MYT Petition for the Control Period FY 2019-20 to FY 2021-22
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
MYT Petition for the Control Period FY 2019-20 to FY 2021-22
MYT Petition for the Control Period
FY 2019-20 to FY 2021-22
Submitted to
Assam Electricity Regulatory Commission
November 2018
ASSAM POWER DISTRIBUTION COMPANY LIMITED (APDCL)
BijuleeBhawan, Paltanbazar
Guwahati-781 001
Assam Power Distribution Company Limited Page 1MYT Petition for the Control Period FY 2019-20 to FY 2021-22
Table of Contents
BEFORE THE HON’BLE ASSAM ELECTRICITY REGULATORY COMMISSION, GUWAHATI ...................... 5
BEFORE THE HON’BLE ASSAM ELECTRICITY REGULATORY COMMISSION, GUWAHATI ...................... 6
NOTES AND ABBREVIATIONS ...................................................................................................................... 7
1: INTRODUCTION ................................................................................................................................... 9
ASSAM POWER DISTRIBUTION COMPANY LIMITED (APDCL) ............................................................................ 9
MULTI-YEAR TARIFF REGULATIONS 2018 .................................................................................................... 10
2: METHODOLODY ADOPTED IN FILING OF THIS PETITION (INCLUDING CONSTRAINTS) ........... 11
METHODOLOGY ........................................................................................................................................... 11
3: MYT PETITION FOR THE CONTROL PERIOD FROM FY 2019-20 TO FY 2021-22 ........................ 12
CONTENTS OF THE PETITION ........................................................................................................................ 12
CATEGORY-WISE ENERGY SALES ................................................................................................................... 12
DISTRIBUTION LOSS TRAJECTORY ................................................................................................................. 15
ENERGY REQUIREMENT ................................................................................................................................ 18
POWER PURCHASE QUANTUM AND COST ....................................................................................................... 19
OPERATION & MAINTENANCE EXPENSES ....................................................................................................... 32
CAPITAL EXPENDITURE AND CAPITALISATION ................................................................................................ 35
DEPRECIATION ............................................................................................................................................ 37
INTEREST & FINANCE CHARGES .................................................................................................................... 41
INTEREST ON WORKING CAPITAL .................................................................................................................. 44
INTEREST ON CONSUMER SECURITY DEPOSIT ................................................................................................. 44
OTHER DEBITS ............................................................................................................................................ 45
RETURN ON EQUITY ..................................................................................................................................... 46
OTHER INCOME ........................................................................................................................................... 46
NON-TARIFF INCOME ................................................................................................................................... 47
REVENUE FROM SALE OF POWER AT EXISTING TARIFF .................................................................................... 48
AGGREGATE REVENUE REQUIREMENT (ARR) AND REVENUE GAP/ (SURPLUS) FROM FY 2019-20 TO FY 2021-
22 ............................................................................................................................................................. 49
4: CUMULATIVE REVENUE GAP TILL FY 2019-20 AND TARIFF FOR FY 2019-20............................ 50
CUMULATIVE REVENUE GAP TILL FY 2019-20 AT EXISTING TARIFF ............................................................... 50
TARIFF PHILOSOPHY AND DESIGN ................................................................................................................. 50
COST OF SUPPLY .......................................................................................................................................... 51
TARIFF PROPOSAL ....................................................................................................................................... 51
TARIFF INITIATIVES..................................................................................................................................... 54
5: WHEELING CHARGES AND CROSS-SUBSIDY SURCHARGE ............................................................. 57
INTRODUCTION ........................................................................................................................................... 57
ALLOCATION MATRIX .................................................................................................................................. 57
WHEELING CHARGES ................................................................................................................................... 58
WHEELING LOSSES ...................................................................................................................................... 58
CROSS-SUBSIDY SURCHARGE ........................................................................................................................ 59
6: TARIFF SCHEDULE ............................................................................................................................. 60
LT CATEGORY-1 JEEVAN DHARA: ................................................................................................................. 61
LT CATEGORY-II DOMESTIC A ...................................................................................................................... 62
LT CATEGORY-III DOMESTIC B .................................................................................................................... 62
LT CATEGORY-IV: LT COMMERCIAL ............................................................................................................. 63
LT CATEGORY V- LT GENERAL PURPOSE SUPPLY ........................................................................................... 63
LT CATEGORY VI-PUBLIC LIGHTING ............................................................................................................. 64
Assam Power Distribution Company Limited (APDCL) Page 2MYT Petition for the Control Period FY 2019-20 to FY 2021-22
LT CATEGORY VII-AGRICULTURE ................................................................................................................. 64
LT CATEGORY VIII – SMALL INDUSTRIES ....................................................................................................... 64
LT CATEGORY IX: TEMPORARY SUPPLY: ....................................................................................................... 65
LT ELECTRIC VEHICLE (EV) CHARGING STATIONS.............................................................................. 65
HT CATEGORY I: HT DOMESTIC ................................................................................................................... 67
HT CATEGORY-II: HT COMMERCIAL ............................................................................................................. 67
HT CATEGORY - III: PUBLIC WATER WORKS ................................................................................................. 68
HT CATEGORY – IV: BULK SUPPLY ............................................................................................................... 68
HT CATEGORY V (A): HT SMALL INDUSTRIES ............................................................................................... 69
HT CATEGORY V (B)-HT-I INDUSTRIES ........................................................................................................ 69
HT CATEGORY V (C): HT-II INDUSTRIES ...................................................................................................... 70
OPTION -1 .................................................................................................................................................. 70
OPTION -2 .................................................................................................................................................. 70
HT CATEGORY VI-TEA, COFFEE AND RUBBER ................................................................................................ 71
HT CATEGORY VII - OIL AND COAL ............................................................................................................... 71
HT CATEGORY VIII – HT IRRIGATION........................................................................................................... 72
HT CATEGORY IX: TEMPORARY SUPPLY ........................................................................................................ 72
HT CATEGORY X: ELECTRIC CREMATORIUM ................................................................................................... 72
HT ELECTRIC VEHICLE (EV) CHARGING STATIONS ............................................................................. 72
HT RAILWAY TRACTION .............................................................................................................................. 73
7: PRAYER ............................................................................................................................................... 74
Assam Power Distribution Company Limited (APDCL) Page 3MYT Petition for the Control Period FY 2019-20 to FY 2021-22
List of Tables
TABLE 1: GROWTH RATES CONSIDERED FOR THE VARIOUS CONSUMER CATEGORIES................................................ 14
TABLE 2: ENERGY SALES TO THE VARIOUS CONSUMER CATEGORIES (MU) ............................................................. 15
TABLE 3: TARGET VIS-À-VIS ACTUAL DISTRIBUTION LOSS OF APDCL.................................................................... 16
TABLE 4: LT: HT RATIO VIS-À-VIS ACTUAL DISTRIBUTION LOSS OF APDCL .......................................................... 17
TABLE 5: PROPOSED DISTRIBUTION LOSS TRAJECTORY FROM FY 2019-20 TO FY 2021-22 ................................. 18
TABLE 6: ENERGY REQUIREMENT FROM FY 2019-20 TO FY 2021-22 (MU)...................................................... 19
TABLE 7: CAPACITY ADDITIONS OF APGCL PLANTS FROM FY 2019-20 TO FY 2021-22 (MW) ........................... 20
TABLE 8: CAPACITY ADDITIONS OF NER PLANTS FROM FY 2019-20 TO FY 2021-22 (MW) ............................... 21
TABLE 9: CAPACITY ADDITIONS UNDER ‘OTHER SOURCES’ FROM FY 2019-20 TO FY 2021-22 (MW) .................. 22
TABLE 10: TOTAL CAPACITY ADDITIONS FROM FY 2019-20 TO FY 2021-22 (MW)........................................... 23
TABLE 11: RPO CALCULATION FROM FY 2019-20 TO FY 2021-22 .................................................................. 24
TABLE 12: POWER PURCHASE ESTIMATES FOR FY 2019-20 .............................................................................. 25
TABLE 13: POWER PURCHASE ESTIMATES FOR FY 2020-21 .............................................................................. 28
TABLE 14: POWER PURCHASE ESTIMATES FOR FY 2021-22 .............................................................................. 30
TABLE 15: COMPUTATION OF THE CPI INDEX..................................................................................................... 32
TABLE 16: EMPLOYEE EXPENSES FROM FY 2019-20 TO FY 2021-22 (RS CRORES) ............................................ 33
TABLE 17: R&M EXPENSES AS %AGE OF GFA (RS. CRORES) ............................................................................... 34
TABLE 18: COMPUTATION OF WPI INDEX.......................................................................................................... 34
TABLE 19: R&M EXPENSES FROM FY 2019-20 TO FY 2021-22 (RS CRORES) ................................................... 34
TABLE 20: A&G EXPENSES FROM FY 2019-20 TO FY 2021-22 (RS CRORES) .................................................... 35
TABLE 21: O&M EXPENSES FROM FY 2019-20 TO FY 2021-22 (RS CRORES) ................................................... 35
TABLE 22: PROPOSED CAPITAL EXPENDITURE FROM FY 2019-20 TO FY 2021-22 (RS CRORES) ......................... 36
TABLE 23: PROPOSED CAPITALISATION FROM FY 2019-20 TO FY 2021-22 (RS CRORES) .................................. 36
TABLE 24: FUNDING PATTERN FOR PROPOSED CAPITALISATION (RS CRORES) ...................................................... 37
TABLE 25: CAPITAL EXPENDITURE AND CAPITALISATION FROM FY 2019-20 TO FY 2021-22 (RS CRORES) .......... 37
TABLE 26: DEPRECIATION CALCULATION FOR FY 2019-20 (RS CRORES) ............................................................ 38
TABLE 27: DEPRECIATION CLAIMED BY APDCL FOR FY 2019-20 (RS CRORES) .................................................. 38
TABLE 28: DEPRECIATION CALCULATION FOR FY 2020-21 (RS CRORES) ............................................................ 39
TABLE 29: DEPRECIATION CLAIMED BY APDCL FOR FY 2020-21 (RS CRORES) .................................................. 39
TABLE 30: DEPRECIATION CALCULATION FOR FY 2021-22 (RS CRORES) ............................................................ 40
TABLE 31: DEPRECIATION CLAIMED BY APDCL FOR FY 2021-22 (RS CRORES) .................................................. 40
TABLE 32: DEPRECIATION FROM FY 2019-20 TO FY 2021-22 (RS CRORES) ..................................................... 41
TABLE 33: INTEREST ON GOA LOAN AND RAPDRP LOAN FOR FY 2019-20 (RS CRORES)..................................... 42
TABLE 34: INTEREST ON GOA LOAN AND RAPDRP LOAN FOR FY 2020-21 (RS CRORES)..................................... 42
TABLE 35: INTEREST ON GOA LOAN AND RAPDRP LOAN FOR FY 2021-22 (RS CRORES)..................................... 42
TABLE 36: CLAIM OF I NTEREST & FINANCE CHARGES FROM FY 2019-20 TO FY 2021-22 (RS CRORES) ............... 43
TABLE 37: INTEREST & FINANCE CHARGES FROM FY 2019-20 TO FY 2021-22 (RS CRORES) .............................. 43
TABLE 38: INTEREST ON WORKING CAPITAL FROM FY 2019-20 TO FY 2021-22 (RS CRORES) ........................... 44
TABLE 39: INTEREST ON SECURITY DEPOSIT FROM FY 2019-20 TO FY 2021-22 (RS CRORES) ........................... 45
TABLE 40: ‘OTHER DEBITS’ FROM FY 2019-20 TO FY 2021-22 (RS CRORES) ................................................... 45
TABLE 41: RETURN ON EQUITY FROM FY 2019-20 TO FY 2021-22 (RS CRORES) .............................................. 46
TABLE 42: ‘OTHER INCOME’ FROM FY 2019-20 TO FY 2021-22 (RS CRORES) .................................................. 47
TABLE 43: NON-TARIFF INCOME FROM FY 2019-20 TO FY 2021-22 (RS CRORES) ............................................ 47
TABLE 44: REVENUE AT EXISTING TARIFF FROM FY 2019-20 TO FY 2021-22 (RS CRORES)................................ 48
TABLE 45: ARR FROM FY 2019-20 TO FY 2021-22 (RS CRORES) ................................................................... 49
TABLE 46: CUMULATIVE REVENUE GAP TILL FY 2019-20 (RS CRORES) ............................................................. 50
TABLE 47: COST OF SUPPLY FOR FY 2019-20................................................................................................... 51
TABLE 48: REVENUE GAP PROPOSED FOR RECOVERY IN FY 2019-20 (RS CRORES) .............................................. 52
TABLE 49: TARIFF PROPOSAL FOR FY 2019-20 .............................................................................................. 53
TABLE 50: CROSS-SUBSIDY FOR FY 2019-20 .................................................................................................. 53
TABLE 51: ALLOCATION MATRIX FOR SEPARATION OF ARR FOR WIRES AND RETAIL SUPPLY BUSINESS .................. 57
TABLE 52: SEPARATION OF ARR FOR WIRES AND RETAIL SUPPLY BUSINESS FOR FY 2019-20 (RS. CRORES) ........ 57
TABLE 53: WHEELING CHARGES FOR FY 2019-20 ............................................................................................ 58
TABLE 54: WHEELING LOSSES FOR FY 2019-20 ............................................................................................... 58
TABLE 55: CATEGORY-WISE CROSS-SUBSIDY SURCHARGE FOR FY 2019-20 (RS/KWH) ........................................ 59
Assam Power Distribution Company Limited (APDCL) Page 4MYT Petition for the Control Period FY 2019-20 to FY 2021-22
BEFORE THE HON’BLE ASSAM ELECTRICITY REGULATORY
COMMISSION, GUWAHATI
Filing No_______________
Case No________________
IN THE MATTER OF: Filing of the MYT Petition for the control period from FY 2019-20 to FY
2021-22
AND
IN THE MATTER OF: AERC MYT Regulations, 2018
AND
IN THE MATTER OF: Assam Power Distribution Company Limited (hereinafter
referred to as ‘’APDCL’’ or ‘’ the Petitioner’’ or Applicant)
I, Sri Arup Kr Baruah, son of Late Jagot Baruah, aged about 59 years, General Manager (Tariff
Regulatory Cell) of the Assam Power Distribution Company Ltd, having its office at 5th
Floor, Bijuli Bhawan, Paltanbazar, Guwahati, Assam, PIN-781001do solemnly affirm and say
as follows:
1. I am the General Manager (Tariff Regulatory Cell) of Assam Power Distribution Company
Limited, the Petitioner in the above matter and am duly authorized by the said Petitioner to
make this affidavit for and on behalf of Assam Power Distribution Company Limited.
2. The statements made in the Petition based on information received from official records and
I believe them to reflect truly and no material has been concealed from the statements so
made or documents or supporting data etc. attached.
3. Solemnly affirm at Guwahati on 15 day of December, 2018 that the contents of this affidavit
are true to my knowledge, no part of it is false or no material has been concealed therefore
and misleading material included therein.
Date: 15/12/2018 General Manager (Tariff Regulatory Cell)
Deponent
APDCL, Guwahati
Assam Power Distribution Company Limited (APDCL) Page 5MYT Petition for the Control Period FY 2019-20 to FY 2021-22
BEFORE THE HON’BLE ASSAM ELECTRICITY REGULATORY
COMMISSION, GUWAHATI
Filing No_______________
Case No________________
IN THE MATTER OF: Filing of the MYT Petition for the control period FY 2019-20 to FY
2021-22
AND
IN THE MATTER OF: Assam Power Distribution Company Limited (hereinafter
referred to as ‘’APDCL’’ or ‘’ the Petitioner’’ or Applicant)
The Applicant respectfully submits as under: -
1. The Petitioner is adeemed licensee under the provisions laid down in Section 14 Proviso 5,
read with Section 131 (2) of the Electricity Act 2003
2. The Petitioner submits that the Hon’ble Commission has issued the following regulation
namely, AERC (Terms and Conditions for determination of Multi Year Tariff) Regulations,
2018for the MYT control period from FY 2019-20 to FY 2021-22 (hereinafter referred to as
“MYT Regulations, 2018”).
3. The said regulations are applicable to power generating stations, transmission system, SLDC
and distribution system where tariff for generation, transmission, SLDC, retail or wheeling is
not determined under section 63 of the Electricity Act 2003 through transparent process of
competitive bidding in accordance with the guidelines issued by the Central Government.
4. The Petitioner is accordingly filing this petition for approval of ARR for the MYT control
period FY 2019-20 to FY 2021-22 and tariff for FY 2019-20.
5. As per the MYT Regulations 2018, APDCL has filed the MYT petition for the ensuing control
period from FY 2019-20 to FY 2021-22 on 30thNovember 2018.
6. The Hon’ble commission during the TVS on 10th December’2018 identified defects in the
petition and directs APDCLto submit the revised petition after rectifying the defects on or
before 15th December’2018 vide order dated 10.12.2018.
7. Accordingly APDCL is submitting the revised petition as per direction.
Date:15/12/2018
Petitioner
General Manager (Tariff Regulatory Cell)
APDCL, Guwahati
Assam Power Distribution Company Limited (APDCL) Page 6MYT Petition for the Control Period FY 2019-20 to FY 2021-22
NOTES AND ABBREVIATIONS
In this Petition:
Control Period is defined as Financial Year 2019-20, 2020-21 and 2021-22
hereinafter referred to as FY 20, FY 21 and FY 22
Ensuing Year is defined as Financial Year 2019-20 or FY 20
Current Year is defined as Financial Year 2018-19 or FY 19
Previous Year is defined as Financial Year 2017-18 or FY 18
All currency figures used in this Petition, unless specifically stated otherwise, are
in Rs. Crores.
Abbreviation Full Description
AEGCL Assam Electricity Grid Corporation Limited
APGCL Assam Power Generation Corporation Limited
APDCL Assam Power Distribution Company Limited
AERC Assam Electricity Regulatory Commission
APR Annual Performance Review
ARR Aggregate Revenue Requirement
AT&C Aggregate Technical and Commercial
CAGR Compounded Annual Growth Rate
CEA Central Electricity Authority
CERC Central Electricity Regulatory Commission
Ckt - kms Circuit Kilometres
DDG Decentralised Distributed Generation
DDUGJY DeendayalUpadhyay Gram Jyoti Yojana
DTR Distribution Transformer
EA - 2003 The Electricity Act 2003
EPS Electric Power Survey
FY Financial Year
GoA Government of Assam
GoI Government of India
HT High Tension
HV High Voltage
HVDS High Voltage Distribution System
Assam Power Distribution Company Limited (APDCL) Page 7MYT Petition for the Control Period FY 2019-20 to FY 2021-22 Abbreviation Full Description IPDS Integrated Power Development Scheme LT Low Tension MVA Mega Volt Ampere MYT Multi Year Tariff PGCIL Power Grid Corporation of India Limited RGGVY Rajiv Gandhi GrameenVidyutikaranYojana RAPDRP Restructured Accelerated Power Development and Reforms Programme UDAY Ujwal DISCOM Assurance Yojana Assam Power Distribution Company Limited (APDCL) Page 8
MYT Petition for the Control Period FY 2019-20 to FY 2021-22
1: INTRODUCTION
Assam Power Distribution Company Limited (APDCL)
1.1 The Government of Assam, vide Memo No. PEL151/2003/Pt./165 dated
December 10, 2004, notified the restructuring of the erstwhile Assam State
Electricity Board (ASEB) into five entities, namely:
i. Assam Electricity Grid Corporation Limited (AEGCL) to carry out function
as State Transmission Utility (STU)
ii. Assam Power Generation Corporation Limited (APGCL) to carry out
function of generation of electricity in the State of Assam
iii. Three Electricity Distribution Companies, namely Lower, Central and
Upper Assam Electricity Distribution Company Limited, to carry out
functions of distribution and retail sale of electricity in the districts
covered under each company area
1.2 All Companies are duly incorporated with the Registrar of Companies as per the
Companies Act, 1956. Further, in exercise of power under Section 172 of the
Electricity Act 2003, the Government of Assam authorized ASEB to continue its
trading functions by periodic notification till September 2009.
1.3 As per the Government of Assam Notification No PEL.41/2006/199 dated May
13, 2009, in accordance with the Assam State Reform (Transfer and merger of
Distribution Functions and undertakings) Scheme, 2009, CAEDCL and UAEDCL
Distribution Companies merged with the LAEDCL, thereby forming one
distribution company for the State. The name of the Company was changed from
LAEDCL toAssam Power Distribution Company Limited (APDCL) vide Certificate
of Incorporation dated October 23, 2009. The Government of Assam vide
Notification dated March 12, 2013 dissolved ASEB under Section 131 of the Act
with effect from March 31, 2013 and transferred ASEB’s current functions and
reassigned its personnel to its successor entities namely APDCL, AEGCL and
APGCL in accordance with the Scheme of Reorganization.
1.4 The Company is a Distribution Licensee within the meaning of Section 2 (17) of
Electricity Act 2003. Further, Section 42 and 43 of the Electricity Act 2003
prescribes the following major duties of the Distribution Licensee:
To develop and maintain an efficient, co-ordinate and economical
distribution system;
To supply electricity on an application of the consumer in accordance with
the provisions specified in the Electricity Act 2003;
Assam Power Distribution Company Limited (APDCL) Page 9MYT Petition for the Control Period FY 2019-20 to FY 2021-22
To provide non-discriminatory open access to the consumers;
To establish a forum for redressal of grievances of the consumers;
Multi-Year Tariff Regulations 2018
1.5 The Hon’ble Commission in exercise of the powers conferred under Section 61
read with Section 181(2) (zd) of the Act, has notified the Assam Electricity
Regulatory Commission (Terms and Conditions for determination of Multi Year
Tariff) Regulations, 2018 (hereinafter referred as “MYT Regulations, 2018”) on
June 28’ 2018. These regulations are applicable for determination of tariff for
Generation, Transmission, SLDC, Wheeling and Retail Supply for the control
period of three financial years from April 1’ 2019 to March 31’ 2022. These
Regulations are applicable to all existing and future Generating Companies,
Transmission Licensees and Distribution Licensees within the State of Assam.
1.6 As per Regulation 18 of the MYT Regulations, 2018, the Generating Company,
Transmission Licensee, SLDC Business and Distribution Licensee shall submit
the MYT petition for the control period by 30th November of the year preceding
the first year of the control period along with the capital investment plan for the
control period.
1.7 It is submitted that the present petition is being filed for approval of Aggregate
Revenue Requirement (ARR) for the Control Period from FY 2019-20 to FY 2021-
22 and tariff for FY 2019-20 in accordance with the provisions of the MYT
Regulations, 2018.
Assam Power Distribution Company Limited (APDCL) Page 10MYT Petition for the Control Period FY 2019-20 to FY 2021-22
2: METHODOLODY ADOPTED IN FILING OF THIS PETITION
(INCLUDING CONSTRAINTS)
Methodology
2.1 APDCL is submitting the petition for approval of ARR for the MYT control period
from FY 2019-20 to FY 2021-22 and tariff for FY 2019-20 in accordance with the
applicable provisions of the MYT Regulations, 2018.
2.2 The MYT petition is being filed based on the actual performance in FY 2017-18
and first half yearly performance of FY 2018-19, which form the basis of
projections of ARR for the MYT control period from FY 2019-20 to FY 2021-22.
2.3 The Petitioner, humbly requests the Hon’ble Commission to approve the ARR for
the control period from FY 2019-20 to FY 2021-22 and tariff for FY 2019-20 as
submitted.
Assam Power Distribution Company Limited (APDCL) Page 11MYT Petition for the Control Period FY 2019-20 to FY 2021-22
3: MYT PETITION FOR THE CONTROL PERIOD FROM FY 2019-20 TO
FY 2021-22
Contents of the Petition
3.1 This petition has in detail, the ARR for the control period from FY 2019-20 to FY
2021-22. The following section explains in detail the key elements of
determination of ARR and thereby the revenue gap/ (surplus) of the utility.
3.2 Determination of Aggregate Revenue Requirement by determination of the
following costs, other income & returns:
i. Power Purchase Cost
ii. Operation& Maintenance (O&M) Cost
iii. Depreciation
iv. Interest & Finance Charges
v. Interest on Working Capital
vi. Interest on Consumer Security Deposits
vii. Other Debits
viii. Return on Equity
ix. Other Income
x. Non-Tariff Income
3.3 The revenue includes revenue from sale of power to arrive at the revenue gap/
(surplus) of the utility.
Category-wise Energy Sales
3.4 The Commission had approved energy sales of 6684 MU, 7524 MU, and 8399 MU
for FY 2016-17, FY 2017-18, and FY 2018-19, respectively in the MYT tariff order
dated March 31’ 2017. The Commission, subsequently approved energy sales of
6526 MU in the truing-up for FY 2016-17. Also, the energy sales were revised to
7107 MU in the APR for FY 2017-18 and 7784 MU for FY 2018-19 as approved by
the Commission in the tariff order dated March 19’ 2018.
3.5 The Petitioner submits that the actual energy sales for FY 2017-18 are 6814 MU
Assam Power Distribution Company Limited (APDCL) Page 12MYT Petition for the Control Period FY 2019-20 to FY 2021-22
as against 7107 MU approved in the APR for FY 2017-18. It is to be noted that
actual energy sales for FY 2017-18 are more than the actual energy sales for FY
2016-17, both for the LT and HT category. The LT sales for FY 2017-18 has
shown an increase in sales of ~6% over LT sales for FY 2016-17 and HT sales for
FY 2017-18 has shown an increase in sales of 1% over HT sales for FY 2016-17.
3.6 The Petitioner submits that it has to complete the remaining household
electrification by December 2018 as per the provisions of the SAUBHAGYA
scheme. This will increase the household consumption, particularly in the rural
areas from FY 2018-19. All efforts are being made to achieve the stipulated
timeline. 9,62,704 households are pending electrification as on 29th November’
2018 in Assam (as per figures on SAUBHAGYA portal). The pending
electrification of households is to be completed by December2018. We have
considered that this addition in households will primarily be in the Jeevan Dhara
category. The Petitioner has considered that this addition in households will
result in additional ~487 MU of energy sales in the Jeevan Dhara category during
FY 2018-19. This additional consumption has been considered over and the
above the 4 year CAGR growth applied to the Jeevan Dhara category during FY
2018-19. The actual impact of the increase in sales due to the SAUBHAGYA
implementation will be considered at the time of true-up of ARR for FY 2018-19.
3.7 The projections of energy sales for FY 2018-19 have been revised based on
actual energy sales for FY 2017-18 and actual performance in H1 of FY 2018-19.
For rest of the consumer categories, energy sales have been projected keeping
historical growth rates in mind and projecting the 3 year, 4 year, 5 year CAGR
along with the Y-o-Y growth seen in the consumer categories. Reasonable
estimates about the growth rates of the various consumer categories have been
made to arrive at the energy sales for FY 2018-19. Accordingly, the Petitioner has
estimated energy sales of 7749 MU in the APR for FY 2018-19.
3.8 For the years of the control period from FY 2019-20 to FY 2021-22, the
Petitioner has considered the historical 4 year CAGR for estimation of sales to
Jeevan Dhara category. For Domestic A category the average YoY growth seen
during last two years, has been applied to estimate the sales for the control
period from FY 2019-20 to FY 2021-22.
3.9 For rest of the consumer categories, the energy sales have been projected
keeping historical growth rates in mind and projecting the 3 year, 4 year, 5 year
CAGR along with the Y-o-Y growth seen in the consumer categories. Reasonable
estimates about the growth rates of the various consumer categories have been
made to arrive at the energy sales forecast for the control period from FY 2019-
20 to FY 2021-22. In case the growth trend is recent years was negative, we
have considered 0% growth rate for those consumer categories. The growth rate
as observed by the trend of CAGR has been adjusted in line with the recent YoY
Assam Power Distribution Company Limited (APDCL) Page 13MYT Petition for the Control Period FY 2019-20 to FY 2021-22
growth rates observed for the different consumer categories wherever required.
3.10 The growth rates considered for the various consumer categories is as below.
Table 1: Growth Rates considered for the various consumer categories
Growth Rate
Consumer Category Growth Rate
(%)
JEEVAN DHARA* CAGR 4 yr 7.8%
DOMESTIC A below 5 kW Adjusted 6.0%
Domestic-B 5 kW and above upto 25 kW YoY 6.0%
Commercial Load above 0.5 kW and upto 25 kW CAGR 3 yr 6.6%
General Load upto 25 kW Adjusted 0%
Public Lighting Adjusted 0%
Agriculture upto 25 kW CAGR 3 yr 25.4%
Small Industries Rural upto 25 kW CAGR 3 yr 9.6%
Small Industries Urban upto 25 kW CAGR 3 yr 2.8%
Temporary YoY 4.6%
LT TOTAL
HT Domestic above 25 kW (30 kVA) Adjusted 0%
HT Commercial above 25 kW (30 kVA) CAGR 3 yr 8.3%
Public Water Works Adjusted 0%
Bulk Supply Govt. Edu Inst above 25 kW (30 kVA) CAGR 3 yr 2.2%
Bulk Supply Others above 25 kW (30 kVA) CAGR 3 yr 0.6%
HT Small Industries above 25 kW (30 kVA) and upto 50
CAGR 3 yr 0.5%
kVA
HT Industries-I 50 kVA to 150 kVA Adjusted 0%
HT Industries-II above 150 kVA YoY 13.7%
Tea Coffee& Rubber CAGR 3 yr 6.6%
Oil & Coal Adjusted 0%
HT Irrigation Load above 25 kW (30 kVA) Adjusted 0%
HT Temporary - -
Increase of 1 MU
HT Electric Crematorium -
each year
HT TOTAL
Note: *- For Jeevan Dhara category, sales estimated to grow at 4 year CAGR of 7.8% during FY 2018-19
plus additional sales of 487 MU due to addition in households due to Saubhagya scheme; for the control
period from FY 2019-20 to FY 2020-21 sales estimated to grow at 4 year CAGR of 7.8%
3.11 For the new consumer category of HT Electric Crematorium created in the last
tariff order dated March 19’ 2018, the energy sales have been considered to
increase by 1 MU in each year of the control period. The energy sales projected
for the various consumer categories for the control period from FY 2019-20 to
FY 2021-22 is as below.
Assam Power Distribution Company Limited (APDCL) Page 14MYT Petition for the Control Period FY 2019-20 to FY 2021-22
Table 2: Energy Sales to the various consumer categories (MU)
FY 17-18 FY 18-19 FY 19-20 FY 20-21 FY 21-22
Consumer Category (A) (P) (P) (P) (P)
JEEVAN DHARA 669 1207 1301 1402 1511
DOMESTIC A below 5 kW 2727 2890 3064 3248 3442
Domestic-B 5 kW and above upto
277 293 311 330 350
25 kW
Commercial Load above 0.5 kW
627 669 713 761 811
and upto 25 kW
General Load upto 25 kW 99 99 99 99 99
Public Lighting 13 13 13 13 13
Agriculture upto 25 kW 20 25 31 39 49
Small Industries Rural upto 25 kW 66 72 79 87 95
Small Industries Urban upto 25 30 31 32 33 34
kW
Temporary 7 8 8 8 9
LT TOTAL 4534 5307 5651 6018 6412
HT Domestic above 25 kW (30
31 31 31 31 31
kVA)
HT Commercial above 25 kW (30
352 381 413 447 484
kVA)
Public Water Works 71 71 71 71 71
Bulk Supply Govt. Edu Inst above
76 77 79 81 83
25 kW (30 kVA)
Bulk Supply Others above 25 kW
383 385 388 390 392
(30 kVA)
HT Small Industries above 25 kW
23 23 24 24 24
(30 kVA) and upto 50 kVA
HT Industries-I 50 kVA to 150 kVA 67 67 67 67 67
HT Industries-II above 150 kVA 702 798 908 1032 1174
Tea Coffee & Rubber 484 516 550 586 624
Oil & Coal 76 76 76 76 76
HT Irrigation Load above 25 kW
15 15 15 15 15
(30 kVA)
HT Temporary
HT Electric Crematorium 1 2 3 4
HT TOTAL 2280 2442 2622 2822 3045
TOTAL 6814 7749 8273 8841 9457
3.12 Accordingly, the Petitioner requests the Hon’ble Commission to approve the
energy sales as estimated above for the MYT control period from FY 2019-20 to
FY 2021-22.
Distribution Loss Trajectory
3.13 The Commission in the business plan order dated September 1’ 2016 had
approved distribution loss of 17.35%, 17.10% and 16.85% for FY 2016-17, FY
2017-18 and FY 2018-19 respectively.
3.14 The Commission during true-up of FY 2016-17 vide tariff order dated March 19’
Assam Power Distribution Company Limited (APDCL) Page 15MYT Petition for the Control Period FY 2019-20 to FY 2021-22
2018 approved the same distribution loss at 17.35% as against actual
distribution loss of 17.89% for FY 2016-17. The Commission maintained the
distribution loss at 17.10% during APR for FY 2017-18 and 16.85% during
revised ARR for FY 2018-19 (as per tariff order dated March 19’ 2018).
3.15 It is to be submitted that the Petitioner has been praying for consideration of loss
at actuals with detailed justification on regular basis.
3.16 The APDCL during FY 2017-18 has achieved actual distribution loss of 17.64%
against the target of 17.10% even with various constraints i.e. adverse LT: HT
ratio, incremental sale to LT consumers, old infrastructure etc. The past years
actual distribution loss of APDCL against the target approved by the Commission
is shown in the following table:
Table 3: Target vis-à-vis actual distribution loss of APDCL
Year Approved Loss (%) Actual Loss Level (%)
2005-06 29.95 31.10
2006-07 30.71 29.43
2007-08 25.05 27.32
2008-09 24.24 24.32
2009-10 22.60 26.06
2010-11 21.60 25.44
2011-12 20.60 26.61
2012-13 19.60 25.85
2013-14 18.60 24.11
2014-15 18.60 21.14
2015-16 17.60 18.12
2016-17 17.35 17.89
2017-18 17.10 17.64
3.17 It is seen that over the years the utility has been able to bring down the losses
gradually. It is pertinent to mention that with specific programs like DSM
initiatives, creation of dedicated cells to monitor high value consumers etc.
APDCL has been able to bring down the loss level significantly even with
restricted resources. The Petitioner, humbly submits that despite the best efforts
of the utility to achieve the target distribution losses, it is getting much more
difficult to reduce the distribution losses now at the same rate as achieved in the
past years.The HT: LT ratio is getting adverse every year as LT sales are
increasing on account of extensive rural electrification and HT sales are not
increasing at the same rate as it is impacted due to other factors like lack of
industrial growth in the state, etc.
3.18 Year-on-year sales mix of APDCL and corresponding distribution losses of APDCL
are as depicted below:
Assam Power Distribution Company Limited (APDCL) Page 16MYT Petition for the Control Period FY 2019-20 to FY 2021-22
Table 4: LT: HT ratio vis-à-vis actual distribution loss of APDCL
LT Sales HT Sales Distribution
FY (MU) (%) (MU) (%) Loss (%)
2008-09 1489(49%) 1555(51%) 24.32
2009-10 1573(48%) 1674(52%) 26.06
2010-11 1769(50%) 1767(50%) 25.44
2011-12 2026(51%) 1944(49%) 26.61
2012-13 2176(52%) 2029(48%) 25.85
2013-14 2593(54%) 2170(46%) 24.11
2014-15 3228(59%) 2257(41%) 21.14
2015-16 3886(63%) 2313(37%) 18.12
2016-17 4270(65%) 2256(35%) 17.89
2017-18 4534 (67%) 2280 (33%) 17.64
3.19 It is understood that HT: LT ratio has a key impact on overall distribution losses
of the state and with the present trend of inverse HT: LT ratio, the distribution
loss targets stipulated for the current control period are difficult to achieve.
Losses increase with increase in LT consumption at the same performance levels.
3.20 The distribution loss scenario of APDCL is also to be seen from the aspect of
overall situation prevailing in some parts of the state. It may be seen that in
predominantly urban areas as well as areas without any social disturbances, the
utility was able to achieve distribution loss far below the approved loss levels.
However, in some areas where the situation is beyond reasonable control of the
licensee, the losses have crossed the approved limit. Further, consumer
behaviour of certain areas under APDCL is at variance from others. Frequent
bandh as well as perennial natural calamities in some part of the State affects the
performance in these areas resulting in higher losses.
3.21 The Petitioner as per first half actual performance in FY 2018-19 has not been
able to achieve the targeted distribution loss of 16.85%. The actual distribution
loss as per H1 of FY 2018-19 is 18.34%. The Petitioner notes that as per the
UDAY MoU, the distribution licensee is to achieve the AT&C loss target of 15% by
FY 2019-20. Considering the collection efficiency of 99.50%, the UDAY MoU had
stipulated the target distribution loss of 14.57% by FY 2019-20. The Hon’ble
Commission in the last tariff order dated March 19’ 2018 had maintained the
distribution loss trajectory as approved by the Commission in the business plan
order dated September 1’ 2016 and accordingly approved the distribution loss of
16.85% for FY 2018-19. As per the latest communication received from the
Hon’ble Commission vide letter dated June 8’ 2018, the Commission is planning
to fix target AT&C loss of 15% for FY 2019-20 and gradually reducing it to 14%
Assam Power Distribution Company Limited (APDCL) Page 17MYT Petition for the Control Period FY 2019-20 to FY 2021-22
by FY 2021-22. It is to be noted that the Commission has stipulated a very steep
reduction in target distribution losses for FY 2019-20 at 15% (assuming 100%
collection efficiency) from 16.85% fixed for FY 2018-19 i.e. reduction of 1.85% in
one year. This appears difficult to achieve.
3.22 Considering collection efficiency of 99%, the licensee would be required to bring
down the losses to 14.14% in FY 2019-20 and to 13.13% in FY 2021-22 with the
above stipulated AT&C loss trajectory. Assuming best case 100% collection
efficiency, the licensee would have to bring down the losses to 14% in FY 2021-
22 from 17.64% in FY 2017-18.
3.23 The Petitioner is to complete the SAUBHAGYA household electrification target by
December 2018. Considering the increase in consumption of LT sales due to
SAUBHAGYA implementation, the Petitionerrequests the Hon’ble Commission to
revisit its plan to approve AT&C loss target of 14% by FY 2021-22. The sudden
increase in LT sales due to increased rural electrification has resulted in
increased distribution losses in H1 of FY 2018-19 vis-à-vis FY 2017-18 actual
distribution loss. The increased rural electrification will make it more difficult to
attain the loss targets stipulated by the Commission. Infact, the distribution loss
during FY 2018-19 (annual) is likely to be more than the FY 2017-18 loss figure.
Accordingly, the Petitioner requests the Commission to approve distribution loss
of 18.34% for FY 2018-19 and further reduction of 0.5% each year during the
control period from FY 2019-20 to FY 2021-22.
3.24 The Petitionerrequests to approve the distribution loss trajectory for the control
period from FY 2019-20 to FY 2021-22 as shown in the following table:
Table 5: Proposed distribution loss trajectory from FY 2019-20 to FY 2021-22
Sr.
Particulars FY 2019-20 FY 2020-21 FY 2021-22
No
1 Distribution Loss (%) 17.84% 17.34% 16.84%
Energy Requirement
3.25 Based on the energy sales as estimated above along with the proposed
distribution loss trajectory, the energy requirement for the control period from
FY 2019-20 to FY 2021-22 has been estimated as below. The intra-state (AEGCL)
transmission loss of 3.44% has been considered as approved for FY 2018-19 in
the latest tariff order of AEGCL dated March 19’ 2018. The latest weighted
average 52-week transmission loss of NER and ER regions has been considered
as 1.55% for the control period from FY 2019-20 to FY 2021-22.
Assam Power Distribution Company Limited (APDCL) Page 18MYT Petition for the Control Period FY 2019-20 to FY 2021-22
Table 6: Energy Requirement from FY 2019-20 to FY 2021-22 (MU)
Sr.
Particulars FY 2019-20 FY 2020-21 FY 2021-22
No
1 Energy Sales 8,273 8,841 9,457
2 Distribution Loss (%) 17.84% 17.34% 16.84%
Energy Requirement at Distribution
3 10,069 10,695 11,372
Periphery T-D
4 Intra-State Transmission Loss (%) 3.44% 3.44% 3.44%
5 Energy input to Transmission System 10428 11076 11777
6 Inter-State (PGCIL) Pooled Loss (%) 1.55% 1.55% 1.55%
7 Total Energy Requirement 10,592 11,250 11,962
3.26 The Hon’ble Commission is requested to approve the estimates of the energy
requirement from FY 2019-20 to FY 2021-22 as shown above.
Power Purchase Quantum and Cost
3.27 Power procurement of APDCL is largely dependent on the state generating
stations of APGCL and central generating stations to meet its base load. However,
in order to meet the peak demand of the state, APDCL ties up with short-term
sources like traders and also sources power from Power Exchanges.
3.28 The existing capacity allocated to APDCL for FY 2018-19 is ~2000 MW. The
power purchase quantum and cost for each year of the control period has been
estimated based on assumptions/details as discussed below.
State Generating Stations
3.29 APDCL has firm allocation of power from state generating stations of APGCL.
Existing thermal plants of APGCL include NTPS, LTPS and LRPP. Hydro plants of
APGCL supplying power to APDCL are MeHEP and KLHEP. The existing capacity
of APGCL plants is 371 MW (100% capacity allocation to APDCL).
3.30 Energy Availability:The Petitioner has estimated the gross energy availability
from the existing stations based on the allocated capacity and the PLF as
approved for these plants in the latest tariff order of APGCL dated March 19’
2018. Auxiliary consumption for these plants has been considered as per the
latest tariff order of APGCL. Intra-state transmission loss of 3.44% as approved
in AEGCL tariff order dated March 19’ 2018 has been considered.
3.31 Power Purchase Cost: The fixed cost for the state generating stations has been
considered as per the latest tariff order of APGCL dated March 19’ 2018 for FY
2018-19 further escalated by 5% during each year of the control period. The
variable charges have been projected based on the average energy charge rate
Assam Power Distribution Company Limited (APDCL) Page 19MYT Petition for the Control Period FY 2019-20 to FY 2021-22
for the latest available six months (April 2018 to September 2018), further
escalated by 5% during each year of the control period. For Myntriang HEP, the
provisional single-part tariff of Rs. 2.18/kWh as approved by AERC has been
considered vide order dated November 29’ 2017. No escalation has been
considered for Myntriang HEP tariff.
3.32 New Capacity Additions: The new capacity additions of APGCL plants considered
during each year of the control period are as tabulated below.
Table 7: Capacity additions of APGCL plants from FY 2019-20 to FY 2021-22 (MW)
Sr.
Particulars FY 2019-20 FY 2020-21 FY 2021-22
No
1 NRPP 62.25
2 Myntriang Other Stages 9.00
3 NRPP (Waste Heat) 36.15
4 Namrup SPV 15.00 -
5 Total capacity addition 71.25 51.15 -
3.33 Suitable assumptions related to PLF and auxiliary consumption for NRPP have
been considered. Tariff of Rs. 4.00/kWh has been considered for NRPP plants.
Central Generating Stations (North East Region)
3.34 The key central generating stations of NER (North Eastern Region) supplying
power to APDCL include plants of NEEPCO, NHPC, OTPC and NTPC (Thermal).
3.35 Energy Availability: The share allocation of the various plants of CGS (NER) has
been considered based on the latest REA. The PLF of these plants has been
considered based on the average of the last 3-4 years actual generation. Auxiliary
consumption has been considered based on the values as approved by CERC in
respective tariff orders of the plants. The latest available inter-state transmission
loss of NER of 1.49% (as per NERLDC) has been considered. Intra-state
transmission loss of 3.44% as approved by AERC for FY 2018-19 has been
considered.
3.36 Power Purchase Cost: The fixed cost for the central generating stations has been
considered as per the latest CERC orders for the respective plants, further
escalated by 5% during each year of the control period. The fixed charges have
been projected by considering the availability vis-à-vis the normative plant
availability factor fixed for the respective plants by CERC. The variable charges
have been projected based on the average energy charge rate for the latest
available six months (April 2018 to September 2018), further escalated by 5%
during each year of the control period. For Pare, the provisional tariff of Rs.
5.00/kWh has been considered. No escalation has been considered for the tariff
of this plant over the control period.
Assam Power Distribution Company Limited (APDCL) Page 20MYT Petition for the Control Period FY 2019-20 to FY 2021-22
3.37 Kameng HEP of NEEPCO (Hydro) will commence operation in FY 2019-20. 65
MW capacity has been allocated from this source. PLF of 50% and auxiliary
consumption of 1% has been considered for this plant. Provisional tariff of Rs.
4.00/kWh has been considered for this plant during the entire control period.
3.38 BTPS-III (NTPC)will commence operation in the second half of FY 2018-19. 144
MW capacity has been allocated from this plant. Tariff of Rs. 6.39/kWh has been
considered for this plant on assumption basis for FY 2018-19 suitably escalated
over the control period as tariff order for the same has not been issued.
3.39 New Capacity Additions: The new capacity additions of plants in the NER region
considered during each year of the control period are as tabulated below.
Table 8: Capacity additions of NER plants from FY 2019-20 to FY 2021-22 (MW)
Sr.
Particulars FY 2019-20 FY 2020-21 FY 2021-22
No
1 Kameng 65 - -
2 NHPC (Subansiri) (allotted capacity) - - 208
3 Total capacity addition 65 - 208
Central Generating Stations (Eastern Region)
3.40 The key central generating stations of ER (Eastern Region) supplying power to
APDCL are Farakka I & II, Kahalgaon I, Kahalgaon II and Talcher.
3.41 Energy Availability: The share allocation of the various plants of CGS (ER) has
been considered based on the latest REA. The PLF of these plants has been
considered based on the average of the last 3 years actual generation. Auxiliary
consumption norms have been considered based on the values as approved by
CERC in respective tariff orders of the plants. The latest available inter-state
transmission loss of ER of 2.00% (as per ERLDC) has been considered. Intra-state
transmission loss of 3.44% as approved by AERC has been considered.
3.42 Power Purchase Cost: The fixed cost for the central generating stations has been
considered as per the latest CERC orders for the respective plants for FY 2018-
19, further escalated by 5% during each year of the control period. The variable
charges have been projected based on the average energy charge rate for the
latest available six months (April 2018 to September 2018), further escalated by
5% during each year of the control period.
Other Sources
3.43 APDCL has allocation of 1 MW from MeECL. Quantum of purchase considered
same as that for FY 2017-18 during each year of the control period. Energy
Assam Power Distribution Company Limited (APDCL) Page 21MYT Petition for the Control Period FY 2019-20 to FY 2021-22
charge has been considered equal to the average energy rate for the latest
available six months (April 2018 to September 2018).
3.44 For HHPCL, PLF and auxiliary consumption have been considered as per AERC
order dated April 12’ 2013. Basis this, the generation from this source has been
projected. The levelised tariff as determined for this plant in tariff order dated
April 12’ 2013 of Rs. 4.11/kWh has been considered for the entire control period.
3.45 Generation from NVVNL Solar Bundled (JNNSM) and NVVNL Coal Bundled
(JNNSM) has been considered equal to that in FY 2017-18 for each year of the
control period. The energy charge rate has been considered equal to the H1
average energy rate for the latest available six months (April 2018 to September
2018) during each year of the control period.
3.46 For Suryapratap Solar (SEIPL), normative parameters of the PLF and auxiliary
consumption as approved by AERC have been considered. The rate for
Suryapratap Solar has been considered as Rs. 8.78 per kWh as per the latest
AERC order.
3.47 For SECI (Solar) JNNSM, quantum has been considered same as that for FY 2017-
18 during each year of the control period. Energy charge rate has been
considered equal to the H1 average energy rate for the latest available six
months (April 2018 to September 2018) during each year of the control period.
3.48 New Capacity Additions: Wind Power (PTC), Wind Power (SECI) and PTC
Nikachu are the new capacity additions during FY 2019-20. SPV (100 MW)
Assam will commence operation from December 2019. The same is tabulated
below.
Table 9: Capacity additions under ‘Other Sources’ from FY 2019-20 to FY 2021-22 (MW)
Sr.
Particulars FY 2019-20 FY 2020-21 FY 2021-22
No
1 Wind Power (PTC) 50 - -
2 Wind Power(SECI) 50 - -
3 PTC Nikachu 80 - -
4 SPV (100 MW) Assam 100 - -
5 Punatsangchhu-I (Bhutan) - - 204
6 Punatsangchhu-II (Bhutan) - - 174
7 Mangdechhu (Bhutan) - - 122
8 Total capacity addition 280 - 500
3.49 The additional capacity expected to be allocated from Bhutan is ~500 MW in FY
2021-22. Actual generation from these sources has been considered to the extent
of meeting the energy deficit, for purposes of arriving at the power purchase
quantum and cost for FY 2021-22 as this is only an indicative timeline and may
get delayed based on actual progress of works at these plants in Bhutan. The
Assam Power Distribution Company Limited (APDCL) Page 22MYT Petition for the Control Period FY 2019-20 to FY 2021-22
impact of the same will be considered in the subsequent tariff filings based on
ground level progress of works at these plants (in Bhutan).
3.50 Wind Power (PTC) tariff considered as Rs. 3.53/kWh based on agreement signed
by the Petitioner. Wind Power (SECI) tariff considered as Rs. 2.72/kWh for the
control period. SPV (100 MW) tariff of Rs. 3.325/kWh considered based on solar
reverse bidding document signed by the Petitioner. Levelised tariff of Rs.
4.152/kWh for PTC (Nikachu) based on Power Sale Agreement (PSA) signed
between PTC India Ltd. and APDCL.
3.51 In addition to above, APDCL has floated e-bidding tender for 50MW Medium
term power at Deep portal and planning to float e-bidding tender for 100 MW
small hydro power. The impact of the same has not been considered for purposes
of this petition; however the same would be considered once the bidder for the
same is allocated.
3.52 The overall capacity addition during each year of the control period is as shown
below. It is to be noted that the below mentioned capacity addition figures are of
the allocated capacity from respective plants.
Table 10: Total capacity additions from FY 2019-20 to FY 2021-22 (MW)
Sr.
Particulars FY 2019-20 FY 2020-21 FY 2021-22
No
1 NRPP 62.25 - -
2 Myntriang Other Stages 9.00 - -
3 NRPP (Waste Heat) - 36 -
4 Namrup SPV - 15 -
5 NHPC (Subansiri) - - 208
6 Wind Power (PTC) 50 - -
7 Wind Power(SECI) 50 - -
8 PTC Nikachu 80 - -
9 SPV (100 MW) Assam 100 - -
10 Punatsangchhu-I (Bhutan) - - 204
11 Punatsangchhu-II (Bhutan) - - 174
12 Mangdechhu (Bhutan) - - 122
13 Total capacity addition 351 51 708
Note: In FY 2019-20, after commencement of NRPP, NTPS capacity will come down to 44 MW
from 99.5 MW, so effective capacity addition in FY 2019-20 is 295 MW.
3.53 The balance energy requirement has been proposed to be met from short-term
sources of power i.e. IEX, power exchanges etc.
Power Purchase from Renewable Sources
3.54 Assam Electricity Regulatory Commission (Renewable Purchase Obligation and
Compliance) Regulations, 2010, (Second Amendment), 2017 dated March 14’
2017 governs the RPO trajectory of the licensee. The relevant clause is
reproduced as below.
Assam Power Distribution Company Limited (APDCL) Page 23MYT Petition for the Control Period FY 2019-20 to FY 2021-22
‘’ The Obligations will be on total consumption of electricity by an obligated entity,
excluding consumption met from Hydro sources of power.
Provided, for Distribution Licensee, the Energy Handled shall be the total Energy
Sale to the consumers within the area of the distribution licensee.‘’
3.55 The purchase from renewable sources as projected has been considered and
balance has been adjusted under REC purchase. The Petitioner has considered
purchase of Solar RECs and Non-Solar RECs at the rate of Rs. 1/kWh and Rs. 1.50
/kWh, respectively, to meet the shortfall in purchase of renewable energy with
respect to the respective RPO.
3.56 The new capacity additions as mentioned above have accordingly been
considered in the respective years for purposes of calculation of RPO compliance.
3.57 The RPO compliance and calculation of REC purchase required is as shown
below.
Table 11: RPO calculation from FY 2019-20 to FY 2021-22
S.
Particulars FY 2019-20 FY 2020-21 FY 2021-22
No.
1 Solar 6.00% 7.00% 8.00%
2 Non-Solar 7.00% 8.00% 9.00%
3 TOTAL 13.00% 15.00% 17.00%
ENERGY SALE EXC. HYDRO
6074.96 6578.05 5753.06
(MU)
1 Solar 364.50 460.46 460.24
2 Non-Solar 425.25 526.24 517.78
3 TOTAL 789.75 986.71 978.02
COMPLIANCE (MU)
1 Solar 88.64 213.16 213.16
2 Non-Solar 308.37 308.37 308.37
3 TOTAL 397.02 521.53 521.53
REC PURCHASE REQD. (MU)
1 Solar 275.85 247.30 247.08
2 Non-Solar 116.88 217.87 209.40
3 TOTAL 392.73 465.17 456.49
REC Cost (Rs. Crores)
1 Solar 27.59 24.73 24.71
2 Non-Solar 17.53 32.68 31.41
3 TOTAL 45.12 57.41 56.12
3.58 The REC cost as projected above has been considered during respective year of
the control period from FY 2019-20 to FY 2021-22.
Assam Power Distribution Company Limited (APDCL) Page 24You can also read