System Status Briefing - BRIAN MOLEFE Group Chief Executive - Eskom

 
CONTINUE READING
System Status Briefing - BRIAN MOLEFE Group Chief Executive - Eskom
System Status Briefing
(April – June 2016)

BRIAN MOLEFE
Group Chief Executive

July 2016

                         CONFIDENTIAL
System Status Briefing - BRIAN MOLEFE Group Chief Executive - Eskom
Contents

     1 Operational highlights

     2     Distribution Overview

     3 Generation Performance

     4 Outlook

     5 New build update

     6 Majuba power station silo & Duvha unit 3 updates

     7 Conclusion
System Status Briefing - BRIAN MOLEFE Group Chief Executive - Eskom
Overview of Eskom’s electricity value chain

                                                                   Distribution challenges

                                                    Generation     Stable, no load
                                                                   shedding

                                                    Transmission   Stable, no major
                                                                   incidents

                                                                   Stable with localised
                                                    Distribution   faults
                        Mining, Metros and large
                        industry                 Total
                                                 Distribution      5,689 million
                                                 Customers

                             Industry, commercial
                             and farming

                           Supply to municipalities
                           and residential
                                    3
System Status Briefing - BRIAN MOLEFE Group Chief Executive - Eskom
We continue to experience overall excellent
operational performance

•   Eskom has sufficient Generation capacity to meet the peak demand, due to improved

    energy availability factor; currently the year-to-date figure stands at 78.9 %. In the next

    five years Eskom will add an additional 8 169 MW capacity from our current new build

    project

•   On the Transmission side, we have excellent performance year-to-date with no system

    minutes incidents greater than 1

•   Distribution network performance (SAIFI and SAIDI) within acceptable limits, however we

    have localised incidents due to illegal connections, theft and plant failure, which are being

    addressed

                                                 4
System Status Briefing - BRIAN MOLEFE Group Chief Executive - Eskom
Contents

     1 Operational highlights

     2     Distribution Overview

     3 Generation Performance

     4 Outlook

     5 New build update

     6 Majuba power station silo & Duvha unit 3 updates

     7 Conclusion
System Status Briefing - BRIAN MOLEFE Group Chief Executive - Eskom
Eskom continues to work hard to speedily restore and
stabilise the Distribution network around the country

 •   In the past few weeks Eskom Distribution has experienced a number of
     localized power outages

 •   The key causes of the power outages are illegal connections which result
     in the overloading of our networks, cable theft and the vandalism of
     electricity infrastructure

 •   Technical faults and routine planned maintenance also result in power
     interruptions

 •   Eskom     responded by replacing damaged or failed equipment and in
     some cases upgrading the infrastructure, this approach has proven not to
     be sustainable
System Status Briefing - BRIAN MOLEFE Group Chief Executive - Eskom
Over the past few weeks, the Eskom team has worked hard to
restore and stabilise the Distribution network in Gauteng

Hot spots identified                         Key cause and impact of outages Remedial actions undertaken
                                          •    Illegal connection and             •   Stabilise
                                               overloading                        •   Repaired and replaced 31 mini
    Soweto                                                                            substations and 287 transformers:
                                          •    Cable theft and vandalism              o 61 transformers in Soweto
                                                                                      o 44 Trf in Randfontein
                                                                                      o 16 transformer in Sandton
    Kagiso                                                                            o 42 transformer in Midrand
                                                                                      o 45 transformer in Ekhureleni
                                                                                      o 42 transformer in the Vaal
    Katlehong                                                                         o 36 transformer in Tshwane
                                                                                  •   Breaker trips – reset breaker, upgrade
                                         •     Plant failure                          and split the network
                                                                                  •   Upgraded & replaced damaged cables
    Mamelodi                                                                      •   Proactively engaged with affected
                                         •     About 5 mini sub-stations fail a       communities
                                               day

    Bophelong

Note: Approximately 250- 500 people impacted when a mini sub-station fails 7
System Status Briefing - BRIAN MOLEFE Group Chief Executive - Eskom
Background and impact of illegal connections, theft
and vandalism
                                Areas such as Soweto, Kathlehong, Diepsloot,
                                  Bramfischerville, Sebokeng have been mostly
                                  affected by localised outages.

                                The design philosophy on these townships was done
                                  with a maximum demand of 2kVA per stand, however
                                  illegal connections overload the transformers,
                                  resulting in failures

                                These areas are infested with illegal connections,
                                  back yard shacks, bypassed meters and
                                  vandalised pillar boxes resulting in network
                                  overloading and thus causing localised power
                                  failures.

                                These factors cause equipment to operate above their
                                  maximum rated or operating parameters thus reduces
                                  the life’s span of the equipment
                                                                                   8
System Status Briefing - BRIAN MOLEFE Group Chief Executive - Eskom
Pictures taken to illustrate the severity of illegal
connections in the Western Cape – 18 July 2016
Illegal connections                 Illegal power lines

                              9
System Status Briefing - BRIAN MOLEFE Group Chief Executive - Eskom
Overloading caused by backyard dwellers increasing
demand on the network
                                                        Assumption and analysis:
                                                            Assuming that Diepsloot has 2000 stands with
                                                               an average of 6 backyard dwellers per stand
                                                            Instead of 2000, the area has now yielded
                                                               12 000 dwellings

                                                        Original design capacity of 4MVA (Based on
                                                         2000 stands), increased to 24MVA as a result

Eight shacks can be seen in the photo
                                                        This will result in continuous trips of the
                                                         transformers feeding this households

                                                        The back yard dwellings (with an observed ratio of
                                                         1: 8 average) , pose a risk to the infrastructures
                                                         and provision of reliable electricity.

                                                        Protective Structures are damaged, forcefully
      There are 15 rooms in this house all illegally
                      connected                          opened and metering equipment is bypassed
                                                                                                              10
Immediate response to this problem

                                      Eskom responded by replacing damaged or failed
                                       equipment and in some cases upgrading the
                                       infrastructure, this approach has proven not to be
                                       sustainable.

                                      Other Interventions included the installation of
                                       protective structures, replacement of burnt fuses,
                                       retention of sagging conductors and load balancing
                                       on phases which are all costly solutions.

                                      Developed community partnerships and intensified
                                       training (develop sense of ownership).

                                      As part of network maintenance all open pillar boxes
                                       are closed and damaged infrastructure is normalised.

                                      Increased security measures to deal with fraud
                                       related to meter bypasses and conductor theft.

                                  11                                                      11
Sustainable solutions

•   A three-pronged approached has been developed to recover, stabilise and
    improve the performance of the electricity network.

•   Eskom remains committed in ensuring that customers have a continuity of
    supply and ensuring a sustainable solution to the current challenges.

•   It is also important for communities to support our efforts towards removal of
    illegal connections and installation of smart meters so as to ensure that we
    can accelerate the overall service level improvement.

•   Eskom customers are urged to report electrical faults at 08600 37566
Contents

     1 Operational highlights

     2     Distribution Overview

     3 Generation Performance

     4 Outlook

     5 New build update

     6 Majuba power station silo & Duvha unit 3 updates

     7 Conclusion
Performance Highlights for Q1 F2017(1/2)

                Description

 Maintenance    •   No load shedding has been implemented since August 2015
 without load       (except for 2 hours and 20 minutes)
 shedding
                •   Average planned maintenance (PCLF) for Q1 F2017 is 11.11 %

                •   OCGT energy sent out has decreased from 1 801 GWh in Q1
                    F2016 to 16 GWh Q1 F2017, which is a 98% decrease in energy
 Low diesel         from diesel generators
 usage and
 spend          •   This resulted in a decrease in diesel costs from R 3.9 bn to
                    R 86 m from when comparing Q1 F2016 and Q1 F2017 which is a
                    98% decrease in diesel spend
Performance Highlights for Q1 F2017 (2/2)

                Description

                • Energy availability reached record highs of 81 % for the month of
                 June. This was last achieved in July 2013.

 Increased      • The energy availability has increased from 69.6 % (Q1 F2016) to
 availability    78.6 % (Q1 F2017) which translates into an additional 3 775 MW of
                 extra power made available from the improvements made in the
                 existing fleet

                • Eskom has been able to meet demand this financial year even during

 Demand and      the weeks where demand was higher than last year

 Sales          • Eskom has increased cross boarder sale by 33% when comparing
                 the energy (GWh) sent out
Plant performance has been improving
  considerably since October 2015
Performance over the past nine months
Percentage                                                  Breakdowns1          Planned maintenance       Available energy

                                                                                                             Insights

                                                              12,9        12,0     9,6     9,3     9,5
 18,0        17,4         14,7        17,0           15,6                                                    • For the month of
                                                                                           9,7     9,7         June 2016, energy
                                                                                   11,5                        availability
                                                              12,9        12,1
                          16,0        11,2           9,8                                                       reached record
 12,0        12,3
                                                                                                               highs of 81 % for
                                                                                                               the month of June
                                                                                                               2016 ,this was last
                                                                                                               achieved in July
                                                                                                               2013

                                                                                   78,9   81,0    80,8
                                      71,8           74,7     74,2        75,9                               • During the last
 70,0        70,3         69,3
                                                                                                               quarter planned
                                                                                                               maintenance
                                                                                                               exceeds
                                                                                                               unplanned
                                                                                                               breakdowns

Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 16-May Jun-16                                    Jul-16

1 - Includes breakdowns and other non plant losses                   16
2 – month to date performance on 17 July 2016
OCGT usage and costs have both decreased as
    a result of improved Generation availability
OCGT performance over the past nine months
GWh                                                                                           Energy Send Out (GWh)
    400      381,2
                                                                                                   Insights
    350
                                                                                                   • Improvements in
    300                286,7                                                                         EAF have resulted
                                                                                                     in lower usage of
    250                                                                                              diesel and hence
                                                                                                     a reduction in the
    200                          180,3                                                               costs
                                                                                                   • For Q1 2017, YTD
    150
                                                                                                     savings in diesel
                                            100,1                                                    costs is R 649.6
    100                                                                                              million
      50                                                                                           • Dispatching the
                                                       21,2                                          diesel generators
                                                              6,6        6,3   4,8   5,0   1,7
       0                                                                                             less frequently,
             Oct        Nov       Dec        Jan       Feb    Mar        Apr   May   Jun   Jul1      has resulted in a
                                                                                                     decrease in
                                                                                                     maintenance
Load           21        16         10           5.6   1.3    0.4        0.4   0.3   0.3   0.2       intervals, which is
Factor (%)
                                                                                                     a further
                                                                                                     decrease in
Cost (R’m)    854        555       278           187    62    25         25    46    14    5.8       maintenance
                                                                                                     cost

 1 – month to date performance on 04 July 2016                      17
The improved performance of the Eskom plant is not
due to lower demand
Daily peak demand compared to available capacity
Megawatts
                                                                                       2                       2

                                                                                           Insights
                                                                                           • The           available
                                                                                             capacity             is
                                                                                             significantly   higher
                                                                                             than the capacity
                                                                                             available last year
                                                                                           • The          available
                                                                                             capacity this year is
                                                                                             greater than the
                                                                                             peak demand last
                                                                                             year and that of this
                                                                                             year
                                                                                           • This means that if we
                                                                                             had     this   year’s
                                                                                             capacity     available
                                                                                             last year we would
                                                                                             have avoided load
                                                                                             shedding last year

1 – improvements made in energy availability and capacity from Medupi 6 and Ingula 4
2 – Excluding IPP’s however including Cahora Bassa
                                                                     18
Comparison of how the highest peak demand was
met in 2015 vs 2016
Build up of how peak demand is met
 Megawatts
         IPP Support                                        OCGT                               Eskom (Excl Gas)
         Mandatory Demand Reductions                        Contracted Demand Reductions1
                                                                                            Insights
                    34481                                              34899
                                                                                            • The peak demand in 2015
                     333                                            779
                                                                               0   0          could not be met and
                                                                   1121
                     2514                                                                     required  2500MW     of
                                                                                              mandatory      demand
                                                                                              reduction as well as
                     2242                                                                     2250MW of OCGT usage.
                      358
                                                                                            • The peak demand so far
                                                                                              in 2016 was supplied
                                                                       32999                  without any mandatory
                    29034                                                                     demand    reduction or
                                                                                              OCGT usage.

                                                                                            • This was possible due to
                                                                                              the Eskom generation
                                                                                              availability being 4000MW
                                                                                              higher in 2016 than in
                11 Jun 2015                                         30 May 2016               2015 during the annual
                                                                                              peak
1- Virtual power station or interruptible load supply agreements      19
With Eskom’s excess capacity, we have increased
our exports
Break down of Southern African Power Pool (SAPP) Sales per customer
SAPP Sales (GWh)
                       EDM      CEC         ZESA          SEC
                                                                      Insights into Quarterly sales
                       ORC      ZESCO       Skorpion      BPC
                       LEC      DAM         NamPower      Motraco     • Eskom has firm cross border sales
                                                                        to end-use customers which have
                                               3,955                    remained    fairly  constant   at
                                                                        ~ 2 200GWh, increasing by 70GWh
                                                                      • The firm and non-firm sales to
                                                                        utilities  has  increased   by
              2,984                                                     ~ 900GWh
                                                                      • The    total  cross-border    sales
                                                                        increased by 970GWh
                                                                      • Eskom supply is making an
                                                                        increasing and positive contribution
                                                                        to support the economies of SADC
                                                                        and to offset the impact of the
                                                                        drought on the Kariba power station
                                                                      • With progressive additional capacity
                                                                        coming online in South Africa
                                                                        Eskom will be reviewing the exports
                                                                        with a view to assess future
                                                                        sustainability
             Q4 2015                          Q4 2016
Contents

    1 Operational highlights

    2   Distribution Overview

    3 Generation Performance

    4 Outlook

    5 New build update

    6 Majuba power station silo & Duvha unit 3 updates

    7 Conclusion
Outlook

  Tetris Maintenance Plan
  •   Our prognosis for winter and beyond is that there will be no load
      shedding

  •   Eskom is progressing well with the maintenance of its power
      generating plant whilst supplying the country’s electricity needs,
      while also minimising usage of open cycle gas turbines

  •   Eskom is targeting a maintenance budget:
       • 8 500 MW in Winter
       • 11 500 MW in Summer

  •   Renewable energy will continue to contribute up to Photovoltaic 900
      MW and wind 880 MW of the total installed capacity of 2 310 MW of
      electricity generated during the day from solar and wind including
      Eskom’s Sere wind farm
The Tetris plan indicates no loadshedding for the
   remainder of the year

               Available Capacity           Operating Reserves         PCLF          UCLF          Peak Demand           Installed Capacity

45000
                                                                                                                  Installed Capacity is the total
                                                                                                                 generating capacity from Eskom’s
                  Winter UCLF                                                       Summer UCLF                  combined fleet
                   5500 MW                               Plant Breakdowns             6500 MW
40000

                                                                                                    Plant Breakdowns: from the available capacity we
                                                                                                    subtract the anticipated breakdowns
35000                                                           Planned Maintenance

                                                      Operating Reserve                             Planned Maintenance: from this we also need to
                                                                                                    subtract the planned maintenance
                                                                                               Operating Reserve: 2000 MW buffer to cater for sudden
30000
                                                                                               Increase in load or if generating units are lost
        Peak Demand: the forecasted demand does not exceed the
        available capacity and we still have the 2000 MW of operating
25000   reserve as a buffer. Therefore the prognosis is no load           Available Capacity
        shedding for the remainder of the year        Available Capacity: the capacity available to meet the demand
                                                    we now have to superimpose the demand forecast for the year
                                                    to compare it with the this available capacity.
20000
         Jul         Aug              Sep              Oct              Nov              Dec               Jan            Feb            Mar
                                                  2016                                                                   2017

   Tetris V4.20
1 Planned Maintenance – July to September 2016
                                                                                                                                                                                                    Available Capacity = Installed Capacity - Peak Demand - UCLF

Eskom is targeting a maintenance budget of 8.5 GW for Winter months
9000

8000

7000

6000
                                                                                                                      Operating Reserve                                                                                                                                                                                              Drakensberg 1

                                                                                                                                                                         Kendal 6                                                                                                                                      Matla 3
5000                                                                                                                                                                                                                                                                                                                Camden 1
                                                                                                                                                                                                                                                                                                                    Hendrina 10
                                                                                                                    Lethabo 3
4000                                                                                                                                                                                                                               Port Rex 3                                                                              Koeberg 1
                                                                                                                     Hendrina 8                                                                                              Gariep 4                                        HCB 1
                                                              Drakensberg 4                                                                                                                                           Komati 5
                                                                                                                       Duvha 5                                                                                                      Komati 7
                                                                                                                                                                                                                            Hendrina 1                                                                                     Majuba 3
3000                                                                                                                                                                                                                   Tutuka 4
                                                                                                                            Tutuka 3
                   Lethabo 1                                                                                                                                                                             Ankerlig 3                                                                                                        Tutuka 6
                                                                                                                                                                       Ankerlig 4
                            Kriel 3
2000                                                                                                                                                                 Matimba 4
                                  Grootvlei 6
                                                                                                                                                                     Grootvlei 1
                                                                                                                                                                             Grootvlei 2
1000                                                                                                                                                                     Kendal 5
                                                                                                                                                       Arnot 1
                                                                                                                                       Komati 3                             Camden 2
   0                                                                                                                                                                 Hendrina 7
       18-Jul
                20-Jul
                         22-Jul
                                  24-Jul
                                           26-Jul
                                                    28-Jul
                                                             30-Jul

                                                                                                                                                                                                                       02-Sep
                                                                                                                                                                                                                                04-Sep
                                                                                                                                                                                                                                         06-Sep
                                                                                                                                                                                                                                                  08-Sep
                                                                                                                                                                                                                                                           10-Sep
                                                                                                                                                                                                                                                                    12-Sep
                                                                                                                                                                                                                                                                             14-Sep
                                                                                                                                                                                                                                                                                       16-Sep
                                                                                                                                                                                                                                                                                                18-Sep
                                                                                                                                                                                                                                                                                                         20-Sep
                                                                                                                                                                                                                                                                                                                  22-Sep
                                                                                                                                                                                                                                                                                                                            24-Sep
                                                                                                                                                                                                                                                                                                                                      26-Sep
                                                                                                                                                                                                                                                                                                                                               28-Sep
                                                                                                                                                                                                                                                                                                                                                        30-Sep
                                                                      01-Aug
                                                                               03-Aug
                                                                                        05-Aug
                                                                                                 07-Aug
                                                                                                          09-Aug
                                                                                                                   11-Aug
                                                                                                                            13-Aug
                                                                                                                                     15-Aug
                                                                                                                                              17-Aug
                                                                                                                                                       19-Aug
                                                                                                                                                                21-Aug
                                                                                                                                                                         23-Aug
                                                                                                                                                                                  25-Aug
                                                                                                                                                                                           27-Aug
                                                                                                                                                                                                    29-Aug
                                                                                                                                                                                                             31-Aug

                                    Jul                                                                                                Aug                                2016                                                                                                        Sep

          The no loadshedding plan allows for available capacity as we seldom dip into the operating reserves
                                                                                                                                                                                                                                                                                                                                                        24
 Source: Tetris Plan V4.20
2 Planned Maintenance – October to December 2016
                                                                                          Available Capacity = Installed Capacity - Peak Demand - UCLF

 Eskom is targeting a maintenance budget of 11.5 GW for summer months
 9000

 8000

 7000

 6000                                                  Operating Reserve
                             Tutuka 5                                         Tutuka 1
          Tutuka 6                                                                                      Matimba 3                              Hendrina 4
             Ankerlig 3                                                                    HCB 1                     Majuba 4        Kriel 1
 5000                                                                                                                                          Duvha 2
                Matla 3                 Hendrina 2                                           Majuba 2               Duvha 6         Kendal 1
                                                     Vanderkloof 1
             Drakensberg 1
              Hendrina 7
                                                 Komati 4                                                             Komati 6
 4000                                                                                                                   Lethabo 6
               Kendal 5                        Koeberg 1

                                               Komati 7 Ankerlig 1                                                       Matla 2
 3000          Majuba 3
                                                             Lethabo 5                                                 Matimba 6
                                                            Gourikwa 1
 2000                                                         Tutuka 4                                                  Medupi 6

                                                                                               Kriel 4
 1000                                                                                Drakensberg 2
                                                                      Camden 1
                                                                     Hendrina 10
                                                                     Hendrina 1
                                                                     Grootvlei 2
                                                                      Camden 2           Komati 3
    0
         01-Oct
         03-Oct
         05-Oct
         07-Oct
         09-Oct
         11-Oct
         13-Oct
         15-Oct
         17-Oct
         19-Oct
         21-Oct
         23-Oct
         25-Oct
         27-Oct
         29-Oct
         31-Oct

        02-Dec
        04-Dec
        06-Dec
        08-Dec
        10-Dec
        12-Dec
        14-Dec
        16-Dec
        18-Dec
        20-Dec
        22-Dec
        24-Dec
        26-Dec
        28-Dec
        30-Dec
        02-Nov
        04-Nov
        06-Nov
        08-Nov
        10-Nov
        12-Nov
        14-Nov
        16-Nov
        18-Nov
        20-Nov
        22-Nov
        24-Nov
        26-Nov
        28-Nov
        30-Nov
                             Oct                                           Nov                                                  Dec
                                                                           2016
        The no loadshedding plan allows for available capacity
                                                         2016 as we seldom dip into the operating reserves                                                  2
Source: Tetris Plan V4.20
3          Planned Maintenance – January to March 2017
                                                                                           Available Capacity = Installed Capacity - Peak Demand - UCLF

Eskom is targeting a maintenance budget of 11.5 GW for summer months
8000

7000

6000

5000                                                                  Operating Reserve                                                          Majuba 1
           Duvha 2                                                                                          Tutuka 3
                                                   Kendal 6                                                                                     Matla 1
       Hendrina 4
                                        Tutuka 6                                      Hendrina 5
4000   Grootvlei 2
       Camden 2                                                                             Tutuka 5                                          Koeberg 2
                                                                           Kendal 2
        Kendal 1 Lethabo 4                                      Gourikwa 2                                             Matla 4
3000                                                                          Ankerlig 5                                Gourikwa 3             Kriel 5
              Kriel 4                                              Ankerlig 7
                                                                      Matimba 2                                         Matimba 1
              Kriel 1                                                                                                   Hendrina 2
2000                                                                            Palmiet 2                               Grootvlei4
             Lethabo 6                                                                                                    Arnot 5
                                                                          Matla 2
Komati 6                 Hendrina 1
1000                                                                                     Kriel 2
                                                                                Hendrina 3
                                                              Hendrina 10
                                                                        Drakensberg 2
   0                                                                      Camden 1
        01-Jan
        03-Jan
        05-Jan
        07-Jan
        09-Jan
        11-Jan
        13-Jan
        15-Jan
        17-Jan
        19-Jan
        21-Jan
        23-Jan
        25-Jan
        27-Jan
        29-Jan
        31-Jan
        02-Feb
        04-Feb
        06-Feb
        08-Feb
        10-Feb
        12-Feb
        14-Feb
        16-Feb
        18-Feb
        20-Feb
        22-Feb
        24-Feb
        26-Feb
        28-Feb
       02-Mar
       04-Mar
       06-Mar
       08-Mar
       10-Mar
       12-Mar
       14-Mar
       16-Mar
       18-Mar
       20-Mar
       22-Mar
       24-Mar
       26-Mar
       28-Mar
       30-Mar
                                  Jan                                        Feb                                               Mar
                                                                            2017
                                                                                                                                                            2
        The no loadshedding plan allows for available capacity as we seldom dip into the operating reserves                                                 6
 Source: Tetris Plan V4.19
Contents

     1 Operational highlights

     2     Distribution Overview

     3 Generation Performance

     4 Outlook

     5 New build update

     6 Majuba power station silo & Duvha unit 3 updates

     7 Conclusion
New Build Update (1/2)

•   Medupi Unit 6 was commissioned on 23 August 2015, adding 794 MW to the
    national grid.

•   Since the previous update, the turbine on barring, first oil fire and first coal
    fire milestones were achieved on Medupi Unit 5, which are important
    milestones towards boiler blow through, first synchronisation and ultimately
    commercial operation of the unit.

•   Medupi Unit 5 is expected to be commercially operational in March 2018
    (P80).

•   Eskom has managed to synchronise all Ingula units to the national grid,
    ahead of schedule. The last two units (2 &1) were synchronised on 21 May
    and 16 June 2016 respectively.

•   lngula Unit 4 was successfully commissioned on 10 June 2016, adding 333
    MW to South Africa’s electricity grid.

•   Repairs on Ingula Unit 3 are progressing well and all the remaining Ingula
    units (3, 2 & 1) are on track for commercial operation during 2017
New Build Update (2/2)

•   Kusile power station continues to achieve set milestones on the path for Unit
    1 commercial operation, recently completing the draught group run milestone
    on 11 June 2016.

•   Kusile Unit 1 is expected to be commercially operational in July 2018 (P80).

•   At the end of May 2016, 10.1 km’s of transmission lines have been
    constructed and 800 MVA’s of substation capacity commissioned for 2016/17
    financial year. The targets for 2016/17 FY are 525 km’s and 1 800 MVA.

•   Since inception in 2005, the capacity expansion programme so far added
    7 364 MW of generation capacity, 6 162 km of transmission lines and
    32 890 MVA of substation capacity to the national grid.
We remain focused on bringing new capacity
    online
    P80 dates
    CO = commercial operation

                                                      CO achieved in
CO in Mar 2015            CO in Aug 2015                 Jun 16              CO by Jul 2017            CO by Jul 2018

     100                      794                          333                    333                        800

   Mar 2015                Aug 2015                      Jun 16                Jul 2017                  Jul 2018         5 620MW
Sere Wind Farm           Medupi Unit 6                Ingula Unit 4          Ingula Unit 1             Kusile Unit 1

                                                                                                                        Post MYPD 3

     Mar 2015                           Jan 2017                   May 2017                    Mar 2018                      2019/20
  Majuba recovery                     Ingula Unit 3              Ingula Unit 2               Medupi Unit 5                 Duvha Unit 3

       1200                                333                         333                       794                            600

600MW from Unit 3 gap                CO by Jan 2017              CO by May 2017          CO by Mar 2018                   Fully recovered
  solution in Feb 2015                                                                                                  Project falls outside
 600MW from Unit 4 in                                                                                                    MYPD3 window
        Mar 2015
New capacity will fuel the South African economy

Additional MW to be added to the South African grid
Installed capacity (MW)                               Medupi + Sere    Ingula
                                                                                                    Insights
                                                      Kusile           Current capacity
                                                                                                    • Eskom is
 55,000                                                                           53,389
                                                          51,789      52,589                          progressively
                                           50,195                                  4,864              adding capacity
 50,000                                                               4,864
                                47,807                     4,864                                      over the next
                                           4,070
                     45,419      2,482                                3,200        4,000              seven years
 45,000   44 420                              1,600        2,400
                           894      800
           1227      1,332     1,332      1,332            1,332      1,332        1,332
                                                                                                    • Ingula will be
 40,000
                                                                                           40,000     fully
                                                                                                      commissioned in
 35,000                                                                                               2017

          43,193     43,193     43,193     43,193         43,193      43,193      43,193            • Medupi will be
                                                                                                      fully
                                                                                                      commissioned by
 10,000                                                                                               2020

  5,000
                                                                                                    • Kusile will be
                                                                                                      fully
                                                                                                      commissioned by
     0
          2016       2017        2018       2019           2020       2021         2022
                                                                                                      2022
Contents

     1 Operational highlights

     2     Distribution Overview

     3 Generation Performance

     4 Outlook

     5 New build update

     6 Majuba power station silo & Duvha unit 3 updates

     7 Conclusion
Majuba Power Station silo & Duvha Unit 3 update

 Majuba Permanent solution                    Duvha unit 3 update

•   Good progress continues on delivering     •   The contract negotiations for the
    the permanent solution for the recovery       rebuild portion of the scope have been
    of the coal silo at Majuba.                   terminated.
•   Completion is on track for end December   •   The supplier was unable to meet the
    2017 (P80)                                    conditions precedent to enable
•   Plans to accelerate completion are in         agreement on the contract.
    place and progressing well
                                              •   Eskom has appointed suppliers who
                                                  will commence with the structural
                                                  assessments and repairs scope of
                                                  work. Based on the current works
                                                  schedule no additional delay is
                                                  foreseen

                                              •   Eskom will commence in a new
                                                  commercial process. Management is
                                                  yet to approve initiation of the new
                                                  commercial process.
Contents

     1 Operational highlights

     2     Distribution Overview

     3 Generation Performance

     4 Outlook

     5 New build update

     6 Majuba power station silo & Duvha unit 3 updates

     7 Conclusion
Conclusion

  •   Eskom has stabilised and to date we have not implemented load
      shedding in almost 11 months (except for 2 hours and 20 minutes)

  •   We are ensuring that power supply remains unconstrained through our
      maintenance programme

  •   We are also aggressively executing the capital build programme which
      will increase our generation capacity.

  •   Eskom has worked hard to restore and stabilise the electricity distribution
      network around the country, and we remain committed in ensuring that
      customers have a continuous supply of electricity.
Video
You can also read