA OF SITE B (5260sqm) REQUIRED FOR SITE C
1
C C
13.8m
12.7m
D D
Tks
El Sub Sta
Inverness Airport Business Park
L Twr
VALLAN
E E
ta
bS
CE ROAD
Su
El
SITE LOCATION
NOT TO SCALE
9.0m OS MAP NH
F REPRODUCED BY PERMISSION OF ORDNANCE SURVEY ON BEHALF OF HMSO. F
CROWN COPYRIGHT AND DATABASE RIGHT 2016. ALL RIGHTS RESERVED.
ORDNANCE SURVEY LICENCE NUMBER EL273236.
G G
P
STO
BUS
H BUS H
STO
P
PRELIMINARY DESIGN ONLY
J
NOT TO BE USED FOR J
CONSTRUCTION
K
DRAFTRev: Drawn: Approved: Description:
K
XX XX FOR INTERNAL COMMENT ONLY.
0A Checked: Date:
XX XX-XX-XX
SSE Inveralmond House, 200 Dunkeld Road
Perth, PH1 3AQ, UK www.sse.com
L Project: L
SITE LAYOUT
SCALE 1:1000 Project Number: LT0000## Location:
Title:
PROPOSED SSEN WAREHOUSE
SCALE AT 1:1000
0m 25m 50m 75m 100m Drawing Status: For Information Drawn: PF
Scale: 1:1000 @ A1 Checked:
Date: 23.09.20 Approved:
M Drawing Number: Sheet No: Revision No: M
Date Plotted: 23.09.2020
File Name: LTXX_AAAA_1104_0001_Proposed SSEN Warehouse Layout.dwg LTXX_AAAA_1104_0001 00 0A
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Proposed location plan
As part of the original Masterplan, planning consent in principle for industrial and storage uses has already been secured at IABP.
Given the existing in principle consent, this application will be in relation to approval of matters specified in conditions, covering
the detail of the siting, design and means of access for the development.
The development by way of the two proposed buildings will have the form and character of typical warehouse buildings which
are standard within the environs of the airport.
06
www.ssen-transmission.co.uk/projects/strategic-spares-warehouseswww.ssen-transmission.co.uk/projects/strategic-spares-warehouses
Project details
The strategic spares warehouse in Inverness will be a standard steel framed design with a pitched
roof and wall cladding within which the majority of SSEN Transmission’s spares will be stored.
There will be 2 No. buildings (possibly linked) length of 100m, depth of 40m and an eaves height
of 10.2m.
Standard construction methods will be utilised for the project consisting of earthworks to establish the formation platform, foundations
and drainage. Structural steel erection will follow on with both roof and wall cladding being installed prior to the casting of the
concrete floor slab.
Internal fit out of the building will then take place whilst external parking and landscaping is ongoing.
Legend:
EGRESS
Notes:
DRAFT
Rev Description Date Issued by
0A For Internal Comment Only 17.03.21 L.Donaldson
www.sse.com
This drawing is protected by copyright and the information contained
therein is confidential.
The drawing may not be copied and the information contained therein
may not be used, or disclosed to a third party, wholly or in part except
with the written permission of, and in the manner prescribed by
SCOTTISH and SOUTHERN ENERGY PLC 2020
ACCESS ROAD
Not Approved
Substation Name
Substation Code Stage
DRAFT
INNES
Project Title
INVERNESS WAREHOUSES
CONCEPT
DRAFT
Project Number Voltage
LT253
LAYOUT Drawing Title
PROPOSED STRATEGIC
WAREHOUSES
Drawn By Checked By Approved By
L.Donaldson
Previous Drawing Number
Drawing Number
LT253_INNE_0805_0001_03
17/03/2021 13:51:21
Status Code Status Code Description
S0
Sheet No. Date Scale (@ A1) Revision
3 11/03/21 0A
A welfare compound for the work force will be established within our plot area for the duration of the construction period.
It is envisaged that the largest strategic spare delivered to the site after construction is most likely to be a Super Grid
Transformer weighing approx. 200T.
Swept path analysis have been carried out to ensure the existing road infrastructure is capable of coping with
these deliveries.
07
www.ssen-transmission.co.uk/projects/strategic-spares-warehouseswww.ssen-transmission.co.uk/projects/strategic-spares-warehouses
Environmental impacts
Landscape and visual Habitat and species
A landscape and visual appraisal will be carried out Most of the habitats within the site are arable, scrub and
to understand how the project will look within the neutral grassland. A conifer plantation has been felled
surrounding area. with the ground now dominated by gorse and broom
scrub with scattered broadleaved trees including cherry
A landscape plan will be developed in accordance with and rowan. The felled conifer plantation was mapped
the airport masterplan design guidance to integrate the as Long-Established Plantation Origin Woodland on the
development into its surrounding landscape. Ancient Woodland Inventory so forms part of a feature of
local/ regional importance.
It will be designed with biodiversity net gain principles
and be supported by a long-term habitat Moray Estates is committed to re-planting woodland in
management plan. the locality as an offset compensatory planting scheme.
The development of the on-site landscaping scheme will
consider opportunities for integrating trees and shrubs
for screening and biodiversity net gain; however, care will
be taken to ensure that the scheme will not attract high
numbers of birds towards Inverness Airport.
Cultural heritage
Ecological surveys are underway and pre-construction
surveys will also be undertaken to inform mitigation to
No statutorily protected cultural heritage features have minimise the effects on wildlife. The land forms part of
been recorded within the site. the habitat of badgers and it is proposed that a Species
Protection Plan will be implemented to minimise the risks
The remains of a croft house have been recorded within to badgers during the construction works.
the felled plantation.
An archaeological evaluation is proposed to be
undertaken to support the planning application.
Noise
Assessments of construction noise and operational noise
Traffic (relating to plant and equipment at the site) will support
the application.
A Construction Traffic Management Plan (CTMP) will
include the intended routing of construction-related
vehicles and routes for abnormal indivisible loads.
An assessment of operational phase traffic and abnormal
load routes for abnormal indivisible loads (such as
transformers) will be also be provided.
08
www.ssen-transmission.co.uk/projects/strategic-spares-warehouseswww.ssen-transmission.co.uk/projects/strategic-spares-warehouses
Striving for Net Zero - one project at a time
SSEN Transmission has set ambitious plans to reduce our own
emissions in line with what is required to meet net zero emissions,
these carbon reduction commitments have been verified by the
Science Based Target initiative, making SSEN Transmission the world’s
first electricity networks company to receive external accreditation
for a science-based target in line with a 1.5°C global
warming pathway.
Aligning with the 2016 Paris The strategic stores warehouse in Inverness
Agreement, the validation of will play its part in SSEN Transmission's plans
our ambitious carbon reduction for net zero as the locational advantages of
objectives will ensure that our the site identified at Inverness is anticipated
business follows a credible and to lead to benefits with regard to improved
scientifically verified carbon repair times, to reduced network and
reduction pathway as we customer risks and will help rationalise
support the journey to net zero spares’ holdings and reduce consequences
emissions. SSEN Transmission of system failures by way of improved
is committed to reducing our logistics and advantageous strategic access
emissions by one third by 2026 to the network area. The selected location
as part of our RIIO-T2 Business also has excellent transport links being in
Plan, A network for Net Zero. close proximity to major trunk roads.
We are delighted
to be a principal
partner to the UK
Government at
COP26, as we seek
to make net zero a
reality.
09
www.ssen-transmission.co.uk/projects/strategic-spares-warehousesWhat happens now and
how do I have my say?
We understand and recognise the value of the Community Liaison Manager,
feedback provided by members of the public
Louise Anderson
during all engagements and consultations.
Without this valuable feedback, the project
development team would be unable to progress
louise.anderson@sse.com
projects and reach a balanced proposal.
We are keen to receive your views and comments in regards to
the following questions: 07384 454 233
• How would you rate the overall quality of information Louise Anderson
presented within this consultation brochure? Scottish and Southern
Electricity Networks,
• How do you feel regarding our proposals to build 200 Dunkeld Road,
a strategic spares warehouse at our chosen site in Perth, PH1 3AQ
Inverness?
• Has the requirement for the warehouse been adequately
explained? Additional information
• Do you feel the project team have given enough Information will also be made available via the project
consideration to environmental impacts associated with webpage and social media channels:
the project to ensure a satisfactory development?
• Do you have any further comments you would like the
Project Website: www.ssen-transmission.co.uk/projects/
project team to consider?
strategic-spares- warehouses
Comments Follow us on Twitter:
@ssencommunity
Your views and comments can be provided to the project team
by completing a feedback form or by writing to Louise Anderson,
Community Liaison Manager.
Follow us on Facebook:
We will be seeking feedback from the members of the public @ssencommunity
and Statutory Bodies until 27 August.
www.s
sen-tra
nsmissi
on.co.
uk/pro
ject s/strate
gic-spa
All received feedback will be assessed and the proposed options
res-war
Your fe ehouse
s
edbac
k
adapted where necessary.
Thank
you for
our con taki
sultatio ng the time
n, plea
se com to read this
Please plete this consult
complet short feed ation boo
e in BLO back form klet. In ord
ments: CK CAP er to reco
her com ITALS. .
rd you
ide furt (Please r view
to prov tick one s and imp
e below Q1 box per rove the
use spac questio
Please How wo n only
)
effectiv
eness
consult you uld of
ation bro rate the ove
chure? rall qua
Excelle lity of
nt informa
tion pre
Good sented
within
Q2 this
How do Averag
e
in Invern you feel reg Poor
ess? arding
our pro
posals
Suppor to bui
t ld a stra
Neithe tegic spa
r suppor res war
t nor obj eho use at
Q3 ect our cho
Has the sen site
require Object
ment
for the
Yes propos
al for
No the war
ehouse
Unsure been ade
Q4 quately
Do you exp lained?
Full nam
e impact feel the pro
s associ ject
ated wit team have
Yes h the pro given eno
ject are ugh
No minimi considerati
sed as on to
Unsure much ensure
Address as pos environ
Q5 sible? menta
Do you l
have any
further
comme
nts you
would
like the
project
team to
conside
ne r?
Telepho
Email box.
se tick this
ect plea
the proj
ress on
d of prog
informe
be kept .
ld like to this box
If you wou please tick
nymous
ain ano
ts to rem
r commen
ld like you
If you wou
form.
www.s
feedback
sen-tra
lete this nsmissi
to comp ods below on.co.
g the time of the meth ite. uk/pro
takin by one ct webs jects/st
Than k you for leted form the proje rategic-
your comp es load from spares-
submit warehous ble to down wareho
Please @sse.com ic-spares- be availa Networks ose. uses
cts/strateg will also
e.anderson o.uk/proje ’s event Electricity this purp
Email: louis smission.c from today Southern feedback for
-tran ation Scott ish and using
www.ssen inform of orks
Online: and all the sly as part ricity Netw
s forms anonymou Southern Elect 11
nload : Comment and published ish and Scotl and No.
Dow used
can be you consent to
Scott tered in in
d Regis Registered
ack form form n Limite bution plc ic Power
on the feedb this feedback Powe r Distributioic Power Distri ern Electr
ation given completing Energy Hydro Electr 3AQ); and South ry Road, Read
ing,
Any informon report. By Southern Scottish PH1
ish and 43 Forbu
consultati name of: Scott No. SC213461; eld Road PerthForbury Place,
trading Scotland 200 Dunk One
orks is a tered in d House at Num
ber
icity Netw mission plc Regis s at Inveralmon tered Office
ern Electr Trans tered Office its Regis
and South Electric having
Scottish ; Scottish Hydro having their Regis No. 04094290
SC213459 3460; (all England & Wales SSE Group.
No. SC21 in the
Scotland n plc Registered bers of
are mem
Distributio RG1 3JH which
Berkshire,
10
www.ssen-transmission.co.uk/projects/strategic-spares-warehouseswww.ssen-transmission.co.uk/projects/strategic-spares-warehouses
Your feedback
Thank you for taking the time to read this consultation booklet. In order to record your views and improve the effectiveness of
our consultation, please complete this short feedback form.
Please complete in BLOCK CAPITALS. (Please tick one box per question only)
Q1 How would you rate the overall quality of information presented within this
consultation brochure?
Excellent Good Average Poor
Q2 How do you feel regarding our proposals to build a strategic spares warehouse at our chosen site
in Inverness?
Support Neither support nor object Object
Q3 Has the requirement for the proposal for the warehouse been adequately explained?
Yes No Unsure
Q4 Do you feel the project team have given enough consideration to environmental impacts
associated with the project to ensure a satisfactory development?
Yes No Unsure
Q5 Do you have any further comments you would like the project team to consider?
11
www.ssen-transmission.co.uk/projects/strategic-spares-warehousesPlease use space below to provide further comments:
Full name
Address
Telephone
Email
If you would like to be kept informed of progress on the project please tick this box.
If you would like your comments to remain anonymous please tick this box.
Thank you for taking the time to complete this feedback form.
Please submit your completed form by one of the methods below
Email: louise.anderson@sse.com
Online: www.ssen-transmission.co.uk/projects/strategic-spares-warehouses
Download: Comments forms and all the information from today’s event will also be available to download from the project website.
Any information given on the feedback form can be used and published anonymously as part of Scottish and Southern Electricity Networks
consultation report. By completing this feedback form you consent to Scottish and Southern Electricity Networks using feedback for this purpose.
Scottish and Southern Electricity Networks is a trading name of: Scottish and Southern Energy Power Distribution Limited Registered in Scotland No.
SC213459; Scottish Hydro Electric Transmission plc Registered in Scotland No. SC213461; Scottish Hydro Electric Power Distribution plc Registered in
Scotland No. SC213460; (all having their Registered Offices at Inveralmond House 200 Dunkeld Road Perth PH1 3AQ); and Southern Electric Power
Distribution plc Registered in England & Wales No. 04094290 having its Registered Office at Number One Forbury Place, 43 Forbury Road, Reading,
Berkshire, RG1 3JH which are members of the SSE Group.You can also read