April - September 2008 Vol. No. 31 Issue No. 2 - lntecc

Page created by Stacy Lang
 
CONTINUE READING
April - September 2008 Vol. No. 31 Issue No. 2 - lntecc
April - September 2008 • Vol. No. 31 • Issue No. 2
April - September 2008 Vol. No. 31 Issue No. 2 - lntecc
Contents
     Expanding horizons of the Indian Steel Industry
                                                            Vol. No. 31
                                                            Issue No. 2

                                                                    4
                                                                          Steel is Our Strength                                                                              Stoves at Blast furnance ‘G’

     K.G. Hariharan - Steeling the Show
     Forging relationship with a Steel Major!
                                                                   16
                                                                   20
                                                                          L   arsen & Toubro has been in the forefront in the
                                                                              implementation of steel plants since the late fifties when
                                                                          construction contracts were undertaken to build the Blast
     Continuing saga of a Growing Relationship!                    24     furnaces. This was followed by the beginning of the very
     Blast Furnace ‘H’ Blown in at Tata Steel, Jamshedpur          28     long innings with TATA STEEL (TISCO in those days) which
     The Largest Indian Blast Furnace at JSW Steels                34     started with a very small package in the Coke Oven By
                                                                          Product Plant and steadily grew to cover the entire gamut
     RINL-Vizag Steel moving at a fast pace                        40
                                                                          of construction and erection of all the different upstream and
     Integrated Plant for Bhushan Steel                            42
                                                                          downstream units within the integrated steel plant.
     EDRC - The Engineering Powerhouse                             48
                                                                          The subsequent years were a period of steady growth for the
     Sinter Plant for ISP Steel plant in Burnpur                   52     steel industry largely contributed through the public sector
     Kaleidoscope                                                  55     enterprises. While TISCO continued its modernisation of the
                                                                          antiquated plant through the eighties and thereby providing
                                                                          opportunities to L&T for the construction and erection of
                                                                          the various units, decontrol of the industry in 1992 brought
                                                                          about a tremendous surge of activities and the industry was
                                                                          propelled into a phase of high growth. It was during this
                                                                          period that several private steel producers went on

     I ron & Steel has had a major influence on our lives,
       from time immemorial. In today’s fast paced world, it is
     impossible to think of a place or a thing without iron and
                                                                          implementation spree and L&T saw itself involved with
                                                                          several steel plants. Notable among them were the ISPAT
                                                                          group who entrusted upon L&T the construction of the major
     steel. The homes we live, buildings and factories we work,           units of their steel plant in Dolvi including the dismantling and
     the cars we drive or any other transport you choose to                                                                                   significant player in the Steel Industry for turnkey large       plant and providing commissioning and performance
                                                                          rebuilding of the Blast Furnace from Germany. The period
     commute, the roads and bridges we traverse, we encounter                                                                                 solutions. Since most customers continued to prefer              guarantees. This places us in the highest echelons of the
                                                                          between 1992 to the present times have seen a growth in the
     countless facets of steel in all these structures, objects and                                                                           the fragmented package approach, L&T’s role in the               capability hierarchy and brings with it a responsibility which
                                                                          steel making capacity from 18MT to 60MT and the present
     myriad applications.                                                                                                                     construction work remained extensive. However with the           needs to be very carefully administered. We are gearing
                                                                          projections are that India will reach a steel making capacity
                                                                                                                                              award and successful execution of rebuilding of ‘F’ Blast        up our systems and processes to bring our execution
     Steel is by far the most important, multi-functional and most        in excess of 100MT (the second biggest capacity after
                                                                                                                                              Furnace of Tata Steel it leapfrogged into a major league         capabilities to the highest benchmark.
     adaptable of engineered materials and the development of             China) in the next 5 years.
                                                                                                                                              for building Blast Furnaces in EPC with major global             While we take pleasure in highlighting the business
     mankind would have been impossible without steel.                    For L&T and Minerals & Metals BU in particular the period
                                                                                                                                              technologists. It was followed up with other critical projects   achievements of the BU through this special issue of
                                                                          between 2000 till date has been very significant. While
     ECC, the Construction Division of L&T has been associated                                                                                of ‘G’ BF, ‘H’BF, RSP / ISP Rebuild, JSW 3 and 4, Bokaro         ECC Concord, it would be most appropriate to take a
                                                                          L&T had been involved in EPC jobs in the past in certain
     with development of iron & steel industry in India from its                                                                              Rebuild, Sinter Plants 3 and 4 of Tata Steel and now with        moment’s break and reminisce the towering personalities
                                                                          projects like the Billet Caster of Durgapur Steel Plant, SAIL
     very beginnings. It has been involved in almost all phases                                                                               ISP, KPO, Bhushan and RSP. With a purported business             who have contributed immensely to the present position
                                                                          in consortium with CONCAST Zurich and Slab Caster
     of development till the recent modernisation & expansion                                                                                 mix of EPC, discrete EPC and construction in mind, the BU        and success of this BU. While Mr. K.G.Hariharan obviously
                                                                          for Bokaro Steel Plant with VAI, Linz, it was still not a very
     programmes of all Public Sector Steel plants as well as                                                                                  has also continued to pursue major construction packages         needs to be largely credited for most of these successes,
     private players including construction of Greenfield plants.                                                                             in the steel melt shop and rolling mills for customers like      other names that immediately come to mind are those of
     Today, by virtue of its long experience, expertise and speed         Corex Plants at Jindal Steel                                        JSW, Bhushan Steel and others.                                   Mr. A.K. Mukherjee, Mr. S.K. Madhok, Mr. A. Sivasubbu,
     of construction with high quality, L&T has set world-class                                                                               The Minerals & Metals BU of MMH&W OC operating out               Mr. P.J. Babu, Mr. M.K. Mohanty and more recently
     standards and new benchmarks in the industry.                                                                                            of Kolkata is firmly in the saddle with very clear Business      Mr. N.R. Sudheer and Mr. D.R.Ray. I wish to use this
     In this issue of ECC Concord, we present to you the Indian                                                                               Objectives and a perspective of the future. The extent of        opportunity to thank all of them for their huge contribution
     Steel Scenario, the wide variety of projects executed /                                                                                  client confidence is reflected in our order book position        in building the Steel industry in their respective eras and
     under execution in the steel sector including a spotlight on                                                                             which includes 6 very large capacity blast furnaces and          in the process establishing L&T’s brand name in the
     the ECC’s Steel Man – K.G. Hariharan. Hope, you will find                                                                                6 equally large capacity sinter plants and Pellet Plants in      industry.
     this interesting. Happy reading!                                                                                                         addition to downstream steel making and rolling projects         In conclusion, I would like to state that “Steel is our
                                                                                                                                              which are in the pipeline. These projects are contracted         Strength” and we will continue to play a more significant
                                                                                                                                              in the EPC mode and will encompass delivery of detailed          role in this sector, in the years to come.
             Editor     V.S. Ramana                                                                                                           engineering based on the process know-how and basic
 Editorial Team K. Sridharan | Alex Benjamin | V. Ramesh Kumar |                                                                              engineering of our technology partners, sourcing/                                                  Derek Michael Shah
		Ashwin Chand | V. Eswar | Subha Anand                                                                                                       manufacturing of equipment, site installation of complete                                        Head-Minerals & Metals BU
     Photography        V.S. Natanavelu
   Design & Layout      Srishti Graphics Design, Chennai.
April - September 2008 Vol. No. 31 Issue No. 2 - lntecc
J    N Tata pioneered Steel Industry in India          Projecting such investments, capacity and

                Expanding horizons of the
                                                                     while Pandit Jawaharlal Nehru had a vision        growth rates have its own pitfalls vis-à-vis past
                                                                for the country and iron & steel making for the        experiences, inadequate growth of supporting

              Indian Steel
                                                                nation’s growth was a priority in his agenda. He       sectors, infrastructure as well as the general
                                                                adopted the socialistic route and government           downturn of a booming economy. However,
                                                                sector organisations were at the forefront of this     achieving a target of 120 MT by 2020 and a per
                                                                developmental effort. It was mainly during the         capita consumption of 90-100 kg is a more orderly
                                                                first and second five year plans that massive          and reasonable objective. Even this conservative
                                                                investments were made in the public sector steel       outlook would mean an annual capacity addition

                      Industry
                                                                plants and the industry grew from around 2 MT to       of 6 million tons which is equivalent to adding 2/3
                                                                20 MT during 1950 to 1990. This was the period         large capacity (3000-4000 cum) blast furnaces
                                                                which saw the growth of the steel conglomerates        and the associated upstream and downstream
                                                                at Bhilai, Bokaro, Durgapur, Rourkela and              facilities for the steel plant every year for the next
                                                                Vishakapatnam.                                         12 years or commissioning 2 three million ton
                                                                                                                       capacity integrated steel plants each year. Chart
                                                                In the Industrial policy announced in July 1991,
                                Vaskar Mukherjee                Iron and Steel industry was removed from the list
                                                                                                                       below shows the conservative and ambitious
                                Minerals & Metals BU, Kolkata   of industries reserved for the Public Sector and
                                                                                                                       estimates of the growth of the Indian steel industry
                                                                                                                       up to 2020.
                                                                also exempted from the provisions of compulsory
                                                                licensing under the Industries (Development &
                                                                Regulation) Act 1951. With effect from May 24,
                                                                1992 Iron & Steel industry has been included in
                                                                the list of high priority industries for automatic
                                                                approval for foreign equity investment up to 51%.
                                                                This limit has been recently increased to 100%.
                                                                Price and distribution of steel were deregulated
                                                                from January 1992.

                                                                Indian steel industry is growing and the present
                                                                rise whose beginning can be traced to year 2001
                                                                seems to have gained critical mass to an extent that
                                                                its shear momentum would carry it forward for a
                                                                few more years and would definitely be considered
                                                                as the longest period of boom for the industry.
                                                                Today the production capacity level is in the region
                                                                of 60 MT and a quick estimate on the brown field       The World Steel Industry                                  The growth of the
                                                                expansion projects that are being implemented                                                                    Indian steel industry
                                                                                                                       USA, Europe, erstwhile USSR and Japan
                                                                is likely to bring this figure up to 90 MT by 2012.                                                              up to 2020
                                                                                                                       dominated the world scenario in technology
                                                                Adding the figures of the new Greenfield plants to
                                                                                                                       prowess and production capacities up to the
                                                                the above, it would touch a figure of 120 MT by
                                                                                                                       seventies. The oil crisis or the ‘energy shock’
                                                                2015. While one would not like to immediately take
                                                                                                                       as it is popularly known during the seventies,
                                                                the figures beyond this, industry optimism, the
                                                                                                                       the declining post war reconstruction activities,
                                                                need for growth, the present trend and the quest
                                                                                                                       collapse of the Soviet Union and its economy as
                                                                for betterment of the infrastructure and socio-
                                                                                                                       well as the environmental consciousness brought
                                                                economic scenario may justify planning a steel
                                                                                                                       forth negative influences on the steel industry in
                                                                production level of 180 MT by 2020. This would
                                                                                                                       the industrialized world.
                                                                bring the annual per capita steel consumption to a
                                                                respectable level of 130-150 kg with indigenously      The growth of the global steel industry during the
                                                                produced steel. This compares admirably well with      last 7 decades have risen from 189 MT in 1950 to
                                                                the industrialized countries of the world.             850 MT in 2000 and projected to reach 1343 MT by
      Blast Furnace ‘F’ for
                Tata Steel

ECC Concord | Apr - Sep 08 4                                                                                                                                               5 ECC Concord | Apr - Sep 08
April - September 2008 Vol. No. 31 Issue No. 2 - lntecc
2010. The last 20 year period of the 20th century       Centres bear testimony to the fact that steel is a     Smelting Reduction process based plants have            have truncated operations like in Neelachal Ispat
                           is considered as a period for rationalization of the    product which can be made only with a lot of grit,     established their usefulness to a limited extent        Nigam Limited (NINL), which is the largest in the
                           Industry, which resulted in closure of many plants.     determination, knowledge and financial resources       with one major steel manufacturer operating two         pig iron spectrum, to a large number of pig iron and
                           Technological developments also played its part         and growth in steel making capacity would have to      C-2000 Corex units (JSW Steel Ltd.)                     construction steel manufacturers who are spread
                           and there continued to be excess production with        be holistic and all inclusive.                                                                                 across India with a significant concentration in
                           depressed prices that brought about losses to           Operations which have short term perspectives          The Secondary Sector                                    eastern India.
                           businesses.
                                                                                   have no place in the steel industry and soon such      The secondary steel and allied industries have          There are many definitions for the secondary
                           It was during 1990s that the Indian steel industry      operations have to vacate the space for larger and     also achieved great resilience and few are in the       sector in the steel industry. Generally speaking
                           was liberalized and the new entrants and older          more optimized and efficient operations. While         threshold of graduating in the higher platform with     it encompasses all companies who have non-
                           players witnessed a torrid period of depressed          Tata has a 100 year history of excellence, SAIL is     their operational and growth performance. Many          integrated operations to produce steel & products
                           prices and many of the new and old players were         approaching its 50 years with great aplomb.
                                                                                                                                                                                                                                                               The process flow in a
                                                                                   There are other very well established players
                                                                                                                                                                                                                                                               BF-BOF based route
                                                                                   who while having a shorter history have no less                                                                                                                             integrated steel plant
                                                                                   credibility and achievement as the original players.                                          Lime Stone              Iron Ore                                              (Source Rourkela
                                                                                   Amongst these we can include RINL, Jindal group                                                                                                                             Steel-SAIL)
                                                                                   of steel companies, Essar steel, Bhusan steel and
                                                                                                                                                                                                                    Sinter Plant
                                                                                   Ispat industries.
                                                                                                                                                      Coal
                                                                                   The Integrated steel plants in India predominantly
                                                                                   follow the Blast Furnace - Basic Oxygen Furnace                                      Coke Ovens                       Blast Furnance
                                                                                   (BOF) route for steel making.

                                                                                   The blast furnace in one form or another has been
                                                                                   around for over 2000 years. Throughout history, it                                                                               Pig Casting M/c       Pig Iron
                                                                                   had to withstand fierce criticism and competition.
                                                                                   Despite innovation in the area of smelting reduction
                                                                                   technologies and the development of the electric
                                                                                                                                                                                                                BOF
                                                                                   arc furnace, the integrated steel making route
      The top ten steel    on the verge of being referred to the financial
                                                                                   remains the only viable option for large scale
   producing countries     reconstruction boards. China with a state controlled
                           economy was silently building the technology,           production of steel. Better understanding of the
            in the world
                           engineering, equipment manufacturing and                blast furnace process coupled with the innovations
  (2006-2007). (Source
                           steel production capabilities and was adding a          in basic oxygen steel making and continuous
      IISI publications)
                           capacity close to 20 MT every year. The net result      casting have ensured that this route will guarantee                                                                          Plate Fill
                           of this growth resulted in the dominance of China.      bulk steel production at the lowest cost and the
                                                                                                                                                                                                                                Plates
                           China’s insatiable appetite for steel impacted the      blast furnace will tower above all other iron making
                           global steel business and India was no exception.       methods.                                                                                                        CC Plates
                           The Indian steel industry first witnessed the revival   The Indian steel industry has also been experi-
                           of its fortunes in early 2001 and this has been a       menting with other technologies and process but                    HR Plates                 Shearing Lines                                     Pipe Plants       Pipes
                           period of steady growth since then. See chart           on a smaller scale and with a mixed bag of suc-
                           above for the top ten steel producing countries.        cess. They are briefly referred below:                    HR Coils for Sale                                                                      Silicon Steel Mill
                           Major Players                                           Gas based DR-EAF route plants are located in                                                                         Hot Strip Mill
                                                                                   western coast where natural gas is available, while
                           SAIL, Tata Steel and IISCO (now ISP SAIL) are the                                                                                            Annealing Lines     CRM
                                                                                   a large number of small capacity coal based DR-                                                                                                  CRNO
                           three major industry entities who have played a                                                                 CRCoils/Sheets
                                                                                   EAF plants are scattered across the country.
                           pioneering role in the growth and development of
                           the steel Industry in India. Each have demonstrated     Hybrid plants using BF-DR-EAF routes are also
                           the ability to nurture and sustain an all inclusive     establishing their presence but in smaller scales      ET Plates      Tinning Line                                    Pickling Lines
                           growth spectrum which is what steel is and today        and limited numbers and most of these DR plants
                           the steel townships with their ancillaries, R&D         are coal based except Ispat, Essar and Vikram                           GPGC     Galvanising Lines
                           establishments and Management Development               who have gas based plants.

ECC Concord | Apr - Sep 08 6                                                                                                                                                                                                                             7 ECC Concord | Apr - Sep 08
April - September 2008 Vol. No. 31 Issue No. 2 - lntecc
• Relocation of Midrex plant from Emden, Germany       matured service provider, offering optimized and
                                                                                                                                           to Essar Gujarat.                                    economical plant configurations for various
                                                                                                                                         • Civil, structural and mechanical works for Hot       customers.
                                                                                                                                           Strip Mill, Air Seperation Plant, Steel Melt Shop    This consortium has already erected and
                                                                                                                                           and Corex modules 1 & 2 including manufacture        commissioned two medium sized (204 sq. m)
                                                                                                                                           and supply of Reduction Shafts and Smelter           sintering plants at TATA STEEL, while two more
                                                                                                                                           gassifier for Jindal Vijaynagar Steel (presently     similar size plants are under execution at ISP SAIL.
                                                                                                                                           JSW Steel Ltd.)                                      This order was received recently against stiff global
                                                                                                                                                                                                competition major Chinese and Russian players.
                                                                                                                                         EPC and Construction Packages                          Apart from these medium sized machines, L&T-
                                                                                                                                         During the last two decades L&T executed some of       Outotec has bagged the sinter plant (496 sq.m)
                                                                                                                                                                                                for Kalinganagar Steel project of Tata Steel and         ESSAR Sponge Iron
                                                                                                                                         the critical EPC/Construction packages for various
                                                                                                                                                                                                the recently concluded contracts for the 360 sq.m        Plant dismantled at
                                                                                                                                         clients. Some of the most important projects
                                                                                                                                                                                                machine at Rourkela Steel Plant and 2 X 204 sq m         Emden, Germany and
                                                                                                                                         include:
                                                                                                                                                                                                machines for Bhusan Steel.                               re-erected at Hazira
                                                                                                                                         • 1992: Greenfield billet caster implemented as
                                                                                                                                           a part of the modernization and expansion of
                                                                                                                                           Durgapur Steel plant executed with Concast
                                                                                                                                           AG.
                                                                                                                                         • 1992: Reconstruction of BF-1 at Durgapur
                                                                                                                                           Steel, a milestone project in terms of speed of
       Panoromic view       related to steel in smaller plant configurations.     and Non-ferrous industry in general and steel            implementation. The project was completed in 6
      of sinter plants at   These plants are mainly into pig iron production      industry in particular through various tie-ups and       months.
              Tata Steel    and many have added downstream value addition         collaborations.                                        • 1994: Greenfield Slab caster project of Bokaro
                            processes to produce construction steel and                                                                    Steel which was executed with well known
                                                                                  During the course of the last five decades of
                            pipes. Their combined capacity is in the region                                                                European technology provider VAI during the
                                                                                  association with Indian steel industry, L&T has
                            of 8 MT. Ferro alloy makers and re-rollers are also                                                            last expansion of Bokaro Steel.
                                                                                  acquired expertise in providing engineering,
                            included in this group.                                                                                      • 1994: Steckel Mill at Salem Steel with SMS
                                                                                  procurement and construction services in
                                                                                  consortium with foreign technology providers. It         Demag
                            L&T’s Track Record
                                                                                  has constructed some of the major steel plants         • 2000: Cold rolling mill of Tata Steel executed
                            L&T’s foray into steel plant construction began in    and pioneered new concepts in dismantling and            with Hitachi
         L&T’s Share in     a modest way during 1950’s when L&T catered to        rebuilding of blast furnaces and DR plants in the
                                                                                                                                         Today, Larsen & Toubro is playing a challenging
                building    the construction needs of Rourkela Steel Plant in     country.
                                                                                                                                         role in the growth phase of the steel industry and
    Sinter Plants – EPC     association with GHH of Germany. Since then L&T
                                                                                  L&T’s canvas of project operation covers the           is fully geared up to meet the industry requirement
                  Route     has had a continuous association with the Ferrous
                                                                                  entire spectrum of steel plant from ore                for the next phase of expansion. It has already
                                                                                                                                                                                                  Air Separation Plant for
                                                                                  beneficiation plants to finishing mills through iron   established selective tie ups with technology
                                                                                                                                                                                                  Jindal Steel at Vijayanagar
                                                                                  making and steel making.                               leaders in agglomeration, iron making and steel
                                                                                                                                         making, etc. While some of the associations have
                                                                                  Packages Executed                                      blossomed in agglomeration and iron making
                                                                                  • Construction of Rolling Mill complex involving       resulting in large value EPC projects, associations
                                                                                    44000 MT of structural steelwork and erection of     in steel making and rolling are also being worked
                                                                                    three 1000 Tons per day capacity blast furnaces      out with the best technology companies and will
                                                                                    at Rourkela.                                         see further progress in the coming months.
                                                                                  • Relocation of the Thyssen Blast Furnace and its
                                                                                    successful reassembly and commissioning at           Agglomeration
                                                                                    Ispat Dolvi.                                         This is one of L&T’s core strength areas and clients
                                                                                  • Construction of Blast Furnace ‘Krishna’ at           in India are gaining immensely by executing their
                                                                                    Visakhapatnam Steel Plant as per design and          projects through the Outotec–L&T combine.
                                                                                    supply of Gipromez, Russia and HEC, Ranchi.          Today this consortium has emerged as a fully

ECC Concord | Apr - Sep 08 8                                                                                                                                                                                                                       9 ECC Concord | Apr - Sep 08
April - September 2008 Vol. No. 31 Issue No. 2 - lntecc
Proven Strength in BF                                      Steel Making and Rolling

                                                                                                                                        The construction of the mammoth 4000 cu.m class            L&T’s earlier successes at Bokaro, Durgapur
                                                                                                                                        blast furnace brought forth a level of challenge           and Salem will soon be replicated in the new
                                                                                                                                        unparalleled in steel plant construction. While it         generation casters and rolling mills that are now
                                                                                                                                        started with the construction of the largest blast         in the planning stage. L&T is consolidating its
                                                                                                                                        furnace in the 80s at Vizag, dismantling relocation        project, technology and engineering strength in
                                                                                                                                                                                                   these areas to give industry the obvious choice
                                                                                                                                        and rebuilding of a large capacity blast furnace at
                                                                                                                                                                                                   both in project economics and project execution.
                                                                                                                                        Dolvi and culminating in the rebuilding of F & G
                                                                                                                                                                                                   The industry may look forward to our plans that
                                                                                                                                        blast furnaces at Tata Steel during the early part of
                                                                                                                                                                                                   will be unveiled progressively
                                                                                                                                        this decade, L&T has been able to display its real
                                                                                                                                        strength and establish its expertise today with a          The Future
                                                                                                                                        widespread engagement in most of the mega size
                                                                                                                                                                                                   Construction of Iron and steel projects generally
                                                                                                                                        blast furnace projects.
                                                                                                                                                                                                   present several complexities unique to the process
                                                                                                                                        L&T is building six of the nine large blast furnaces       and seldom seen in other projects. Primarily,
                                                                                                                                        presently under construction at Tata Steel, Vizag          the very nature of the smelting process with              L&T’s Share
                                                                                                                                        Steel, JSW, ISP, Bhusan, RSP and BSP. Together             very high temperature operations, handling and            in building
                                                                                                                                        these 9 blast furnaces will add a combined volume          transportation of molten metals in bulk over a wide       large BFs – EPC
                                                                                                                                        of around 36000 cu.m and an annual production              area, working in great heights and preponderance          Route
                                                                                                                                        of 27 MT. They will be progressively commissioned
                                                                                                                                        during the next 30 months. Very few companies
    Continuous Casting     Iron Making                                            Tata Steel ‘G’ BF Rebuild: Though a smaller           in the world would have achieved as illustrious a
     Plant at Durgapur                                                            package was built in 2005, it is nevertheless a       pedigree as L&T, in engineering and construction
                           L&T-Paul Wurth combination is an established
            Steel Plant                                                           landmark project in terms of having exceeded the
                           EPC consortium in India with a string of recent                                                              of complex iron and steel plant units, specifically
                                                                                  mission objectives.
                           successes in Greenfield and Rebuild projects in                                                              large capacity blast furnaces.
                           the blast furnace area. They are briefly highlighted   Tata Steel ‘H’ BF, Greenfield: The largest blast
                                                                                                                                        The success of engineering, procurement and
                           below:                                                 furnace implemented through the EPC consortium
                                                                                                                                        construction projects lie in its timely completion as
                                                                                  route in India. This was commissioned on May 31,
                           Tata Steel ‘F’ Blast Furnace Rebuild: Built and                                                              well as carrying out all trials and commissioning
                                                                                  2008.
                           commissioned in 2002, the ‘F’ Blast Furnace was                                                              runs with a stringent safety record and thereafter
         Blast Furnace     a landmark project in terms of size, specifications    RINL BF-3, Greenfield: Similar to Tata BF-H, this
                                                                                                                                        the vertical take-off on commissioning. However,
            ‘Krishna’ at   and speed of execution. Even today, this has been      project is under execution and this has taken off
                                                                                                                                        the acid test lies in the Project Manager’s ability to
        Visakhapatnam      serving as an ideal reference for all present and      very well and is progressing as per schedule.
                                                                                                                                        fulfill all these project objectives within the shortest
             Steel Plant   future blast furnace rebuilds projects.                Rourkela BF-4 Rebuild:   Executed in 2005 has         possible time. This is the dream of all Project
                                                                                  already found a place in the record book of SAIL      Managers and L&T has built a team of young
                                                                                  as a major venture, successfully completed in
                                                                                                                                        Project Managers who can take on the mantle of                                              Blast Furnace re-constructed at DSP, Durgapur
                                                                                  record time.
                                                                                                                                        mega projects with ease as exhibited in all these
                                                                                  Bokaro BF-2 Rebuild: The consortium of L&T-           critical project. To achieve this all-round success,
                                                                                  Paul Wurth recently bagged this prestigious           L&T structured several consortium arrangements
                                                                                  project of SAIL and project activities have already   with the best technology companies to give
                                                                                  commenced.                                            the unique advantage to the client should they
                                                                                  Bhusan Steel BF-2, Greenfield: This is similar to     choose to have it. With a variety of project award
                                                                                  the Vizag and Tata ‘H’ blast furnace and presently    mechanisms in place in this country, the best
                                                                                  under planning and mobilization stage.                projects are with steel makers who choose to
                                                                                  Tata Steel ‘I’ BF, Greenfield: Based on the           give due weightage to all the contributing factors
                                                                                  successful execution of ‘H’ blast furnace, Tata       that go to make a project benchmarked against
                                                                                  Steel has reposed faith again in the L&T-Paul         the best – globally tested technology, superior
                                                                                  Wurth combine to build the equally challenging ‘I’    equipment, optimized engineering and rapid and
                                                                                  blast furnace.                                        safe execution.

ECC Concord | Apr - Sep 08 10                                                                                                                                                                                                                        11 ECC Concord | Apr - Sep 08
April - September 2008 Vol. No. 31 Issue No. 2 - lntecc
of lower cost but will definitely not stand to scrutiny   generally had a short term view which prevented
                                                                                      on overall benefit.                                       them from nurturing technology development.
                                                                                                                                                The result is the abysmal level reached in patent
                                                                                      Tendering and Project Award                               registration and technology development which
                                                                                                                                                even surprises overseas technology providers who
                                                                                      There is a wide array of methodologies which are
                                                                                                                                                are repeatedly approached by Indian companies
                                                                                      adopted for tendering and project award across
                                                                                                                                                for every small developmental effort.
                                                                                      the spectrum of integrated steel companies. While
                                                                                      many have evolved and exhibit an elevated level of        We do need to look at China to see how they picked
                                                                                      transparency to bring forth fair competition, proper      up from where the Russians let off during the post
                                                                                      benchmarking of offered technologies and better           cold war era in the mid eighties. While India’s initial
                                                                                      economics for the owner/employer, certain other           technology development base in the public sector
                                                                                      methods in vogue leave elements of subjectivity.          was very sound and well focused, the recession
                                                                                      In all cases the time frame for award of contract         in the steel industry in the nineties coupled with
                                                                                                                                                an upswing in the IT industry gave a severe blow          engineering with technology oriented functions and      Exterior view of
                                                                                      is extensive, often extending to more than one
                                                                                                                                                to the sector. It is during the last 10 years that the    shall have a firm plan in place in the coming years.    Sinter Plant No.4
                                                                                      year, which often contribute to escalation of costs
                                                                                                                                                steel sector has transformed and surged ahead in                                                                  at Tata Steel
                                                                                      and other influences during the tendering process.                                                                  The technology companies in the iron and steel
      Blast Furnace ‘F’         of toxic and explosive gases present very high
                                                                                      Necessary measures need to be taken to reduce             engineering and project management. However               sector went through several reorganizations over
           at Tata Steel        risks.
                                                                                      the time taken for the bidding process and award          the technology scenario remains forever weak and          the last two decades in tune with severe upheavals
                                Therefore, successful implementation of these         of contracts to facilitate faster implementation of       dependence of overseas technology is increasing           in the iron and steel sector, the world over.
                                projects call for an appreciation of these hazards    projects and achieving the production targets.            with every passing day.                                   Technology companies in USA declined along
                                and having foolproof protocol and procedures in                                                                                                                           with their steel industry while the behemoths of
                                                                                                                                                A recipe for change could be in the form of patrons
                                place to minimize their impact.                       Technology Scenario                                                                                                 Russia got fragmented and dissipated. Japanese
                                                                                                                                                willing to take the mantle as financial mentors and
                                Global players and consortia with well experienced    India is dependent to a large extent on overseas          allow bright and young people to be deployed              companies well known for their excellent methods
                                and established partners are playing a major role     technology providers in many areas of the iron            for technology development. To begin with all             turned non-competitive in the face of growing
                                in the construction and modernization of steel        and steel making process chain due to the                 steel companies need to have a technology                 competition from European, Korean, and to a lesser
                                plants bringing in attributes of modern technology,   singular fact that entrepreneurs, organizations           development mission with a sizable funding and            extent Chinese companies who were emerging in
                                economic operation, with simpler, faster and safer    and patrons have not betted on the capability of          motivated individuals at the helm. Short term results     the upstream technologies. It was in this scenario
                                execution methodologies including optimum client      Indian technologists/engineers in the Iron & Steel        should not be the guiding principle but a holistic        that L&T went about selecting technology partner
                                interface essential for the future of this growth     sector. It was the public sector which could instill      system oriented approach with incremental growth          in early 2000 initially in the upstream technologies    204 sq.m sinter
                                phase. Disintegrated project packages with            some sense of pride and glamour in iron and steel         targets should be put in place. L&T has looked            and progressed into steel making and rolling            machine at Tata
                                multiple agencies may give the apparent benefits      plant technology development while the industry           at the possibility of backward integration of its         technologies.                                           Steel

                Tata Steel at
      Jamshedpur showing
      Sinter Plant No.3 with
     raw material conveyor

ECC Concord | Apr - Sep 08 12                                                                                                                                                                                                                              13 ECC Concord | Apr - Sep 08
April - September 2008 Vol. No. 31 Issue No. 2 - lntecc
manufacturing capability development and                 could cater to a steel capacity addition of up to 2 MT
                                          Various technology companies along with their peers.
                                                                                                                                       growth of construction capabilities. What China          annually. Concurrently other small manufacturing
                                          L&T’s partners in the technology space are highlighted
                                                                                                                                       may have missed in software or business process          facilities catering to steel plant equipment was
                                                                                                                                       outsourcing was more than amply compensated              set up in Rourkela, Bhilai and locations in North
                                 Blast Furnace                      Sinter Plant                      Coke Oven                        in growth of infrastructure and manufacturing            India and western India. Together these facilities
                                 - Paul Wurth                       - Outotec                         - TPE                            capability which has catapulted the country to the       have the capability to service the steel sector for
                                 - Siemens VAI                      - Siemens VAI                     - Paul Wurth                     big league. There is no short cut in growth and          capacity addition of 4-5 MT per year. Yet many of
                                 - POSCO E&C                        - POSCO E&C                       - MCC                            we have understood that a nation goes into the           the critical and core equipments including heavy
                                 - Danieli Corus                    - TPE, Russia                     - Sino Steel                     knowledge economy phase only after creation of a         duty cranes, critical castings, large diameter
                                 - MCC, China                       - MCC, China                      - SSIT                           proper manufacturing and infrastructure base.            technological valves, grinding equipment, have
                                 - Shougan                          - Kawasaki                        - Udhe GmbH                                                                               to be sourced from China and Europe which
                                                                    - Shoughan, China                                                  Construction Plant & Machinery                           have built the manufacturing infrastructure to
                                                                                                                                                                                                service their own growth and which has a surplus
                                                                                                                                       Heavy plant & machinery and haulage equipment
                                                                                                                                                                                                capacity.
                                                                                                                                       are the order of the day as higher levels of precast,
                                 Steel Making                        Casters                          Rolling (Flat)                   prefab and engineered pre assemblies will be             L&T has been a traditional steel plant equipment
                                 - TPE                               - SMS Demag                      - SMS Demag                      used to declutter construction sites and speed up        manufacturer and Kansbahal works have been
                                 - SMS Demag                         - Siemens VAI                    - Siemens VAI                    processes. Project planners and engineers as well        supplying critical steel plant equipment. However
                                 - Siemens VAI                       - Danieli                        - Danieli                        as layout architects and logistic specialists will       the extended recession of the 1990s and early
                                 - J.S. Plant tech                                                                                     need to see the trend and the logical requirements       2000 gave reasons for re-evaluating the potential
                                                                                                                                       while planning the projects at the concept stage.        of growth in the steel sector. Today, L&T is taking a
                                                                                                                                       More rebuilds and retrofits will be the norm to keep     comprehensive view of the steel plant equipment
                                                                                                                                       the existing ageing plants in proper trim.               sector and hope to participate in even greater
                                                                                                                                                                                                measure in the expansion stakes.
                                 CRM/Galvanising                                                    Rolling (Long)                     Manpower training
                                 - SMS Demag                                                        - Morgan, USA                                                                               Environment impact
                                                                                                                                       Indian labour and construction supervisors
                                 - VAI                                                              - SMS Demag                        will need advanced levels of training for which          This is a specialized subject particularly in the
                                 - Hitachi                                                          - Siemens VAI                      construction companies need to have their captive        context of steel making. World needs steel and
                                 - Andritz, GmbH                                                    - Danieli Group                    schools for training labour and supervisors in the       it has to be made either in China, Korea, Japan,
                                 - Sendzimer                                                        - Davy Morgan, UK                  advanced methods. L&T runs its own workmen               South Africa, Brazil and India amongst others.
                                                                                                                                       training initiative which is boosting its capabilities   Many of the developed countries have abandoned
                                                                                                                                       further to take up the challenge.                        bulk steel making in favour of high end value
                                                                                                                                                                                                addition. Moreover coal and coke usage will be
                          Engineering Scenario                                    an enormous amount of work in keeping the
                                                                                                                                       Project management                                       in the forefront in steel making. Matters related to
                                                                                  engineering industry well serviced with their
                          L&T has a robust engineering set up and realizing                                                                                                                     carbon emission and use of superior technology
                                                                                  products. With the declining fortunes of many        Project management will be the cornerstone in
                          the potential of the sector, we are persuading fresh                                                                                                                  to reduce levels of energy input per tonne of
                                                                                  such old workhorses, we have to have new             execution of such mega plans and each steel
                          engineers from civil, mechanical, metallurgical,                                                                                                                      steel making is not the subject matter here. But
                                                                                  mothering units in the private sector who are able   plant owner will have to device their own strategies
                          electrical and structural streams to join engineering                                                                                                                 technologists and project personnel would do well
                                                                                  to look beyond short term goals and nurture an       based on their own specific conditions. Steel plants
                          work which is more fulfilling, prestigious and                                                                                                                        in evaluating projects also from the framework of
                                                                                  engineering pool for the future.                     have treated their project functions differently
                          contributes to the nation building. The existing                                                                                                                      future environmental requirements. L&T on its part
                                                                                                                                       depending on their execution methodologies.
                          productive engineers are ageing and we need to          L&T has been very actively involved and making                                                                would like to work with technology companies who
                                                                                                                                       Moreover project personnel are much more mobile
                          see young engineers taking up the mantle in larger      a significant contribution to this sector with its                                                            carry the mantle of environmental sensitivities.
                                                                                                                                       than operational personnel. Hence plants which
                          numbers who are willing to work in engineering          engineering bases and office networks spread         have long term growth perspectives need to have
                          offices and project sites.                              across the length and breadth of this country. No                                                             L&T’s preparedness
                                                                                                                                       a captive project function to be available through
                          The modern day engineering offices will be IT/ITes      doubt, L&T is also gearing up further for the next   this entire growth phase.
                                                                                                                                                                                                L&T is fully established to be the most visible and
                          enabled which will be located in knowledge zones        round of growth.
                                                                                                                                                                                                successful enterprise in the development of the
                          of bigger planned cities in progressive modern                                                               Manufacturing infrastructure
                                                                                  China’s growth in steel making capacity up to                                                                 steel making infrastructure. Our present portfolio
                          states.                                                 declared levels of 490MT has been possible only      Robust manufacturing capabilities were built up in       of projects and our future engagement will bring
                          Moreover, engineering capability building is            through institutional development of technological   the early sixties like L&T, HEC & MAMC to cater to       greater rewards to the stakeholders and bring
                          restricted to few enterprises that have done            & engineering capabilities; a demand based           the Mining and Steel sector. The facilities created      India at par with world players in steel.

ECC Concord | Apr - Sep 08 14                                                                                                                                                                                                                      15 ECC Concord | Apr - Sep 08
April - September 2008 Vol. No. 31 Issue No. 2 - lntecc
With more than Rs. 6000 crore worth of orders from steel industry
                                                                pouring in to the portals of L&T during the last few years, ECC has
                                                                been in the limelight. However, one person is sitting pretty cool on
                                                                these hot ovens and continuing to bag more and more orders, least
                                                                perplexed and least hyped up. He is the “Steel Man” of ECC and the
                                                                rock anchor of steel & metallurgical sector business. This acronym,
                                                                he has been labeled for his high resoluteness and firm determination.
                                                                Moreover his association and long innings in the steel industry is deep
                                                                rooted like the rock anchor. There is no parallel for him in the industry
                                                                when it comes to construction of major steel plants, establishing long-
                                                                standing good customer relationship or securing high value orders
                                                                for mega steel plants – be it repeat orders from a single client or
                                                                new orders for the construction of Greenfield steel projects in the
                                                                country. To top it all he has the unique distinction of having executed
                                                                the maximum number of blast furnaces in the country with new benchmarks in project execution.
                                                                With his experience and expertise gained over a long period, he has proved himself an authority and
                                                                a force to reckon with in the steel industry. With his inimitable style of people friendly leadership and
                                                                project management capabilities, he has been stealing the show from the entire steel industry, not only
                                                                from India but technology suppliers, the world over, with regard to meeting stringent time frames and
                                                                other project deliverables. Everyone knows him popularly as KGH. Meet Mr. K.G. Hariharan, Senior
                                                                Vice President & Chief Mentor of Industrial Projects & Utilities (IPU) Sector, catering to Minerals &
                                                                Metallurgical, Bulk Material Handling and Water Project operations at ECC Division of L&T.

                                                                G     reat leaders have achieved the impossible
                                                                      with great teams, it is said. Forging alliances,
                                                                bringing up teams, nourishing and nurturing them
                                                                with collaboration, care and trust as well as Team
                                                                Building is one of the most important roles of a
                                                                leader. This is very much true of Mr. Hariharan,
                                                                who says concentrated team efforts and results
                                                                are two sides of the same coin. During his tenure
                                                                as Head of the IPU business sector, he had the
                                                                unique distinction of executing some of the major
                                                                multi-disciplined engineering projects in M&M,
                                                                BMH and Water & Effluent treatment business
                                                                units. It is also a fact that KGH’s association with
                                                                the steel plant construction is almost synonymous

                                K.G. Hariharan                  with L&T‘s foray into this area of business. Be it

                                Steeling
                                                                the LD shop at Tata Steel - Jamshedpur, Billet
                                                                Caster for DSP-Durgapur built on EPC basis with
                                                                                                                         himself, KGH has been able to successfully            With Mr. Ratan Tata,
                                                                Concast, relocation of Thyssen Blast Furnace from
                                                                                                                         develop similar vision and forethought among his      Chairman of the
                                                                Duisburg Germany to ISPAT Dolvi which marked
                                                                                                                         team members. The Tirumala water supply pipeline      Tata Group and
                                                                ECC’s foray into expanded business in Iron making
                                                                                                                         project was the crowning glory and landmark of        Mr. A. Ramakrishna, then
                                                                or the Slab Caster for Bokaro Steel Plant, the IPU
                                                                                                                         KGH’s immense faith in his people where passion       Deputy Managing Director,
                                                                sector of ECC led by KGH brought accolades to

                                   the Show...
                                                                                                                         worked far beyond money and status. Similar urge      L&T during the presentation
                                                                the organization.
                                                                                                                         and strong drive led by KGH in the teeth of extreme   of special memento to
                                                                Achievement motivation has been a guiding                difficulties led to the successful completion of a    celebrate 25 years of
                                                                philosophy of KGH. Being an outstanding leader           17 km long overland conveyor for Lafarge Cement       L&T-Tata association.
                                         R.P. Das
                                         Minerals & Metals BU
ECC Concord | Apr - Sep 08 16            Bhubaneswar                                                                                                                     17 ECC Concord | Apr - Sep 08
April - September 2008 Vol. No. 31 Issue No. 2 - lntecc
KGH along with
                                                                                                                                                                 At the time of signing the strategic alliance with Paul Wurth
              Dr. J.J. Irani,
        Mr. Ratan Tata and
        Mr. B Muthuraman
              at Tata Steel

                                                                                                                                         the Minerals & Metals Business Unit of ECC has                     effective solutions to the Indian Steel Industry,      L&T-ECC Workshops
                                                                                                                                         cut down on the delivery time for blast furnace and                selection and nurturing of long term relationship      near Chennai is the
                                                                                                                                         sinter plant construction as well as blast furnace                 with technology partners in equal terms is a vital     brain child of KGH.
                                                                                                                                         rebuild, bettering the best standards set by                       area of interest, emphasized Mr. Hariharan. The        He is seen with
                                Plant in Bangladesh, one of the longest single     in his college days that he developed his distinct    international technology and construction majors.                  successful partnership with Outotec, Germany           Mr. A.M. Naik,
                                flight belt conveyors in the world.                skills in human resource management. After a          The rebuild of Blast Furnace ‘F’ at Tata Steel was                 is a shining example which reaped rich dividend        Chairman and
                                                                                   short stint with couple of other organizations, KGH   an example of his formidable achievement to set a                  in booking a record six consecutive Sinter plant       Managing Director
                                Hailing from the former princely state of
                                                                                   joined Engineering Construction Corporation           new global benchmark for such projects. Against                    orders for L&T.                                        at the time of
                                Trivandrum, Karamanai Gopalakrishna Hariharan
                                                                                   Limited (ECC), then a wholly owned subsidiary         contractual shut down period of 150 days, KGH                                                                             inauguration of the
                                (KGH) obtained his Diploma in Mechanical                                                                                                                                    The secret of my success is ‘My People’ says
                                                                                   of L&T in 1971. During 1984, in due recognition       was approached by top management of TATAs                                                                                 workshop
                                Engineering, in 1963. It was as a student leader                                                                                                                            KGH. They have been nurtured by motivation, trust
                                                                                   of his outstanding performance at many of the         to reduce the shutdown period by 30%. KGH in
                                                                                                                                                                                                            and support, kindled by the spirit of innovation,
                                                                                   projects he was involved, KGH was elevated to         his characteristic style took up the challenge and
                                                                                                                                                                                                            commitment to time and quality.
                                                                                   become the youngest Regional Manager of ECC at        personally guided the Planning and Mobilization
                                                                                   Kolkata. It was during his earlier tenure as ECC’s    teams to reach the seemingly impossible target.                    However, “All work and no play” is a view KGH
                                                                                   Construction Manager at Tata Steel - Jamshedpur       The result was unprecedented. Providing                            does not subscribe to. He strongly believes that
                                                                                   and subsequently as Regional Manager – Kolkata        stupendous challenge to the project management                     happy families make happy workers. People have
                                                                                   Regional Office (KKRO) that KGH carefully nurtured    capability of L&T-Paul Wurth teams, the Blast                      to be taken care before they can take care of their
                                                                                   L&T’s relationship with Tata Steel. Over a period,    furnace was blown in 104 days creating a record                    assignments.
                                                                                   the relationship grew very strong and blossomed       in the steel industry.                                             In the midst of his busy schedule, Mr. Hariharan
                                                                                   to such an enviable position that L&T is executing                                                                       is a family man at heart. With both daughters
                                                                                                                                         Although partnering L&T is a first choice for
                                                                                   almost all of Tata Steel’s prestigious projects.                                                                         settled in life, Mrs. Hariharan and songs from Hindi
                                                                                                                                         foreign technology suppliers to offer cost
                                                                                   ECC set its first foot at Tata Steel Jamshedpur way                                                                      movies of yesteryears rejuvenate him after a hard
                                                                                   back in 1978 and today it has touched 30 years.                                                                          day’s work.
                                                                                                                                               A well known name in the steel industry, KGH at a steel
                                                                                   Moreover, this association is continuing to grow
                                                                                                                                                              workshop along with Mr. Sajjan Jindal         Given the present boom in the economy, the
                                                                                   stronger and stronger with ECC securing many
                                                                                   new and bigger projects year after year. This                                                                            steel sector has thrown open huge opportunities
                                                                                   is certainly a remarkable achievement attributed                                                                         and challenges for project engineering and
                                                                                   purely to the customer relations bondage                                                                                 construction. Under these circumstances while all
                                                                                   developed and nurtured by KGH.                                                                                           major players are basking in the glory of huge order
                                                                                                                                                                                                            inflows, KGH makes a typical cautionary note. He
                                                                                    Mr. Hariharan has identified himself so closely                                                                         opines “While actions are limited, possibilities
                                                                                   with the metallurgical sector that his colleagues                                                                        are immense”. The management style of KGH
                                                                                   and contemporaries refer to him as the ‘Steel                                                                            is quite different from others. As the saying goes
                                                                                   Man’ of L&T. KGH strongly believes that records                                                                          successful people don’t do anything different but
                                                                                   are meant to be broken. Under his able guidance                                                                          they do things differently.

ECC Concord | Apr - Sep 08 18                                                                                                                                                                                                                                19 ECC Concord | Apr - Sep 08
Forging relationship with a                 T    ata Steel and L&T – two names that enjoy a         foundations, underground cable tunnels, electrical
                                                                                      special place in the corporate firmament of        and other service buildings, etc. The quantum of

                                     Steel Major
                                                                                 India are well set to carve a niche for themselves      work involved 3,10,000 cu.m of excavation, 58,000
                                                                                 in the growing stakes of the iron and steel industry.   cu.m of concrete , 1,50,000 sq.m of shuttering and
                                                                                 The two private sector companies, established in        3,400 t of reinforcement and it was completed
                                                                                 the pre-independence days, have contributed in          within a period of 4 months. To meet this massive
                                                                                 a major way to the industrial development of free       volume of works, ECC had to install a centralized
                                                                                 India and continue to be significant players in the     batching plant with a capacity of 60 cu.m for
                                                                                 country’s all-round growth. In their own unique         supplying concrete and also had to deploy earth
                                                          R.P. Das               ways, they have proved to be builders of modern         excavators and other heavy machinery like crane,
                                                          Minerals & Metals BU   India.                                                  dumper and dozers.
                                                          Bhubaneswar            L&T’s Engineering Construction & Contracts              The following are some highlights of ECC’s work
                                                                                 (ECC) Division has an unbroken association              for this projects at Tata Steel:
                                                                                 with Tata Steel since 1978 when it opened its site
                                                                                                                                         • ECC had to design, fabricate and erect 40 t of
                                                                                 office at Jamshedpur. ECC has been Tata Steel’s
                                                                                                                                           structural steel framework of 16 m height to
                                                                                 partner and has executed a number of projects for
                                                                                                                                           make room for continuous casting of 450 cu.m              Coil storage area in
                                                                                 the steel major.
                                                                                                                                           of concrete for each foundation of 130 t capacity         the Bar and Rod Mill
                                                                                 L&T-ECC’s association with Tata Steel started             LD converters.                                            at Tata Steel
                                                                                 when it was awarded the contract for construction
    Electrostatic Percipitator for                                               of new coke ovens by-product plant and since then
       waste gas at Sinter Plant                                                 ECC has been continuously carrying out large and
                                                                                 small orders for the upgradation / maintenance of
                                                                                 its various facilities at Jamshedpur. The unbroken
                                                                                 client-contractor relationship is a typical example
                                                                                 of customer delight begetting customer loyalty.
                                                                                 Thus, ECC is associated with all ambitious plans
                                                                                 and modernization programmes of Tata Steel right
                                                                                 from phase I, which began in 1980s to the current
                                                                                 expansion plans.

                                                                                 First Modernization

                                                                                 Recently Tata Steel celebrated the silver
                                                                                 jubilee i.e. 25 years of completion from the first
                                                                                 modernization programme. Tata Steel undertook
                                                                                 its first modernization in 1980-83 at an estimated
                                                                                 cost of Rs. 220 crores. This comprised setting up a
                                                                                 1.1 million tons oxygen steel making plant (better
                                                                                 known as LD shop or Basic Oxygen Furnace
                                                                                 Shop) to replace the outmoded duplex process at
                                                                                 steel melting shop No. 1, introduction of one six-
                                                                                 strand continuous casting and one 130 t vacuum
                                                                                 arc degassing and refining facility.

                                                                                 Against very stiff competition from leading
                                                                                 companies, ECC bagged the entire civil works and
                                                                                 major portion of the structural works of the steel
                                                                                 melting shop, tar dolomite calcining plant and at
                                                                                 a later stage received the electrical installation
                                                                                 contract also for the same project.

                                                                                 ECC’s scope of work in the LD shop involved
                                                                                 construction of heavy column and equipment

ECC Concord | Apr - Sep 08 20                                                                                                                                                                21 ECC Concord | Apr - Sep 08
                                                                                                                                                                  Low tension switchgear control panels
plant, but it overcame them with a high sense of                                                                                         Cold Rolling
                                                                                   determination, hard work and team spirit resulting                                                                                       Mill
                                                                                   in completion of the contract very much ahead of
                                                                                   schedule and Tata Steel was able to commission
                                                                                   this project on March 23, 1983. The successful
                                                                                   completion of this challenging project ahead of
                                                                                   schedule is a record for Tata Steel.

                                                                                   In coping with the tight schedule of the time-
                                                                                   conscious and result-oriented client, Tata Steel,
                                                                                   ECC faced a number of hurdles, initially in operating
                                                                                   in a highly congested, hazardous, round-the-clock
                                                                                   operating steel plant. ECC staff and workmen had
                                                                                   to get conversant with the hazards of steel plant
         Inside view of   • Massive and deep excavations up to 17m                 like movement of cranes, wagons, locos, electrical
      Sinter Plant No.3     below ground level with L&T-Poclain hydraulic          bus bars, molten metal, gases, etc. However, it
                            excavators.                                            took very little time to overcome this problem
                                                                                   with a high sense of determination and hard work
                          • Laying of a 2km road and 7km of railway tracks
                                                                                   by carrying out routine works on set procedure
                            in the shop.
                                                                                   and customers, cooperation and team spirit by
                          • Very high degree of accuracy in fabrication and        each individual from engineers to supervisors
                            fixing of steel embedments and bolts in various        and workers. All this was achieved by the then
                            structures.                                            Construction Manager, Mr. K.G. Hariharan’s
                          • A record pour of 400 cu.m of concreting in a           versatile vision and forward planning, overall
                            single day and a running record of 5,300 cu.m          control, alert watch on performance, periodical
                            of concrete in a month.                                review and monitoring, timely achievement of
                          The mechanical works involved 13,000t of                 targets coupled with dynamic leadership, drive,
                          fabrication and erection of steel works and 54,000       help and support. The determination of Mr.
                                                                                                                                              Erection in progress   Plant #2, 2.4 mpta Sinter Plant #3, Blast Furnace
                          sq.m of sheeting in a period of 24 months. This          Hariharan in holding the whole team together,
                                                                                                                                                                     ‘H’ and 2.4 mtpa Sinter Plant#4
                          also involved testing, flushing, thermal insulation,     keeping tension under surface and above all his
                          painting and commissioning of LD gas and other           human touch and relationship boosted everyone’s                                   Global Benchmark
                          utility works for gas recovery system of LD.             morale and made it possible to complete the
                                                                                   project well ahead of schedule, helping to create                                 ECC provided the sinews for Tata Steel’s 1.2
                          The entire structure was made of heavy build-up of       a new record for Tata Steel. This was the turning                                 mtpa state-of-the-art Cold Rolling Mill (CRM) at
                          steel columns averaging 40 t in weight consisting        point in our association with Tata Steel and there                                its Jamshedpur works. The CRM plant was Tata
                          of trusses, crane girders, monitors, etc. One            has been no looking back for ECC since then.                                      Steel’s top-most priority in the face of global
                          notable achievement was fabrication and erection                                                                                           recession in steel market in 1998. L&T-ECC’s role
                          of fully riveted (consisting of about 4.5 lakh rivets)   Further Phases                                                                    in setting up the 1.2mtpa plant included erection,
                          crane girder. This 42 m span crane girder has a                                                                                            commissioning of a coupled pickling line and
                                                                                   The second phase (1985-1992), saw a 0.3 mtpa
                          width of 6 metres and weight of 175 tons.                                                                                                  tandem cold mill, along with civil, structural and
                                                                                   (million tonne per annum) bar and rod mill, a
                                                                                                                                                                     underground piping works, equipment erection
                          Another milestone was fabrication of 1,000t of           2.5-mtpa sinter plant, power house, raw material
                                                                                                                                                                     and commissioning of the CRM.
                          structural steel and erection of 1,100 t of structures   bedding & blending plant and coal handling
                          in a month’s time.                                       plant.                                                                            In completing the project, L&T-ECC set up
                                                                                                                                                                     several records in structural steel, fabrication and
                          The tar dolomite brick plant involved fabrication        The third phase (1988-2000) saw the rising up of
                                                                                                                                                                     concreting. Most outstanding of all was a global
                          and erection of 1,600t of structural steel and 6,800     energy optimizing furnace (EOF), lime calcining
                                                                                                                                                                     benchmark for supply and commissioning of the
                          t of sheeting. The electrical work involved 300km        plant, billet caster, blast furnace ‘G’, hot strip mill,
                                                                                                                                                                     plant in a world record time of 27 months, a whole
                          of cabling, 45km of earthing, 21,000 terminations        slab caster and LD shop – 2.
                                                                                                                                                                     month ahead of the previous record for a similar
                          and 430t cable trays.
                                                                                   The fourth phase (2000 onwards) saw the 1.2 mtpa                                  plant held by POSCO of South Korea. It was a
                          ECC faced a number of hurdles working in a big           Cold Rolling Mill, Blast Furnace ‘F’ upgradation,                                 crowning moment in the Tata Steel-L&T Saga and
                          way, in Tata Steel’s highly congested operating          Blast Furnace ‘G’ augmentation, 2.3 mtpa Sinter                                   augured well for the future.

ECC Concord | Apr - Sep 08 22                                                                                                                                                                                         23 ECC Concord | Apr - Sep 08
Continuing saga of a                   T   ata Steel’s growth into the future has been                  temperature of 400oC and is provided with a
                                                                     through both organic and inorganic routes.                   waste heat recovery system.

                          Growing
                                                                 Today, Tata Steel is the world’s 6th largest steel       •       Nitrogen based CPI system is provided for
                                                                 company with an existing annual crude steel                      the blast furnace to achieve a 150 kg/thm
                                                                 capacity of 28 million tonnes. Asia’s first integrated           level of injection. One 60 tph vertical roller
                                                                 steel plant and India’s largest integrated private               mill is provided. Pulverised coal fineness is
                                                                 sector steel company is now the world’s second                   designed at 80% below 90m with surface

                          Relationship
                                                                 most geographically diversified steel producer,                  moisture less than 1.5%.
                                                                 with operations in 24 countries and commercial
                                                                                                                          The project broadly involved a total of 60,000
                                                                 presence in over 50 countries. Tata Steel completed
                                                                                                                          cu.m of civil work, 1500 nos. of bored cast in-situ
                                                                 100 glorious years of existence on August 26,
                                                                                                                          piles, 28,000 tons of structural work, 20,000 tons
                                                                 2007 following the ideals and philosophy laid
                                                                                                                          of equipment erection, 22,000 tons of refractory
                                                                 down by its Founder, Jamsetji Nusserwanji Tata.
                                                                                                                          work,1.5 km of rail track and 1500 km of electrical
                                                                 The first private sector steel plant which started
                                                                                                                          cabling.
                                                                 with a production capacity of 1,00,000 tonnes has
                                               Anupam Kumar
                                                                 transformed into a global giant. Its 5 million tonnes    Challenges
                                               Project Manager
                                                                 per annum (mtpa) Jamshedpur Works plans to
                                                                 double its capacity by 2010. L&T has played a            The plant was configured in a limited land area in the
                                                                 significant role in Tata Steel’s expansion process       existing slag and skullyard. Installation of 1000mm       Panoramic view
                                                                 at every stage. Recently it helped Tata Steel            dia piles on complete slag filled strata needed           of cast house
                                                                 commission India’s largest blast furnace ‘H’ and
                                                                 Sinter Plant No.4 in their plant at Jamshedpur.

                                                                 Salient Features

                                                                 The capacity of the ‘H’ blast furnace is 2.5 mtpa
                                                                 with daily production of around 7850t. The hearth
                                                                 diameter is 13m with 38 tuyeres and an inner
                                                                 volume of 3814 cu.m. The furnace has four tap
                                                                 holes in two cast houses.

                                                                 The blast furnace has few special features, which
                                                                 can be listed as follows:
                                                                 •    Low thickness (95mm) copper stave collers in
                                                                      the bosh, belly and lower stack for enhanced
                                                                      thermal exchange efficiency
                                                                 •    Double cardan type tuyere stocks for high
                                                                      temperature and pressure operations.
                                                                 •    Compact design INBA cast house slag
                                                                      granulation plant with low energy consumption,
                                                                      high reliability and minimum maintenance
                                                                      with very low operating manpower.
                                                                 •    Compact internal combustion chamber stoves
                                                                      (48m high and 10.7m dia) with a mushroom
                                                                      dome for better stability of dome bricks.
                                                                      Dome temperature designed for 1450oC with
                                                                      a maximum blast temperature of 1250oC with
                                                                      a blast pressure of 4.5 bar(g) and maximum
                                                                      blast volume of 3,60,000 Nm3/h. The hot
                                                                      blast system is designed for a max top gas
                                                                      pressure of 2.5 bar(g).
                                                                 •    The stoves operate on a maximum waste gas
                          Night view of Blast Furnace ‘H’                                                                     Hot metal at cast house
ECC Concord | Apr - Sep 08 24                                                                                                                                                25 ECC Concord | Apr - Sep 08
Salient Features of Blast Furnace – H
                                                                                   Furnace
                                                                                   BF inner volume              :   3814 cu.m
                                                                                   Daily production             :   7150 ton /day
                                                                                   Hearth Diameter              :   13 m
                                                                                   Number of tuyer              :   34 nos
                                                                                   Daily Production (Avg)       :   7150 tons / day
                                                                                   Furnace oprtg top pressure   :   2.5 bar g
                                                                                   Fuel Rate                    :   540 kg / per ton
                                                                                   Cast House
                                                                                   No. of cast houses           :2
                                                                                   No. of Tapholes              : 4 nos
      Hot stoves under     several modification to designed pile location at
                                                                                   Hot Blast Stove
             operation     various stages of the execution process.
                                                                                   Hot blast flow               : 360000 Nm3/h
                           Furnace productivity with high annual hot metal         Hot blast temperature        : 1250 deg C           start to finish, absolute safe working conditions     suction pressure of 170 m bar. The stack emission       Control room of
                           production and 15-20 years campaign life was            Stoves                                              for all construction, erection, operation and         level is 50 mg / Nm3.                                   the Sinter Plant
                           one of the top prerequisites of this project. All       (internal combustion type)   : 3 nos                maintenance were given top priority. A powerful
                                                                                   Blower                                              three dimensional modeling of H-Blast furnace was     Major Quantities
                           operational and logistics constraints were taken
                                                                                   Electric blower              : 2 nos                developed for optimum use of space, visualization
                           in to account at the time of planning, design and                                                                                                                 L&T’s scope involved 6000 t of mechanical supply
                                                                                   cap 190000 Nm3/hr
                           engineering. Major challenges of accommodating                                                              for easy maintenance and safety of operating
                                                                                   Motor MW for each blower     : 23                                                                         under and 800t from Outotec, 6800 t erection,
                           all necessary auxiliary and support facilities within                                                       people and identify the problems in accessibility,
                                                                                   Blast pressure               : 5 bar g                                                                    37000 cu.m of RCC, 8000 t of structural steel work
                           boundary limits was achieved through meticulous                                                             maintenance and erection plans. The quality of
                                                                                   Gas Cleaning                                                                                              and more than 36000 sq.m of sheeting work.
                           layout planning.                                        BF gas flow rate wet         : 550,000 Nm3/h        equipment manufactured was controlled from the
                                                                                   BF gas pressure              : 2.5 bar g            beginning of the project. The quality department
                           The project consumed 25000 tonnes of steel                                                                                                                        Salient Features
                                                                                   Coal Injection                                      at the Headquarters and the site team worked
                           structure, 59000 cu.m of concrete, 22000 tonnes                                                                                                                   Some of the salient features of this project
                                                                                   Average injection            : 160 Kg/thm           together to maintain the quality standards.
                           of equipment and more than 21000 t of refractory.                                                                                                                 include installation of sophisticated systems like
                                                                                   Peak injection               : 200 kg/thm
                           Handling such a massive volume of materials                                                                 As usual, L&T was committed to the welfare
                                                                                   BF cooling                                                                                                Automated Distributed Control System (DCS),
                           within the limited space was a major challenge                                                              of more than 4000 strong workforce with the
                                                                                   Hearth cooling
                                                                                              : Cast iron staves                                                                             Intelligent MCC for direct control from DCS,
                           and it was overcome with meticulous planning.           Shaft cooling
                                                                                              : Copper & Cast iron                     establishment of labour colony, training for safe
                                                                                                                                                                                             waste heat recovery system and VVVF (Variable
                                                                                                staves                                 working environment and adequate healthcare
                                                                                                                                                                                             Voltage Variable Frequency) electrical energy
                           Safety and Quality                                      Automation : DCS based Level-1                      measures tailor-made for the workforce.
                                                                                                                                                                                             saving system. For the lowest fuel consumption,
                                                                                                automation
                           The safe and quality construction within a                                                                  The project work, which commenced in August           short ignition furnace was used and CCTV control
                                                                                   		 Optimisation by
      Sinter machine at    stipulated time frame has always been a major                        level-2 automation                     2005 was completed in 31st May 2008 with the          monitors were installed for monitoring.     Other
       Sinter Plant No.4   challenge for all brownfield projects.  From                                                                blow in of the blast furnace.                         features include deployment of infra red scanners
                                                                                                                                                                                             for furnace monitoring and vibration isolation
                                                                                                                                       Sinter Plant #4:                                      system for fans to reduce foundation size.
                                                                                                                                       Sinter Plant # 4 has been built by the joint          The major challenge during the project execution
                                                                                                                                       consortium of L&T and Outotec GmbH (formerly          was stabilizing and pre-conditioning the soil
                                                                                                                                       Outokumpu Technology) on an EPC basis.                to avoid piling and save time. The detailed
                                                                                                                                       Valued at Rs. 350 Crores, this project was started    procedure was worked out by the Foundation
                                                                                                                                       in July 2005 with a contract duration of 24 months.   Engineering Department of L&T to achieve the
                                                                                                                                       According this was completed in November 2007         desired bearing capacity. Tower crane was used
                                                                                                                                       and production commenced thereafter.                  for erection of structures as well as equipment
                                                                                                                                       The product capacity of sinter plant # 4 is 2.3       right from the initial stage of construction. A well
                                                                                                                                       mtpa with the designed machine productivity of        co-coordinated system helped to procure quality
                                                                                                                                       around 34 t per sq,m per day. The suction area        equipment at the right time. The documented
                                                                                                                                       of the machine is 204 sq.m and the pallet width is    learning experienced during the construction of
                                                                                                                                       3m with bed height of around 700 mm. The sinter       Sinter plant #3 was implemented from the design
                                                                                                                                       cooler area is 202 sq.m. The sinter plant has got     stage onwards to ensure smooth implementation
                                                                                                                                       the waste gas fan capacity of 170 Nm3/sec with        and commissioning of the project.

ECC Concord | Apr - Sep 08 26                                                                                                                                                                                                                 27 ECC Concord | Apr - Sep 08
You can also read