References List 2008 2021 - Inprocess
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Document Control
Document Title Inprocess References List 2008 - 2021
Date 23 June 2021
Document Reference 2021.3
Author Josep Anton Feliu/Mar Prada
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 2Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Process Company
Project Type Customer Project Title Year Country Industry Short Description
Simulator Type
Inprocess delivered a dynamic simulation study in order to
German analyze the dynamic behavior of a 3-stage compressor
Dynamic Aspen Equipment
Compressor DSS for Gas Turbo 2021 Qatar Oil & Gas driven by a gas turbine with speed variation for various
Simulation Study
Manufacturer for Compressors for an HYSYS Manufacturer transient operations. The simulation scenarios evaluated the
for Compression
a Qatar oil upstream field adequacy of the antisurge valve sizing, the ESD valve
Systems
company requirements, this may be hot or cold gas as needed as well
as the confirmation settle-out conditions of the system.
Inprocess developed a dynamic simulation model in Aspen
HYSYS of the compression system with the objective of
determining its adequacy and the need for any additional
protection system that might be required. Therfore,
German Inprocess analyzed the adequacy of the anti-surge valve
Dynamic Simulation
Dynamic Compressor Aspen Equipment size and its timing to avoid surge during the compressor
Study for the 2021 Iraq Oil & Gas
Simulation Study Manufacturer shutdown; we evaluated the requirements of a hot/cold gas
treatment HYSYS Manufacturer
for Compression (US Office) for bypass valve; we confirmed the settle-out conditions of the
compressors in an
Systems an Iraq oil& field system; we demonstrated the effectiveness of the control
oil field
operator system in different scenarios such as variation of the feed
gas pressure, turndown or blocked outlet; we performed the
compressor system start-up to validate the start-up
procedure, confirm the process control performance, verify
the trip settings and identify possible limitations.
Inprocess helped the client in the development of a steady
state simulation model of the triple effect evaporator system
to be used by client to improve the understanding of the
Japanese Petrochemic process, its constraints and interactions, in order to improve
Steady State Model Aspen the current and future operation of the triple effect columns.
Steady State Multinational 2021 Spain Operator als; Bulk
development of the
Simulation Petrochemical HYSYS The project was carried out in three phases: a) To study the
triple effect Chemicals
Modelling Study company historical data of the plant during one-year and looking for
evaporator
(Spanish site) issues or bad operations; b) To build a steady state model of
the plant, the model was calibrated to a representative day;
c) To analyse with the model a number of operational
scenarios
Inprocess will adapt its Historian_Link application to the
German needs of this client, operator of an FPSO in the Danish
Connection of an UniSim Instrumentatio
Instrumentation 2021 Denmark Oil & Gas sector of the North Sea, who wants to connect the OTS that
Operator Training Operator Training
Provider for a Design n Provider Inprocess is currently developing for them with the historian
System (OTS) System to the plant
French Oil&Gas database in a way that it is possible to upload operating
Historian database
Operator conditions recorded in the historian and use them as initial
conditions for an OTS exercise
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 3Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Process Company
Project Type Customer Project Title Year Country Industry Short Description
Simulator Type
Inprocess has developed an Operator Training Simulator
(OTS) for Ascensus Specialties’ hydrogen producing plant
located in Elma, Washington (USA).
This hydrogen plant is part of the Ascensus production plant
that meets the growing, global demand for high-quality
Sodium Borohydride, reactive and alkali metals, boranes,
and related chemical compounds.
Inprocess project comprises the design, engineering,
Development of a delivery, testing and installation of the OTS, as well as
direct-connect OTS Aspen Fine training scenarios and project management. For the
Operator Training US Chemicals 2021 USA Operator
for a steam-reformer HYSYS Chemicals execution of this project, Inprocess has been using Aspen
System (OTS) Company
hydrogen producing HYSYS® Dynamics as the process simulation engine,
plant Emerson’s SimulatePro as the DCS emulation package, and
Inprocess Infrastructure Suite (IIS) to provide all the required
data connectivity and instructor functionalities.
This Direct-Connect OTS by Inprocess utilizes a high-fidelity
dynamic model of the process, including the following plant
areas: Natural Gas Preparation, Catalytic Reformation
furnace, Catalytic Shift conversion, PSA, Vent Gas
Recovery, Waste Heat Recovery/Steam Generation, and
Water Treatment.
Inprocess is in charge of developing the emulated OTS that
will comprise the processing facilities and their associated
Operator Training utilities of four Habshan fields.
Implementation Simulators for four
Services processing facilities Aspen Consulting & The Operator Training Simulator OTS will be developed for
Operator Training 2021 UAE Oil & Gas the main process units in Habshan 0, Habshan 1, Habshan
Provider for a (and their HYSYS Services
System (OTS) 2 and Habshan 4; as well as their associated Utilities. The
UAE National Oil associated utilities)
Company in four Emirates scope for this project includes the complete delivery and
oil&gas fields commissioning of the OTS including design, development,
engineering, configuration, training, and commissioning
activity for this emulated ABB 800xA
Simulation for new Taking advantage of the dynamic simulation model
Dynamic FPSO Operator throttle valve Aspen developed for the OTS currently in use in the FPSO, our
2021 Ghana Operator Oil & Gas
Simulation in a WestAfrican upstream High HYSYS client requested us to carry out additional operability
Modelling Study field Pressure Fuel Gas analysis of the throttle valve located upstream of the
Compressors compressors in the high pressure fuel gas system.
In-House Technical This german refinery operator requested one of the
Steady State German Support during the Aspen Inprocess engineers to work on-site to provide Technical
2021 Germany Operator Refining
Simulation Refinery development and HYSYS Support to the refinery engineers during the development of
Modelling Study Operator usage of the refinery the Steady State model of the refinery unit and as well to
unit SS model monitor its usage and the benefits obtained from it.
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 4Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Process Company
Project Type Customer Project Title Year Country Industry Short Description
Simulator Type
Dynamic Simulation Aspen Revalidation by dynamic simulation of some of the valves in
Flare Systems Study to revalidate 2021 Belgium Operator Refining this Belgian refinery
Belgian Refinery HYSYS
Analysis the NC3 valves in
the refinery
Dynamic Japanese FPSO Dynamic Simulation OLGA 2021 USA EPC Oil & Gas Dynamic Simulation Study to analyze the operational
Simulation constructor Studies for the behaviour of the subsea lines that connect the many
Modelling Study (USA office) FPSO subsea lines wellheads with the FPSO
The simulation project main purpose was to deliver to the
EPC the results of the dynamic simulation studies in order to
evaluate (with the new data, after an improvement study to
Dynamic Simulation optimize the operating modes and to increase the NH3 and
Study for a Steam & Aspen Bulk Urea production) the response of the system and the
Dynamic 2021 Qatar EPC suitability of the protective controls and devices currently
Power Generation
Simulation Italian EPC HYSYS Chemicals
System in an installed in the Steam & Power System.
Modelling Study
Ammonia and Urea To validate the planned strategy, it was considered
complex necessary to carry out operating tests using an already
existing dynamic simulation model for both Steam and CO2
Networks, after updating and improving it, before carrying
out the necessary series of simulation scenarios.
Update and
improvement of an Aspen
Dynamic 2021 Italy EPC Natural Gas An existing dynamic model already built and delivered by
existing dynamic
Simulation Italian EPC HYSYS Inprocess in a different framework was required to be
simulation model
Modelling Study udpated for a different client application
already develivered
by Inprocess
Brazilian Training Simulator Aspen Bulk Inprocess entered into a framework agreement with client to
Operator Training Chemical for the chlorine 2021 Brazil Operator develop a series of training tools based on dynamic
HYSYS chemicals
System (OTS) Company processing system simulations (OTS). The initial project has been to develop an
in a VCM complex OTS for the chlorine processing system in the VCM plant
PDH plant in the
Inprocess has developed a Digital Twin (rigorous dynamic
Spanish site of a Aspen Petrochemic
Online Digital Twin 2021 Spain Operator simulation model) of two units of the PDH complex
Online German
for the depropanizer HYSYS als (depropanizer and C3 splitter) and has connected it online
Appplication chemicals
unit in the PDH plant with the instrumentaiton database. The DT will then serve to
company
monitor equipment performance and to run what-if studies
Migration of an
Process Bulk Client decided to change the online platform where the
Process existing Inprocess VMGSim 2021 Denmark
Technical Support existing OTS that was delivered by Inprocess was being
Licensor OTS to a new Licensor chemicals
& Consultancy hosted. Client requested technical support to facilitate the
client's online
migration project from the old platform to the new one
platform
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 5Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Process Company
Project Type Customer Project Title Year Country Industry Short Description
Simulator Type
Under the contract with the FPSO constructor, client will
deliver six centrifugal compressor trains: one low pressure
(LP), three medium pressure (MP) and two high pressure
Swiss Dynamic Simulation (HP), which are all driven by fixed speed electric motors.
Dynamic Study for six
Compressor Aspen Equipment The whole application will have the following capacities for
Simulation Study compressors trains 2021 Senegal Oil & Gas
Manufacturer for each compression system:
for Compression in a FPSO offshore HYSYS Manufacturer
a Japanese • LP - One Train with 100% capacity
Systems Senegal
FPSO
• MP - Three trains with 50% capacity each
constructor
• HP - Two trains with 100% capacity each.
Client has requested Inprocess to carry out a Dynamic
Simulation Study for all these FPSO Compressors
The existing Export Gas Compressor in the offshore gas
plant, is expected to become a bottleneck beyond year 2021
to handle the forecasted export gas profile. During a FEED
Abu Dhabi office
Dynamic Dynamic Simulation Aspen United Arab study, it was proposed to augment the export gas handling
of an Egyptian 2021 EPC Natural Gas
Simulation Study Study for Off Gas capacity by operating Amine Bypass Unit Compressor in
EPC working for HYSYS Emirates
for Compression Compressor at at an ‘export mode’ permanently in parallel with the Export Gas
a Middle East
Systems Offshore Gas Plant Compressor and to install a new Off Gas Compressor to
NOC
handle low pressure gas. The detailed dynamic simulation
study needed to determine the adequacy of the proposed
arrengement
After deciding to increase production in an Emirates field to
85 MSTBOPD of crude oil, the depressurization, MDMT and
De-Pressurisation,
United Arab hydrates formation study already carried out by Inprocess in
Emirates EPC MMDT and Hydrate OLGA 2020 EPC Oil & Gas
HIPPS or other 2015 needed to be updated with the new production levels
for an Emirates study for the 85 Emirates
Depressurization and compositions performing simulated topside
NOC MBD Wellhead
depressurizations for all WHT and pipelines determining the
Towers
minimum temperature achieved and determining if selected
metals are valid and if hydrates will be formed
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 6Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Process Company
Project Type Customer Project Title Year Country Industry Short Description
Simulator Type
Development and commissioning of a Lifecycle OTS whose
main purpose will be to train the control room operators of
an FPSO located in the gulf of Mexico. On top of that,
because this OTS is going to be built following Inprocess’
Lifecycle approach:
• Client's engineers will benefit from the results obtained with
the dynamic simulation model (built in Honeywell’s UniSim
Design) during the design phase of the FPSO’s topsides,
• The proposed operating procedures will be validated and
Japanese FPSO Lifecycle OTS for an UniSim tested in a preliminary Process Trainer (emulated OTS),
Operator Training 2020 Mexico EPC Oil & Gas
constructor FPSO to be located Design • The configuration of the Integrated Control and
System (OTS)
(Mexican office) in the Gulf of Mexico Safeguarding System (ICSS) provided by ABB will be
checked out in a virtual FAT (against the results of the
process simulation model),
• The control room operators will be deeply trained well
before first oil in the risk-free environment provided by the
direct-connect OTS,
• Client’s Operations team will be supported during the start-
up of the FPSO by the Inprocess’ engineers which would
have gained extensive process, control, and procedures
knowledge during the development of the OTS
Development of a dynamic simulation model of a C3 splitter
Dynamic German Aspen Petrochemic in a PDH plant in order to improve the understanding of the
Dynamic Simulation 2020 Spain Operator
Simulation Study Chemical process, controls, constraints and interactions, in order to
Study for a C3 HYSYS als
for Process Company improve the current and future operation of the unit (e.g.
Splitter Unit
Control Analysis (Spanish site) hydraulic conditions and flooding limits, optimal sensitive
tray, etc.)
Dynamic Simulation Study to determine the revamp
Dynamic Simulation Germany
Dynamic Swiss Aspen Equipment possibilities of a compression system that included as driver
Study for the 2020 Refining
Simulation Study Compressors a fix-speed electrical motor, a speed increasing gear box
revamping of an HYSYS Manufacturer
for Compression Manufacturer and one-barrel compressor, type RV 35-4. For future
existing
Systems (German Office) operation the barrel compressor will be revamped and E-
compression system
motor and gear box will be reused
Dynamic Swiss Aspen Equipment Feasibility study by dynamic simulation to determine the
Feasibility Study for 2020 Germany Natural Gas
Simulation Study Compressors adequacy of a 4-stage propylene compressor evaluating any
Propylene HYSYS Manufacturer
for Compression Manufacturer driver limitation during the start-up of the compression
Compressor
Systems (German Office) system
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 7Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Process Company
Project Type Customer Project Title Year Country Industry Short Description
Simulator Type
Project to evaluate by dynamic simulation the Start-up of the
Refrigeration Compressor in the Mixed Refrigerant Cycle
Dynamic
system.
Simulation Study
UniSim Equipment Additionally, Inprocess developed a software application that
for Compression German MRC Simulation 2020 Germany Natural Gas facilitated Atlas Copco's engineers to interface with the
Systems; Compressors Model and Design Manufacturer
Dynamic Simulation model, allowing changing key selected
Software Manufacturer Application
data of the models and perform sensitivity analyses of the
Extension and
different predefined configurations. The application had a
Programming
library of different possible compressor configurations with
the capability of expand it by users when required.
Development of a Lifecycle Operator Training Simulator (LC-
OTS) for Anna Nery Floating Production Storage and
Offloading (FPSO) platform, which will be deployed at
Petrobras' Marlim field in the Campos Basin.
Although the LC-OTS's main purpose is to train the control
room operators on a direct-connect OTS, Yinson, like it has
Singapore Lifecycle OTS for an Aspen done before with other LC-OTS with Inprocess, will benefit
Operator Training 2020 Singapore EPC Oil & Gas
FPSO FPSO located in a HYSYS from a wider scope during the engineering phases including:
System (OTS)
Constructor Brazilian field * DynamicSimulation studies, operating procedures
validation.
* Early operators and engineers training with an Early-
Emulated OTS.
* Virtual commissioning of the ICSS configuration.
* Processing facilities start-up support.
* Post start-up support with the resulting Digital Twin.
Inprocess has performed a complete dynamic model for the
Engineering Studies Aspen FPSO topside facility. This dynamic model has been
Dynamic 2020 Norway EPC Oil & Gas
FPSO for Operations planned to be used for some initial verification of the process
Simulation HYSYS
Constructor Support for an unit during the initial phase of the production start of the
Modelling Study
FPSO plant. Up to fifteen different upset production scenarios
hasve been tested in this project
Depresurization calculations using dynamic simulation to
Depressurization for Aspen accurtely determine the Minimum Design Metal Temperature
HIPPS or other 2020 Mozambique EPC Natural Gas
Italian EPC a Domestic Gas Unit HYSYS (MDMT) in a small domestic gas unit that is dedicated to
Depressurization
in Mozambique produce a stream of treated gas to be sent to local
distribution grid
Aspen Two-phase Flare System Revalidation project where the
Study and HYSYS; PSVs of a plant section, associated to several services will
Modelization of the Flarenet/As 2020 Spain Operator Refining
Flare Systems Spanish be revalidated by simulation results for different possible
system to discharge
Analysis Refinery pen Flare operating contingencies. In the second project phase, the
to flare of a refinery
Analyzer complete flare network will also be revalidated with the new
section
loads calculated during the PSV revalidation phase
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 8Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Process Company
Project Type Customer Project Title Year Country Industry Short Description
Simulator Type
Client was interested in developing a methodology to
operate the liquid side of the 1st stage separator (having a
Dynamic Process Control Aspen
2020 France Operator Oil & Gas slug catcher functionality) and improving the process control
Simulation Study French E&P Dynamic Simulation
HYSYS philosophy and the PID parameters of the 1st stage
for Process Company Study for 1st Stage
separator. Such a controlability study was carried out with
Control Analysis Separator
the help of a dynamic simulation model of the system and
the subsequent analysis
Collection of nine Generic OTSs for upstream units intended
Generic OTSs for up UniSim Educational to train the students of an Iraq educational institution in the
Oil & Gas 2020 Iraq Oil & Gas
Operator Training to nine units in an operation of an Oil Gas Separation Unit, a Gas Compression
Training Design Institution
System (OTS) upstream Unit, a Gas Sweetening with Amines unit, a Dehydration Unit
Institution in Iraq
processing plant with glycol, an NGL Unit, an LNG Unit, an LPG Unit, an
Energy Unit and a Treatment Unit
Update of an OTS developed by Inprocess to the new
Update of the Aspen
2020 Bolivia Operator Oil & Gas version of the DCS (Emerson DeltaV). Additionally, the
Operator Training Spanish E&P existing OTS
HYSYS dynmiac model was also updated with the inclusion of a new
System (OTS) Company simulation model
booster compressor, a new gas turbine and the associated
with new equipment
filters
Planning for a platform production capacity increase, a flow
assurance (steady state and transient) was required by the
Flow Assurance operating company in order to ensure current equipment
Multinational
Analysis for an OLGA 2020 Saudi Arabia EPC Oil & Gas was capable to cope with the increase. After receiving a
Flow Assurance EPC for a
increase in existing pipelines simulation models in SPS and OLGA,
Analysis Middle East
production in a Inprocess did update them with newer information. With the
NOC
Middle East field updated models, Inprocess executed different simulation
scenarios (SPS for Steady State, OLGA for Transient) in
order to obtain results to confirm the project objectives.
Inprocess was requested to develop a dynamic simulation
model of a depropanizer column, part of a PDH plant, in
Spanish branch Dynamic Simulation
Dynamic Aspen order to help to solve client's current issues with the
of a Study for the 2020 Spain Operator Petrochem
Simulation Study multivariable process controller in operation and to support
multinational controllability and HYSYS
for Process client's plan to increase production the following year. Once
chemical debottlenecking of a
Control Analysis the rigorous model will be ready, it will also be used to infer
company Depropanizer Unit
the values of certain process variables that are difficult (if
not, impossible) to measure in the real plant
The project main objective is to build a dynamic simulation
model for the rich and lean gas segregation pipelines in the
Phase 2 of the
UniSim country national gas grid. The results obtained for a series of
Dynamic Omani EPC for Dynamic Simulation 2020 Oman EPC Natural Gas scenarios, carried out with the model will allow identifying
Simulation a Middle East Study for the Design
potential problems both, in steady state conditions, when
Modelling Study Gas company debottlenecking of a
blending composition changes (up to six cases), and in
gas grid
transient conditions when either some of the consumers trip
or some of the suppliers also do.
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 9Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Process Company
Project Type Customer Project Title Year Country Industry Short Description
Simulator Type
Dynamic Simulation
Aspen Dynamic Simulation Study (DSS) for a BOG compression
Dynamic Study for a series of 2020 Mozambique EPC Natural Gas system in order to analyse different operating scenarios and
Simulation Italian EPC Boil-Off Gas HYSYS
upset cases and considering all the piping, controls and
Modelling Study Compressors in an
equipment handling BOG in the abovementioned plant.
African LNG plant
Dynamic Simulation Study of an Ethylene Refrigeration
Dynamic Dynamic Simulation Compressor, for only one initial condition, to evaluate if the
Swiss
Simulation Study Study for Ethylene Aspen Equipment acceleration phase during the start-up to identify driver
Compressors 2020 Germany Petrochem
for Compression Refrigeration HYSYS Manufacturer limitation or requirement based on the calculated load curve
Manufacturer
Systems Compressor (ERC) and if the compressor behaviour in the compressor map
when the system accelerates
Development of the Lifecycle Operator Training Simulator
(LC-OTS) for Almirante Barroso (MV32) Floating Production
Storage and Offloading (FPSO) platform, which will be
installed in the Búzios field, offshore Brazil. The MV32’s LC-
OTS will be installed in the same training centre in Rio
Lifecycle Operator where Inprocess is already deploying LC-OTS for MV30 and
Major FPSO
Training Simulator MV31 FPSOs.
Operator Training constructing and UniSim
for Almirante 2020 Singapore EPC Oil & Gas
System (OTS) operating Design Although the LC-OTS's main purpose is to train the control
Barroso (MV32)
company room operators on a direct-connect OTS, client will benefit
FPSO
from a wider-scope during the engineering work including:
Flare system validation, operating procedures drafting, early
operators and engineers training with an emulated OTS,
virtual commissioning of the ICSS configuration, start-up and
post start-up support.
Spanish Oil Flare system Aspen Revalidation study for the flare system of a butadiene plant,
Flare Systems Major revalidation study HYSYS; comprising the resizing of a number of safety valves,
2020 Spain Operator Petrochem
Analysis (petrochemicals for the butadiene Aspen Flare together with the revalidation of the flare network, by steady
branch) plant Analyzer state simulation
Slug and Pigging
Flow Assurance Flow Assurance study for two pipelines and two different
Portuguese EPC Analysis for a OLGA 2020 Portugal EPC Oil & Gas
Analysis scenarios for each one
Libyan O&G field
Italian EPC for HIPPS Study for an
HIPPS or other Aspen Dynamic Simulation Study for a HIPPS protection system in
an FPSO FPSO in Angola 2020 Angola EPC Oil & Gas
Depressurization HYSYS order to determine the setpoint of operation
constructor coast
Dynamic Dynamic Simulation Dynamic Simulation Study to determine the correct setup of
Compressors Aspen Equipment
Simulation Study for a 2020 USA Oil & Gas the turbo expander machinery, its process control and its
Manufacturer HYSYS Manufacturer
Modelling Study Turboexpander protection system
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 10Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Process Company
Project Type Customer Project Title Year Country Industry Short Description
Simulator Type
Dynamic Process
Norwegian EPC
Simulation of a Dynamic hydraulic study for an oil export pipeline. The
Flow Assurance for a Norwegian
North Sea OLGA 2020 Norway Operator Oil & Gas possibility of wax deposition along the line was also
Analysis Oil & Gas
installation Oil investigated
Company
Export System
Planning for a future Operator Training System to be
Dynamic developed following the concept of Lifecycle Simulator,
FPSO Dynamic Simulation Aspen
Simulation 2020 Norway EPC Oil & Gas Inprocess' client requested to start separately the dynamic
Constructor Model of a FPSO HYSYS
Modelling Study simulation studies around the equipment to be installed in the
processing facilities of an FPSO
A cracker plant was having trouble when operating the
Steady State
propane/propylene splitter distillation column. Inprocess
Austrian Modelling of a C3
Steady State oversaw building the steady state simulation model and
Petrochemical splitter and de- Aspen
Simulation 2019 Sweden Operator Petrochem running a Sensitivity Analysis in order to evaluate the options
Company, ethanizer distillation HYSYS
Modelling Study to limit propylene losses in the bottom stream and to analyse
Swedish site columns in a cracker
how MAPD can be limited to the maximum allowable
plant
concentration in the column with the current instrumentation.
Dynamic Simulation The French compressor manufacturer providing the
Dynamic
French Study for the equipment to a Russian LNG plant required Inprocess to
Simulation Study Aspen Equipment
Compressor Overhead 2019 Russia Natural Gas determine by means of dynamic simulation the protection
for Compression HYSYS Manufacturer
Manufacturer Compressor in an requirements (anti-surge circuit, hot gas bypass valve
Systems
LNG train requirements, etc.) for the overhead compressor
Dynamic Simulation The French compressor manufacturer providing the
Dynamic
French Study for the equipment to a Russian LNG plant required Inprocess to
Simulation Study Aspen Equipment
Compressor Regeneration 2019 Russia Natural Gas determine by means of dynamic simulation the protection
for Compression HYSYS Manufacturer
Manufacturer Compressor in an requirements (anti-surge circuit, hot gas bypass valve
Systems
LNG train requirements, etc.) for the regeneration compressor
The client wanted to process an alternative feedstock (from
bio sources) into their PDH and PP3 plants, and it was in need
of testing the evolution of the concentration of this alternative
Austrian Dynamic Simulation
Dynamic feedstock at the exit of the polymerization plant, once the
Petrochemical Model for a Propane Aspen
Simulation 2019 Belgium Operator Petrochem feedstock tank at their logistic partner was connected to the
Company, dehydrogenation HYSYS
Modelling Study pipeline feeding the PDH plant. Therefore, a dynamic
Belgian site plant
simulation model of the plant was built, and it was used to
determine the residence time of the new feedstock, after
switching from the traditional one.
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 11Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Process Company
Project Type Customer Project Title Year Country Industry Short Description
Simulator Type
Inprocess built the dynamic model of the flare network of a
propane dehydrogenation plant for an Italian engineering
company who was in charge od carrying out a safety gas
Dynamic Flare evaluation in the plant
Dynamic Italian EPC for Network Analysis for Final client was facing a problem with the Flare system for
Simulation an Austrian safety gas which the reduction load applied was not properly supported
Aspen
Modelling Study; petrochemicals evaluation in a 2019 Belgium EPC Petrochem by a simulation, and the HIPS implementation is not enough
HYSYS
Flare Systems company Propane to close the safety gap coming from a LOPA analysis.
Analysis (Belgian Site) dehydrogenation Inprocess carried out a flare simulation for the design
(PDH) plant scenario (power failure) in order to check if the time-
dependence of the overpressure phenomena can give
additional credit to close the safety gap going to safe reduce
the flare design.
Flare Systems
Multinational Inprocess carried out the revalidation of the Flare System of
Analysis for a
Flare Systems Chemical Aspen a propane dehydrogenation plant by means of process
Propane 2019 Spain Operator Petrochem
Analysis Company, HYSYS simulation, simulating contingencies and revalidating system
dehydrogenation
Spanish site dimensions
plant
FEED Flow
Italian EPC for a Assurance Study for By means of transient simulation of the pipeline using OLGA,
Flow Assurance
Russian O&G an Oil Export OLGA 2019 Italy EPC Oil & Gas Inprocess carried out a FEED study for the oil export pipeline
Analysis
company Pipeline to a Tank from the processing facilities to the tank farm vessels
Farm
French
Dynamic Compressor Dynamic simulation Inprocess built a dynamic simulation model of the three-
Simulation Study Manufacturer for study for a three Aspen Equipment stages compression system to validate the sizing of the
2019 Indonesia Oil & Gas
for Compression an Indonesian stages centrifugal HYSYS Manufacturer proposed anti-surge valves and the configuration of the
Systems Oil&Gas compression system recycle loops
company
Dynamic Simulation Inprocess updated an existing dynamic simulation case in
Dynamic Process for a high-pressure order to match Steady State conditions, according to H&MB,
Aspen
Simulation Licensor division gas circuit in a 2019 Italy EPC Refining in order to tune up controllers and instrumentation as well as
HYSYS
Modelling Study of an Italian EPC hydroconversion to check dynamics to verify that in three different scenarios,
type unit no overpressure and overtemperature will occur
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 12Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Process Company
Project Type Customer Project Title Year Country Industry Short Description
Simulator Type
During the start-up of two units of a green refinery lots of
operational problems were detected, actually leading to the
impossibility of starting them. Inprocess created a dynamic
DSS to study start- simulation model of the units and helped out the engineers
Dynamic
up procedures for Aspen there to find During the start-up of two units of a green refinery
Simulation Italian EPC 2019 Italy EPC Refining
two units in a green HYSYS lots of operational problems were detected, actually leading
Modelling Study
refinery to the impossibility of starting them. Inprocess created a
dynamic simulation model of the units and helped out the
engineers there to find and define the right procedure to
smoothly start the refinery units
Due to the construction of new processing facilities in
Emirates EPC gathering centre of an oil & gas field, new desalter treating
Dynamic Dynamic Simulation
working for an Aspen trains need to be built. Inprocess did carry out the dynamic
Simulation Study for Desalter 2019 Kuwait EPC Oil & Gas
Middle East HYSYS simulation of such series of desalter trains in order to assess
Modelling Study trains in new GCs
NOC their dimensions, their desalting capacity, and their control
and safety strategy for start-up and shutdown sequences
A surge analysis of a 121 km long crude oil export pipeline,
Surge Analysis
Italian EPC for a between two tan farms, was carried out by Inprocess using
Study for a Crude
Flow Assurance Russian Oil OLGA with PVTSim in order to determine the adequate line
Oil Export Pipeline OLGA 2019 Iraq EPC Oil & Gas
Analysis Company in size (48"), the NPSHA for booster and shipper pumps, the
between two tank
Middle East cool down as well as testing other different operational and
farms (121 km)
emergency situations
Client wanted an updated Aspen Flare Analyzer model of their
Spanish site of a Flare Network
Flarenet/As flare network (93 sources relieving). Inprocess built the model
Flare Systems German Evaluation for the Bulk
pen Flare 2019 Spain Operator and run the proposed scenarios (Power Failure, Cooling
Analysis Chemicals whole producing site Chemicals
Analyzer Water Failure, Instrument Air Failure and Fire) and suggested
company (several plants)
possible ways of overcoming the detected bottlenecks
Inprocess’ refinery experts did analyse the status of the
existing Hydrogen Network with the aim to investigate
Feasibility Study for
different alternatives to optimize hydrogen utilization at the
Hydrogen Serbian Refining Hydrogen Network Aspen
2019 Serbia Operator Refining refinery. Afterwards, Inprocess, in collaboration with its EPC
Network Study Company Modelling and HYSYS
partner, did conduct the Technical and Economic Evaluation
Optimization
of the proposed alternatives as well as created the required
technical documentation for the selected solution.
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 13Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Process Company
Project Type Customer Project Title Year Country Industry Short Description
Simulator Type
• Revalidation of the plant PSVs: Calculation of the
discharge load from every service protecting the units, for
Aspen every defined contingency and calculation of the sizing of
Modelling and Study
HYSYS; the services (only for those PSVs whose dimensions are
of the Flare System
Flare Systems Spanish Flarenet/As not known)
of the Conversion 2019 Spain Operator Refining
Analysis Refinery pen Flare • Flare network revalidation: Determination of the services
Section of the
Analyzer; affected by the common contingencies and development
Refinery
Flaresim of a flare network model, in order to determine its hydraulic
behaviour and possible limitations.
• Flare revalidation: Seal and Tip design and radiation study
Development of a Minimum Metal Temperature Study for the
Minimum Metal Gas-Lift Compressor System in an oil & gas field (offshore
Temperature Study Abu Dhabi) using BLOWDOWN technology available in
Spanish EPC
HIPPS or other (FEED) for a Gas- Aspen Aspen HYSYS. This technology has been incorporated by
working for and 2019 Abu Dhabi EPC Oil & Gas
Depressurization Lift Compression HYSYS Aspentech in Aspen HYSYS keeping the code unchanged in
Emirates' NOC
System in an Abu order to maintain the accuracy of the original depressurization
Dhabi offshore field technology developed by Dr. Graham Saville and Prof.
Stephen Richardson
Dynamic Simulation
Dynamic Dynamic Simulation Studies, with different operational
Study of the Gas
Simulation Study FPSO Aspen scenarios, to calculate sizes of equipment and of safety
Injection 2019 Ghana Operator Oil & Gas
for Compression Constructor HYSYS devices for the Gas Injection compressor installed in a FPSO
Compressor in an
Systems in Africa
FPSO in Ghana
Dynamic study to confirm the design of the Anti-Surge Valve,
Dynamic Simulation including the trim characteristic, and to evaluate the need of
Dynamic
Swiss Study for three hot gas bypass valve; to detect potential reverse rotation of
Simulation Study Aspen Equipment
Compressor compression 2019 Indonesia Oil & Gas the compressor; to perform the compressor system start-up,
for Compression HYSYS Manufacturer
Manufacturer systems in an oil & including interfaces with the process sequence identification
Systems
gas plant of required starting torque, starter driver sizing, and the
required acceleration limitations
German
PSVs and Flare
Engineering An Inprocess modelling expert remotely supported the EPC
Flare Systems network revalidation UniSim
Company for a 2019 Germany EPC Refining firm to carry out a PSVs and flare network revalidation study
Analysis for a German Design
German for a refinery in Germany
refinery
Refinery
Dynamic Dynamic Simulation Studies, with different operational
British DSS for the LLP and
Simulation Study Aspen Equipment scenarios, to calculate sizes of equipment and of safety
Compressor LP compressors in a 2019 Senegal Oil & Gas
for Compression HYSYS Manufacturer devices for the LLP and LP compressors installed in a FPSO
Manufacturer FPSO in Africa
Systems in the west coast of Africa
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 14Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Process Company
Project Type Customer Project Title Year Country Industry Short Description
Simulator Type
The compressor manufacturer wanted Inprocess to build a
Swiss
Dynamic Dynamic simulation dynamic model and to run simulation scenarios to determine
Compressor
Simulation Study study for a booster Aspen Equipment if their compressor design was satisfying final client needs to
Manufacturer for 2019 Uzbekistan Oil & Gas
for Compression compressor station HYSYS Manufacturer boost the pressure of a declining field to keep desired
an Uzbek oil &
Systems (two stages) discharge pressure (by moving from one-stage to two-stages
gas company
compression system)
An Operator Training System for the Ammonia, Urea and
Methanol plants (plus the associated Utilities plant) has been
built for a fertilizers company in Malaysia. The dynamic
Operator Training process model has been built using UniSim Design, the
Malaysian
Operator Training System for an UniSim Bulk emulation of the Yokogawa DCS has been included in the
Fertilizers 2019 Malaysia Operator
System (OTS) Ammonia, Methanol Design Chemicals process model, the Advanced Process Control Module has
Company
and Urea Plant been connected to the process model and the emulated HMI
has been developed with Inprocess Instructor Station that is
also acting as the communication hub for the whole of the
system
Dynamic Dynamic study to
Simulation Study FPSO select adequate Aspen Dynamic Simulation studies carried out for different
2019 Ghana EPC Oil & Gas
for Compression Constructor compressors in an HYSYS compressor alternatives in order to select the best suited one
Systems FPSO
EPC (Italian Dynamic analysis of
Dynamic Inprocess carried several operation scenarios to determine
office) working a steam network in Aspen
Simulation 2019 Bahrain EPC Refining the operability of the steam network of the utilities section of
for a Middle East a desalination plant HYSYS
Modelling Study a desalination plant in Middle East
NOC during shutdown
A dynamic model of one section of the sulphur oxide gas
treatment plant has been built in Aspen HYSYS dynamics to
Dynamic Dynamic Model and
Spanish help client engineers to improve current process control
Simulation Study Technology Transfer Aspen
Metallurgical 2019 Spain Operator Metallurgy setup. The model development activity will be supported by a
for Process for a Sulphur Oxide HYSYS
Company series of knowledge transfer sessions that will guide control
Control Analysis Plant
engineers on how to benefit from the dynamic simulation
results to improve plant controllability
Steady State Model
An existing Steady State model in Aspen HYSYS will be
Steady State Canadian Improvement and
Aspen Process Bulk reviewed and enhanced in terms of convergence time and
Simulation Process Exergy Analysis of a 2019 Canada
HYSYS Licensor Chemicals redundant information. Once validated, the model will be used
Modelling Study Licensor Compressed Air
to identify potential energy improvements by exergy analysis
Storage System
Depressurization
Dynamic FPSO and re- Dynamic Study to determine the operating procedure for the
Aspen
Simulation Constructor in pressurization 2019 Ghana Operator Oil & Gas switch from automatic to manual in the gas export line from
HYSYS
Modelling Study Singapore dynamic study for a FPSO to the continent
gas export sealine
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 15Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Process Company
Project Type Customer Project Title Year Country Industry Short Description
Simulator Type
Aspen
Revalidation of the After several successful previous projects, the refinery owner
HYSYS;
Flare Systems Spanish PSVs protecting the has requested Inprocess to carry out another project to
Flarenet/As 2019 Spain Operator Refining
Analysis Refinery coker, the HGO and revalidate the sizing of the Pressure Safety Valves protecting
pen Flare
the CLE & LVN some other units in the refinery (Coker, HGO, CLE & LVN)
Analyzer
Swiss
Compressors The main objective of the project was to deliver a dynamic
DSS for a
Dynamic Manufacturer simulation study for a compression system to confirm the
compressor train
Simulation Study (German Aspen Equipment viability of eliminating VDS, though the verification of the
changing from VSD 2019 Germany Refining
for Compression branch) for an HYSYS Manufacturer operation under a number of defined procedural and upset
drive/control to fixed
Systems Oil Major conditions. The model will allow evaluating the design and
speed drive
operating in identifying potential problems.
Qatar
Inprocess has developed a dynamic simulation model of the
three compression systems designed to work in a FPSO
German Dynamic Simulation
Dynamic offshore Brazil with the objective of determining the anti-surge
Compressor Study for three
Simulation Study Aspen Equipment requirements for the three systems; to evaluate the
Manufacturer for Different 2019 Brazil Oil & Gas
for Compression HYSYS Manufacturer compressor start-up procedures and the driver ability to
an FPSO Compressor Trains
Systems provide sufficient torque at the settle out pressure with/without
constructor Systems in a FPSO
soft starter; and to evaluate an emergency shutdown or trip
event.
Inprocess has developed a dynamic simulation model of the
Spanish Dynamic Simulation
Dynamic chilling water network in Aspen HYSYS in order to help client
Synthetic Study for the rubber Aspen
Simulation 2019 Spain Operator Petrochem to determine hydraulic bottlenecks in its chilling water network
Rubber plant chilling water HYSYS
Modelling Study and to help client to find solutions that could lead to its
Producer network
removal
The main objective of the project is to deliver a dynamic
Dynamic Simulation
Dynamic simulation study for the Feed Gas Booster compression
German Study for Feed Gas
Simulation Study Aspen Equipment system and for the Boil-Off Gas compression system in order
Compressors Booster Compressor 2019 Germany Natural Gas
for Compression HYSYS Manufacturer to confirm its proper operation under several defined
Manufacturer and Boil Off Gas
Systems procedural and upset conditions. The model will allow
Compressor
evaluating the design and identifying potential problems.
Operator Training Simulator for a Gas Utilization Plant that will
Operator Training use Siemens PCS7 as distributed control system. Inprocess
Middle East
Operator Training Simulator for a gas Aspen has developed a direct-connect OTS, with a dynamic model
Control Systems 2019 Iraq EPC Natural Gas
System (OTS) plant in Basrah HYSYS of the process based on Aspen HYSYS, the emulation of the
Implementor
(Iraq) Siemens DCS based on PCS7Sim and SIMIT, and an
instructor station developed with Inprocess Instructor Station
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 16Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Process Company
Project Type Customer Project Title Year Country Industry Short Description
Simulator Type
Within the innovation process on going, client is evaluating
the use of Aspen Plus to perform integrated process
simulation models for High-Octanes Technologies, more
specifically MTBE, ETBE and TAME synthesis and related
side reactions.
Process Client is currently simulating the whole process (reaction,
Steady State Licensor division On-site Support for product separation and reactant recovery) using different
Simulation of an Italian Aspen Plus MTBE Aspen Plus 2019 Italy EPC Petrochem tools with an important effort related to the integration of the
Modelling Study engineering Reactor Modelling results from one tool to the other until a stable convergence is
company reached. The reason of this is linked to the reliability of each
tool results that were confirmed over the years with data
coming from several operating plants all over the world.
Client requested Inprocess its support to implement the whole
of the existing models and routines into a single process
simulation tool, like Aspen Plus.
Inprocess and client will jointly devote R&D resources to
Research, Development of a
Norwegian Oil develop a software tool capable of detecting process
Development and Bad Actors Aspen
and Gas 2019 Norway Operator Oil & Gas anomalies due to the deviation between the real equipment
Innovation Detection HYSYS
company behaviour and that expected from a rigorous first-principles
(R+D+I) Application
dynamic process simulator
Inprocess updated and upgraded an existing simulation
system for the complexes of Fluidized Catalytic Cracking
Upgrading of an
(FCC) and Mild Hydrocracker (MCC) to the new process
existing Operator
Operator Training Greek Refining UniSim simulator (UniSim Design), matching current plant conditions.
Training Simulator 2019 Greece Operator Refining
System (OTS) Company Design On top of the new model, Inprocess created an Operator
for an MHC refinery
Training Simulator, simulating the Honeywell control system
unit
and the safety system with Proconex software and developing
the instructor capabilities with Inprocess Instructor Station
Operator Training Inprocess developed an OTS for an old topping complex in
Simulator of a the refinery, developing the process model with UniSim
Operator Training Greek Refining UniSim
continuous catalytic 2019 Greece Operator Refining Design, simulating the Honeywell control system and the
System (OTS) Company Design
reforming refinery safety system with Proconex software and developing the
unit instructor capabilities with Inprocess Instructor Station
Inprocess developed an OTS for continuous catalytic
Operator Training reforming unit in the refinery, developing the process model
Operator Training Greek Refining UniSim
Simulator of a 2019 Greece Operator Refining with UniSim Design, simulating the Honeywell control system
System (OTS) Company Design
topping refinery unit and the safety system with Proconex software and developing
the instructor capabilities with Inprocess Instructor Station
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 17Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Process Company
Project Type Customer Project Title Year Country Industry Short Description
Simulator Type
A major FPSO constructing and operating company has
awarded Inprocess the construction of an Operator Training
Simulator for their new Carioca (MV30) Floating Production
Storage and Offloading (FPSO) platform, which is soon to be
installed off the coast of Brazil (in the Sepia field). These fields
produce a natural gas with a high CO2 content, thus a careful
Major FPSO Lifecycle project and design of the processing facilities in the FPSO is required as
Operator Training constructing and OTS for one FPSOs UniSim well as precise operating procedures in order to be able to
2019 Brazil Operator Oil & Gas
System (OTS) operating to be located Design adequately process the fluids produced. The OTS being built
company offshore Brazil to train the control room operators are, however, part of a
wider-scope simulation lifecycle project which will include
dynamic simulation studies to be executed before the actual
construction of the topsides, as well as validation of the
proposed operating procedures, checkout of the ICSS
databases, operator training, start-up support and post start-
up updates.
A major FPSO constructing and operating company has
awarded Inprocess the construction of an Operator Training
Simulator for their new Guanaraba (MV31) Floating
Production Storage and Offloading (FPSO) platform, which is
soon to be installed off the coast of Brazil (in the Libra field).
These fields produce a natural gas with a high CO2 content,
Major FPSO Lifecycle project and thus a careful design of the processing facilities in the FPSO
Operator Training constructing and OTSs for one FPSO UniSim is required as well as precise operating procedures in order
2019 Brazil Operator Oil & Gas
System (OTS) operating to be located Design to be able to adequately process the fluids produced. The
company offshore Brazil OTS being built to train the control room operators are,
however, part of a wider-scope simulation lifecycle project
which will include dynamic simulation studies to be executed
before the actual construction of the topsides, as well as
validation of the proposed operating procedures, checkout of
the ICSS databases, operator training, start-up support and
post start-up updates.
Slovak EPC for Dynamic Simulation
Dynamic EPC dynamic simulation studies to verify basic engineering
a Slovak Study for Ethylene Aspen
Simulation 2019 Slovakia EPC Petrochem calculations for the facilities of the storing complex of an
petrochemicals Storing Facility HYSYS
Modelling Study ethylene production plant
company Subcooling Section
Inprocess will take advantage of existing models in Aspen
OTS for a Dynamics to build an OTS based on Aspen HYSYS Dynamics
Operator Training German Resins Hydrogenated Aspen Bulk to train control room operators on the behaviour of the plant
2019 Germany Operator
System (OTS) Company Hydrocarbon Resin HYSYS Chemicals that is controlled by a PCS7 Simatic from Siemens. Inprocess
plant Instructor Station will be the software acting as data hub and
providing the Instructor functionalities
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 18Inprocess Technology & Consulting Group, S.L.
Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com
Inprocess References List: 2008-2021
Process Company
Project Type Customer Project Title Year Country Industry Short Description
Simulator Type
Software
Steady State model Inprocess will build new steady state standalone models for
Extension and Norwegian
expansion and two new fields to be integrated with an existing CORF model.
Programming; Exploration & Aspen
software extension 2019 Norway Operator Oil & Gas Models will be fed with real plant data from PI system.
Steady State Production HYSYS
upgrade for a North Software extensions will be upgraded to cope with the new
Simulation Company
Sea field feeds
Modelling Study
The purpose of this hydraulic analysis was to establish the
line size requirements for the new transfer lines from PADs
Spanish EPC for Flow Assurance and Main Transfer line forming a Fish Bone Network for the
Flow Assurance
an Emirates oil Study for an oil field OLGA 2019 Abu Dhabi EPC Oil & Gas Oil Gathering Network. The analysis also evaluated and
Analysis
company in Middle East identified the various problems that could be faced during
start-up, shutdown, pigging operations of the gathering
network facility
A petrochemical complex in a coastal town in the Province of
Cádiz (Spain) has awarded Inprocess a project to develop
and implement an OTS and an ITS (3D VR) for its Linear
Alkylbenzene (LAB) plant. The plant is currently updating its
facilities – in a new upgrade project, valued at $110 million -
to take advantage of the most modern, efficient DETAL
technology now available.
Petrochemical OTS and ITS for a By using Aspen HYSYS Dynamics for the simulation of both
Operator Training Aspen
Spanish greenfield DETAL 2019 Spain Operator Petrochem the processing plant and its process control, the Inprocess-
System (OTS) HYSYS
Company plant emulated OTS solution will also evolve to incorporate 3D
Virtual Reality vision to simultaneously train control panel
operators and field operators.
As a side project benefit, Inprocess will invest in the
development of the Digital Twin, the future basis for the OTS
and ITS (3D VR), by creating an inferential variables
generation tool to be used in Process Optimization
applications.
Steady State Aspen + Conceptual Client requested Inprocess technical support to help them to
Bulk
Simulation German EPC Design of Distillation Aspen Plus 2019 Germany EPC build a model in Aspen Plus that should help them to select
Chemicals
Modelling Study Sequence the best distillation sequence configuration
Development of an Operator Training system for one FPSO
Operator Training
Brazil office of a located offshore Brazil. The dynamic model will be developed
Operator Training System for one UniSim
Dutch FPSO 2019 Brazil Operator Oil & Gas taking advantage of a previously built dynamic model for EPC
System (OTS) FPSO located Design
constructor studies. The control and safety system (from Siemens) will be
offshore Brazil
simulated with Siemens softcontroller based on SIMIT
All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L.
23 June 2021 Inprocess Reference List 2008 - 2021 Page 19You can also read