FROM THE CEO
SCOTT ASHBY
CHIEF EXECUTIVE OFFICER
I am pleased to present this issue of The Quarter, the City of Onkaparinga’s key performance report for our
communities.
The Quarter summarises our performance and activities over the past three months and reports on our progress
towards achieving our communities’ goals as outlined in the Community Plan 2030.
It provides an extensive and thorough review of our projects, services and programs. It also details significant
events and other related matters that have occurred during the period.
The Quarter, together with our community satisfaction survey, annual report and annual business plan, all provide
detailed and easily accessible information on the operations, direction and performance of council.
I trust that you will find its content valuable and informative.
THE QUARTER OCT-DEC 2020 CEO MESSAGE
Page 2 of 59COVID-19 UPDATE
The impacts of COVID-19 are being felt by everyone in our community.
As an organisation we have responded to COVID-19 restrictions through the organisation’s Crisis Management
Team (CMT). The focus of CMT has been to ensure continuity of critical services and functions across council,
whilst ensuring a safe environment for staff and the community. As restrictions have eased, the organisation has
responded in returning services to community in accordance with government guidelines and restrictions.
During the initial stages of COVID-19, many of our services to community were impacted. Critical services continued
to be offered during this time with no interruption to service delivery. Government restrictions closed a number of
Council services and sites making them unavailable to the community. A large number of services forced to close
during this period such as libraries, youth centres, positive-ageing centres; adapted their delivery models to ensure
some level of service and contact was still provided to community. This was especially important for services
regularly working with isolated and vulnerable communities.
In this issue of The Quarter, statistics may vary for services that were impacted by closures, restricted services or in
some cases an increase in demand.
For more information on our response to COVID-19, please visit our dedicated COVID-19 Community Update
website page by clicking on the below image:
This page includes information such as:
• Customer Service Office information (all reopened)
• Continued restrictions on services
• Community relief measures
• Playgrounds and open space
• How to report people breaking or ignoring restrictions
• External links for more information
THE QUARTER OCT-DEC 2020 COVID-19
Page 3 of 59CORPORATE
CHRIS WHITE, DIRECTOR CORPORATE
Anthony Spartalis, Chief Financial Officer
Managers:
Jade Bird, Manager Financial Services
Desma Morris, Manager Governance
Jordan Littlefair, Manager People and Culture
Heath Colebatch, Manager Organisational Effectiveness
Brian Strawbridge, Manager Information Communication & Technology
THE CORPORATE DIVISION
SUPPORTS THE BUSINESS IN FINANCIAL SERVICES
DELIVERING INTERNAL Financial Planning & Analysis
SERVICES THAT FACILITATE THE
GREAT WORK OF OUR Financial Accounting
CUSTOMER-FACING TEAMS. WE
PROVIDE SUPPORT FOR THE Revenue
BUSINESS VIA FINANCE AND
Procurement Services
BUDGETING SERVICES,
PROCUREMENT AND
PURCHASING, COMPLIANCE, GOVERNANCE
INFORMATION MANAGEMENT,
POLICY AND AUDIT SUPPORT, Civic & Elected Member Liaison
INFORMATION TECHNOLOGY
Corporate Governance
SUPPORT, AND FUNCTIONAL/
SERVICE REVIEW SUPPORT. WE Corporate Information Management
ALSO SUPPORT OUR FANTASTIC
STAFF, ELECTED MEMBERS AND
COMMITTEES VIA THE PEOPLE AND CULTURE
PROVISION OF TRAINING AND
DEVELOPMENT SERVICES, Human Resources
PAYROLL, RECRUITMENT,
ELECTED MEMBER LIAISON, Learning and Development
AGENDA AND MINUTE
CREATION, AND INDUSTRIAL Organisational Development
SERVICES.
Work Health and Safety
Payroll
ORGANISATIONAL EFFECTIVENESS
Business Performance Improvement
INFORMATION COMMUNICATION TECHNOLOGY
Business Systems
Technology Support
ICT Reform
THE QUARTER OCT-DEC 2020 CORPORATE
Page 4 of 59CORPORATE
WORKFORCE - FULL TIME
EQUIVALENT
The following table and chart reflect the
number of full time equivalent
employees including externally funded
positions. This figure is inclusive of staff
on leave, however does not include
agency staff, trainees or apprentices.
WORKFORCE - FULL TIME EQUIVALENT
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
FTE 696.29 700.74 701.54 694.11 704.21
WORKFORCE - EMPLOYEE
TURNOVER
The following table and chart reflect the
employee turnover results by quarter
with a further breakdown by employee
initiated and organisational initiated
categories. This figure is not inclusive of
agency staff or trainees and
apprentices.
EMPLOYEE - STAFF TURNOVER
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Employee
Turnover 1.69% 2.31% 1.17% 2.89% 1.86%
THE QUARTER OCT-DEC 2020 RECRUITMENT
Page 5 of 59CORPORATE
WORK HEALTH AND SAFETY
We aim to provide and promote a healthy and safe work environment that minimises the risk of injury or illness arising from
work activities.
This data is provided from the Local Government Association Workers Compensation Scheme (the Scheme). This data is
used by the Scheme to calculate the percentage of our salaries and wages payable as workers compensation insurance
premium.
The statistics are updated on a monthly basis but the currency/accuracy of data is dependent upon the status of a claim and
the injured employee’s return to work. If an employee is away from work for an extended period of time, their claim information
is not provided until they have returned to work. If a claim is pending, it may be many months before wages are claimed from
the Scheme. This reporting approach is uniform across local government areas in South Australia and in no way has any
adverse effect on our Health & Safety or Injury Management responsibilities or outcomes.
LOST TIME INJURIES
The following table and chart reflect the
number of lost time injuries incurred
(one complete shift or more of lost time).
LOST TIME INJURIES
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Lost Time Injuries 2 2 4 7 3
INJURY MANAGEMENT – NEW
WORKERS COMPENSATION CLAIMS
The following table and chart reflect the
number of new workers compensation
claims.
INJURY MANAGEMENT – NEW WORKERS COMPENSATION CLAIMS
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Workers
Compensation
Claims 3 5 5 7 4
THE QUARTER OCT-DEC 2020 WORK HEALTH & SAFETY
Page 6 of 59CORPORATE
VOLUNTEER INVOLVEMENT -
NUMBER OF COUNCIL
VOLUNTEERS
The table and graph represents the
number of volunteers who support the
delivery of council services and
programs to our community.
VOLUNTEER INVOLVEMENT - NUMBER OF COUNCIL VOLUNTEERS
2019 2020 2020 2020 * 2020*
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
City of
Onkaparinga
Volunteers
(number) 571 570 526 483 476
TOTALS 571 570 526 483 476
VOLUNTEER INVOLVEMENT -
HOURS CONTRIBUTED
The table and graph represents the
number of hours contributed by our
volunteers to support the delivery of
council services and programs to our
community.
VOLUNTEER INVOLVEMENT - HOURS CONTRIBUTED
2019 2020 2020* 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
City of
Onkaparinga
Volunteers
(hours) 22,484 19,624 7,407 21,087 19,690
TOTALS 22,484 19,624 7,407 21,087 19,690
*
Please note, figures for the Apr-Jun
2020 period may be indicative of any
changes to service in response to
COVID-19 restrictions (as stated on
page 2 of this report).
THE QUARTER OCT-DEC 2020 VOLUNTEERS
Page 7 of 59CORPORATE
GOVERNANCE - ELECTED MEMBER
REQUESTS GOVERNANCE - ELECTED MEMBER REQUESTS
The following chart and table reflects
the number of requests received per 2019 2020 2020 2020 2020
quarter from elected members via our Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
elected member request process.
Completed 157 233 224 287 377
In Progress 2 1 1 8 11
TOTALS 159 234 225 295 388
THE QUARTER OCT-DEC 2020 ELECTED MEMBER REQUESTS
Page 8 of 59CORPORATE
PROJECT REPORTING
Est Completion Percent On
SERVICE - CIVIC - COUNCIL, COMMITTEES AND EM On Time
Date Complete Budget
WORKSHOP MANAGEMENT
30/11/22 100% Y Y
To facilitate and manage the logistics of Council and Committee meetings
Status Update
The Civic Governance section supported Council, its Committees and Elected Member sessions during the October to
December 2020 quarter through the production of agendas and minutes for three Council meetings and ten Committee
meetings.
Meetings of the Strategic Directions Committee, Audit Risk Value and Efficiency Committee, ICT Reform Project Steering
Committee, Australia Day Awards Committee and Council Assessment Panel were held.
Three Elected Member sessions were held with topics including the Long Term Financial Plan and the Grants and
Sponsorship Program Review.
Est Completion Percent On
On Time
SERVICE - FACILITATION OF CIVIC EVENTS AND AWARDS Date Complete Budget
30/11/22 100% Y Y
Plan, schedule and host civic and corporate events and forums on behalf of the Mayor and the City including development of
protocols, official and civic guest lists.
Status Update
A citizenship ceremony was held on Monday, 12 October at 7pm at the Hopgood Theatre. Deputy Mayor Geoff Eaton
presided over the ceremony with 40 conferees from 16 different countries receiving Australian Citizenship. Amanda Rishworth
MP, Federal Member for Kingston, Rebekha Sharkie MP, Federal Member for Mayor and Nat Cook MP, Member for Kaurna
attended and spoke at the ceremony. The 2020 Mayors Garden Competition awards presentation evening was held on
Monday 16 November. The Mayor and staff judged the nominated gardens with the winners listed below. Best Urban Garden:
Dee Jones, Best Community Garden: The Big Backyard, Best Courtyard Garden: Melanie and Ben Volkmann, Best School
Garden: Willunga High School, Best Rural Garden: Irene Moon. The 2020 Mayors Christmas light display competition was
judged by the Mayor, Cr Geoff Eaton and Cr Alayna de Graaf with the winners being Best Street: Keane Court, Old Reynella,
Best Single House: 67 Emmerson Drive, Morphett Vale (Hall of Fame), Community Spirit: 20 Summerford Road, Aberfoyle
Park.
THE QUARTER OCT-DEC 2020 CORPORATE - PROJECT REPORTING
Page 9 of 59PLANNING & REGULATORY SERVICES
RENEE MITCHELL, DIRECTOR PLANNING &
REGULATORY SERVICES
Managers:
Ben Victory, Manager Development Services (Acting)
Ian Hawkins, Manager Community Safety & Property
PLANNING, PROPERTY,
RANGERS AND COMPLIANCE DEVELOPMENT SERVICES
SERVICES ARE KEY TO OUR Development Policy
COMMUNITIES. EXTERNALLY
FOCUSSED, THE PLANNING AND Planning
REGULATORY SERVICES
DIVISION WILL ACTIVELY DRIVE Building & Development Compliance
THE ORGANISATION’S
Development Support
DEVELOPMENT POLICY AND
OVERSEE PLANNING AND
DEVELOPMENT APPLICATIONS, COMMUNITY SAFETY & PROPERTY
ASSESSMENTS AND Community Health
COMPLIANCE. THE DIVISION
WILL LEAD COMMUNITY HEALTH Community Rangers
AND COMMUNITY SAFETY
SERVICES, INCLUDING OUR Community Safety Business Support
APPROACH TO MANAGEMENT
OF CATS AND DOGS, WORKING Property Management
CLOSELY WITH OUR ELECTED
MEMBERS AND RESIDENTS TO
DELIVER SAFER, MORE VIBRANT
COMMUNITIES.
THE QUARTER OCT-DEC 2020 PLANNING & REGULATORY SERVICES
Page 10 of 59PLANNING & REGULATORY SERVICES
PLANNING - DEVELOPMENT
APPLICATIONS LODGED
All development, as defined by the
Development Act 1993, requires the
lodgement of a development application
to seek development approval.
PLANNING - DEVELOPMENT APPLICATIONS LODGED
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Development
Applications
Lodged 840 808 953 1,163 1,314
THE QUARTER OCT-DEC 2020 DEVELOPMENT APPLICATIONS LODGED
Page 11 of 59PLANNING & REGULATORY SERVICES
PLANNING - DEVELOPMENT
DECISIONS BY TYPE
The Development Act sets out different
assessment path types for development
applications, including Building Rules
consent only (Development Plan
consent not required), complying,
Residential Development Code
complying, merit and non-complying. In
these reported statistics, we’ve
combined Building Rules consent only
and complying together, and we’ve also
separated land division applications
(which are almost all merit) from
building/land use applications.
PLANNING - DEVELOPMENT DECISIONS BY TYPE
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Complying 223 197 213 281 309
Land Division 33 54 39 53 48
Merit 362 390 326 411 458
Non-Complying 5 4 4 6 5
Residential Code 29 43 43 55 70
TOTALS 652 688 625 806 890
PLANNING - DEVELOPMENT
DECISION TURNAROUND TIMES
(DAYS)
All development applications are subject
to prescribed assessment timeframes,
the length of which depends on the
required assessment path and whether
the application seeks Development Plan
consent, Building Rules consent, Land
Division consent and/or development
approval. These timeframe averages do
not include requests for further
information or referrals to state
government agencies.
PLANNING - DEVELOPMENT DECISION TURNAROUND TIMES
(DAYS)
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Complying 7 9 8 9 6
Land Division 23 34 36 19 22
Merit 21 25 21 24 23
Non-Complying 74 90 150 73 42
Residential Code 8 11 9 10 9
THE QUARTER OCT-DEC 2020 DEVELOPMENT APPLICATIONS TURNAROUND TIMES
Page 12 of 59PLANNING & REGULATORY SERVICES
COMPLIANCE - CUSTOMER
REQUESTS
The following table and chart reflect the
number of development compliance
related investigations undertaken as a
result of customer enquiries for the
quarter.
In many instances the investigation of
enquiries and complaints may require a
number of inspections, letters, possibly
enforcement notices issued and court
appearances made by staff; however,
this is not reflected in the provided
figures.
COMPLIANCE - CUSTOMER REQUESTS
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Advertising /
Signage 6 15 20 9 10
Breach of
Approval 35 46 49 26 50
Change of Use 1 2 2 1
Control of Dust 5 3 9 5 10
Development
General/Misc 26 32 42 65 72
Election Signage 1 1
Fencing /
Retaining 5 7 11 4 6
Home Activities 5 11 8 10 10
Other 48 48 50 45 55
Proactive /
Internal 19 1 11 13 17
Significant Tree
Removal 3 5 2 7 5
Stormwater
Flooding 6 17 37 22 17
Unauthorised
Development 16 26 41 44 30
Unsightly
Premises 25 9 19 17 27
TOTALS 199 222 301 270 310
THE QUARTER OCT-DEC 2020 COMPLIANCE REQUESTS
Page 13 of 59PLANNING & REGULATORY SERVICES
BUILDING AND COMPLIANCE -
INSPECTIONS
The Building Team has carried out
inspections of building work, new pool
inspections and building compliance
inspections over the quarter.
Inspections by the Building Team are
reflected within the following table and
bar chart.
In many instances the inspection of
building work or a swimming pool will
reveal non-compliance with the Building
Rules and as a result require further BUILDING AND COMPLIANCE - INSPECTIONS
inspections and follow up with builders
and/or owners, and in some cases the
issuing of enforcement notices.
2019 2020 2020 2020* 2020
However, this activity is not reflected in Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
these figures. Building
Inspections 275 236 270 193 185
Compliance
Inspections 1 6 1 4 3
Swimming Pool
Inspections 59 51 49 22 41
TOTALS 335 293 320 219 229
*
Please note, figures for the Apr-Jun
2020 period may be indicative of any
changes to service in response to
COVID-19 restrictions (as stated on
page 2 of this report).
THE QUARTER OCT-DEC 2020 BUILDING & COMPLIANCE INSPECTIONS
Page 14 of 59PLANNING & REGULATORY SERVICES
COMMUNITY HEALTH - CUSTOMER
REQUESTS
Environmental Health Officers respond
to customer requests with regard to
communicable disease (eg poor food
handling practices and dirty premises,
alleged risks to health, failed
wastewater systems, unhygienic skin
penetration operations and public pools)
COMMUNITY HEALTH - CUSTOMER REQUESTS
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Food 66 40 17 29 30
Public Health 114 174 156 130 108
TOTALS 180 214 173 159 138
COMMUNITY HEALTH -
INSPECTIONS
Environmental Health Officers
undertake proactive inspections of
activities and businesses at risk of
spreading communicable disease,
activities include:
- food businesses serving vulnerable
populations are audited in accordance
with their audit frequency
- high risk food businesses are
inspected against national food safety
standards
- public swimming pools and spa pools
are tested to ensure public health and
safety
- skin penetration businesses are
inspected to ensure adequate sanitation ENVIRONMENTAL HEALTH - INSPECTIONS
and hygiene
- high risk manufactured water systems 2019 2020 2020 2020 2020
(cooling towers and warm water Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
systems) are audited.
Food Audits 12 12 11 13 9
Food Inspections 202 239 302 279 176
HRMWS Audits 6 7 2 1
Public Swimming
Pools 16 21 10 17 22
Skin Penetration 1 2 7
TOTALS 231 280 330 311 215
THE QUARTER OCT-DEC 2020 ENVIRONMENTAL HEALTH REQUESTS & INSPECTIONS
Page 15 of 59PLANNING & REGULATORY SERVICES
IMMUNISATION - VACCINES
DELIVERED (CITY OF
ONKAPARINGA)
Registered Nurses provide regular
public immunisation clinics, deliver the
school based immunisation program
and offer workplace vaccines in line with
the National Immunisation Program,
Immunisation Schedule.
IMMUNISATION - VACCINES DELIVERED (CITY OF ONKAPARINGA)
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Childhood Clinics 1,032 1,069 2,865 775 533
School 1,930 845 3,232 1,470 1,417
Workplace 0 502 1,237 0 0
TOTALS 2,962 2,416 7,334 2,245 1,950
IMMUNISATION - RATES
We share a responsibility with other
levels of government and healthcare
providers to improve immunisation
coverage. Immunisation services are
primarily provided by Council and
General Practitioners with a small
percentage of vaccines delivered by
Aboriginal Health Services, Community
Health Centres and Hospitals. Vaccines
are delivered in accordance with the
National Immunisation Program,
Immunisation Schedule.
*Fully immunised at 60-PLANNING & REGULATORY SERVICES
COMMUNITY HEALTH -
WASTEWATER APPLICATIONS
Environmental Health Officers assess
wastewater applications (septic tank
systems) and inspect the installation of
systems to ensure public health and
safety.
COMMUNITY HEALTH - WASTEWATER APPLICATIONS
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Wastewater
Applications 34 47 50 58 80
THE QUARTER OCT-DEC 2020 WASTEWATER APPLICATIONS
Page 17 of 59PLANNING & REGULATORY SERVICES
COMMUNITY RANGERS - ANIMAL
MANAGEMENT
Community Rangers:
- Recognise and promote the majority of
responsible pet owners in our
community.
- Respond to customer requests of dogs
wandering, dog attacks and barking
dogs.
- Promote the identification,
microchipping and desexing of dogs and
cats.
- Provide education on the impact of
stray and partially owned cats.
COMMUNITY RANGERS - ANIMAL MANAGEMENT
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Cat 2 1 1 1
Dog- Additional
Permit 30 64 92 48 33
Dog - Attack/
Harassment 97 77 107 115 126
Dog - Barking 63 106 96 111 68
Dog - Other 328 446 446 504 370
Dog - Pickup/
Wandering 286 300 318 369 314
TOTALS 806 994 1,059 1,148 912
COMMUNITY RANGERS – BYLAWS
Community Rangers investigate and
respond to reports of non-compliance
with council’s by-laws and the Local
Government Act 1999. Key activities
include abandoned vehicles,
overhanging vegetation and foreshore
activities.
COMMUNITY RANGERS – BYLAWS
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Abandoned
Vehicles 116 160 127 131 115
Bylaws - Other 48 67 74 77 65
Footpath
Obstruction 25 21 20 22 22
TOTALS 189 248 221 230 202
THE QUARTER OCT-DEC 2020 ANIMAL MANAGEMENT & BYLAWS
Page 18 of 59PLANNING & REGULATORY SERVICES
LOCAL NUISANCE AND LITTER
CONTROL
The Local Nuisance provisions of the
Local Nuisance and Litter Control Act
2016 commenced on 1 July 2017
introducing offences for nuisances
involving noise, animals, smoke,
odour, unsightly conditions and
depositing of rubbish.
Customer requests relating to this Act
are detailed in the adjacent table.
Request types are managed by a
number of teams including Rangers,
Development Compliance, Fire
Prevention and Environmental Health.
LOCAL NUISANCE REQUESTS
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Insanitary 8 10 19 14 14
LN-Dust -
Development Site -
Compliance 1
LN-Odour -
Spraypaint - Health 1 2
Noise 8 7 15 18 12
Nuisance Animals 9 21 21 17 26
Odour 4 7 6 13 4
Rubbish Dumped 87 129 141 111 108
Smoke 7 1 15 15 2
Unsightly 4 9 5 1 4
TOTALS 127 185 224 189 171
THE QUARTER OCT-DEC 2020 LOCAL NUISANCE
Page 19 of 59PLANNING & REGULATORY SERVICES
COMMUNITY RANGERS -
FORESHORE
Community Rangers ensure effective
management of foreshore activities,
particularly in relation to vehicle access,
dog behaviour and Australia Day
celebrations.
COMMUNITY RANGERS - FORESHORE
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Foreshore -
General 5 8 6 1 10
Foreshore - Jet
Skis 1
Vehicles On
Beach 2 5 14 13 4
TOTALS 8 13 20 14 14
COMMUNITY RANGERS – PARKING
REQUESTS
Community Rangers undertake both
proactive and re-active enforcement of
parking controls. Enforcement is
prioritised in the following order -
hazardous parking (around schools, on
footpaths, in bus and bicycle lanes),
followed by permit holder access
(disabled parking spaces) and lastly,
turnover of trade (time limited parking).
Key Activities include: education about
parking regulations, parking expiations,
complaint resolution, general patrols, COMMUNITY RANGERS – PARKING REQUESTS
parking management at 57 schools and
Private Parking Area management at 2019 2020 2020 2020 2020
Seaford Shopping Centre.
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Parking Requests 434 484 368 388 344
THE QUARTER OCT-DEC 2020 FORESHORE & PARKING
Page 20 of 59PLANNING & REGULATORY SERVICES
BURNING IN THE OPEN PERMITS
Our Fire Prevention Officers manage
requests for permission to burn during
the non-fire danger season for the
purpose of bushfire hazard reduction.
Permits are issued on non-domestic
premises in accordance with the
Environmental Protection (Air Quality)
Policy.
Please note that as no burning permits
were requested in the Jan-Mar 2019
BURNING PERMITS (ENVIRONMENT PROTECTION ACT)
period, there is no data to display.
2019 2020 2020 2020
Oct - Dec Apr - Jun Jul - Sep Oct - Dec
Burning Permits 9 73 64 10
THE QUARTER OCT-DEC 2020 FIRE PREVENTION
Page 21 of 59PLANNING & REGULATORY SERVICES
PROJECT REPORTING
Est Completion Percent On
On Time
LOCAL HERITAGE INITIATIVES Date Complete Budget
30/06/21 50% Y Y
The Local Heritage Incentive Scheme comprises the Local Heritage Fund and the Heritage Advisory Service, both of which
assist the community in heritage conservation. The Local Heritage Fund distributes grants annually to owners of local heritage
places to assist with practical conservation works.
Status Update
In this quarter, we progressed assessment of heritage grant related to works at 30 St Matthews Street, Willunga, 62 Grants
Gully Road, Clarendon, 17 St Marys Street, Willunga, 35 High Street, Willunga and 120 Little Road, Whites Valley. A report
was presented to SDC on 1 December 2020 for approval of works at 62 Grants Gully Road, Clarendon as the requested grant
amount was above $5,000.
Est Completion Percent On
On Time
SELLICKS BEACH STRUCTURE PLAN Date Complete Budget
30/06/21 10% Y Y
A structure plan is being prepared for Sellicks Beach for the Deferred Urban Zone, Primary Production Zone (outside of the
Character Preservation District), and the (existing) Residential Zone. A structure plan is not a rezoning exercise nor will it
deliver on the ground infrastructure, its purpose is to provide a strategic approach to guide growth in the area that is also
reflective of community values and aspirations. The Sellicks Beach Structure Plan will inform the location, form and
sequencing of development together with what infrastructure and services will be required to support the community and to
facilitate appropriate urban development.
Status Update
The Sellicks Beach Structure Plan project is progressing. The draft Structure Plan and the Community Engagement Plan were
endorsed by Council on 30 November 2020 for the purposes of community consultation. Community engagement with the
wider community and relevant stakeholders has now commenced. We are seeking to understand the communities' vision for
the future development of Sellicks Beach, their satisfaction levels and their views on what they consider are important
attributes of the area. We have sought to pique interest over the engagement period through various means such as
preparation of fact sheets, roadside banners, direct mail out, Your Say page with interactive mapping tool, static displays,
series of short videos, social media posts and the holding of three community information sessions which are scheduled to be
held in early February 2021. Council's Development Policy Team staff have also met with two representatives from each of the
four resident community groups in Sellicks Beach as part of this process to explore their concerns, opinions and the range of
issues and opportunities that they consider Sellicks Beach should look like in the future. This meeting particularly focused on
character, sustainability principles, land use and residential density, roads and transport. An additional resident community
group meeting has also been scheduled to be held in late January 2021 to continue our discussions in more detail. At the
conclusion of the engagement process, Council will be provided with a review of all feedback received, details of how the draft
Structure Plan has been amended and to seek adoption of the final Sellicks Beach Structure Plan.
THE QUARTER OCT-DEC 2020 PLANNING & REGULATORY SERVICES - PROJECT REPORTING
Page 22 of 59PLANNING & REGULATORY SERVICES
Est Completion Percent On
SOUTH AUSTRALIAN PLANNING REFORMS + SYSTEM On Time
Date Complete Budget
CHANGES
31/12/20 80% Y Y
Council maintains a strong commitment to reviewing and responding to proposed changes to the South Australian planning
system by government and other industry sectors. Doing so ensures we remain engaged in these deliberations and protect
the interests of our community but also ensures that we flag any significant implications to our council should the ideas be
implemented by government.
Status Update
The State Planning Commission has received substantial feedback from local government, the building industry and the
community on the State’s new planning system. In seeking to overcome concerns of and in response to industry, local council,
and community feedback, the State Government provided an additional six-week consultation period (from early November to
18 December) to allow more time to understand the updated Code, to prepare and become business ready before the new
code is implemented and to identify issues regarding the proposed changes. Council staff have continued to provide feedback
to the content and the spatial application of these changes. More recently, staff prepared a second submission to the State
Government (endorsed by Council at its meeting 8 December 2020) which provided a clear position of the administration on
the revised draft Planning and Design Code, new zone modules and new and amended technical overlays. This was to ensure
that the proposed planning policy is the best and most appropriate fit for future development of our council area. All formal
submissions have now be considered by the State Planning Commission (Commission) and it has since been announced by
the Minister, the Honourable Vickie Chapman MP that Phase Three of the Planning and Design Code will be implemented on
19 March 2021.
THE QUARTER OCT-DEC 2020 PLANNING & REGULATORY SERVICES - PROJECT REPORTING
Page 23 of 59CITY OPERATIONS
KIRK RICHARDSON, DIRECTOR CITY OPERATIONS
Managers:
Morgan Ellingham, Manager Assets and Technical Services
Matt Buckell, Manager Construction and Projects
Daryl Sowerby, Manager Parks and Facility Operations
Jessica Tucker, Manager Fleet, Civil and Waste
OUR ROLE IS TO EFFICIENTLY AND ASSETS AND TECHNICAL SERVICES
EFFECTIVELY PLAN FOR,
INTRODUCE, IMPROVE AND Community Assets
REJUVENATE INFRASTRUCTURE
AND COMMUNITY ASSETS Infrastructure Asset Management
THROUGH THE DELIVERY OF THE Spatial Information Services
FOLLOWING SERVICES FOR OUR
COMMUNITY. Technical Services
PARKS AND FACILITY OPERATIONS
Facility Operations
Parks and Natural Resources
FLEET, CIVIL AND WASTE OPERATIONS
Business Support
Fleet and Stores
Waste & Recycling
Civil Maintenance
CONSTRUCTION AND PROJECTS
Projects
Construction
THE QUARTER OCT-DEC 2020 CITY OPERATIONS
Page 24 of 59CITY OPERATIONS
CIVIL MAINTENANCE -
CUSTOMER REQUESTS
This graph and table represent the
number of customer requests received
in relation to civil maintenance. They are
related to general maintenance on
sealed and unsealed roads, kerbing
and/or drainage matters.
CIVIL MAINTENANCE - CUSTOMER REQUESTS
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Civil Priority 85 99 108 120 105
Dead Animals 72 61 70 88 82
Drainage 44 97 197 96 67
Footpath & Verge 194 153 218 202 142
Sealed Roads 144 187 274 415 297
Unsealed Roads 9 7 14 20 8
TOTALS 548 604 881 941 701
FACILITY OPERATIONS -
CUSTOMER REQUESTS
This graph and table represent the
number of customer requests
received and recorded proactive
tasks in relation to our facility
management and asset protection.
These relate to graffiti removal,
building and/or general
maintenance, security and/or
vandalism issues, signage or
sports grounds.
FACILITY OPERATIONS - CUSTOMER REQUESTS
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Building Maintenance 488 537 447 602 471
Grafitti 432 524 438 475 383
Maintenance 118 163 149 165 118
Security 14 14 21 23 19
Signs 312 281 358 403 354
Sports Grounds 11 23 28 26 8
Syringe 19 11 27 17 9
Vandalism 17 19 21 18 20
TOTALS 1,411 1,572 1,489 1,729 1,382
THE QUARTER OCT-DEC 2020 CIVIL MAINTENANCE & FACILITY MANAGEMENT AND ASSET PROTECTION
Page 25 of 59CITY OPERATIONS
PARKS AND NATURAL RESOURCES -
OPERATIONAL REQUESTS AND
PROACTIVE TASKS
This graph and table represent the
number of customer requests received
and recorded proactive tasks in relation
to our Parks and Natural Resources
services. These relate to trees, parks
and gardens maintenance, ovals,
irrigation works, nature conservation
and biodiversity activities and weed
control.
PARKS AND NATURAL RESOURCES - OPERATIONAL REQUESTS
AND PROACTIVE TASKS
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Bio-Diversity 23 34 36 30 38
Irrigation 29 36 13 21 26
Landscapes 7 6 11 13 12
Mowing 196 62 39 103 316
Parks Priority 119 195 131 134 167
Trees 1,401 1,972 1,912 1,796 1,690
Weed Control 329 101 64 197 311
TOTALS 2,104 2,406 2,206 2,294 2,560
THE QUARTER OCT-DEC 2020 PARKS AND NATURAL RESOURCES
Page 26 of 59CITY OPERATIONS
WASTE AND RECYCLING -
CUSTOMER REQUESTS
This graph and table represent
the number of customer
requests received and
recorded proactive tasks in
relation to our Waste and
Recycling services.
WASTE AND RECYCLING - CUSTOMER REQUESTS
2019 2020 2020 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Green Organics Passes 1,951 1,265 2,602 2,505 1,682
Hard Waste Collections 2,773 3,382 3,588 3,868 3,387
Illegally Dumped
Rubbish 574 726 679 660 574
Kerbside Green Organics 1,562 2,489 1,883 1,903 2,310
Kerbside Recycling 1,237 1,569 1,490 1,523 1,470
Kerbside Waste 2,248 2,800 2,425 2,541 2,503
Other 92 143 55 67 64
Road/Street Sweeping 37 132 88 59 64
TOTALS 10,474 12,506 12,810 13,126 12,054
CONSTRUCTION PROJECTS BY CONSTRUCTION PROJECTS BY STAGE (PROJECT AND CAPITAL
STAGE (PROJECT AND CAPITAL WORKS )
WORKS )
Not Commenced 169
This table represents the Project and
Capital Works projects delivered by the In Progress 29
City Operations Construction team. Completed 71
Project stages are represented as either On Hold 1
'Not commenced' meaning the start date
TOTALS 270
for the project has not yet commenced,
'In Progress' meaning the project start
date has commenced, 'Completed'
meaning the project is complete and 'On
Hold' meaning the project is currently
awaiting additional information or
resources.
THE QUARTER OCT-DEC 2020 WASTE AND RECYCLING & CONSTRUCTION
Page 27 of 59CITY OPERATIONS
PROJECT REPORTING
Est Completion Percent On
3 YEAR ROLLING CAPITAL WORKS PROGRAM DEVELOPMENT On Time
Date Complete Budget
(2019-20 - 2021-22)
1/08/21 90% Y Y
Ensure alignment of works spanning multiple categories and engage internal stakeholders at a program level and well in
advance of budgeting to ensure PCW bids are both accurate and achievable from a delivery perspective.
Objectives:
2020/21: Construction of PCW program.
2021/22 projects: Complete preliminary designs by March 2021 for budget allocations. Complete all designs by end of June
2021.
2022/23 projects: Project scope PM2s completed by end of June 2021 to inform the 2021/22 design program and 2022/23
allocations.
Status Update
We are currently constructing projects on the 2020-21 PCW program. Scoping for the 2021-22 financial year is almost
complete and we plan on starting the 2022-23 scoping in February. We are currently progressing with the designs of the
2021-22 projects and aim to have all preliminary designs completed by March 2021 to inform budget allocations. A substantial
effort has been made to streamline the processes and ensure all aspects of the business are kept informed and involved,
which has resulted in efficient delivery of the program and high quality projects.
Est Completion Percent On
ALDINGA SPORTS PARK - MASTER PLAN AND STAGE 1 On Time
Date Complete Budget
UPGRADES
30/06/22 10% Y Y
This project involves the planning and implementation of several projects to upgrade the Aldinga Sports Park (ASP). The
focus of delivery in 2020/21 is the completion of a site master plan, delivery of a soccer pitch and club building with federal
funding, relocating equestrian and upgrading existing sports facilities including netball courts, cricket nets and lighting for
hockey, bowls and croquet.
Status Update
The draft Aldinga Sports Park Master Plan was finalised following feedback from community engagement. A report presenting
the results of engagement and approval of the final master plan was approved by Council's Strategic Directions Committee on
2 February 2021. The concept development for the shared soccer and hockey clubroom building is underway, informed by
engagement with the clubs and preliminary costing (part of the $2.26M Federal grant funding). Detailed design of the Stage 1
civil works (including design of site services upgrade, car parking, earthworks, storm water, sports lighting and the soccer
pitch), is progressing. The identification of a suitable site for relocation of the Aldinga equestrian clubs is continuing, The re-
construction of the netball courts commenced in November 2020.
Est Completion Percent On
CHRISTIE DOWNS RENEWAL - MORTON ROAD RESERVE On Time
Date Complete Budget
UPGRADE (DESIGN)
30/09/21 60% Y Y
Morton Road Sports and Community Hub upgrade will create an active, family friendly destination featuring a skate park,
multi-use courts, junior and youth playspaces, barbecue facilities, irrigated lawns and public toilets.
The City of Onkaparinga has received $1.5M state government grant funding through the Open Space Places for People
Program for the Morton Road reserve upgrade, Christie Downs. The Roger Rasheed Sport Foundation (RRSF) has pledged a
further $100,000 towards the project which will expand the scope to include two multi-use tennis courts.
The Commonwealth Government has also contributed $400,000 for the tennis courts and oval through the Local Roads and
Community Infrastructure grant program.
This grant funding will enable delivery of a $3.5M upgrade of this reserve. This will focus on priority open space facilities
including a skate park, tennis courts and adventure play space.
Status Update
Construction of the Skate Park commenced on the 16 of November 2020 and is well underway. The first obstacles have been
formed up and poured including flat banks, suspended ledge, kerb ledges, banks and transition platforms. Works paused over
Christmas and the New Year period. Completion of the skate park is anticipated by March.
Construction of the multi-use courts commenced February 2021.
Documentation for the wider reserve works has been finalised and procurement for construction commenced December 2020.
Construction is anticipated to commence mid March 2021.
THE QUARTER OCT-DEC 2020 CITY OPERATIONS - PROJECT REPORTING
Page 28 of 59CITY OPERATIONS
Est Completion Percent On
On Time
CONTINUOUS IMPROVEMENT - ASSET MANAGEMENT Date Complete Budget
30/06/22 90% Y Y
Efficiency gains identified by the Infrastructure Assets team
Status Update
Process mapping of new asset creation and valuation methodologies plus condition monitoring is underway to take advantage
of the Technology One ALM modelling abilities.
Discussions around the governance of asset creation to empower staff at the correct level for managing the complex assets
have commenced. These discussion have included considerations such as financial audit-ability of asset creation versus the
flexibility required to enable works to be booked to assets that may not as yet be in the system.
Est Completion Percent On
On Time
FLAGSTAFF HILL COMMUNITY CENTRE UPGRADES Date Complete Budget
1/06/21 60% X Y
Development of new building, sports and recreation facilities at the Flagstaff Hill Community Centre including upgrading of the
clubroom social space, new changeroom facilities, renewal of cricket nets, upgraded play spaces and supporting upgrades to
site services and amenity.
Status Update
This complex project has numerous components: 1) the change room module 2) playground upgrades. 3). cricket net upgrade
4) site services upgrade including stormwater drainage 5) pathway and landscape improvements integrated with new project
works. Works completed by end 2020 include the two playgrounds, and installation of site services infrastructure including
new stormwater and sewer connections to York Drive. Construction of the cricket nets was delayed due to the COVID-19
lockdown and contractor availability and is now expected to be complete by early March. The tennis court re-build project
commenced in December and is expected to be complete by early April. Regarding the changeroom building project, the
funding agreement between the Flagstaff Community Centre (FCC) and Council has now been finalised and executed.
Development approval has been granted (12 January 2021) and issued to the FCC. Funds from the FCC were received by
Council (11 February 2021). Council will now proceed to engage AUSCO to deliver the changeroom building with completion
anticipated in early July 2021.
Est Completion Percent On
On Time
FLAT TO VALE TRAIL (DESIGN) Date Complete Budget
30/04/21 40% Y Y
2.5m wide Shared Path link from McLaren Vale Sports Ground to McLaren Flat (Blewitt Springs Road)
Status Update
Flat to Vale Trail preliminary design is underway. Detailed survey and geotechnical investigations are complete. The concept
design is being finalised subject to the final pathway alignment around the McLaren Vale Sports Club (MVSC), delayed due to
amendments requested by the club late last year. Community consultation for the project was undertaken between 10 October
and 9 November 2020 with positive feedback received. Landowner negotiations are ongoing and once finalised Technical
Services team will finalise the engineering drawings to detailed design status.
Est Completion Percent On
On Time
HACKHAM SOUTH EAST INFRASTRUCTURE UPGRADES Date Complete Budget
30/06/22 30% Y Y
As part of the rezoning of an area of land in Hackham and Onkaparinga Hills in 2015, landowners that wish to develop are
required to enter into an infrastructure agreement with council to contribute to the upgrade of roads, stormwater and lighting.
This project encompasses the infrastructure works that council is required to construct under these agreements.
Status Update
In 2020-21 Council’s planned works include;
• Highview Court roadworks – scheduled to commence in January 2021 in conjunction with adjacent development works.
• Sturt Lane (part) roadworks – scheduled to commence in February 2021 in conjunction with adjacent development works.
• Hepenstal Road roadworks – is scheduled to commence in March 2021 by council’s internal construction crew.
The upgrade of Gates Rd is on hold to allow design and construction of this road to be coordinated with the planned
residential development works on the western side of Gates Road (outside of the area of Hackham SE bound by the
Infrastructure Contribution Agreement).
THE QUARTER OCT-DEC 2020 CITY OPERATIONS - PROJECT REPORTING
Page 29 of 59CITY OPERATIONS
Est Completion Percent On
HACKHAM SPORTS COMPLEX - UNISEX CHANGE ROOMS On Time
Date Complete Budget
CONSTRUCT
30/06/21 50% Y Y
To construct new unisex change rooms facilities for all players and officials, independent and adjacent to the existing change
room in line with State Sports and Australian Building Code specifications.
Status Update
The City of Onkaparinga received $500,000 (50%) in state government funding towards the construction of a new multi- use
unisex change room facility. To help promote participation in sport by community members of all ages and capabilities, the
upgrade includes dedicated umpire and player change rooms that meet modern sporting facility requirements. The project is
currently under construction with completion expected by June 21.
Est Completion Percent On
On Time
MCLAREN FLAT TENNIS/NETBALL - COURT REHABILITATION Date Complete Budget
Completed 100% Y Y
The three multi use courts within the McLaren Flat Recreation ground are cracking due to moisture content and poor drainage.
The cracking has left the courts in poor condition and in need of reconstruction. We have recently completed construction of
three new multi use courts which include new surrounding fencing and drainage to help protect new courts against future
moisture.
Status Update
Project 100% complete
Est Completion Percent On
NOARLUNGA OFFICE AIR CONDITIONING REPLACEMENT AND On Time
Date Complete Budget
ASSOCIATED WORKS
30/06/21 60% Y Y
The Noarlunga office air conditioning system has reached the end of its serviceable life and is at risk of a major failure. The
project involves upgrading the entire air conditioning system works including, renewing carpets on levels one and two,
painting, replacing ceilings and installing energy efficient LED lighting, electrical and data cabling. This work is an essential
asset replacement project involving critical building infrastructure. A staged 12 month implementation period is anticipated with
impacted staff required to relocate while works are undertaken.
Status Update
Following an open tender process, Shape Australia are delivering the project in four stages with works currently completed on
level one (stage 1) and ground floor west (stage 2), behind the customer service desk. Improvement of the ground floor east
area (stage 3) is currently underway with an anticipated early March completion date which will be followed by level 2 (stage
4) set to be completed in May 2021.
Est Completion Percent On
On Time
O'SULLIVAN BEACH COAST PARK - CONSTRUCTION Date Complete Budget
Completed 100% Y Y
The O'Sullivan Beach Coast Park encompasses a 700m section of foreshore spanning from the O'Sullivan Beach boat ramp
to Mentone Parade. This initiative is part funded through the Department for Planning, Transport & Infrastructure's Open
Space and Places for People grant program.
Status Update
Construction was completed in October 2020. The shared use path is now open to public.
Est Completion Percent On
On Time
PORT NOARLUNGA MULTI-USE SPORT BUILDING (DESIGN) Date Complete Budget
30/06/22 10% Y Y
New building facility combining sports and social facilities sited adjacent the Port Noarlunga Sports Ground oval and hard-
courts.
Status Update
The State Government's Local Government Infrastructure Partnership Program now provides an opportunity to apply for
matching funding ($1.65M) enabling delivery of the project over a single stage. This grant application was submitted in
January 2021. Concept design has progressed with input from key stakeholders. Preliminary costing has been undertaken to
test design feasibility against the project budget.
THE QUARTER OCT-DEC 2020 CITY OPERATIONS - PROJECT REPORTING
Page 30 of 59CITY OPERATIONS
Est Completion Percent On
On Time
PORT NOARLUNGA WEARING STREET PRECINCT - (DESIGN) Date Complete Budget
30/09/22 40% Y Y
Development of a detailed plan for rejuvenation and redevelopment of the Wearing Street Aquatics and Arts precinct
comprising the Onkaparinga riverfront and surrounds of the historic Sauerbier Homestead.
Status Update
Community engagement on the Wearing Street project has been an ongoing focus with several modifications to the concept
plan developed in response to community feedback. Following the CEO review of the project, the 8 December 2020 meeting
of Council approved a revised concept plan for the site which creates a larger aquatic launch area with two riverbank access
ramps and an increase of 40 riverfront carparks (overall total of 65 carparks within the precinct). The concept plans will be
further developed and staged construction of the estimated $4.8M project is anticipated to commence in spring 2021, subject
to securing additional external funding, the transfer of state government owned land to council and statutory approvals.
Engagement with local Kaurna communities is continuing.
Est Completion Percent On
PORT WILLUNGA NORTH COAST PARK - PLANNING AND On Time
Date Complete Budget
DESIGN
30/06/21 80% Y Y
Investigations and planning for the Maslin Beach unclad car park to the Former Caravan Park segment of the Port Willunga
North Coast Park.
Status Update
Community engagement commenced on the 14 September and closed on the 9 October 2020. Due to community interest and
community requests, engagement was extended to the 6 November 2020.
The outcomes of community engagement was presented to Council on the 19 January 2021 seeking approval to proceed to
detail design noting the planned design approach and amendments in response to the feedback.
Targeted stakeholder engagement will continue with select land holders to inform options to navigate Chinaman Gully.
Est Completion Percent On
On Time
PROJECT - OLD COACH ROAD, ALDINGA Date Complete Budget
26/03/21 95% Y Y
Reconstruct Old Coach Road from Iverene Road to Township Lane ASSETID: RSA79369(PART), RSA79370, RSA 79371
(PART)
Status Update
Old Coach Road reconstruction is from Township Lane to Iverene Road, Aldinga. The project consists of the reconstruction of
the road pavement, drainage infrastructure and shoulder works. The onsite construction commenced on the 20 July 2020.
Civil Construction works are complete with tree planting remaining and scheduled for May 2021.
Est Completion Percent On
On Time
STRATEGIC ASSET MANAGEMENT PLAN 2020 (SAMP) Date Complete Budget
28/02/21 90% Y Y
Review of the content and framework of the Strategic Asset Management Plan (SAMP) to supercede the Corporate Asset
Management Plan (CAMP). The SAMP provides the community with an overview of the council owned assets, their status and
performance, how they are managed and what future improvements are required to achieve the outlined goals and objectives.
We are aiming to deliver a more concise community facing document.
Status Update
Following the Elected Member workshop in September 2020, Council were presented with a draft SAMP in November and we
engaged with the community between late November and mid December to seek feedback on the draft. The feedback was
presented to Council in its January meeting and the final document will be presented for endorsement at the February
meeting.
THE QUARTER OCT-DEC 2020 CITY OPERATIONS - PROJECT REPORTING
Page 31 of 59CITY OPERATIONS
Est Completion Percent On
STURT RIVER LINEAR PARK STAGE THREE (DESIGN AND On Time
Date Complete Budget
CONSTRUCT)
31/01/21 100% Y Y
The Sturt River Linear Park is a key component of Adelaide’s Metropolitan Open Space System (MOSS) providing a strategic
link in the open space network from the Adelaide Hills to the coast. This project involves the concept and detailed design of
stage three of the Sturt River Linear Park, from the Institute Building on Main Road to Horner’s Bridge in Coromandel Valley.
The project has both landscape and civil works. Landscape works include removal of woody weeds and revegetation with
local native and ornamental plants to improve amenity and water quality.
The civil works include a sealed shared use trail for pedestrians and cyclists, balustrade and fencing for user safety,
replacement of an existing bridge and installation of new pedestrian bridges.
Status Update
Sturt River Linear Park Stage 3 was completed mid December 2020 and is now open to the community. Project is currently in
landscape maintenance period and 12 month defects liability period.
A project launch is being coordinated with relevant federal and state ministers, mayors from both Onkaparinga and Mitcham
and scheduled to take place on 12 March 20201.
Est Completion Percent On
On Time
WITTON BLUFF BASE TRAIL Date Complete Budget
1/12/21 10% Y Y
The Witton Bluff Base Trail forms part of the State Government’s Coast Park initiative and the Council's Coast Park Plan 2019.
The section of coast around the base of Witton Bluff from Christies Beach to Port Noarlunga is approximately 1.37km long.
This project involves detailed design and construction of the base trail.
Status Update
State Government funding of $2.65 million for the Witton Bluff Base Trail was announced in May 2020 matching Council's
budgeted amount. The total project budget is $5.3 million. Completion of the project is required by December 2021.
Updates on the cliff stability, geotechnical, ecological assessment and a boardwalk design basis report have been completed.
The seawall remediation works concept design is being progressed. Community engagement outcomes and a Section 48
Prudential report were presented to Council for consideration in November. Procurement of the boardwalk structure, via an
ECI Design and Construct process, is underway. The coast of our council is significant to Kaurna in the context of the Tjilbruke
Dreaming Track. In acknowledging this, we remained focussed on engagement with Kaurna to ensure that cultural
considerations can be incorporated into the project.
THE QUARTER OCT-DEC 2020 CITY OPERATIONS - PROJECT REPORTING
Page 32 of 59COMMUNITY SERVICES
PHILOMENA TAYLOR, DIRECTOR COMMUNITY
SERVICES
Managers:
Terra Lea Ranson, Manager Community Capacity
Stuart Purves, Manager Libraries and Customer Relations
Nick Carr, Manager Recreation Services
THE COMMUNITY SERVICES COMMUNITY CAPACITY
DIVISION LEADS THE
DEVELOPMENT OF STRATEGIC Active Ageing and Disability
DIRECTIONS FOR OUR COMMUNITY
Community Development
AND ORGANISATION, ACHIEVED VIA
STRUCTURED ENGAGEMENT AND Youth
MANAGEMENT OF STRATEGIC Arts, Reconciliation & Cultural Development
RELATIONSHIPS WITH OUR
STAKEHOLDERS. IN SUPPORT OF
THIS, WE PROVIDE SERVICES AND LIBRARIES AND COMMUNITY CENTRES
WORK ALONGSIDE OUR RESIDENTS Libraries:
TO BUILD CAPACITY TO ACHIEVE
THEIR GOAL OF STRONG VIBRANT Aldinga Library
COMMUNITIES AS ARTICULATED IN
THE COMMUNITY PLAN 2035. Aberfoyle Hub Library
Noarlunga Library
Seaford Library
Willunga Library
Woodcroft Library
Customer Relations
RECREATION SERVICES
Recreation & Club Development
Recreation Facilities
THE QUARTER OCT-DEC 2020 COMMUNITY SERVICES
Page 33 of 59COMMUNITY SERVICES
COMMUNITY CAPACITY -
ACTIVITIES HELD
The table and graph present the
numbers of activities facilitated by the
Community Capacity section. These
activities are designed in consultation
with our residents and build their
capacity to build connections and a
sense of safety.
COMMUNITY CAPACITY - ACTIVITIES HELD
2019 2020 2020 * 2020 * 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Community
Development
Programs 188 113 180 210 169
Community
Events 37 11 21 12 22
Recreation and
Healthy Lifestyles 509 497 6 346 702
Youth
Development
programs and
committees 60 72 70 25 39
Youth events 190 145 163 165 99
TOTALS 984 838 440 758 1,031
COMMUNITY CAPACITY -
PARTICIPANTS AT ACTIVITIES
The table and graph present the
numbers of participants who attend the
activities facilitated by the Community
Capacity section.
COMMUNITY CAPACITY - PARTICIPANTS AT ACTIVITIES
2019 2020 2020* 2020* 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Community
Development
Programs 2,571 1,731 1,125 867 1,256
Community
Events 5,109 3,122 1,865 1,856 4,133
Recreation and
Healthy Lifestyles 15,209 11,287 97 5,495 7,275
*
Please note, figures for the Apr-Jun
Youth
Development
Programs and
and Jul-Sep 2020 periods may be Committees 316 336 371.5 266 232
indicative of any changes to service
Youth Events 1,736 1,027 11,760.5 1,288.5 773
in response to COVID-19 restrictions
(as stated on page 2 of this report). TOTALS 24,941 17,503 15,219 9,772.5 13,669
THE QUARTER OCT-DEC 2020 COMMUNITY CAPACITY
Page 34 of 59COMMUNITY SERVICES
COMMUNITY PROGRAMS -
SERVICES PROVIDED
The table and graph present the
numbers of services provided for our
residents who are ageing and/or
disabled.
COMMUNITY PROGRAMS - SERVICES PROVIDED
2019 2020 2020* 2020 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Community
transport
journeys 7,597 6,426 637 3,220 3,145
Hours of service
provided for the
ageing 16,523 14,975 10,147 13,354 12,715
Hours of services
provided for
people with
disabilities 1,606 1,134 462 1,341 2,249
Hours or service
provided for
carers 3,674 2,502 1,225 3,012 3,446
Number of meals
served 6,806 6,658 9,517 11,576 8,894
TOTALS 36,206 31,695 21,988 32,503 30,449
*
Please note, figures for the Apr-Jun
and Jul-Sep 2020 periods may be
indicative of any changes to service
in response to COVID-19 restrictions
(as stated on page 2 of this report).
THE QUARTER OCT-DEC 2020 COMMUNITY PROGRAMS
Page 35 of 59COMMUNITY SERVICES
CENTRES - NO OF ATTENDEES
CENTRES - NO OF ATTENDEES
The table presents the numbers of
participants who attend the activities of
our Centres to provide an indication of
2019 2020 2020
* 2020 * 2020
how well our centres are used. Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Arts Centres (2) 8,978 7,709 1,029 8,766 7,156
Community
Centres (8) 52,800 34,874 6,463 37,058 29,440
In-house
Community Halls
(5) 5,074 3,802 718 1,619 5,036
Positive Ageing
Centres (2) 9,307 7,025 280 6,320 6,447
Youth Centres (3) 11,417 12,959 734 9,646 6,969
TOTALS 87,576 66,369 9,223.5 63,408.5 55,048
CENTRES - HOURS OF USAGE
CENTRES - HOURS OF USAGE
The table presents the numbers of
hours of usage to provide an indication
of how well our centres are used.
2019 2020 2020 * 2020 * 2020
Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Arts Centres (2) 2,056 1,639 720 1,504 1,577
Community
Centres (8) 10,698 7,591 1,899 9,836 9,754
In-house
Community Halls
(5) 847.5 623 84.5 1,313 567.5
Positive Ageing
Centres (2) 2,179 2,186 102 1,581 1,803
Youth Centres (3) 7,655.75 7,473.25 187.5 7,796.75 4,052
TOTALS 23,436.25 19,512.25 2,993 22,030.75 17,753.5
CENTRES - NO OF VOLUNTEERS
CENTRES - NO OF VOLUNTEERS
The table presents the numbers of
volunteers who give their time to deliver
services through our separately
2019 2020 2020* 2020 * 2020
incorporated Community Centres. Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
No of Volunteers 517 487 406 464 447
TOTALS 517 487 406 464 447
CENTRES - VOLUNTEER HOURS
CENTRES - VOLUNTEER HOURS
The table presents the numbers of
hours of work contributed by Community
Centre volunteers to deliver services for
2019 2020 2020* 2020 * 2020
our residents. Oct - Dec Jan - Mar Apr - Jun Jul - Sep Oct - Dec
Volunteer Hours
Worked 18,000 13,336 4,943 16,281 13,950
TOTALS 18,000 13,336 4,943 16,281 13,950
*
Please note, figures for the Apr-Jun
and Jul-Sep 2020 periods may be
indicative of any changes to service
in response to COVID-19 restrictions
(as stated on page 2 of this report).
THE QUARTER OCT-DEC 2020 COMMUNITY CENTRES