Capital Project Update - Q4 2018 - BUILDINGS Air Exchange Unit - Grounds Shop - Town of Banff
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Capital Project Update – Q4 2018
BUILDINGS
Air Exchange Unit - Grounds Shop
Project description & goals: Installation of an air-exchange unit in the grounds shop to improve air quality and
worker safety
Current Status: Complete
Banff Elementary School Partnership
Project description & goals: Partnership with Canadian Rockies Public Schools to incorporate space in phase 2 of
the Banff Elementary school redevelopment for Out–of–School Club and an expanded gymnasium to better suit the
needs of the community.
Current Status: Partnership with CRPS has been collaborative and productive. Construction is ongoing with
completion scheduled for the Spring of 2019. The Town has commenced design work for provide complimentary
upgrades – sidewalks and formalized curb and gutter/parking to Bighorn and Moose Sts. Construction of these
public realm upgrades are planned for next summer to be complete ready for the start of the 2019/2020 school
year.
Buildings Lifecycle Maintenance
Project description & goals: Scheduled maintenance and capital replacements for facilities
Current Status:
Library interior paint. Completed
101 Bear Street, replace main doors upper storey. Completed
Day Care –
Shingle replacement- Complete
Interior paint- Completed
Exterior paint- moved to 2019
Upgrade HVAC system. Engineering phase in process
449 Cougar St., exterior paint- Completed
Fire Hall-
Replace cedar shingles-Completed
Exterior renovation & paint- Completed
552 Banff Ave., exterior paint-Completed
1Projects for 2019:
Town Hall Shingles, Attic Ventilation/ Insulation
Town Hall Kitchen renovations
Fire Hall Recycle Fence replacement
Parkade Plumbing
Operations Office Structural Assessment
Library Ext. Paint
Fleet Services Access Door Control Hardware
Compound Main. Bldg.
-Replace Overhead unit, exhaust chimneys & stacks
-Roof inspection
Wolf St Washroom Roof Drain Repair/ South Side Fascia
Norquay Shelter Sheeting and Shingles replacement
Gazebo Shingles replacement, Electrical & lighting upgrades
221 Beaver Back Fence
Staff Residence
552 Banff Ave Replace all railings and deck coverings
552 Banff Ave Replace hall carpet
449 Cougar St. replace small decks, landings
Council Chambers Redesign and Audio Sound System
Project description & goals: to enhance audio and visual capabilities in Council Chamber and improve the room
layout and functionality
Current Status: Audio components are substantially installed and complete.
Exhaust Extraction System - Fleet Building
Project description & goals: Installation of direct venting for vehicle exhausts to improve worker safety and air
quality
Current Status: TBC November 2018 - Electrical work already completed
The Fenlands Lifecycle Maintenance
Project description & goals: the inspection, testing, service, repair or replacement of The Fenlands mechanical and
structural envelope to ensure life expectancy is met.
Current Status:
Arena Lobby HVAC: Installation of air exchanger for hockey arena lobby complete
Painting/Staining Exterior/Interior Walls- In progress
Show power- Complete
Arena & Curling entrance overlay complete
Arena 2 benches refurbish-Completed
SCBA replacement-Complete
Bio-swale on going 80% completed
Fleet Transit Building – Fire Alarm
Project description & goals: Installation of an audible alarm system that can be heard over work noise.
Current Status: Project Completed
Operations Building Space Analysis & Redesign
Project description & goals: a needs assessment, in collaboration with a consultant, to redesign and maximize the
space available in the operations buildings (main building, transit building, fire hall and The Fenlands) and deliver
comprehensive floor plans with associated renovation costs
2Current Status:
RFP accepted & contract expected to be awarded in Q4
Cave Ave Housing (COU17-142)
Project description & goals: 6 lots on Cave Ave have been earmarked for the development of affordable rental
accommodation. TOB negotiated the release of lots 145-155 Cave Ave with Parks Canada based on specific criteria
for release, with the intent the BHC will manage and own the property post construction completion.
Current Status: Preliminary site analysis and geotechnical work has been completed, resident survey has been
completed to determine potential interest in types of units and from a neighbourhood perspective. Currently
preparing a report to council that will summarize activity to date related to rental housing projects that have
occurred in Banff (and across Bow Valley) and rental housing demand since the community housing strategy was
implemented. This will provide information that will assist council in making time frame decisions related to this
project.
Town Hall copy room renovation
Project description & goals: renovation of copy room into office space to allow for additional staffing needs in
Corporate Services
Current Status: Complete
Fleet Building Solar Panels
Project description & goals: Installation of a 24kw Solar array on the Transit Fleet building
Current Status: The Banff Transit-Fleet Building in the industrial compound is the newest solar installation in Banff.
Officially turned on August 24, 2018.
This is now the municipality’s second largest solar system behind The Fenlands. This project was completed with
the support of the Alberta Municipal Solar Program, which provided 25% funding for the project.
System power performance is provided live throughout the day in the link below:
Transit-Fleet Building Solar Power Generation
3Town Hall Modernization
Project description & goals: Due to changes in the service delivery as well as the demographics of Banff since the
development of Town Hall, the reception area and how we interact with customers is in need of functional
changes. This project contemplates:
• Increase the efficiency of the available space
• Increase the sense of welcoming
• Increase visibility of Town services (Community Services)
• Additional space for interaction with the public.
Current Status: Detail design ongoing, construction to start in Q1 2019
4FIRE
70 Congregate Lodging Cots & Pads
Project description & goals: to purchase congregate lodging cots and pad for Emergency Social Services.
Current Status: Project complete
Automated External Defibrillators
Project description & goals: to purchase automated external defibrillators on a Ten (10) year lifecycle replacement
schedule.
Current Status: project complete
Bunker Gear
Project description & goals: Purchase of 8 sets of bunker gear for 2017 recruit class.
Current Status: Project complete
Fire Hose Replacement
Project description & goals: Lifecycle replacement of firefighting hose.
Current Status: Project complete
Fire vehicle replacement
Project description & goals: Lifecycle replacement of 25-year-old aerial truck
Current Status: Truck is in production with an anticipated delivery of November 2018.
Pager Replacement
Project description & goals: to purchase 34 pagers on a five year lifecycle replacement schedule. The pagers are
the primary mode of calling out fire department members in an emergency.
Current Status: project has been pushed to early 2019
Type 5 wildfire pick-up truck kits
Project description & goals: to purchase six (6) type 5 slip in Wildland Urban Interface pumping units. These units
consist of 150 gal tank, pump, 200 foot hose reel and associated equipment for pump and run tactics to
extinguish small fires started by fire embers landing in the community.
Current Status: project complete
5FLEET
Facilities - New Vehicle
Project description & goals: Purchase of Kia Soul electric vehicle for use by facilities. Vehicle replaces GMC 1500 V8
Current Status: Completed
Fall Arrest System
Project description & goals: Installation of fall arrest system to protect employees working at height in the fleet
building
Current Status: TBC early December 2018
Fleet Management – Vehicle Replacement
Project description & goals: Fleet Equipment replacement to align with Maximizing Life Cycle effectiveness, Green
Fleet Policy C6000 & Equipment Task Right Sizing.
Current Status: 10 Vehicles/equipment replacements were scheduled for 2018 with an additional 2 replacements
carried over from 2017. Of the 12 total, 3 unit have been replaced with more fuel efficient/scope of work
maximizing alternatives. 5 Units are in very good shape and can have their useful service life extended (these will
be adjusted in the forecasted capital replacement budgets). 3 Units will be replaced in the next 6 months with
Electric or Hybrid alternatives (Ice re-surfacer, parkade sweeper and a sedan/suv) and 1 unit will have a
replacement with 4 season usefulness (current unit is only used in summer months).
Sidewalk Tractor
Project description & goals: Increased service level for route 4 and all other pedestrian snow routes necessitated
new equipment
Current Status: Currently purchased 2 walk-behind power brooms, snow blower and a drop-down ramp to easily
move the equipment around in interim. Currently evaluating machinery that best fits the scope of work and narrow
sidewalks. The balance will be carried into 2019 with a request to blend approved capital and vehicle replacement
dollars to purchase an appropriate multi-function machine for both summer and winter use.
Small Equipment
Project description & goals: purchase of miscellaneous small equipment
Current Status:
Bobcat Bucket – Complete
2 x heavy duty jack stands – Complete
Snow Plow Blade
Project description & goals: Snow plow to enhance functionality of new hook lift truck fleet
Current Status: Ordered, expecting installation mid October 2018
6PARKS & RECREATION
Banff Recreation Grounds
Project description & goals: Design and construction of projects identified in the Recreation Grounds Master Plan.
Current Status
• Skateboard Park – complete
• Seasonal south parking lot expansion – complete
• Multi-purpose building – geotechnical investigation complete, discussions ongoing with Frank Lloyd
Wright initiative to establish if feasible to combine multi-purpose building with proposed rebuild.
Further scope definition required in 2019.
• Ball diamond irrigation and regrading – to be completed in conjunction with the sports field
improvements. Update at 2019 service review
• Ball diamond fencing improvements – to be completed fall of 2018
• Campfire pits maintenance – complete
• Removal of mountain biking skills park consisting of various constructed wooden and dirt features –
complete
• Existing picnic tables improvements – complete
• Horseback riding trail construction – update at 2019 service review
• Topographical site survey – complete
• North parking lot repair – complete fall 2018
• North playground – complete fall 2018/spring 2019
7Bike Racks Program
Project description & goals: This project supports council’s priorities of transportation, trails, recreation and
environment by creating approximately 180 net new bike parking stalls in key areas, mainly in downtown and at
major trail connections.
Current Status: 94 bike parking stalls were added in 2016 and a further 190 stalls were added in 2017. The total
available stalls is over 800. The original project goal was exceeded by 104 for total added capacity of 284; $29,000
under budget. Demand for further increases in capacity exists in additional locations and project savings can be
directed towards additional racks. In summer 2018 bike rack capacity for 8 bicycles was installed at the Rec
Grounds. In autumn 2018 bike rack capacity for 6 to be installed in Bear Parkade and weather permitting, bike
parking capacity for 16 will be added in 4 locations along Banff Avenue.
Usage of new In Ground
U bike racks at Cascade
Shops, Sat., August 19, Demand for greater capacity at Caribou–Bear NE
2017. corner, Saturday, May 27, 2017.
8Bow Falls Viewpoint – Upgrade & Rehab
Project description & goals: Improve Bow Falls Viewpoint by formalizing and re-surfacing trails and viewing areas,
installing fencing to protect existing vegetation, constructing a new viewing platform and installing washrooms.
Current Status: Preliminary design work is complete and will be presented, along with the results of a visitor
survey, to council to help inform the scope of the project.
Central Park Washroom Replacement
Project description & goals: Relocation and reconstruction of central park washroom.
Current Status: The new washroom facility was opened to the public on July 1 2015. Outstanding deficiencies were
completed in 2016. Remaining unspent funds to be returned to the reserves.
Columbarium & Memorial Garden
Project description & goals: The development and installation of a columbaria, scattering garden and memorial
wall at 606 Buffalo Street on Town-owned lands, outside of the Old Banff Cemetery. Both the adjacent Old Banff
Cemetery and the Transformer Substation are protected municipal heritage resources and require some special
considerations.
Current Status: Structural investigation of the Banff Transformer Substation to determine if the building is suitable
for the use of an enclosed columbaria has been completed. The results of the engineering report and options for
landscaping, interior and exterior columbaria structures and scattering garden will be presented to Council and
along with proposed project timelines and design development scope in Q4 2018.
Commonwealth Walkway
Project description & goals: The Commonwealth Walkway program
is designed to encourage active modes and commemorate the
values of the 71 commonwealth nations and territories. Banff was
chosen as the location for Canada’s Commonwealth Walkway.
Installation of bronze markers form trails for self-guided
interpretive tours around Banff townsite and the national park. This
project is in partnership with Parks Canada, The Community
Foundation of Banff and Canmore, Banff & Lake Louise Tourism, The
Fairmont Banff Springs and Banff Centre.
Current Status: Project is complete, $24,000 under budget – 38
markers have been installed to form four trails radiating from a hub
at the corner of Banff Ave to 1) Vermillion Lakes, 2) Sundance
Canyon Day use area, 3) the Spray River trailhead via the Banff
Springs Hotel and Bow Falls and Tunnel Mountain via the Banff
Centre. Route tour descriptions are online at
banff.ca/commonwealthwalkway and banffcanmorecf.org. This
initiative completes the Visitor Loop recommendation in the Trails
Master Plan. Remaining funds will be returned to the rerserves.
9Community Greenhouse #2
Project description & goals: Design and construction of a deep water line and foundation in 2018 to host a new
greenhouse structure to be installed in 2019.
Current Status: Environmental Assessment completed and approved; water line and foundation to be substantially
complete by the end of 2018.
Cemetery Software
Project description & goals: Upgrade obsolete operating system which assists with regulatory cemetery records
and information.
Current Status: Project delays due to supplier organizational structure changes; expect to be completed by year
end 2019, awaiting contract finalization and implementation.
Greenhouse Exhaust Fan Update
Project description & goals: Upgrade existing exhaust fan to assist in larger volume of air movement through the
greenhouse building.
Current Status: Complete, surplus funds to be returned to reserves
10Legacy Trail – Banff Avenue Connection
Project description & goals: Provide a safe, protected cycling experience from the west end of the Banff Avenue
Legacy trail into Banff.
Current Status: Traffic studies were completed and conceptual design integrating the Legacy Trail, adjacent
developments (Husky, Voyageur Inn, Inns of Banff) and the Banff sign were completed. The project needs to be
coordinated with Parks Canada due to proximity to the town boundary. Construction is planned for fall 2019.
Concept design completed that would integrate a variety of east entrance components, and calm vehicle traffic.
Proposed alignment is in line with industry best practice to ensure the safety of cyclists, pedestrians, Roam users
and drivers. Application for project funding support has been made to Trans Canada Trail.
Mountainview Cemetery Roadway Improvement
Project description & goals: To repair damaged curbs and remove excess vegetation and regrade and level driving
surfaces.
Current Status: Oct 2 2018 saw significant snow amounts with the project postponed until Spring 2019.
Norquay Road Trail
Project description & goals: better provide for pedestrians and cyclist Fenlands users – dedicated trail that can be
winter maintained
Current Status: a complete land survey was conducted, concept drawings for full integration with other proposed
west entrance improvements, and traffic study. Construction of trail and new lighting on track for 2019
construction.
Neighborhoods Parks – Upgrades
Project description & goals: Upgrade the Middle Springs Cabin windows in efforts to reduce vandalism. Included
the install of plexiglass panes over windows to maintain the look and character of the building.
Current Status: Carried forward to 2019. Will be undertaken in conjunction with other projects scheduled for the
facility inclusive of floor repair/replacement.
11Trails Improvements
Project description & goals: Implement the recommendations identified in the Trails Master Plan.
Current Status
• Key connector from Bow River to Trail to Banff Ave at Legion re-graded to 5% by adding 20m for greater
accessibility, new border fence, new ramp section sidewalk, and associated landscaping
• After extensive public consultation, on-road active transportation routes (painted lanes) on Tunnel
Mountain Road and Buffalo Street were completed in time for summer 2018 usage.
• Bow Falls Road mixed use trail with horses or expanded road shoulder are currently being designed.
• Bow River Trail, from the pedestrian bridge around Central Park to Wolf Street: pre-design complete for
recommended widening to 3m. Administration will be seeking council direction on scope in 2019.
• Trail signage upgrades: 200 signs were designed and installed, along with 20 net new posts at key locations.
30 new mini maps were designed and installed for visitor orientation.
• Whyte Museum trail connector, from Bear Street to Bow Ave: Agreement is being developed. Procurement
is complete and construction is planned for spring 2019.
• Twelve bike boxes were painted at downtown Banff Ave intersections for a safer cycling experience.
• Upgrade all staircases on trails to include a bike ramp or rail. Four feasible staircases were upgraded with a
bike ramp or rail in 2018. Other staircases were either too narrow or already had a natural gravel ramp.
• Evaluate existing bike sharrow pavement markings – evaluation completed by consultant Stantec.
• Complete a design to improve road conditions to the Banff Centre via St. Julien from Moose St. to Banff
Centre in 2021– consultations with Banff Centre and Parks Canada, design in progress. Crosswalk to Tunnel
Mountain Trailhead installed in advance
• Gather shared bike use statistics from hotels – on-going.
• Update web-based maps as trail improvements occur – in progress.
• Update print base maps after key phases of trail improvements are completed – in progress.
• Amend bylaws to limit rickshaw and horse use on trails – Traffic Bylaw changes completed.
• Improve access to Bow Falls in winter – signs to allow at-risk access are installed
12Trail Lighting Projects
Project description & goals: Replacement of the pedestrian bridge lighting in line with the Trails Lighting Policy.
Now dimed and more directional toward centre.
Current Status: Complete. Design of the accesses to the pedestrian bridge from Buffalo Street and Glen Avenue is
underway for 2019 installation.
13Water Bottle Filling Stations
Project description & goals: Installation of 4 free-standing water bottle fill
stations in downtown area along Banff Ave.
Current Status: Three stations have been installed, a fourth station will be
installed close to Cascade Plaza in 2019
Parking, Traffic and Transit
Comprehensive off–street smart parking system
Project description & goals: Installation of a smart parking system to help guide drivers to available parking stalls.
Current Status: Real time parking stall monitoring was installed in nine lots from 2015 to 2017. Local signage is
provided by the lots and real time data is available on the traffic dashboard.
Accuracy issues have been identified in small lots with high stall turnover – where a 1% miscount of several
thousand vehicles per day can compound to lot-count inaccuracies to a scale greater than 10% of the number of
stalls. Tail-gating and cyclist/motorcycle/trailer-use of the lots also tends to exacerbate inaccuracy issues with the
gate-counter technology implemented.
Alternative technology – using overhead cameras with digital counting algorithms to monitor individual stall
occupancy – will be installed as a trial in the Town hall lot and, if successful, will be installed in other suitable lots
where accuracy issues continue to be an issue.
14Downtown Pedestrian Counter
Project description & goals: Installation of six pedestrian counter stations on Banff Avenue, Caribou Street, Bear
Street and Wolf Street.
Current Status: Five monitoring stations have been installed using stereoscopic video counting technology, which
can detect pedestrian volumes and heights for traffic occurring beneath it. Accuracy rates are validated in the 90%
to 100% range, although only traffic passing beneath the unit is measured. Weekly count data is currently being
distributed to TOB staff, BLLT, and hosting landlords.
Transit Fleet for Increased Frequency on Banff Routes (Phase I)
Project description & goals: Purchase of 3 new buses to enable peak 20-minute frequency on Routes 1 and 2
Current Status: Bus purchase complete and fully funded through PTIF and GreenTRIP funding. Unspent funds to be
returned to reserves.
Local Bus Stop Installation
Project description & goals: Design and construction of transit shelters or other user improvements at key bus
stops.
Current Status: Design is ongoing. Approximately 5 shelters are planned to be built in 2019. Other bus stop
improvements to improve route connectivity and marketing (signage) are being developed.
On-Street Parking Improvements
Project description & goals: The original goal of this project was to Increase parking density along streets where
enough right-of-way is available.
Current Status: Council directed administration to focus on the streets adjacent to the Banff Elementary School. It
was then decided to delay the project to complete the work in conjunction with the rebuilt of the school. Design
consultants have been engaged to develop designs for sidewalk/curb and gutter along Big horn and Moose Streets
to formalize parking around the Banff Elementary School. It is unlikely that parking capacity will be increased, but
rather existing parking will be formalized. Construction is planned for Summer 2019
15Traffic Monitoring Equipment Purchase
Project description & goals: Purchase, install and operate 4 additional BluFAX devices for monitoring traffic.
Expanding the network will grow the sections of roadway being monitoring and increase the accuracy of data.
Current Status: Complete. New routes have been added to the traffic dashboard website.
Transit Bus Storage
Project description & goals: Construction of a bus storage facility to prolong the life of the expanded fleet for Roam
transit
Current Status: Building size and performance specifications are being developed with the BVRTSC and Fleet. Cost
sharing of the operating costs of the facility are being discussed with the BVRTSC commission members. RFD to
confirm project scope and location will be brought to council in Q4 2018.
Transit Hub
Project description & goals: Development of a transit hub to connect between regional and local routes.
Current Status: The Dillon Banff Local Transit Service Review has recommendations on the location of a transit hub
on the 300 block of Banff Avenue. The hub is located on both sides of Banff Ave at Elk Street. The hub will serve the
users of routes 1, 2, 3, 4, 6, 7, 8 and On-it. Construction is planned to be substantially complete by the end of 2018.
16Roads
Bear St Woonerff
Project description & goals: Re-construction of Bear Street to permanently foster pedestrian priority.
Current Status: In 2018, council directed administration to replace the deep utility services and to prioritize the
street design of the pedestrian and cyclists over motorised transportation. Also in 2018, council directed
administration to eliminate all on-street parking with the exception of two accessible stalls. Following these
decisions, a consultant was retained through a Request for Proposal process to lead the development of conceptual
designs. The concepts will include Bear, Wolf & Caribou Street and administration plans to present them to council
by early 2019.
Bow River Bridge Piers Maintenance
Project description & goals: The Bow River Bridge was designated a municipal heritage resource in December
2016. Council committed funding from both a Capital Project Allocation and the Municipal Heritage Reserve. The
project scope includes rehabilitation of the decorative masonry along the northern retaining land pier and the first
river pier along the northern shoreline. The scope of work is purely cosmetic.
Current Status: The Town was successful in receiving a grant from Alberta Culture of $11,920 to help fund this
project, the grant falls short of the $150,000 required to complete the work. The project has been tendered and
pricing is not within the approved funding limits. RFD will be presented to council to seek direction on project
funding and scope.
Bridge and Culverts Maintenance
Project description & goals: Inspection of all town trail bridges and replacement of the Marmot Crescent culvert.
Current Status: The inspection of all trail bridges was completed by a consultant. Minor repairs and further
inspections are required. This work is planned to be performed within the remaining capital budget.
The Marmot Crescent culvert replacement contract has been awarded; construction is ongoing and is scheduled to
be complete by the end of 2018.
Cave Avenue Reconstruction
Project description & goals: Complete reconstruction of Cave Avenue from the Luxton Museum to the Cave and
Basin National Historic Site. The scope included burial of overhead utilities, reconstruction of the water, sanitary
and storm systems, new curb and gutter both sides of the street and sidewalk on the north side, new street lighting
on the north side of the street, reconstruction of the full road structure.
Current Status
Asphalt cracks have been sealed. Project complete $180,000 under budget. Remaining unspent funds to be
returned to reserves.
Lynx Street Light Replacements
Project description & goals: Support the replacement and re-design of Fortis managed street lights along Gopher
Street and Lynx street.
Current Status: Detailed design has been completed for phase 1 of the project and the projected construction date
is November 2018.
Permanent Rainbow Crossing
Project description & goals: To show though this most visible symbol the Town of Banff supports and advocates for
an inclusive community.
17Photo courtesy of RMOL
Current Status: Complete
Streetscape Design Guidelines Project
Project description & goals: The Town of Banff is developing Streetscape Design Guidelines that describe standard
roadway configuration options and overall style for each of the public street types in Banff. Developing streetscape
design options collectively will provide a unified design standard for future roadway reconstruction projects and
individual infrastructure improvement projects.
Current Status: Administration is currently working with a team of professional landscape architects and engineers
to develop streetscape design options that include cross-sections and detailed plans. The goal is to finish this
project in 2018.
Railway Station Intercept Lot - Public Rd Enhancements
Project description & goals: Design and potentially implement roadway improvements relating to the construction
of an intercept lot located east of the railway station.
Current Status: Initial design work has commenced on temporary changes at the Railway / Elk / Lynx intersection.
Any proposals for permanent improvements will be returned to Council in order to address funding and related
implications.
Roadway Overlay Program
Project description & goals: Prioritized roadway overlays across the townsite to prolong the life of the road
surface.
Current status: 2018 scope was as follows
• Banff Ave from Wolf to Fox Streets
• Rabbit St from Banff Ave to Marten St
• Marmot St
• ~10 localised patches associated with utility repairs or local deterioration of the road surface.
• Banff ave overlay was re-scheduled to 2019 due to weather conditions and the risk of creating issues with
the pavement surface and road substructure by attempting the work in less than ideal weather conditions.
The last town wide pavement assessment was carried out in 2014 and is in need of update; in 2019 the town
will engage an inspection company to carry out a condition assessment that will inform future year’s scopes.
18Sidewalk Improvement Program
Project description & goals: Complete a series of upgrades and replacements to maintain and improve the quality
of sidewalks.
Current Status: The Town have engaged a consultant to develop streetscape design guidelines to develop concept
templates of how street cross sections to better inform how we build and replace right of way infrastructure,
including our sidewalks, in a more integrated fashion. This design work should be complete by the end of the year.
Also this year a full review of our sidewalk conditions has been undertaken as per policy C7001, a report will be
provided to council in September. Two high priority wheelchair ramps near the hospital were also replaced.
St. Julien Road Shallow Reconstruction & Storm Improvement
Project description & goals: Reconstruction of St Julien Road to enhance pedestrian & cyclist connectivity, lighting
and storm water management.
Current Status: The sewer line under St Julien was inspected in 2018, to assess the condition of the line and
determine if it should be replaced during this scope of work. Design has been prioritized with other projects and is
pending the results of the streetscape design project (currently underway).
Street Lighting Upgrades Program – LED Retrofit
Project description & goals: Retrofitting of existing Town-owned street lights with energy-efficient fixtures.
Current Status: Design work is underway for the Moose Street/Moose Hotel area. LED fixtures have been ordered
for two remaining locations to be installed in 2019.
Thermoplastic Line Painting
Project description & goals: Permanent line painting at crosswalks and other important intersections.
Current Status: Operations and engineering are determining best locations for new markings and to co-ordinate
where applicable, with the roadway overlay program. Following the repaving of Banff Ave, thermoplastic line
marking will be applied to Banff ave from Wolf to Fox streets
Banff Refreshing - Wolf & Caribou Trial
Project description & goals: Implement seasonal pedestrian improvements over the next few years to reflect the
Banff refreshing standard. The new streetscape provides adequate space for active or passive pedestrians while
responding to the new AGLC requirements and Sidewalk Seating/Cafe Policy.
Current Status: Complete, but minor improvements may occur in years going forward.
Before
19After
Resource Recovery
Automated Driveway Gate
Project description & goals: Add driveway gate to resolve potential wildlife conflicts and better control movement
of vehicles and waste into the Resource Recovery yard
Current Status: Project has been awarded with installation to happen in Q4 2018.
District Heating System
Project description & goals: Examine the feasibility of burning wood waste as a method of building heating
Current Status: Final administrative review and edit is in progress; New Service Request to be presented at the
2019 Service Review
Food waste decant and storage
Project description & goals: Construction of a food waste storage area to enable the consolidation of trips to the
Waste Water Treatment Plant (WWTP). Reducing operating costs per tonne and the number of wildlife
disturbance events are the principal project goals.
Current Status: This project is linked to a consideration of potential improvements to bio-solids & food waste
processing. A temporary ramp will be created and roll-off bins used to bulk and decant Food waste liquids before
shipping to a compost facility east of Calgary.
Pedestrian Bin Replacement
Project description & goals: replacement of selected pedestrian bins at the end of their natural life cycle.
Current Status: Finishing the wood cladding on this year’s bins with plans to exchange old for new by years end.
More bins to be replaced in 2019.
20Residential Bin Area Enhancement
Project description & goals: enhance appearance of the residential area bins.
Current Status: Have temporarily put this project on hold to wait the outcome of the targets and tactics presented
at the 2019 Service Review but will replace residential bins as needed.
Rotating Grapple Attachment
Project description & goals: Purchase of a rotating grapple to increase the efficiency of handling and sorting of
material in the resource recovery yard
Current Status: Purchase has been awarded, awaiting for grapple to arrive and be installed.
Transfer Station Upgrades
Project description & goals: Repair of building siding and installation of a steel containment wall to increase
capacity of the waste transfer site. The project will resolve storage shortages that arise when the West Dried
Meats Lake Landfill is closed. Discussions are ongoing with the Bow Valley Waste Management Commission
regarding cost sharing for the upgrades.
Current Status: Now that business in the Transfer Station has slowed, the distorted exterior sheet metal has been
replaced. The Bow Valley Waste Management Commission’s engineer to review Banff’s stamped drawing in order
to access BVWMC funds for a portion of the improvements.
SEWER
Bow River Siphon Replacement & Ped Bridge
Project description & goals: Replacement of the pipework carrying all sanitary waste across the Bow River by
suspending 2 new sanitary force-mains to a new pedestrian bridge. The concept used funds allocated to
excavation and environmental protection related to a recommended open cut solution to complete the pipework
and pedestrian bridge within the project budget.
Current Status: project complete. 4,000 average daily crossings in July and August 2017 (250,000 crossings).
Upgrades to the level detection, mixer, grinder and odour control systems to mitigate the effects of rags and grease
in the collection system have been completed within the project budget. Remaining unspent funds to be returned
to reserves.
Bear St Woonerf - Sanitary Sewer
Project description & goals: In 2018, council directed administration to replace the deep utilities. Design will be
integrated with the new streetscape design.
Current Status: Design ongoing.
21Sewer Main Repairs
Project description & goals: Using condition assessment data, prioritize and complete sanitary sewer repairs as
budget permits.
Current Status: 2017 funds were directed towards the replacement of 220 metres of pipe along Glen Avenue that
was found to be in poor condition. This pipe replacement work is complete and the pipe is back in service. RFD to
council requesting funds be moved ahead from the 2019 budget year to 2018 to address an emergency service
installation to the Banff Springs Hotel. Work is progressing this fall weather dependant.
Sulphur Mtn Sanitary Sewer Main Replacement
Project description & goals: Replacement of the fractured clay tile sanitary sewer from the Gondola/Hot springs
parking lot to the Banff Springs Hotel
Current Status: Design work complete and project is out to tender.
(Fractured clay pipe)
Trunk Sanitary Sewer Condition Assessment & Cleaning
Project description & goals: Cleaning and condition assessment of the sanitary main from Glen Avenue to the
Waste Water Treatment Plant.
Current Status: Cleaning is complete and the majority of the line was found to be in good condition. Council
directed savings from the cleaning project to the replacement of 220 metres of pipe along Glen Avenue (above).
Work completed, remaining unspent funds to be returned to reserves.
WWTP Capital Upgrades
Project description & goals: Upgrades to maintain operational efficiency and effluent quality. See individual
project descriptions and current status below.
Filter upgrade 2017–2018:
Replace existing filter technology, dual media gravity filter, to disk filtration. New technology
Update:
• Design–Build contract has been awarded to Tritech Group Ltd.
• Filter equipment issues for fabrication
• Communicated with Parks and Alberta Environment to identify regulatory requirements.
• Installation of new filter package planned in March–April 2018. Complete commissioned fall 2018
22Honeywell Building management system migration to plant SCADA
Honeywell building management system controls the HVAC system of WWTP. Migrating HVAC control
narrative to SCADA system eliminate the annual license and maintenance fee.
Current Status :
The project has been completed.
N–Viro Roof 2017–2018:
Replacement of existing roof and upgrade to HVAC system to improve indoor environment
Status: Fall 2018- project substantially complete with deficiencies and final commissioning scheduled
October 2018
Clarifier Drives:
Three clarifier drives have been leaking for the last couple of years. Installation of purchased drives
schedule in 2017–2018.
Status: Contract has been awarded to Davenport Millwright. Work underway primary one clarifier
complete. Contractor working on replacement of 2 secondary drives
23WATER
Bear St Woonerf – Water
Project description & goals: In 2018, council directed administration to replace the deep utilities. Design will be
integrated with the new streetscape design.
Current Status: Design ongoing.
Chlorinator
Project description & goals: Install new flow-paced chlorinator to dose chlorine in line with water demand
Current Status: New chlorinator is on site, awaiting proposals for ventilation system and flow pacing equipment.
New chlorinator scheduled to be online winter 2018
Emergency Generators
Project description & goals: Install emergency generators at key locations to safeguard critical needs in the event
of prolonged power outage.
Current Status: Generator installations have been completed for Town Hall (which included Central Park lift station
and upgrading electrical infrastructure along with a new event panel for Central Park). Additionally, Elk Street,
Whiskey Creek, Marmot and Birch Street sewage lift stations generator installations are complete.
The 600kw generator for the wellhead water supply has been delivered but not commissioned. Administration is
working with Parks Canada and Associated Engineering to finalize a path forward regarding a permanent location.
Town is in alignment with Environment Canada guidelines for placement generator in current location. Parks
Canada has chosen to conduct independent analysis on generator placement. Awaiting results of Parks study.
SCADA Upgrades
Project description & goals: upgrades to the Supervisory Control and Data Acquisition (SCADA) system used to
monitor and operate the town’s water and wastewater systems.
Current Status: WWTP communication between PLCs switched to fibre optic, faster and reliable. Commissioning
and testing have been successfully completed. The merger of distribution & collection and WWTP have been
completed. PLC updates at Middle springs and Mountain avenue booster stations round out the project.
24Valve Replacement
Project description & goals: Using condition assessment data, prioritize and complete valve repairs or
replacement as budget permits.
Current Status: 2018 phase one Mountain Avenue completed which entailed service relocation and the
capping of the 150mm water main on Mountain Avenue to prevent mainline freezing conditions. Phase 2 is the
relocation of the fire hydrant on Mountain Avenue and capping the main north of parks administration
building. Work scheduled to be complete this fall weather permitting.
OTHER
Bylaw Alberta First Responder Radio Communication System (AFRRCS) Radios
Project description & goals: Update the current radios to multi-band AFRRCS compatible radios to effectively
communicate with RCMP and other response agencies.
Current Status: Currently, the RCMP is working on transition to the AFRRCS system, Bylaw radios will be purchased
once the RCMP transition is made. This initiative is moved into 2019.
Catch Basin Replacement Program
Project description & goals: Using condition assessment data, prioritize and complete catch basin repairs or
replacement as budget permits.
Current Status: 38 catchbasins with surface damage (grates or localized settling) were repaired in 2018. 2018 is the
final year of this program however there is some carry over budget that the Administration intends to use to
complete more surface repairs of catchbasins in 2019. Administration will also undertake an assessment in 2019 to
inform future funding requests for storm water infrastructure.
Conversion to Electronic Forms Project
Project description & goals: Electronic forms which can be filled out and submitted from any ToB mobile device.
Current Status: Complete, final invoicing pending.
The use of e–forms is resulting in improvements in efficiency of operations in the field and in the quality of data
available for use by all staff.
The initial electronic form project saved completed forms in pdf format. These were not searchable. It was hoped
that this form saving process would be modified to save competed forms in a database format, but when the
project was started there was no internal capability to do so, and it was intended that a third party would be
engaged and paid to complete this conversion.
25In 2015-16 John McAulay, IT Coordinator, ToB IT department, converted all existing forms to be saved to a
database. John continues to work with ToB form creators to ensure new forms are configured to insert completed
information into the database.
Now that the database conversion has been completed, and is the repository for form data, a greater detail of data
reporting and a more streamlined search function is possible. At the moment reporting is performed by a request
to the IT department.
The next step will be to complete a user accessible reporting mechanism, which has been started by IT, working
with Fleet Services.
Financial Software Update
Project description & goals: Update of financial software to current version including training for staff on the
software.
Current Status: Substantially complete. Administration is exploring options for the replacement of our job costing
software with the remaining budget.
Information Governance Master Plan Implementation
Project description & goals: In 2015 council accepted the Information Governance Master Plan as a guiding
document for the Town’s information governance program. The plan is a multi-year, multi-phase forward roadmap
to achieve an essentially complaint information management. The capital project approved in 2017 is for
expenditures for electronic content management (ECM) and electronic records and document management
systems (EDRMS) systems.
Current Status: Continued implementation of the IG Master Plan foundations. A technology ready Information
Governance Policy and Retention Schedule will be presented to council in Q4, 2018. The IT Coordinator worked
closely with the Town of Canmore in the implementation of their pilot project. Once the best practices and
learnings from the Canmore pilot project are fully developed, work will commence the final procurement of the
required technologies.
Public Art Exhibit Project
Project Description & Goals: Commission 4 artworks for 4 ½–year temporal exhibition at Bear Street Mall and Banff
Town Hall; proceed with fabrication of all artwork exhibition materials/hardware and required installation.
Current Status
Bear Street Mall exhibition (When I Close My Eyes) to remain in place until end of 2019, at minimum.
Banff Town Hall exhibition: Raven #2 was exhibited 2013-2014; Stuff Animals exhibit was extended to July 2017
as it was temporarily removed during its display because of hardware failure; Love is Touching Souls will be
exhibited from July 2017 until end of 2018.
26River Ribbon Public Art Project
Project description & goals: Commission new permanent art installation, River Ribbon by Alexander Caldwell;
Current Status: River Ribbon was installed in December 2017.
27Recreation Program & Facilities Software
Project description & goals: The previous booking and registrations software is obsolete and servicing expired in
2017, resulting in need to purchase new software. Procurement process was undertaken and BookKing was
selected in spring of 2017. Improved reporting, online registration and payment and mobile point of sale and
membership registrations (i.e. tablets for scanning membership cards at community classes, drop–in sports, etc.)
identified as key features.
Current Status: Project is 90% complete. Data transfer to new system is complete and on-line registration
launched in the fall of 2018. All programs, services and facilities are now housed in the new system. Flex
registration for children and youth programs is the only element still being processed in Class as we await the
module development from BookKing(currently underway). A few remaining equipment pieces to support the new
drop in punch passes and any supporting technology related to the child/youth program flex registration are still to
be purchased in 2019 as we assess our needs for these supplementary pieces to best support the new system.
Signage & Wayfinding Master Plan
Project description & goals: Town–wide wayfinding installation to enhance visitor experience.
Current Status: The entrance sign on Norquay Road and a digital message sign to be located by the hospital are
complete. Discussions with Parks Canada on the location of the entrance and digital message signs on Banff
Avenue (east entrance) are ongoing
Storm Water Consulting Design
Project description & goals: consultation and survey work to identify underlying issues causing ponding during
heavy rain events and/or snow melt in several areas of town
Current Status: consultant scope has been awarded and is ongoing
Town Entrance Sign Enhancement
Project description & goals: construction of a crossing and traffic calming by the Banff sign at the Fenlands
Current Status: Preliminary design work complete, project to be brought to council for discussion during budget to
help inform the scope of the landscaping and traffic calming measures
28DEER (Coyote) LANE
Coyote Lane
Project description & goals: Construction of 131 below-market rental units – designed to meet or exceed priorities
of liveability, environmental performance, Banff Design Guidelines, ease of maintenance, construction and
operating costs. Project to be self-funding - without the need for a tax subsidy.
Current Status:
• Parks Canada supplied land for a 131–unit development at a 95% discount. The Provincial Government
supplied $11.9M in funding.
• The three main buildings achieved occupancy permit in late June 2018, 13 months after breaking ground.
• 114 out of 122 units are currently occupied.
• Rents for all units are 10-15% below market rate.
• Construction of a further 9 units in 3 A-frame buildings is underway and scheduled for completion in
November 2018 - 4 months after breaking ground on those units.
• The project was completed on schedule and is currently under budget.
• The building incorporates energy-saving initiatives including R50 roof insulation, heat-recovery ventilation
systems in each unit, low flow plumbing fixtures, energy-efficient appliances and triple glazing
• The building exceeds 2011 National Energy Code of Canada for Buildings (NECB) reference building efficiency
(minimum building code) by 23%.
• Electricity costs for the entire building, including all commonspace lighting, fans and pumps, elevator, door
openers, suite heating, lighting and cooking and temporary power to the A-frames under construction were
$5,000 ($41/unit) for the month of August when 110 units were occupied.
• Offsite work is largely complete and will be complete before the end of 2018, off-site improvements to this
area include:
o Replacement of stormwater and sewer manholes in the lane as part of servicing the building.
o Reconstruction of Coyote Lane, including paving and stormwater management improvements.
o Sidewalks along Antelope St and Marmot St.
o Formalization of 90 degree angle parking on Marmot St and pavement renewal.
o Extensive tree planting along Antelope St and in the Deer Street ROW.
• An official ribbon cutting ceremony is scheduled for October 17.
2930
You can also read