LS2 planning meeting A.Tauro - CERN Indico
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Safety files
• HSE memo and instructions:
• HSE Covid-19 directive EDMS 2370902
• HSE Covid-19 directive contractors EDMS
2373120
EN versions FR versions
26.6.2020 LS2 preparatory meeting 2Safety files
• HSE memo and instructions:
• HSE Covid-19 directive EDMS 2370902
• HSE Covid-19 directive contractors EDMS
2373120
• HSE FAQ: https://hse.cern/content/faq-covid-
19
26.6.2020 LS2 preparatory meeting 3Safety files
• HSE memo and instructions:
• HSE Covid-19 directive EDMS 2370902
• HSE Covid-19 directive contractors EDMS
2373120
• HSE FAQ: https://hse.cern/content/faq-covid-19
• ALICE specific instructions:
• EDMS 2369007
26.6.2020 LS2 preparatory meeting 4Safety files
• HSE memo and instructions:
• HSE Covid-19 directive EDMS 2370902
• HSE Covid-19 directive contractors EDMS
2373120
• HSE FAQ: https://hse.cern/content/faq-covid-19
• ALICE specific instructions:
• EDMS 2369007
• Mandatory to come to CERN:
• Covid-19 safety course
https://learninghub.cern.ch
• Attestation de déplacement obligatoire
https://cesaam.web.cern.ch
• Valid IMPACT and being in ALICE white list
(check O.C. 2 in ADAMS)
26.6.2020 LS2 preparatory meeting 5LHC LS2 Baseline V2.5 FRAME 12th June LHC-PM-MS-0018 v.2.5
LS2 Day, 12th June 2020 7
26.6.2020 LS2C 12.6.2020 Marzia Bernardini 6Detector installation sequence
• Schedule v40 DRAFT:
• Additional time in July for TPC test
• Restart the detector installation sequence on July 28th
• 16w global commissioning at the end (28 June to 15 October 2021)
• RB24 beampipe reinstalled by end April 2021 OK to inject low intensity beam by September 2021
• The present plan foresees 0.5 and 3.5 months contingency with respect to the LS2 end date of 1 st November 2021
and 1st February 2022 respectively
v40: DRAFT
now
July 27th: open
cleanroom roof .5m
3.5m
26.6.2020 LS2 preparatory meeting 8TPC/beampipe/Miniframe reinstallation sequence (v40)
v40: DRAFT Jun 29th – Jul 24th – complete TPC commissioning, X-ray tests
Jul 28th – open cleanroom roof and start cage insertion test
Jul 28th – Aug 21st – cage insertion test and prepare TPC for transportation
Aug 24th – transportation TPC to SX2
Aug 25th – Sep 29th – reinstall TPC
TPC moved to IP, adjusted and put back to parking position
Sep 30th – Oct 27th install cage and central beampipe
Oct 28th – Nov 2nd – move TPC to IP – start connection TPC
Nov 3rd – 30th – prepare miniframe installation
Dec 1st – 3rd – reinstall miniframe
26.6.2020 LS2 preparatory meeting 9Key dates
Activity v39 V40: DRAFT
Open cleanroom roof, start cage insertion test 29 Jun 2020 28 Jul 2020
Move TPC to SX2 21 Jul 24 Aug
Install TPC (parking position) 22 Jul – 31 Aug 25 Aug – 29 Sep
Install cage and central beampipe 1 – 30 Sep 30 Sep – 27 Oct
Move TPC to IP 1 – 6 Oct 28 Oct – 2 Nov
Install Miniframe 4 – 6 Nov 1 – 3 Dec
FDD-C installation* Before 6 Nov
FDD-A installation 30 Nov – 7 Dec 7 – 14 Jan
MFT & FIT-C installation and checks 16 Nov – 8 Jan 2021 4 Jan – 12 Feb 2021
ITS installation and checks 11 Jan – 2 Apr 15 Feb – 7 May
FIT-A installation 5 – 9 Apr 10 – 14 May
ITS & MFT commissioning time 1 ½ months (6w)
ALICE global commissioning time 3.5 months (16w)
End of LS2 – stop UX25 access (baseline) 1 Feb 2022
End of LS2 – stop UX25 access (option 1) 1 Nov 2021
* Requires LHC tunnel access to be done before cool down S23 (starting in w46 2020) or between w1 and w5 2021
26.6.2020 LS2 preparatory meeting 11CR3 status (A.Augustinus)
• February
• Modify water circuit (add TA valves CR3 and CR4) – kept DCS up and running – DONE (10.02 – 21.02)
• Additional rack installed for extension of main network starpoint outside CR2
• Arrival of new racks (25.02)
• Installation 1st row of racks (26.02)
• March, April, May
• COVID closure
• Arrival of new servers (28.04, originally foreseen end of March)
• Installation of the servers in the new racks – DONE (finished 15.05)
• Remove TOF cluster – DONE (26.05), last racks removed – DONE (28.05)
• June
• Installation of 2nd row of new racks - DONE (03.06)
• Re-installation TOF cluster – DONE and tested (08.06)
• Installation network fibres for network – DONE (17.06); final tests to be done 25.06
• July – August – September
• Reconnection new racks to electricity – dates t.b.c.
• Installation of network infrastructure (some network interruptions to be foreseen, details to be defined with IT-CS) – dates t.b.c.
• Migration from old servers to new servers (first central systems, then detector systems)
• October – November
• Removal of old servers and last old racks
26.6.2020 LS2 preparatory meeting 12Cabling: new planning after Covid-19
Miniframe complete 8/9
FDD-C complete 25/9
MFT P sensors complete 2/10
ITS DSS complete 6/11
TPC complete 10/11
FDD-A complete 12/11
26.6.2020 LS2 preparatory meetingFIT-A complete 23/11 13Installation ITS DSS cables 26.6.2020 LS2 preparatory meeting 14
Cabling progress
ALICE LS2 - EN-EA cabling control follow-up 26-06-2020
ITS TPC MFT CPV
FIT T0+ FIT V0+ MCH ALL DETECTORS
26.6.2020 LS2 preparatory meeting 15EN-EL interventions
• 18kV, 3.3kV and LV network maintenance: 20-24 Jan 2020 – Done
• AUG P2: Monday 27 January 2020 – Done
• Auto transfer test: 17 July 2020 not affect LHC (we will be repowered from the machine network)
• Test secours (10 min at 6:00 AM): 30 July 2020
• Will cut everything that is not on UPS (max. 10 minutes CERN-wide cut)
• At P2 the racks in UX and CR are not affected, nor CR0
• Only general services will be cut
• This will affect all P2 buildings including SX2 and SXL2 (cleanroom)
• Services like gas, circulation of mixed and iced water and ventilation will be affected
• As this is CERN-wide, also offices, labs etc. in Meyrin will be affected.
• AUG Meyrin (zone administrative): 4 Sep 2020 (tbc)
26.6.2020 LS2 preparatory meeting 16Optical fibers (EN-EL)
• Done:
• Installation and test TPC fibers between CR4 and CR1
• Installation and test fibers for IT (for upgraded network) from CR2 starpoint to
CR1 and to CR3
• Procurement 2 x FDD optical cables (requested in March 2020) fibers
ordered but not yet received
• Test HMPID fibers
• Optical measurement fibers SR2-SX2 (photo)
• To be done:
• Cleaning TRD trigger fibers connectors and replacement of damaged ones
• Installation TPC optical fiber un the cavern between A and C-sides
• Unfold and connect ITS and TPC trunk cables after Miniframe installation
in November
26.6.2020 LS2 preparatory meeting 17TB 18.6.2020
ITS and MFT inox pipes (Rampower)
• Work restarted two weeks ago: finalize ITS and MFT connections to cooling plant
• Pipework should be completed by end July
• Verified ITS cooling plant installation sequence (transport at Meyrin, P2, installation in the pit)
ITS cooling plant
Remaining pipework to be done
26.6.2020 LS2 preparatory meeting 18EN-CV interventions
• Big maintenance:
• SF: from Nov 2019 to mid Jan 2020. NO impact on ALICE as both magnets will be OFF – done
• UW: stop UX mixed water for 2 days in week 41/2019 (October) – Tue 8 and Wed 9 Oct – done
• SU: various small perturbations + 1 day stop all cooling UX + 1 day stop all cooling SXL2 in week 16/2020 (April) – not done
• Small maintenance:
• UW: from mid Aug 2020 to mid Sep 2020. Stop mixed water UX for 1 day in week 37/2020 (September).
• SF+SU: weeks 45-47/2020: cleaning towers (stop SF 1 week) + 1 day stop all cooling UX.
• Renovation transformer UIAC220 in w10/2020 transparent but need to reduce mixed-water consumption
• Stop demineralized water from 17 to 20 December 2019
• Ventilation:
• SG2 (2019): w7/2019
• SG2 (2020): Tue-Wed - w3/2020
• Gas extraction: w8/2019
• UX25 cavern: w2/2020
• MCH and MTG: Mon-Thu - w3/2020
• L3: need to replace extractor 2 days stop will cut flammable gases (maybe in week 17) - Done
• ITS: will be done before end June
• Raw water:
• Test after Apr 2019. Short interruption (1 day), can be used tap water during the test.
26.6.2020 LS2 preparatory meeting 19Racks status
• Racks currently powered on:
• HMPID: I01, I02
• PHOS-CPV: A16, A17
• CTP: C21, C22, C24, C25, C26, C27 (CTP) (and VME crates on)
• MCH: C08, C10, C37, C39
• TOF: O03, O04, O05, O30, O31, O32, I03, I04, I05, I30, I31, I32
• TRD: O06, O08, O26-29, I06, I08, I26-29, C16-19, C29
• Dcal, EMcal: A14, O12
• Detectors can be powered, compatible with current activities inside L3
26.6.2020 LS2 preparatory meeting 20Other activities
2020:
• Renovation PX24 access system (PAD-MAD): w33-34 (10-21 Aug)
• Renovation PM25 access system (PAD-MAD): w41-43 (5-23 Oct)
• LASS functional test: no access to UX25 on Friday 30 Oct 2020 whole day (weekend 31 Oct /1 Nov as contingency)
• LASS global verification of entire LHC: 1 day no access to UX25 (date tbc)
• BIW test: no access underground on 5 and 6 Oct 2020 from 18:00 to 00:00
2021:
• For powering permit: w1 2021 (tbc) (needed to start LHC powering test)
• For RF recommissioning LSS4: w7 2021
• For powering permit, following UPR53 installation: date tbd
• For beam permit: date tbd
• LHC sector test (beam through ALICE): no access to UX25 from 26 to 29 March 2021
26.6.2020 LS2 preparatory meeting 21IT intervention on databasesCERN wide
• Motivated by the analysis of the incident which happened on 27 th
May
• Downtime of several hours
• Data corruption & data loss for few databases
• Several urgent actions have been identified with the help of NetApp
Courtesy Eva Dafonte Perez
(storage vendor)
• It requires full downtime as the software version needs to be upgraded
Approved by TIOC
• Additional hw repair and configuration changes are needed
Intervention on
• More details on the intervention :
https://cern.service-now.com/service-portal?id=outage&n=OTG0057263 Sat. 27th June
• Impact on the Oracle database services details:
Machines CLOSED
https://cern.service-now.com/service-portal?id=outage&n=OTG0057201
• Impact on the DBoD service details:
https://cern.service-now.com/service-portal?id=outage&n=OTG0057252
22
LMC, 24th June 2020Work regie des eaux Gessiennes
• Dans le cadre du renouvellement du réseau d’assainissement des eaux
usées, mené par la Régie des Eaux Gessiennes à SAINT-GENIS-
POUILLY, le chemin de la Tatte sera en travaux à compter du
22/06/2020 et pendant les mois de juillet et août 2020.
• Il est prévu de maintenir l’accès au point 2 ALICE pendant toute la durée
du chantier. Vous êtes toutefois invité à la réunion de chantier du
mercredi 24/06/2020 à 14h00.
• Access to P2 won’t be blocked at any time
26.6.2020 LS2 preparatory meeting 23André
New rack turbines
• All 85 units (200kCHF) ordered: https://edh.cern.ch/Document/SupplyChain/MAG/8289388
• Technical specifications: EDMS 1963491
• ALICE units will be made available from end-August 2020
• Installation immediately afterwards, transparent for users (ALTEAD + P2 tech.)
Ventilation unit front view Pluggable motor
26.6.2020 LS2 preparatory meeting 24André
Consolidation Wiener LVPS
• 205 power supplies in total LHCinv PartNo To be done Modules
7043 0M21.0003L 1 6
• 14 MCH LVPS ready in SX2 7272 0M21.2004L-2 1 4
•
7276 0M21.3004L 2 6
Rework in batches (1/week), to be started in the coming days: 7302 0M21.0006 1 6
1. Disconnection and deinstallation detectors 7305 0M21.0104 6 6
7306 0M21.0102L 25 6
2. Conditioning ALTEAD + P2tech 7307 0M21.2104L-2 62 4
3. Transport to EN-EA (Meyrin) 7308 0M21.2103L-1 32 5
7309 0M21.3104L 20 6
4. Rework and test EN-EA + P2tech (Evgeny and Philippe) 7310 0M21.1104L 1 6
7311 0M21.0101L-4 2 2
5. Transport to P2
7312 0M21.0106 3 6
6. Reinstallation detectors 7314 0M21.0103L 1 6
7315 0M21.0104L 8 6
7316 0M21.0101L-5 2 1
• Andre will contact each detector to establish a planning 7317 0M21.0101L-3 2 3
7352 0M21.0102L-3 3 3
7358 0M21.3103-1 4 5
7431 0M21.0106L 1 6
7231 0P17.0701 7 VME
7237 0P17.0711 12 VME
7238 0P17.1143 4 VME
7239 0P17.1126 5 VME
total: 205
69 6 modules
36 5 modules
63 4 modules
5 3 modules
2 2 modules
2 1 modules
28 VME
6 modules Wiener LVPS Training with Wiener (June 4th) Repair campaign in 2016 205
26.6.2020 LS2 preparatory meeting 25IMPACT list (1/3) 26.6.2020 LS2 preparatory meeting 26
IMPACT list (2/3) 26.6.2020 LS2 preparatory meeting 27
IMPACT list (3/3) 26.6.2020 LS2 preparatory meeting 28
Day-by-day sequence w26
ALICE Other CERN
Institutes Transport Scaffolding EN-EA
technicians groups
EN-EL Rampower
26.6.2020 LS2 preparatory meeting 29UX25 activities w26 – Mon 22 Jun 2020
Replacement PM25 lift (until 7 August) LHC access via ALICE (PX24)
TE-VSC: install valve on RB26 beampipe
No access A-racks
during cabling
scaffolding
Remove
VSC:
remove
ITS cabling turbopump
HV cables
Test TPC
PP0-A side
racks
MCH
6:00 AM to 7:30 AM
Supports for Re-route
cooling pipes ITS/MFT
(Cedric) cooling pipes
26.6.2020 LS2 preparatory meeting 30UX25 activities w26 – Tue 23 Jun 2020
Cleaning cavern (Topnet): 13:00 to 15:00
No access A-racks
during cabling
scaffolding
Remove
ITS cabling
HV cables
Test TPC
PP0-A side
racks
MCH
Re-route
ITS/MFT
cooling pipes
26.6.2020 LS2 preparatory meeting 31UX25 activities w26 – Wed 24 Jun 2020
EN-EL: test HMPID fiber ageing
P2tech: install and weld beams to support CR3 false floor (Philippe + Cedric)
HV cables
Test TPC
MCH
Re-route
ITS/MFT
cooling pipes
26.6.2020 LS2 preparatory meeting 32UX25 activities w26 – Thu 25 Jun 2020
EN-EL: optical measurement fiber SR2-SX2 (intervention inside SX2)
HV cables
Modify ITS/MFT
Test TPC
racks (Philippe,
Cedric)
MCH
Re-route
ITS/MFT
cooling pipes
26.6.2020 LS2 preparatory meeting 33UX25 activities w26 – Fri 26 Jun 2020
ALTEAD+HSE: inspection lifting equipment (AM)
HV cables
Test TPC
MCH
Re-route
ITS/MFT
cooling pipes
26.6.2020 LS2 preparatory meeting 34SXL2 activities w26 – Mon 22 Jun 2020
C-side
A-side
26.6.2020 LS2 preparatory meeting 35SXL2 activities w26 – Tue 23 Jun 2020
C-side
A-side
26.6.2020 LS2 preparatory meeting 36SXL2 activities w26 – Wed 24 Jun 2020
insertion test
preparation
(Yannick)
C-side
A-side
Cage
26.6.2020 LS2 preparatory meeting 37SXL2 activities w26 – Thu 25 Jun 2020
insertion test
preparation
(Yannick)
C-side
A-side
Cage
26.6.2020 LS2 preparatory meeting 38SXL2 activities w26 – Fri 26 Jun 2020
C-side
A-side
X-ray
tests
26.6.2020 LS2 preparatory meeting 39Miniframe activities w26 – Mon 22 Jun 2020
Cooling patch panel ITS OB,
cut ITS crate cooling lines
ITS cables patch
panel and cable
trays (Mimmo)
(Philippe)
Barriers, patch
panel/ MNF
extension (Cedric)
26.6.2020 LS2 preparatory meeting 40Miniframe activities w26 – Tue 23 Jun 2020
Cooling patch panel ITS OB,
cut ITS crate cooling lines
ITS cables patch
panel and cable
trays (Mimmo)
(Philippe)
Barriers, patch ITS/MFT insertion
panel/ MNF HDW interface to
extension (Cedric) MNF (Peter)
26.6.2020 LS2 preparatory meeting 41Miniframe activities w26 – Wed 24 Jun 2020
ITS
connectors
ITS
connectors
ITS
connectors
26.6.2020 LS2 preparatory meeting 42Miniframe activities w26 – Thu 25 Jun 2020
ITS
connectors
ITS
connectors
ITS
connectors
26.6.2020 LS2 preparatory meeting 43Miniframe activities w26 – Fri 26 Jun 2020
ITS
connectors
ITS
connectors
ITS
connectors
26.6.2020 LS2 preparatory meeting 44Day-by-day sequence w27
ALICE Other CERN
Institutes Transport Scaffolding EN-EA
technicians groups
EN-EL Rampower
26.6.2020 LS2 preparatory meeting 45UX25 activities w27 – Mon 29 Jun 2020
Replacement PM25 lift (until 7 August) LHC access via ALICE (PX24)
No access A-racks
during cabling
ITS cabling
PP0-A side
racks
MCH
Re-route
ITS/MFT
cooling pipes
26.6.2020 LS2 preparatory meeting 46UX25 activities w27 – Tue 30 Jun 2020
Cleaning cavern (Topnet): 13:00 to 15:00 EN-HE: maintenance cavern crane
No access A-racks
during cabling
ITS cabling
PP0-A side
racks
MCH
Re-route
ITS/MFT
cooling pipes
26.6.2020 LS2 preparatory meeting 47UX25 activities w27 – Wed 1 Jul 2020
MCH
Re-route
ITS/MFT
cooling pipes
26.6.2020 LS2 preparatory meeting 48UX25 activities w27 – Thu 2 Jul 2020
MCH
Re-route
ITS/MFT
cooling pipes
26.6.2020 LS2 preparatory meeting 49UX25 activities w27 – Fri 3 Jul 2020
MCH
Re-route
ITS/MFT
cooling pipes
26.6.2020 LS2 preparatory meeting 50SXL2 activities w27 – Mon 29 Jun 2020
and services
and services
Blue covers
Blue covers
C-side
A-side
X-ray
tests
Modify and mount blue
covers. Secure fibers and
cables
26.6.2020 LS2 preparatory meeting 51SXL2 activities w27 – Tue 30 Jun 2020
and services
and services
Blue covers
Blue covers
C-side
A-side
X-ray
tests
26.6.2020 LS2 preparatory meeting 52SXL2 activities w27 – Wed 1 Jul 2020
and services
and services
Blue covers
Blue covers
C-side
A-side
X-ray
tests
26.6.2020 LS2 preparatory meeting 53SXL2 activities w27 – Thu 2 Jul 2020
and services
and services
Blue covers
Blue covers
C-side
A-side
X-ray
tests
26.6.2020 LS2 preparatory meeting 54SXL2 activities w27 – Fri 3 Jul 2020
and services
and services
Blue covers
Blue covers
C-side
A-side
X-ray
tests
26.6.2020 LS2 preparatory meeting 55Miniframe activities w27 – Mon 29 Jun 2020
Cooling patch panel ITS OB,
cut ITS crate cooling lines
ITS cables patch
panel and cable
trays (Mimmo)
(Philippe)
Barriers, patch
panel/ MNF
extension (Cedric)
26.6.2020 LS2 preparatory meeting 56Miniframe activities w27 – Tue 30 Jun 2020
Cooling patch panel ITS OB,
cut ITS crate cooling lines
ITS cables patch
panel and cable
trays (Mimmo)
(Philippe)
Barriers, patch
panel/ MNF
extension (Cedric)
26.6.2020 LS2 preparatory meeting 57Miniframe activities w27 – Wed 1 Jul 2020
ITS
connectors
ITS
connectors
ITS
connectors
26.6.2020 LS2 preparatory meeting 58Miniframe activities w27 – Thu 2 Jul 2020
ITS
connectors
ITS
connectors
ITS
connectors
26.6.2020 LS2 preparatory meeting 59Miniframe activities w27 – Fri 3 Jul 2020
ITS
connectors
ITS
connectors
ITS
connectors
26.6.2020 LS2 preparatory meeting 60You can also read