Kenya Marine Fisheries and Socio-Economic Development

Page created by Hazel Davis
 
CONTINUE READING
Kenya Marine Fisheries and Socio-Economic Development
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

                             GOVERNMENT OF KENYA

 STATE DEPARTMENT OF FISHERIES, AQUACULTURE AND THE BLUE ECONOMY (SDF – BE)

                MINISTRY OF AGRICULTURE, LIVESTOCK andFISHERIES

 Kenya Marine Fisheries and Socio-Economic Development
                   (KEMFSED) (P163980)

            PROJECT PROCUREMENT STRATEGY FOR DEVELOPMENT (PPSD)

                                  JANUARY 2020

                                                                         1|Page
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

                                 ABBREVIATIONS AND ACRONYMS

BMU            Beach Management Unit
CBO            Community Based Organizations
CDD            Community Driven Development
CIDP           County Integrated Development Plans
CIG            Common Interest Groups
CMA            Co-Management Area
CPIU           County Project Implementation Unit
ESIA           Environmental and Social Impact Assessments
ESMF           Environmental and Social Management Framework
ESMP           Environmental and Social Management Plan
GoK            Government of Kenya
GRS            Grievance Redress Service
ICS            Individual Consultant Selection
IDA            International Development Association
JCMA           Joint Community Management Area
KEMFSED        Kenya Marine Fisheries and Socio-Economic Development
M&E            Monitoring and Evaluation
MCS            Monitoring, Control, and Surveillance
MoALF          Ministry of Agriculture, Livestock, and Fisheries
MSP            Marine Spatial Planning
NAMARET        National Mariculture Resource and Training Center
PDO            Project Development Objective
PGM            Project Grant Manual
PIM            Project Implementation Manual
PPSD           Project Procurement Strategy for Development
QCBS           Quality and Cost Based Selection
RFB            Request for Bid
RFP            Request for Proposal
RFQ            Request for Quotation
SDFA&BE        State Department of Fisheries, Aquaculture, and the Blue Economy
SEA            Sexual Exploitation and Abuse
SOPs           Standard Operating Procedures
STEP           Systematic Tracking of Exchanges in Procurement

                                                                                  2|Page
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

                                                  Table of Contents
1     Project Overview................................................................................................................ 5

2     Overview of Country, Borrower and Marketplace ......................................................... 12

3     Procurement Risk Analysis .............................................................................................. 22

4     Procurement Objectives .................................................................................................. 25

5     Recommended Procurement Approach for the Project: ............................................... 26

6     Preferred arrangement for low value, low risk activities (if applicable) ....................... 30

7     Summary of PPSD to be inform the Bank’s preparation of the PAD ............................. 31

Annex 1: Procurement Plan ..................................................................................................... 33

Annex 2: List of Consultants Expressed Interest for the consulting opportunities through the
KEMFSED Project [PPA] ............................................................................................................ 51

                                                                                                                        3|Page
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

                                                              List of Tables

Table 1: Procurement Category wise Spend Profile [Including Contingencies] ........................ 6

Table 2: Broad List of Component Wise Procurement Activities .............................................. 7

Table 3: Kenya at Glance: Indicators........................................................................................ 12

Table 4: List of Registered Contractors with National Construction Authority of Kenya as on
2017 ......................................................................................................................................... 20

Table 5: Level of Participation for Consulting opportunities through KEMSSED PPA ............. 20

Table 6: Procurement Risk Analysis ......................................................................................... 22

Table 7: Detailed Procurement Approach and Options .......................................................... 29

Table 8: Procurement Plan for First 18 months: For Goods (including ICT and Supply &
Installation), Works, and Non-Consulting Services.................................................................. 38

Table 9: Procurement Plan for First 18 months: Consultancy Services - Firm and Individual. 45

                                                                                                                                4|Page
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

    Kenya Marine Fisheries and Socio-Economic
    Development (KEMFSED)
1   Project      Procurement Strategy for Development
     Project Overview

    (PPSD)
Country:                                     Kenya
Full Project Name:                           Kenya Marine Fisheries and Socio-Economic
                                             Development (KEMFSED)
Total Finance ($):                           USD 100 million
Project Number:                              P163980

1 Project Overview
1.1        Project Development Objectives: To improve management of priority fisheries and
           mariculture and increase access to complementary livelihood activities in coastal
           communities.
1.2        PDO Level Indicators:
            PDO Level Indicator #1: Fisheries management plans implemented
            PDO Level Indicator #2: Proportion of nearshore waters under improved management
            PDO Level Indicator #3: Annual production in mariculture by small-scale producers
             supported by the project
            PDO Level Indicator #4: Beneficiaries in targeted coastal communities with access to
             complementary livelihood activities (disaggregated by sex)
            PDO Level Indicator #5: Share of target beneficiaries with rating ‘Satisfied’ or above on
             project interventions (disaggregated by sex)
1.3        Broad List of Component-based Procurement Activities
     Project Procurement Profile:
      The procurement profile is a mix of low to high value but non-complex contracts procured
      centrally at the National level, and low value contracts procured at the County and community
      level [Through community procurement] .
      Procurement of Goods and Non-Consulting Services: These comprise the procurement of motor
      vehicles and motorcycles, office and IT equipment, IT software & information systems, office
      furniture, conferencing facilities, and printing services.
      Procurement of Works: The construction of an office building to house the fisheries agencies,
      the National Mariculture Resource and Training center (NAMARET), the construction and/or
      rehabilitation of fisheries related infrastructure such as fish landing sites in selected areas, and
      the upgrading of county fisheries and Beach Management Units (BMU) offices. Livelihood

                                                                                               5|Page
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

        projects for informal small-scale producers and enterprises and targeted social services delivery
        projects will also be undertaken at the community level.
        Procurement of consultancy services: These includes, i) technical and financial feasibility studies
        and analysis, ii) monitoring and evaluation, iii) technical audits, iv) training and capacity building,
        v) third party procurement audits, vi) technical assistance and (vi) the staffing of National Project
        Coordination Unit (NPCU) and County Project Coordination Units (CPCUs).
       Spend Profile:
                   Table 1: Procurement Category-based Spend Profile [Including Contingencies]

No                           Category                           Total estimated Cost in US $ Million

    1     Consultancies and Services                                                                  17.73
    2     Goods, Equipment and Materials                                                               6.70
    3     Civil Works                                                                                 23.26

    4     Trainings, workshops etc. [few of them to be
          procured as Non-consulting services]                                                         8.24
    5     Sub Project Grants                                                                          28.76
    6     Operating Costs                                                                             15.29

                                                      Total                                         100.00

                                                                                                  6|Page
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

   Operational Expenses: The project will also finance from the Bank proceeds for costs associated with operational travel, accommodation, per-diems,
    office consumables and maintenance, motor vehicle maintenance, and remuneration for project implementation support personnel categorized as
    “incremental operation cost1”. These expenditures will not be subject to procurement clearance hence will not be reflected in the approved
    procurement plan. Items under this category would be procured using the implementing agencies’ internal procurement and administrative procedures
    acceptable to the Bank. The expenditure plan under this category will be submitted annually to the Bank for no objection and will be subject to national
    financial audit.
   Trainings / Capacity Development initiatives through the project are not Procurement Transactions unless a service provider is exclusively hired from
    Market through agreed Selection Methods of Consultant / Non-consulting services as appropriate to render training or capacity development. If there is
    no price discovery and the fund is transferred to the communities or to the counties, then these transactions are not part of the procurement plan for
    first 18 months and through Banks’ STEP.

                                                        Table 2: Broad List of Component-based Procurement Activities
Project Components               Description of Activities             Key Procurement transactions – Goods                  Key Procurement transactions –Consulting
      and Sub-                                                         and IT, Works, Non-Consulting Services                               Services
    Components
Component 1: Governance and Management of Marine Fisheries (approx. US$49.8 million)
Sub-Component 1.1:          A. Fishery           Governance              Printing and dissemination of                      Selection of consultants :
Enhance Governance             Instruments                                Policy/legal instruments $160,000                  Selection of consulting firm for Finalization of
of Marine Fisheries         B. Preparation of Marine Spatial             Procurement of hardware and                         National Fisheries Policies etc.$360,000
and Blue Economy               Plan (MSP)                                 software at National and County                    Selection of consulting firm for Marine Special
(approx. US$15.6            C. Fisheries        Management                Governments for Fisheries                           Planning [MSP] $3,940,000
million)                       Capacity, monitoring, data                 Management Capacity, monitoring,                   Selection of Consulting firm for IT-TA
                               collection and Processing                  and data collection $400,000                        consultancy and operationalizing the database
                            D. Specialist    Fishery     and             Printing and Dissemination of the                   $ 540,000
                               Aquaculture      consultancies             Tuna Strategy for Fisheries                        Socio economic assessment of marine
                               and TAs                                    Management Support $20,000                          fisheries $180,000
                            E. Training                                  Hiring of motor vehicles and                       Development of curriculum for fisheries

1“Incremental Operating Costs” means the reasonable costs of incremental operating expenditures incurred during the implementation of the Project, which expenditures would not have
been incurred absence of the Project

                                                                                                                                                                      7|Page
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

Project Components        Description of Activities        Key Procurement transactions – Goods                 Key Procurement transactions –Consulting
      and Sub-                                             and IT, Works, Non-Consulting Services                              Services
    Components
                                                               Motorcycles, at the county and                    training [Bandari college] $60,000
                                                               national levels for Monitoring Control           Development of Strategy & action plan
                                                               and Surveillance [MCS]$750,000                    implementation $330,000

                                                                                                                 Various Individual Consultants through
                                                                                                                 Individual Consultant Selection [ICS].
Sub-Component 1.2:    A. Support       fisheries     co       Printing and distribution of Joint
Improve                  management            technical       Community Management Area                        Selection of consultants
Management of            caucus                                [JMCA]Plans, by-laws, SOPs $100,000             Technical support on CMA guidelines, SoPs, ToT
Nearshore Fisheries   B. Consultations to finalize            Purchase of Patrol and rescue boats$             & performance monitoring $1,475,000
(approx. US$8.3          national CMA guidelines &             360,000                                         Conduct social and ecological survey for JCMAs
million)                 BMU sops                             Purchase of surveillance equipment               $300,000
                      C. Technical support on Co-              $120,000                                        Development of JCMA plans incorporating
                         Management Area [CMA]                Procurement of Co-Management                     priority fisheries FMP management measures;
                         guidelines for SOPs, TOT and          Area [CMA] demarcation equipment,                sensitization of BMU members on co-
                         performance                           data collection and monitoring                   management; development of by-laws
                      D. Development of new and                $450,000                                         $500,000
                         review of existing JCMAs                                                              Review performance of BMUs/JCMAs $100,000
                      E. Joint Community                                                                       Establishment of Bad weather SMS alert system
                         Management Area [JMCA]                                                                 for fishemen $250,000
                         plan and BMU mentoring and                                                            Review performance of BMUs/JCMA $100,000
                         follow up                                                                             Establishment of Bad weather SMS alert system
                      F. Equipment to support JCMA                                                              for fishermen            $250,000
                         implementation
                      G. Review performance of Beach
                         Management Unit
                         [BMU]s/JCMA
                      H. Establishment of Bad weather
                         SMS alert        system for
                         fishermen

                                                                                                                                                   8|Page
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

Project Components          Description of Activities     Key Procurement transactions – Goods           Key Procurement transactions –Consulting
      and Sub-                                            and IT, Works, Non-Consulting Services                        Services
    Components
                       I. Support for establishment
                          and ops IOWB and exchange
                          visits
Sub-Component 1.3:     A. Construction of KEFS building      Construction of EFS building at            Selection of consultants:
Infrastructure            in Nairobi                          Nairobi (UVUVI House) $10,000,000         architectural design & Construction Supervision
Development for        B. Upgrade/Renovate/furnish           Construction of County Fisheries                $1,550,000
Fisheries                 County fisheries                    construction Infrastructure               County Fisheries Infrastructure - Site survey,
Management                infrastructure                      $2,000,000                                 EIA $50,000
(approx. US$25.9       C. National mariculture resource      Construction of Training and              County Fisheries Infrastructure Architectural
million)                  & training center (NAMARET)         Resource Center & Accommodation            and Design Consultancy $100,000
                                                              $1,000,000                                National Marine Resource & Training Centre -
                                                             Procurement of Training equipment          NAMARET- Review / revision or hatchery and
                                                              /furniture $200,000                        laboratory design and supervision of
                                                             Marine Hatchery - Construction of          construction $150,000
                                                              Infrastructure $900,000                   Environmental Impact Assessment
                                                             Marine Hatchery - Culture facilities       (EIA)$20,000
                                                              $200,000
                                                             Procurement of Laboratory
                                                              equipment and Chemicals $500,000
                                                             Construction or upgrading of county
                                                              fisheries infrastructure $8,880,000

Component 2: Coastal Community Empowerment and Livelihoods (approx. US$41.1 million)
Sub-Component 2.1:         Enhanced Coastal                 Printing and Developing IEC -         Selection of consultant:
Enhance Coastal             Communities Livelihoods           Information              Education  Technical Assistants for management of Grant
Community                                                     Communication Materials $330,000       programs $516,000
Livelihoods (approx.                                         Procurement of 20 Motorcycles and 6  Training of Trainers & mentoring consultancy
US$29.1 million).                                             Motor Vehicles $520,000                for PICD $900,000
Sub-component 2.2:         Support Services for             Procurement of Office equipment  Technical Audit for sub projects $500,000

                                                                                                                                            9|Page
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

 Project Components       Description of Activities       Key Procurement transactions – Goods                   Key Procurement transactions –Consulting
       and Sub-                                           and IT, Works, Non-Consulting Services                                Services
     Components
Support Services for      Livelihoods Enhancement           $1,000,000                                          Strategic  partnership    processes     and
Livelihood                                                                                                       engagement $1,000,000
Enhancement and
Capacity
Development
(approx. US$12.0
million).
Component 3: Project Management, and Monitoring and Evaluation (approx. US$9.1 million)
National Level                                            Procurement of Hardware for MIS/ERP            Selection of consultants:
(NPCU)                                                     $66,000                                          Development of MIS / ERP (incl. website)
                                                          Office rehabilitation and furnishing              $66,000
                                                           $100,000                                       Monitoring and Evaluation $400,000
                                                          Procurement of Motor vehicles
                                                           $260,000                                       Selection of Individual Consultant for:
                                                          Procurement of ICT Equipment                     Preparation of a communication strategy
                                                           (Computers/        laptops,       printers,       $40,000
                                                           projectors, and related accessories            Development        of    Citizen's   /stakeholder
                                                           etc.,.) for National Offices - Nairobi and        engagement plan $40,000
                                                           Mombasa $20,000                                Development and operationalization of Plan to
                                                          Developing Information Education                  address GBV and SEA related issues and risks
                                                           Communication         [IEC]      Materials        $40,000
                                                           $59,480
CPIU                                                      Procurement of Motor vehicles (5
                                                           units) $315,000
                                                          Procurement of Motorcycles - County
                                                           Offices [TBC] (10 units) $50,000
                                                          Procurement of ICT Equipment
                                                           (Computers/laptops and accessories)
                                                           for EACH CPIU $100,000

                                                                                                                                                10 | P a g e
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

Project Components      Description of Activities       Key Procurement transactions – Goods     Key Procurement transactions –Consulting
      and Sub-                                          and IT, Works, Non-Consulting Services                  Services
    Components
                                                        Procurement of Boats & accessories (1
                                                         Mombasa; 3 Kilifi; 2 Tana River; 1
                                                         Lamu) $325,000

                                                                                                                                11 | P a g e
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

2 Overview of Country, Borrower and Marketplace
       a. Operational Context
       Kenya at Glance:
       Kenya has an estimated population of about 48 Million (Est 2018) and a geographical area of
       580,367 Sq. km, and is situated in the East of Africa bordering Somalia to the East, Uganda to the
       West, Ethiopia to the North and Tanzania to the South. Kenya’s rapid population growth resulted
       in more than 40% of the population being under the age of 15, making Kenya one of the
       countries in the World with the highest population of young people.
                                                    Table 3: Kenya at Glance: Indicators

                             2004      2015       2016       2017        2018          2019               Remarks
                                                                                                    Progressive
Ease of Doing
                                                                                                    Improvement in
Business (Overall                129   113         92          80         612              56       the ranking with
Ranking 189
                                                                                                    various measures
countries)
                                                                                                    Corruption
Corruption
                                                                                                    perception index
Perception Index3
                                 145   143        145         143         144           145         remains
((Ranking out of
                                                                                                    relatively the
175 countries)
                                                                                                    same since 2004
                                                                                                    There is room for
Competitive Index4
                                 96     90         99          93         99               95       improvement
(Ranking out of 140
countries)
          Governance aspects:
       Kenya functions under democratic governance and has made good progress towards establishing
       a competitive economy. Kenya’s current constitution was enacted on 27th August 2010 replacing
       the old one that had been in place since Kenya’s Independence in 1963. It provides a Structure of
       the Government that consists of The Executive, The Legislature, The Judiciary and The Devolved
       Units of Government. The Executive comprises of the President, the Deputy President, and the
       Cabinet. The Judiciary constitutes of the Supreme Court, the Court of Appeal, and High Court,
       Magistrates Courts, Kadhi Courts and Tribunals. The President is the Head of State and
       Government, Commander-in-Chief of the Kenya Defence Forces, and the chairperson of the
       National Security Council. The 2010 constitution provides for two autonomous but
       interdependent levels of government: national and 47 county governments with mainly elected
       assemblies, elected governors, and governor-appointed cabinet members ratified by the
       assembly. The constitution eliminated the previous third tier of government, the urban and rural
       local authorities, and transferred their revenues and functions to the county governments.
          Economic Aspects

2 Doing Business 2019 Training for Reform; The World Bank, October 2018. ‘Getting Electricity’ Indicator is one out of 10
indicators that comprise the Doing Business Index. In that indicator, out of 190 economies, Kenya jumped from 127 in 2016
to 71 in 2017 reflecting the increased electricity connections during the period. Kenya ranked 75 in the indicator in 2019
3   Transparency International
4
    Global Competitiveness Report published by the World Economic Forum 2018

                                                                                                          12 | P a g e
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

       Kenya is the economic, financial, and transport hub of East Africa. Kenya’s real GDP growth has
       averaged over 5% during the last decade. The Gross Domestic Product (GDP) in Kenya was worth
       US $ 74.94 Billion in 2017. The GDP value of Kenya represents 0.12 percent of the World
       economy. Since 2014, Kenya has been ranked as a lower middle-income country after attaining
       the World Bank threshold of US$ 996 GDP Income per capita. The economic expansion has been
       boosted by a stable macroeconomic environment, low oil prices, rebound in tourism, strong
       remittance inflows and a government led infrastructure development initiative.
       Kenya imports machinery and transportation equipment, oil, petroleum products, motor
       vehicles, iron and steel, resins and plastic [US $ 17.1 Billion in 2017] and exports [in 2017] US $
       6.17 Billion tea, horticultural products, coffee, petroleum products, fish, cement, apparel5. The
       trade deficit of US $ 10.93 Billion.
       Kenya Shillings (KES) is stable and floating around 100 per US$ during previous year. The inflation
       Rate in Kenya averaged 9.67 percent from 2005 until 2019.
       Kenya applies East African Community (EAC) Common External Tariff – In general, Customs duty
       is levied at rates between 0% and 100%, with an average rate of 25%. Regarding the sales tax,
       imports into Kenya are subject to a standard VAT rate of 16%, levied on the sum of the CIF value,
       duty, and other applicable taxes6.
       The macro economic factors are stable. Kenya does not produce key commodities and inputs for
       infrastructure development such as materials for transmission lines, transformers, sub stations,
       and meters. These are the main inputs for the supply and installation. The contractors will
       import these requirements and hence, the Government of Kenya likely to consider in providing
       tax exemption to project, or budgeting should take the taxes in to considerations. This
       exemption may help the project to get economical price and may take additional activities from
       tax savings.
           Sustainability Aspects:
       The project will not use the sustainable procurement options. The detailed feasibility studies
       and business plans increases the sustainability of various initiatives taken up by community and
       county governments. Empowerment would be assessed in terms of the extent to which these
       initiatives specify goals for project-supported activities, implement these activities successfully
       (including the management of their own contributions, if any), and efficiently operate on viable
       business model and maintain the resulting assets. The Ministry is expected to facilitate the
       implementation of envisaged initiatives and build the capacity of the business communities with
       the support of various advisors/service providers hired through various consultancies.
       Each created asset through project funds will be operated and maintained by the respective IAs
       and ensure that created assets are used for designed life span. The IAs keep adequate spares
       and the staff were provided with adequate training
       The Project will use the appropriate bidding documents (Bank’s Standard Procurement
       Documents) and contracts formats, to ensure satisfactory environmental, social, health and
       safety performance of contractors incorporate these conditions. The clauses will cover six issues
       (1) Environment, Health and Safety (EHS); (2) Environmental and social monitoring by contractor;
       (3) Environmental and social liabilities (4) Grievance mechanism for workers’, (5) Gender Based
       Violence (GBV) and (6) Sexual Exploitation and Abuse (SEA).
           Technological Aspects:

5   https://atlas.media.mit.edu/en/visualize/tree_map/hs92/export/ken/all/show/2017/
6   Further details: https://www.kra.go.ke

                                                                                            13 | P a g e
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

   For envisaged Works and Goods, Equipment, Machineries are of standard specifications and
   changes in the technology are gradual. Hence, the variation of price due technological changes
   on the overall price is minimal.
   The community will be implementing various sub projects of small size both in value and
   complexity with different objectives scattered over five coastal counties. The technological tools
   will be helpful for concurrent monitoring, guidance, cross learning, exchange of information
   through platforms and closed groups. The Project will attempt to leverage these technological
   tools (platforms for facilitation, peer discussion and intensive training through boot camps,). The
   technological (ICT / web based) tools will facilitate the implementation of various envisaged
   initiatives and concurrently monitor the progress.

   Key Conclusions:

       (i) Kenya is categorized as Lower Middle Income Non-Fragile Country. Kenya’s real GDP
           growth has averaged over 5% for the last eight years;
       (ii) Kenyan currency is fairly stable since 2015 and the potential foreign providers may opt
            to quote in either local or foreign currency or a combination of both.
       (iii) The Project will use various technological tools and leverage from existing benefits for
             effective implementation
   b. Client Capability and PIU Assessment
   Legal and Regulatory Framework: The Public Procurement & Asset Disposal Act (PPADA 2015)
   sets out the rules and procedures of public procurement by MDAs and County Governments and
   provides mechanisms for enforcement of the law. Under the PPADA, the Public Procurement
   Regulatory Authority (PPRA) has been established in addition to the Public Procurement
   Directorate in the National Treasury. The PPRA has oversight and regulatory functions, including
   undertaking procurement reviews and audits. There is a Public Procurement Complaints
   Administrative Review and Appeals Board (Appeal Board) under the secretariat of PPRA that
   deals with complaints received from bidders or consulting firms following national market
   approach. The provisions of PPADA have been assessed and found to be largely consistent with
   the World Bank Procurement Regulations, Section V, Para 5.4, National Procurement
   Procedures. However, the delay in issuing the attendant Regulations may affect the
   implementation of the project for contracts following the national market approach.
   The proposed project’s implementing agency at the national level is the Ministry of Agriculture,
   Livestock, and Fisheries (MoALF) with its State Department for Fisheries, Aquaculture, and the
   Blue Economy (SDFA&BE) having the overall project implementation responsibility. A national
   project coordinating unit (NPCU) would be established in Nairobi to manage and coordinate
   project implementation activities. The five coastal counties (Kwale, Mombasa, Kilifi, Tana River,
   and Lamu) would be responsible for carrying out specific activities at the county level.

                                                                                          14 | P a g e
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

    The project will be implemented by the fully staffed NPCU and CPIUs at the Ministry and County
    levels respectively. The national NPCU however, would be responsible for overall coordination
    and project/contract management. The NPCU led by a project coordinator, will include technical
    fisheries experts, and fiduciary (Financial Specialist and Procurement Specialist), M&E, and
    environmental and social safeguards staff. The technical implementation is at the national and
    local levels. At the national level, a NPCU has been established with a full-time procurement
    officer who is supported by an experienced procurement consultant conversant with Bank
    Procurement Regulations and procedures and the use of STEP. The NPCU is currently
    implementing a PPA of US$2 million and most of the activities to be undertaken are at advanced
    stages of procurement and/or implementation. The Bank has provided the requisite training and
    capacity building on the Bank’s Procurement Regulations and use of STEP to the NPCU staff.
    Although at the County level most activities will follow the national market approach hence use
    of national procurement procedures, basic training on implementation of Bank financed
    operations and the use of STEP will be necessary.
   Community Procurement: The Project will provide support to each county for capacity building
    and institutional strengthening through a standard package of goods, equipment and training.
    CPIUs (through county field officers) or staff from the productive alliance partnerships will also
    provide support to communities in organizing smallholder fishing and non-fishing households
    into common interest groups (CIGs) for the participatory identification and preparation of
    livelihood, social or environmental sub-projects. Community sub-project support would be
    provided to beneficiaries organized into CIGs to be formed in the 19 coastal sub-counties of the
    five project counties. The roles and responsibilities for the implementation of sub-projects by
    CIG is outlined in a tripartite Memorandum of Understanding (MoU) to be signed between the
    SDFA&BE, the county and each partner, prior to initiating implementation. CDD approach using
    simplified procurement methods and arrangements to be elaborated in the relevant manuals
    including the PGM, PIM and procurement manual, to be approved by the Bank and made
    publicly available by the GoK. County interventions and support to community activities will also
    be defined in the PGM. As the considerable amount spend through community sub projects [ US
    $ 28.76 million Sub project grants, the scope of internal audit includes the post procurement
    review of representative sample including physical inspection and submit report to NPCU. The

                                                                                        15 | P a g e
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

     NPCU will consolidate financial year wise report and submit to the World Bank within Two
     months after completion of Financial Year. Besides, this oversight the county offices will
     undertake periodic monitoring [procurement] of these sub projects. The procurement specialist
     at NPCU is responsible for overall procurement monitoring of the project procurement activities
     including contract management in liaison with the concerned officers at various levels.
      Experience
     The MOALF has previous experience in implementing World Bank-financed projects, having
     implemented many Bank financed operations in the past, including the ongoing National
     Agriculture and Rural Inclusive Growth (NARIG) and Kenya Climate Smart Agriculture (KCSA)
     Projects. However, the State Department of Fisheries, Aquaculture and the Blue Economy is new
     and most of the staff do not have prior experience in implementation of World Bank funded
     projects, in particular in the application of the Procurement Framework [NPF]. The predecessor
     of the SDF-BE implemented the Kenya Coastal Development Project [P094692] that was closed
     on June 30, 2017. The institutional memory however was not retained due to change of staff
     that were involved in the implementation of the KCDP project. The implementation of the KCDP
     was initially characterized by substantial delays, partly due to weak procurement capacity. The
     lessons learnt will be incorporated in the design of this project. Part of the risks have been
     mitigated by hiring of an experienced procurement specialist to support the proposed project’s
     preparation and implementation of the PPA. It is also envisaged that experienced procurement
     specialists will be deployed to all the five counties’ CPIUs.
      Need for hands-on support:
     As mentioned above, project is already engaged a qualified and experienced Procurement
     Specialist at NPCU to provide hands-on support in articulating project procurement with the help
     of Procurement Specialists at the County Governments. The Project may seek Bank’s guidance
     on complex procurements. Hence, hands-on support is not required.
      Contract management capability and capacity
     Supported by a fully staffed NPCU and CPIUs, the ministry will be responsible for overall
     project/contract management. High risk and high value procurements will be identified for
     increased contract management support and will be identified in the procurement plan. The
     NPCU has already developed a set of key performance indicators (KPI) for such identified
     contracts and the KPIs would be monitored during actual execution of contracts. The Bank team
     will provide additional due diligence and independent review of contract performance of such
     identified procurements.
     In view of the fact that MoALF is not familiar with procurement and contracting of construction
     works envisaged in Sub-component 1.3. to support the NPCU, a consulting firm will be selected
     to provide the planning, architectural design and construction supervision services. The Design
     and documentation phase of the consultancy assignment will be a Lump sum form of contract
     and payment will be based on the deliverables. The construction supervision phase will be Time
     Based, and the payment is based on the direct inputs. The NPCU will ensure that the payment
     terms are balanced and devoid of front loading. This procurement approach will ensure that the
     design consultant is accountable for their design/solution, minimizes the design revisions after
     identification of the contractor, and subsequent contractual variations (cost and time overrun).
     Besides, NPCU may hire need based contract management specialist cum civil engineer with
     specialisation of construction of building and other type of works envisaged through the project
      Complaints management and dispute resolution systems
     The NPCU will establish systems and mechanisms for addressing and escalating their grievances
     and complaints as outlined in the PIM. A consultancy is envisaged through the project to provide

                                                                                        16 | P a g e
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

   advice on institutionalisation of complaints and dispute resolution mechanisms throughout
   project implementation.
   The contacts of key persons involved in the project implementation with their contact details will
   be disclosed at strategic places within the ministry accessible to the public. The disclosure will
   also prescribe the number of days for resolving grievances/complaints at each level. In addition,
   the Public Procurement and Asset Disposal Act 2015 also provides the option for submitting the
   procurement related complaints to the Public Procurement Administrative Review Board.
   The Communities and individuals who believe that they are adversely affected by a World Bank
   (WB) supported project may submit complaints to existing project-level grievance redress
   mechanisms or the WB’s Grievance Redress Service (GRS).

                           Key Conclusions:

   (i) Kenya has a legal and regulatory framework that governs public procurement enacted in
       December 2015 which provides for open advertisement of procurement opportunities,
       universal eligibility, and an effective complaint handling mechanism hence conducive for the
       participation of international/foreign service providers;
   (ii) The NPCU has limited experienced and working knowledge of Bank’s procurement
         procedures and the procurement and management of high value and complex consultant
         assignments. Enough technical support and handholding in the initial stages of project
         implementation will therefore be critical.
   (iii) MoALF and SDF-BE is not a live department dealing with procurement and contract
         management on a day to day basis. The procurement activities were involved only during
         the developmental projects.

   c. Market Analysis
   Supply Positioning Model — Identify the risk and value thresholds of the project
High                                                                                                                High
                               Strategic Critical                        Strategic Core
                                  Hiring hatchery training specialist      Selection of consultant for Marine
                                   for NAMARET US $ 400,000                  Special     Planning    [MSP]     US
                                  Selection of consulting firm for          3,940,000
                                   Development of JCMA plans US $           Selection of consulting firm for
                                   500,000                                   Technical     support     on CMA
   Risk or Vulnerability

                                  Selection of consulting firm for          guidelines,     SoPs,      ToT     &
                                   Establishment of Bad weather              performance monitoring US $
                                   SMS alert system for fishermen $          1,470,000
                                   250,000                                  Construction or upgrading of
                                  Procurement of hardware and               county fisheries infrastructure $
                                   software at National and County           8,800,000
                                   Governments for Fisheries                Construction of EFS building at
                                   Management Capacity,                      Nairobi (UVUVI House) US $
                                   monitoring, and data collection           10,000,000
                                   US $ 400,000; and Procurement            Construction of County Fisheries
                                   of Office equipment US $                  construction Infrastructure US $
                                   1,000,000 [Same process with              2,000,000
                                   different schedules]                     Construction of Training and

                                                                                                           17 | P a g e
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

                                  Procurement of Laboratory              Resource Center & Accommodation
                                   equipment and Chemicals US $           US $ 1,000,000
                                   500,000                             Marine Hatchery - Construction of
                                Selection of consulting firm for         Infrastructure US $ 900,000
                                   Finalization of National Fisheries  Selection of consulting firm for
                                   Policies US $ 360,000                  architectural design & Construction
                                Selection of Consulting firm for         Supervision US $ 1,550,000
                                   IT-TA consultancy and
                                   operationalise the database $
                                   540,000
                               Tactical Acquisition                   Tactical Advantage
                                   Developing Information              (1)    Purchase of Patrol and rescue
                                   Education Communication [IEC]       boats US $ 360,000, and Procurement
                                   Materials                           of 20 Motorcycles and six motor
                                                                       vehicles US $ 520,000 for National and
                                                                       Procurement of Motor vehicles 5 units
                                                                       US $ 315,000 for Counties [Same
                                                                       process with different schedules]

                                                                       (2)    Procurement of Boats &
                                                                       accessories (1 Mombasa; 3 Kilifi; 2
                                                                       Tana River; 1 Lamu) US $ 325,000
Low                                                      Estimated to Cost / Value                              High

         Market sector dynamics
       The envisaged procurement transactions comprises of works construction mainly construction of
        Construction of EFS building at Nairobi (UVUVI House) US $ 10,000,000
           and rehabilitation of buildings and supply of various equipment / goods. As per the National
          Construction Authority, adequate number of contractors are available in the Kenyan market.
          For equipment, vehicles, and ICT hardware & software, no domestic manufacturing capacity
          or facility to produce these Goods, Equipment and Machineries. The bidders import the
          equipment / goods and provide the after sales support. The country has a large market of
          qualified and experienced local and foreign consultancy firms in all sectors, and association
          between local and foreign firms is a common feature in situations where firms come together
          to enhance their capacity. .
          The potential bidders/proposers may treat the bidding opportunities under the project as
          strategic, given that Kenya as gateway to other land locked countries, the participation and
          winning of contracts in Kenya is perceived as an opportunity for further expansion.
          Contractor/Consultant preferencing matrix
          High
           Attractiveness of

                                       Development                         Core
                                       -   Pool of International           Pool of International contractors are
                                           consultants are available and   available and may likely associate with
           account

                                           may likely associate with       international /national contractor(s)
                                           national consulting firm as     as JV to carry out the Works and bring
                                                                                                                        High
                                           their associate to enhance      on board local experience and the

                                                                                                         18 | P a g e
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

                         their capacity to win business potential     to        win      business
                         opportunities                  opportunities

                     Nuisance                             Exploitable
                     -   None                             -   None
                                              Relative value of account
     Low

    Financial
     Business risk in Kenya is generally considered to be ranging from moderate to low. . The
     Kenyan Shilling is a relatively stable currency while the bidders are free to quote in any freely
     convertible currency including the national currency. Foreign currency availability and
     repatriating forex is not difficult. Banking and financial institutions are well developed and
     operating internationally. Bid prices are generally competitive. The country being East African
     Economic hub, having good proximity to major global markets, with good internet and
     telephone connectivity; recent commencement of operation of the Standard Gauge Railway
     [SGR] services from Mombasa to the capital, …etc would make Kenya attractive to do
     business.. However, limited access to and high cost of working capital affects the development
     of domestic contractors with interest rates exceeding 13 % based on 2018 figures. . Due to
     lack of sufficient financial resources, their capability to withstand effects of delayed payment
     is limited. To improve the domestic contracting capacity, various policy improvements are
     required to create an enabling environment.
    Procurement trends: The NPCU has procured various procurements through Project
     Preparatory advance [PPA]. The Table 5 provides the list of contracts, number of participation
     and procurement lead time.
    Potential Contractors in National Market:
     As per the National Construction Authority’s [NAC] data base, the registered contractors are
     graded and categorized into 8 categories. It is evident from the chart shown below that there
     are adequate number of contractors in the market.

                                                                                        19 | P a g e
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

        Table 4: List of Registered Contractors with National Construction Authority of Kenya : 2018

                  Category of Contractors Registered with NCA of Kenya
        1400
                                                                           1235
                                                                                     1186
        1200

        1000

         800
                                                                   627
                                                                                                  Total
         600

         400
                                                        237
                                                 177
         200
                  20       15        30
           0
                NCA 1     NCA 2    NCA 3     NCA 4     NCA 5      NCA 6    NCA 7    NCA 8

      Potential Consultants:
         Table 5: Level of Participation for Consulting opportunities through KEMSSED PPA

                                                                                     Proposal
                                       Name of            Contract Cost        Open/National and          Lead Time
 No      Contract Description
                                      Consultant             in US$                 number of              Months
                                                                              applicants/proposers?

                                                                                                 #7
        Review of the state of                                                                               3.50
        stocks of priority          Dr. Philippe
C001
        fisheries in Kenya to       Lallemand                 50,292.00
                                                                                      National
        inform infrastructure
        and value addition
                                                                                             #4
        Scoping study on                                                                                     4.0
                                    Dr. Julian
C002    status of marine spatial
                                    Roberts                   37,330.00
        planning in Kenyan                                                           National
        waters
                                                                                             #5
        Rapid Assessment of                                                                                   2
        fisheries and
                                    Dr. Constantine
C003    aquaculture
                                    Stamatopoulos             64,992.00
        information                                                                   National
        management system
        (FIMS)
                                                                                                  #6
        Development of                                                                                        3
                                    Dr. Bernard M.
C004    baseline to measure
                                    Fulanda                   51,980.00
        project outcomes on                                                           National
        governance and

                                                                                              20 | P a g e
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

        management
        effectiveness
                                                                                              #6
        Institutional                                                                                   2.5
                                   Mr. Arnold
C005    Assessment for project
                                   Omondi Menya         40,349.50
        implementation of                                                        National
        KEMFSED
                                                                                              #6
C006    KEMFSED Project Team       Rose Koboge                                                          6
                                                        72,000.00
        Leader                                                                   National
                                                                                             #18
        KEMFSED Project            Benedict                                                             6
C007
        Financial Management       Olwenyo              48,000.00
                                                                                 National
        Consultant
                                                                                             #12
        KEMFSED Project                                                                                 6
C008                               John Mugo
        Procurement                                     48,000.00
                                                                                National
        Consultant
                                   Multiface
                                                                                           #8
        Preparation of             Research                                                             9
        Environmental and          Development
C009
        Socio Safeguards           Centre in JV         264,184.20
                                                                                i National
        Instruments                with Spantrack
                                   Consultant Ltd
        Intervention portfolios
                                   Capital                                                              9
C010    To Increase Value in
                                   Guardians            133,903.00
        Selected Marine Areas                                                    National
        Mariculture Scoping        Advance Africa                                            #6
C011    Study with respect to      Management                                                           9
                                                        108,346.32
        Kenya Marine Waters        Service                                      National
        Strategic Approach for
                                                                                            # 13
C012    Enterprise                 AESA EA Ltd                                                          9
                                                        72,244.80
        Development                                                              National
        Preparation of Project                                                             #8
                                   Jacob Okidi                                                          2
C013    Grant Manuals and
                                   Omolo                47,118.00
        Translation to Kiswahili                                                 National

                                                      10,38,739.82

The similar trend of participation is seen from the other projects in Kenya for supply of Goods.
It is evident from the above table that the there is no perceived suppliers’ risk for the procurement
envisaged under the project. The list of participated bidders for C009, C010, CO11, CO12 is provided
in the Annex 2: List of Consultants Expressed Interest for the consulting opportunities through the
Project.

Key Conclusions:

                                                                                        21 | P a g e
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

(i) There are sufficient potential service providers available in the market (national as well as
    international) to render services like Marine Spatial Planning, Design & Supervision consultants,
    and ICT/ERP implementation. No perceived suppliers’ risk for the procurement envisaged
    through procurement transactions.
(ii) For Works (fisheries infrastructure), the contractors are available in the national market as per
     the National Construction Authority of Kenya;
(iii) Many of the Goods or marine specific equipment are not manufactured in Kenya and need to be
      imported.

3 Procurement Risk Analysis
                                    Table 6: Procurement Risk Analysis

Risk Description         Description of Mitigation                                     Risk Owner

Difference in Kenya         The selection methods followed for all project            NPCU SDF-BE
Government                   procurement will be in accordance with the Bank           and MoALF
procurement                  Procurement Regulations [applicable version]. The
System and Bank’s            Ministry of Agriculture, Livestock, and Fisheries
procurement                  [MoALF] will adhere to the Bank’s Procurement
Framework [NPF]              Regulations for all the project procurement. If any
                             inconsistencies between the FA and PPAD Act 2015 &
                             associated Regulations, the FA will prevail.
                            A Project Implementation Manual is being developed
                             for day to day reference.

The project will be         Already deployed a procurement specialist at NPCU.        MoALF and
the first in the state      During the first six months, deploy Procurement           County
department to                Specialist the Five project counties.                     Governments
follow the Bank’s           Provide orientation on NPF to key project functionaries
procurement                  at PCU and at the county level; Need based refresher
framework (NPF) in           courses in procurement may be conducted at regular
its implementation           intervals.
MoLAF and SDF-BE            Train Procurement Specialist in contract management       NPCU SDF-BE
is not a live               Hire a civil engineer cum contract management             and MoALF
department dealing           specialist for management of all envisaged Works and
with procurement             related design and supervision consultants
and contract
management on a
day to day basis.
The procurement
activities were
involved only during
the developmental
projects

Procurement profile
include a major
Building work and
other construction

                                                                                         22 | P a g e
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

Risk Description        Description of Mitigation                                     Risk Owner
activities.
Decentralized level        At the community level, Goods and works procurement       NPCU and
activities to be            shall not exceed RFQ threshold and shall be in            County
carried out by the          accordance with the CDD arrangements provided in the      Governments
Beneficiary                 Bank Procurement Regulations. The procedure is
/community level            detailed out in the Project Grant Manual [ PGM ] and
and oversight               Project Implementation Manual [PIM]
mechanism                  Standard specification and standards (marine, if any)
                            for Goods defined by will be the basis for Beneficiary
                            purchasing goods from the open market.
                           As part of due diligence appropriate authority assigned
                            by Ministry shall sign off to ensure compliance by the
                            Beneficiary in purchasing as per the defined
                            specification from open market for Goods and technical
                            compliance. A common specification will be developed
                            for common requirement and where ever possible,
                            Framework Agreement will be used. In regard to works,
                            detailed work description and drawings to be
                            developed [as these are rehabilitation and repair type]
                            and ensuring its physical inspection [photographs
                            before repair and after repair].

Multiple levels of         The NPCU in MoALF being the nodal agency will             NPCU
implementation,             monitor the contractual performance of major
many players,               procurements including contract management at all
multiple type of            levels.
activities. The            The PCU also monitors and provides guidance and
procurement profile         oversight in regard to community level procurement
is mix of small value       with the support of a customized MIS.
at community and
high value at NPCU.        Each county will undertake the post procurement
                            review as part of the Internal Audit and submit county
                            wise report to NPCU. The NPCU will consolidate
                            financial year wise report and submit to the Bank with
                            first two months after closure of Financial Year

Efficient purchase         Capacity building of the Procurement committee at the     NPCU
of goods,                   community level for CDD procurement.
equipment and              The NPCU and CPCU will develop the specification of
small works at              standard goods / common requirement across
community level.            community and wherever possible, use the Framework
                            agreement, which minimizes the procurement efforts.
                           The County governments shall carry out training of
                            trainers and ensure appropriate availability of
                            resources for carrying out capacity building of the
                            purchase committee who are responsible for
                            procurement at the community level.

                                                                                        23 | P a g e
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

Risk Description      Description of Mitigation                                    Risk Owner
                         The Procurement Specialists at County at NPCU and
                          County level are responsible for overall training and
                          monitoring

Ensure Delivery of       Guideline issued by GoK for purchase of only             NPCU and
quality goods and         appropriate standard (Marine) certified Goods and        County
proper after sales        Equipment’s with standard warranty and guarantee         Government
service and use of        and after sales service followed by technical and        and
the goods                 physical verification by cluster assistance. The         Community
purchased.                Community may be sensitized through capacity             organisations
                          development.
Procedural delays        It is proposed to monitor and track the community        NPCU, CPIUs,
for beneficiary           procurement and overall implementation status under      County
Fisheries/Beach           the scheme through robust MIS.                           Government,
committees on                                                                      and
                         Deploying competent staff (preferably with prior
selection,                                                                         Community
                          experience in the Bank funded projects) for hand
verification of                                                                    organisations
                          holding support and monitoring after initiating the
installations and         project
disbursement of the
grants may affect
the achievement of
targets planned.
Oversight of             The Terms of Reference (ToR) for Internal Audit          NPCU
procurement               includes review [post procurement review of
carried out at            representative sample] of the compliance with agreed
decentralized level       procurement procedure as per the agreed Bank’s
                          Procurement Regulations and Procurement
                          Implementation Manual. The ToR also includes physical
                          verification of infrastructure / Goods procured by
                          Beneficiary /community on sample basis. Alternatively,
                          this may be carried out by an independent
                          procurement consultant hired under the project. GIS
                          tagging of assets may be explored.
    For implementation of the KEMFSED, the project procurement is as per the following
    Procurement arrangements:
    a) Carry out the project procurement activities in accordance with the World Bank
        Procurement Regulations for IPF Borrowers [Procurement Regulations] – July 2016, updated
        in November 2017 and August 2018. Operational
    b) Initiate the procurement process only after obtaining no objection from the World Bank to
       Procurement Plan [PP]. Enter the PP through World Bank’s portal Systematic Tracking of
       Exchanges in Procurement [STEP] and update the PP at least annually. Update the PPSD, at
       least annually or whenever there are substantial changes in the PP; Submit updated PPSD to
       the Bank for seeking concurrence before changing the PP in the STEP.
    c) Use the Bank’s SPDs for Goods, Non-Consultancy Service and Works and Bank’s SRFP for
       Consultancy services;

                                                                                     24 | P a g e
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

   d) Publish the contract award details in the suppliers.go.ke or eProcurement platform and in
      the IAs official websites;
   e) Adhere to the Prior / Post Review thresholds are prescribed in the Procurement Plan for first
      18 months and subsequent revisions as per the Bank’s instructions
   f)   Extend the necessary cooperation for conducting Bank’s post procurement review or any
        other reviews desired by the Bank including complaints cases if any. The IAs uploads all
        relevant procurement documents to the STEP portal; and
   g)   Maintain a separate complaint registers and procedure for redressing grievances and
        complaints, if any.

4 Procurement Objectives
  (i) Update/upgrade PP periodically and update the PPSD, whenever substantially changes or at
      least annually.
  (ii) In accordance with agreed Procurement Regulations, Select and deploy credible, qualified and
       experienced contractors, suppliers, and consultants / service providers to collaborate with
       Project as partners for the accomplishment of PDOs;
  (iii) From procurement perspective, contribute to the task team in the preparation of
        comprehensive ToRs and associated detailed cost table & budget for all envisaged consultancy
        transactions;
  (iv) Complete the procurement processes and award the contracts within initial validity period
       without seeking extension of the bid / proposal validity;
  (v) a Carry out procurement monitoring regularly & periodically to review the performance of all
      contracts and ensure that the tasks are completed on time, and without cost overruns, and
      with minimum change in scope;
  (vi) Provide training and capacity building to the key project staff on the Procurement Framework
       and Procurement Regulations including members of adhoc evaluation committee members;
       and
  (vii) Provide timely and effective procurement advice at all times throughout project
        implementation.

        Procurement Result Indicators [KPIs]

 Selection of Consultants: Should not take more than 6 months for competitive selection
 Procurement of Works/Goods/Non-Consulting Services: Should not take more than 6 months for
   international open procurement; more than 4 months for national open procurement.
 Contract Management: 80% of the Contracts are completed within initial stipulated time,15% of
   the Contracts are completed within 150% of the initial completion period including EOT and 5%
   of the contracts are completed 200% of the initial completion period including EOT (Extension of
   time).

                                                                                          25 | P a g e
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

5 Recommended Procurement Approach for the Project:
              For Works: The Works activities envisaged under the project comprise of construction of
              buildings and other small infrastructure facilities. The specification are of a standard nature and
              as per the national building laws and regulations.

                      1. Construction of EFS building at
                         Nairobi (UVUVI House) $10,000,000     Specifications: Standard
                      2. Construction of County Fisheries
                         construction Infrastructure           Contract: Traditional
                         $2,000,000
                      3. Construction of Training and Resource Pricing: Bills of Quantities / Admeasurement
                         Center & Accommodation in
                                                                   These will be procured through Request
                         Mombasa $1,000,000
                                                                   For Bids [RFB], Traditional Contract type,
                      4. Marine Hatchery - Construction of
                                                                   fixed Price [many of them are less than
                         Infrastructure $900,000
                                                                   18 months of construction period], Open
                      5. Marine Hatchery - Culture facilities
                                                                   National with Single stage and Single
                         $200,000
                                                                   Envelope [both technical and financial].
                      6.

                      7. Construction or upgrading of county            These may be scattered small value
                         fisheries infrastructure $8,880,000            construction activities. The nature of
                                                                        these activities are likely be repair and
                                                                        rehabilitation. Hence, these will be
                                                                        packaged county wise. Very small works
                                                                        at community may be excluded from the
                                                                        package

For All Major Works:
Attribute
Category

                            Attribute              Selected                          Justification
                                                   Approach

                    1.1                          Conformance      Contractors would be selected based on their
                          Specifications/quali                    competence and qualifications [post] commensurate
  1. Requirements

                    fications                                     with the scope & complexity of work. The works
                                                                  contract will have complete detailed design and
                                                                  specifications that should be met during
                                                                  construction.

                    1.2 Additional               Not Applicable
                    sustainability
                    requirements

                                                                                                      26 | P a g e
PPSD: P163980 Kenya Marine Fisheries and Socio-Economic Development (KEMFSED)

Attribute
Category                        Attribute             Selected                              Justification
                                                      Approach

                                                                       The nature of the works, quantities and
                         2.1 Contract type         Traditional/ad       specifications are well defined (client has detailed
                                                   measurement          design prepared by design and supervision review
                                                                        consultants).
                                                                       No innovations or new technologies expected,
                                                                        Client I not having experience. Hence, the Design
                                                                        and Supervision Consultant will be hired.
                                                                       Estimate of quantities will be available from
                                                                        detailed engineering design review, for fair bid
                                                                        competitions, while actual quantities will be paid
                                                                        based on contractual unit prices.

                         2.2 Pricing and costing   Bill of            Scope of works is defined in the design, comparing
                         mechanism                 Quantities         unit price offers, identification of unbalanced pricing,
                                                   comprising unit    abnormally low tenders, management of variations,
                                                   price and total    and so on and will be better managed.
                                                   price

                         2.3 Selection of cost     Unit price and     In traditional contracts, timely and quality contract
  2. Contract strategy

                         and price mechanism       total price        delivery responsibility/risk is of the contractor while
                                                   exclusive of       design change risks are of the employer and unit
                                                   applicable         price is appropriate.
                                                   taxes, but
                                                   inclusive of
                                                   costs covering
                                                   defect liability

                         2.4 Supplier              Collaborative      Best option given scattered location [except UVVI
                         relationship                                 House] and multitude of challenges

                         2.5 Price adjustments     Percentage/ind The contracts periods are more than 18 months.
                                                   exes
                                                                  Compensation for price changes during
                                                                  implementation period.

                         2.6 Form of contract      World Bank         The market are well accustomed to this form of
                         (terms and conditions)    Standard           contract. Employer needs support through a
                                                   Procurement        dedicated civil engineer [as the Ministry is not a live
                                                   document           department]

                                                                      This form of contract, which is part of the SBD, has
                                                                      been well updated over the years to reflect
                                                                      cumulative experience.

                                                                      Risk allocation is for a party who is in a better

                                                                                                               27 | P a g e
You can also read