- 81 - City of San Diego
Fiscal Year 2021 Adopted BudgetPage Intentionally Left Blank
Airports
The Airports Division manages and operates Brown Field Municipal Airport and Montgomery-Gibbs Executive
Airport with a combined 1,330 acres of real estate. These two general aviation airports contain nearly eight miles
of runways and taxiways, which safely accommodate over 300,000 annual aircraft operations, including those of
the military, U.S. Customs and Border Protection, San Diego Police, San Diego Fire-Rescue, Cal-Fire, Sheriff, Medi-
Evacs, as well as business and recreation sectors. The most critical factor associated with airport management is
maintaining safety. To that end, the Capital Improvements Program plays an important role by rehabilitating and
repairing the pavement and lighting of runways, taxiways and aircraft ramp areas. These capital improvements
are largely funded by Federal Aviation Administration (FAA) and Caltrans matching grants, as well as enterprise
funds.
2020 CIP Accomplishments
The Airports Division had several accomplishments and successes in Fiscal Year 2020, including:
Montgomery-Gibbs Executive Airport (KMYF)
• Completed rebuild of a section of Taxiway Hotel in response to a sinkhole under the pavement
• Completed electrical upgrade system (Coast Flight)
Brown Field (KSDM)
• Completed the 8R/26L Runway Drainage Consultation
2021 CIP Goals
The CIP Goals of the Airports Division are the provision of safety, and compliance with Federal, State, and local
regulations and policies. To achieve this in Fiscal Year 2021, the Airports Division is pursuing the following goals:
Montgomery-Gibbs Executive Airport (KMYF)
• Asphalt rehabilitation of non-movement area and an airport parking lot (east side)
• Runway 10L/28R Grooving and Marking Design and Construction
• Initiate Montgomery Field Commercial Building tenant improvements (Engineering Campus)
Brown Field (KSDM)
• Asphalt rehabilitation of non-movement and ramp areas
• Initiate the design for the rehabilitation of Runway 8R/26L
- 83 - City of San Diego
Fiscal Year 2021 Adopted BudgetPage Intentionally Left Blank
Airports: Capital Improvement Projects
Prior Fiscal FY 2021 Future Fiscal
Project Years Adopted Years Project Total
Brown Field / AAA00002 $ 9,261,696 $ - $ - $ 9,261,696
Montgomery-Gibbs Executive Airport / AAA00001 1,996,294 - - 1,996,294
Total $ 11,257,990 $ - $ - $ 11,257,990
- 85 - City of San Diego
Fiscal Year 2021 Adopted BudgetPage Intentionally Left Blank
Airports
Brown Field / AAA00002 Airport Assets
Council District: 8 Priority Score: Annual
Community Planning: Kearny Mesa Priority Category: Annual
Project Status: Continuing Contact Information: Rubio, Jorge
Duration: 2002 - 2040 858-573-1441
Improvement Type: Betterment jerubio@sandiego.gov
Description: This annual allocation provides for as-needed improvements within the City's Brown Operating Budget Impact: None.
Field Airport; which can include, but is not limited to, pavement, drainage, striping, and signage Relationship to General and Community Plans: This project is consistent with the Otay Mesa
for scheduled rehabilitation in order to meet current Federal Aviation Administration (FAA) Community Plan and is in conformance with the City's General Plan.
standards. Schedule: Projects will be scheduled on a priority basis. Design for SDM's 8R/26L runway is
Justification: This project maintains an airport which promotes the safe use of the runways as anticipated to begin in FY2021 and be completed in FY2022. Construction is anticipated to begin
required by the FAA, Caltrans (Division of Aeronautics), and compliance with federal and State in FY2023 and be completed in FY2024.
ADA regulations. Summary of Project Changes: It is anticipated that approximately $500,000 will be spent on a
design contract for SDM's 8R/26L runway in FY2021.
Expenditure by Funding Source
FY 2021 Unidentified Project
Fund Name Fund No Exp/Enc Con Appn FY 2021 Anticipated FY 2022 FY 2023 FY 2024 FY 2025 Future FY Funding Total
Brown Field Special Aviation 700028 $ 1,579,921 $ 1,998,082 $ - $ - $ - $ - $ - $ - $ - $ - $ 3,578,004
Grant Fund-Enterprise-Federal 710000 5,683,692 - - - - - - - - - 5,683,692
Total $ 7,263,613 $ 1,998,082 $ - $ - $ - $ - $ - $ - $ - $ - $ 9,261,696
- 87 - City of San Diego
Fiscal Year 2021 Adopted BudgetAirports
Montgomery-Gibbs Executive Airport / AAA00001 Airport Assets
Council District: 6 Priority Score: Annual
Community Planning: Kearny Mesa Priority Category: Annual
Project Status: Continuing Contact Information: Rubio, Jorge
Duration: 2002 - 2040 858-573-1441
Improvement Type: Betterment jerubio@sandiego.gov
Description: This annual allocation provides for as-needed improvements within the Operating Budget Impact: None.
City's Montgomery-Gibbs Executive Airport; which can include, but is not limited to, pavement, Relationship to General and Community Plans: This project is consistent with the Kearny Mesa
drainage, striping, and signage for scheduled rehabilitation in order to meet current Federal Community Plan and is in conformance with the City's General Plan.
Aviation Administration (FAA) standards. Schedule: Projects will be scheduled on a priority basis.
Justification: This project maintains an airport which promotes the safe use of the runways as Summary of Project Changes: It is anticipated that approximately $500,000 will be spent on a
required by the FAA, Caltrans (Division of Aeronautics), and compliance with federal and State design contract for SDM's 10R/28L runway in FY2021.
ADA regulations.
Expenditure by Funding Source
FY 2021 Unidentified Project
Fund Name Fund No Exp/Enc Con Appn FY 2021 Anticipated FY 2022 FY 2023 FY 2024 FY 2025 Future FY Funding Total
Montgomery Field Special Aviation 700030 $ 506,455 $ 1,489,838 $ - $ - $ - $ - $ - $ - $ - $ - $ 1,996,294
Total $ 506,455 $ 1,489,838 $ - $ - $ - $ - $ - $ - $ - $ - $ 1,996,294
- 88 - City of San Diego
Fiscal Year 2021 Adopted BudgetYou can also read