120/25-kV Bonsecours Substation and 120-kV Supply Line
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
120/25-kV Bonsecours Substation
and 120-kV Supply Line
Conversion of the 49-kV System in Estrie
GENERAL INFORMATION • SPRING – SUMMER 2018
Current situation Recommended solution
The project area is currently supplied Hydro-Québec TransÉnergie’s recommended solution
by a 49-kilovolt (kV) system that was is to build a new 120/25-kV substation between
built by the Southern Canada Power the Lawrenceville and Valcourt substations, and
Company in the 1940s. Due to growth connect it to the grid with a 120-kV line. This new
in the region’s electricity demand, line, approximately 20 km long, will connect the
this system has reached its maximum new substation to Stukely substation in Stukely-Sud.
capacity.
The 49-kV Lawrenceville and Valcourt substations,
Hydro-Québec must increase the as well as some sections of the 49-kV lines, will then
system’s capacity to meet the be dismantled.
region’s future requirements.
This project is part of the plan The project will also require:
to convert Estrie’s 49-kV system, • Additions and changes to the distribution system
which began with the 2016 to connect local customers to the new substation,
commissioning of the new including the conversion of the 25-kV facilities
120/25-kV Adamsville substation belonging to BRP (Bombardier Recreational Products)
in Bromont. • Related work at Stukely substation
• Reconstruction of an existing line in the regional
county municipalities (MRCs) of Brome-Missisquoi
and La Haute-Yamaska (the 120-kV Cleveland–
Waterloo line).Study area
The study area covers 143 km2 and includes five municipalities in the MRC
of Val-Saint-François—Valcourt, Canton de Valcourt, Lawrenceville, Bonsecours
and Sainte-Anne-de-la-Rochelle—as well as Stukely-Sud and Eastman,
two municipalities in the MRC of Memphrémagog.
The study area was selected to encompass all the elements from the
biophysical environment, human environment and landscape that are
likely to be affected by the project.
Technical and environmental studies
In the coming months, Hydro-Québec will conduct technical studies and
detailed environmental inventories to identify the project’s characteristics
and obtain an in-depth understanding of the host environment.
Once these studies are completed, the project team will be able to identify
potential substation locations and route variants that will be presented
to the public. These locations and routes will be subject to comparative
analyses based on environmental, technical and economic criteria. From
the beginning, and at every step of these studies, Hydro-Québec will take
the community’s concerns into account to determine the line route and
location with the least impact.
272°25' 72°20' 72°15'
Project
Riv component
Maricourt,
ièr
e
Study area
M Brandy
No
ire
Substations and power transmission lines
Riv
Roxton, CT
#
ièr
49 kV u
e
# 49 kV (private substation) ss
ea
243
ui
222 R
#
Noir
120 kV
e
45°30'
Boundaries
45°30'
Valcourt, V
Regional county municipality (MRC)
222
Municipality
533 #
# Bombardier Produits
Saint- Valcourt substation Récréatifs inc. substation
rd
Racine, M
ga
Joachim-de-
re
(to be dismantled)
au
Shefford, M
Be
da
Ruisseau ACTON LE VAL-
Ben
(MRC) SAINT-FRANÇOIS Valcourt, CT
(MRC)
seau
Ruis
Béthanie, M
LA HAUTE-
YAMASKA
(MRC)
Lawrenceville, VL Lac des
Français
# Lawrenceville substation
(to be dismantled)
Lac
45°25'
243 Bowker
45°25'
Bonsecours, M
Riviè
524
ire
re
No
Sainte-Anne-
Ro u
de-la-Rochelle, M
ge
re
Riviè
Orford, CT
Lac
Stukely
Shefford, CT
MEMPHRÉMAGOG
Stukely- (MRC)
Sud, VL
Lac Parc
45°20'
Brousseau
Lac national du
45°20'
Parker Mont-Orford
112 Stukely
Eastman, M
substation 1388
1192 0 1.1 2.2 km
#
540 MTM, zone 8, NAD83 (SCRS)
File: 7576_bu_slq_001_180518a.mxd
Lac
a ms 523 d'Argent Eastman
illi
Qu substation
# 513
10 Austin, M
Magog, V
540
Lac
u
Saint-Étienne-
ea
Bolton-Ouest, M
6 Orford 112
53
iss
de-Bolton, 245
Ru
BROME-MISSISQUOI M
(MRC) 72°25' 72°20' 72°15'
Bolton-Est, M
Document for information purposes only. For any other use, please contact Géomatique at Hydro-Québec Innovation, équipement et services partagés.
3Public participation Project development phases
Favorable reception by local
communities is an essential DRAFT DESIGN
condition for Hydro-Québec Studies and public
projects. As a result, the company consultation Spring 2018 – spring 2019
will implement a public participation
and consultation process to ensure PROJECT
that project studies are carried
out in collaboration with the host Permitting 2019–2020
communities. The company will
Construction 2021–2022
thus be able to take into account
the concerns and expectations Commissioning 2022
expressed by the public and by
key stakeholders so as to adapt Dismantling of 49-kV structures 2023
the project as best possible to
local realities.
Tangible support
for community
development
Hydro-Québec’s projects provide For more information
an opportunity to participate in
the host communities’ development. Info-project Line
Funding is made available to
eligible organizations through Estrie-Montérégie
Hydro-Québec’s Integrated 1 877 653-1139
Enhancement Program (IEP) for
community improvement projects NADINE JEANNOTTE
relating to the environment, Advisor – Community Relations – Estrie
municipal, community or and Montérégie
recreational infrastructure, or Direction – Affaires régionales et collectivités
regional or tourism development. 705, boul. Clairevue, 1er étage
Saint-Bruno-de-Montarville (Québec)
J3V 6B6
ramrichelieu@hydro.qc.ca
www.hydroquebec.com
Ce document est également publié en français.
This is a translation of the original French text.
2018E1425-A
100 %You can also read