Renewable Energy Scenarios - for Municipalities in South Africa January 2018 - CITY ENERGY

Page created by Corey Frank
 
CONTINUE READING
Renewable Energy Scenarios - for Municipalities in South Africa January 2018 - CITY ENERGY
Renewable
Energy Scenarios
for Municipalities in South Africa
January 2018
Renewable Energy Scenarios - for Municipalities in South Africa January 2018 - CITY ENERGY
Opportunities in Renewable Energy and Energy Efficiency for Municipalities in South Africa

                                            2
Renewable Energy Scenarios - for Municipalities in South Africa January 2018 - CITY ENERGY
Opportunities in Renewable Energy and Energy Efficiency for Municipalities in South Africa

Contents

1            Introduction................................................................................................................2
1.1          Structure of This Booklet.............................................................................................2

2            What is Renewable Electricity Generation?............................................................3
2.1          Some Key Terms..........................................................................................................3
2.2          Overview of the Legislation.........................................................................................4

3            Procuring Renewable Electricity..............................................................................6
3.1          Scenario One: Procuring Electricity From a SSEG......................................................6
3.2          Scenario Two: Procuring Electricity From an IPP........................................................7

4            Generating Renewable Electricity............................................................................10
4.1          Scenario Three: Generating RE for Own Use..............................................................10
4.2          Scenario Four: Generating RE for Sale........................................................................11

5            Facilitating Additional Electricity Services..............................................................13
5.1          Scenario Five: Wheeling of Private Sector Electricity..................................................13
5.2          Scenario Six: Increasing Energy Access and Reducing Energy Poverty.....................14
5.3          Scenario Seven: Operating a Storage Facility.............................................................16

    Produced by SALGA, in partnership with the Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ), Pretoria, January 2018

                                                                      1
Renewable Energy Scenarios - for Municipalities in South Africa January 2018 - CITY ENERGY
Renewable Energy Scenarios for Municipalities in South Africa

1. Introduction

The electricity industry is undergoing consider-                 ipalities. It is targeted at municipal councillors
able changes around the world. The key global                    and officials and outlines several possible sce-
trend in the electricity sector is to move away                  narios that a municipality may be faced with. The
from centralised generation and distribution                     booklet also outlines some ways in which mu-
monopolies to more localised and integrated                      nicipalities can respond to changes in the sector.
electricity systems. Increasingly, new play-
ers are becoming involved in generating and                      This booklet is part of a series of booklets about
distributing electricity at a local level. There is              Energy and Electricity for Municipalities. This
also a growing trend towards digitisation and                    booklet is about Renewable Energy. Another
alternative low-carbon electricity technologies.                 booklet in the series is about Opportunities for
This is driven by a reduction in the costs of                    Municipalities in Energy Efficiency. Other book-
renewable energy technologies, such as so-                       lets are under preparation, including a booklet
lar photovoltaic and wind turbines, combined                     on the Challenges in the Electricity Distribution
with increasing integration with telecommuni-                    Industry. The purpose of the series of booklets is
cations networks through smart metering.                         to provide municipalities with information on key
                                                                 topics within the energy and electricity sector that
These trends are also becoming visible in South Af-              have implications for the role of municipalities in
rica, which has a traditional monopolistic electricity           energy and electricity. The booklets also provide
industry. Eskom has been the primary generator                   guidance on dealing with the various issues as
and transmitter of electricity, with bulk electricity            well as access to additional resources.
being distributed to customers by both Eskom and
municipalities through local grids. However, there               1.1 Structure of This Booklet
is now an emerging trend where municipalities                    This booklet summarises three primary areas of
and consumers (such as local businesses and res-                 potential change, linked to the renewable ener-
idents) are beginning to generate their own elec-                gy trends. These are:
tricity. This is due to high electricity tariff increases,       •     Procuring electricity
supply constraints and load shedding, cost reduc-                •     Generating electricity
tion and increasing environmental awareness. This                •     Facilitating electricity
results in both a reduction in demand for electricity
and an increase in new players in the market.                    Within each of these sections, possible scenarios
                                                                 facing municipalities are presented, outlining the
Changes in the electricity sector have the po-                   key challenges and possible ways in which munici-
tential to create both risks and opportunities for               palities can respond to these trends and challenges.
municipalities. Without adequate preparation,
municipalities may not be able to adapt quickly                  It is important to note that this is a snapshot in
enough to the changing market. This could have                   time representing the status quo in early 2018.
a significant impact on income streams for mu-                   The renewable energy sector is very dynamic,
nicipalities, as well as result in a potential loss of           and opportunities and risks are evolving con-
opportunities in the new emerging sector.                        stantly. However, by proactively engaging with
                                                                 the changing environment of the electricity sector,
The purpose of this booklet, therefore, is to pro-               municipalities can continue to ensure that com-
vide background information on the current key                   munities have access to affordable, sustainable
topics in relation to renewable energy in munic-                 and simplified electricity services into the future.
                                                             2
Renewable Energy Scenarios - for Municipalities in South Africa January 2018 - CITY ENERGY
Renewable Energy Scenarios for Municipalities in South Africa

2. What is Renewable Electricity Generation?

Renewable electricity (RE) is generated by                  ogies, such as coal, nuclear and various renew-
resources that are easily replenished, such                 able energy technologies.
as wind, solar, biomass and hydro power. Re-
newable electricity generation, therefore, re-              Independent Power Producer (IPP)
fers to electricity from non-traditional forms              An IPP is defined as an entity in which the
of base load generation, such as large-scale                government or any organ of state does not
coal and nuclear. Renewable energy is much                  hold controlling ownership that undertakes or
more scalable than traditional forms of elec-               intends to undertake the development of new
tricity, with installations ranging in size from            generation capacity.
small residential ones to large-scale wind
farms. However, they are limited by the avail-              Levelised Cost of Electricity (LCOE)
ability of the renewable resources and often                An LCOE is way of calculating the value of a
a mix of technologies is required to accom-                 unit of electricity (at present Rand value) over
modate fluctuations in resource availability.               the lifetime of a generating asset. LCOE con-
RE may also involve additional investment in                siders a range of factors, such as financing,
the electricity grid infrastructure to allow for a          fuel, operational and maintenance costs, to
more flexible flow of electricity.                          determine a price for electricity generated from
                                                            a particular installation. LCOE costs are often
2.1     Some Key Terms                                      required for financing large-scale RE projects.
Balancing Costs
Balancing costs are the costs of having elec-               Power Purchase Agreement (PPA)
tricity reserves in place to accommodate the                A PPA is a contract that outlines the conditions of
difference in forecasted generation and the                 an agreement by a generator of energy and a pur-
actual generation from RE facilities. For exam-             chaser of that energy. PPAs are usually long term
ple, a wind farm may forecast production of                 and specify the rate at which the electricity will be
100MWh but only manages to produce 80MWh.                   bought for between the period of the agreement.
The system still needs to have the additional
20MWh in reserve. The cost of maintaining this              Renewable Energy Independent Power
reserve is called the balancing cost.                       Producer Procurement (REIPPP)
                                                            The REIPPP Programme was set up by
Grid Parity                                                 the state to add new sources to the ener-
Grid parity refers to a situation where the cost            gy mix in South Africa, as defined in the IRP.
of producing energy from a renewable energy                 Through the REIPPP, renewable energy is
source is similar to, or less than, the cost of pur-        purchased from IPPs and connected to the
chasing energy from the traditional electricity grid.       national electricity grid. For more info see:
                                                            https://www.ipp-projects.co.za/
Integrated Resource Plan (IRP)
The IRP is the National Electricity Plan and is a           Small-Scale Embedded Generator (SSEG)
subset of the Integrated Energy Plan (IEP). The             Small-scale embedded generation refers to
IRP directs the expansion of the electricity sup-           power generation facilities located at residential,
ply over the long term. The IRP lists targets for           commercial or industrial sites where the electric-
generation of electricity from different technol-           ity is generally also consumed. These are mainly

                                                        3
Renewable Energy Scenarios - for Municipalities in South Africa January 2018 - CITY ENERGY
Renewable Energy Scenarios for Municipalities in South Africa

solar photovoltaic (PV) systems, but also include                lution on the financial benefits of the con-
other technologies such as wind and biogas. A                    tract and authorised the municipal man-
SSEG customer generates electricity on the cus-                  ager to sign the contract on behalf of the
tomer’s side of the municipal electricity meter, to              municipality.
which the generation equipment is connected,
and which is synchronised with the municipal                The Electricity Regulation Act (No. 4 of 2006)
electricity grid (i.e. ‘embedded’).                         and the Electricity Regulation Amendment Act
                                                            (No. 28 of 2007) defines ‘municipality’ that
Wheeling                                                    has executive authority and rights to reticulate
Wheeling refers to the transportation of elec-              electricity within its boundary. These regula-
tricity from a generator to a customer using the            tions provide municipalities with the ‘authority
electricity grid. Since the wheeling of electric            function’ of energy reticulation. This function
energy requires the use of transmission and/or              includes the development of policies, drafting
distribution infrastructure, there is often an asso-        by-laws, setting tariffs, deciding how energy re-
ciated fee paid by the users to the infrastructure          ticulation services are provided and regulating
owners. This fee is called ‘use of system charge’.          the provision of these services in terms of the
                                                            by-laws and other mechanisms.
2.2     Overview of the Legislation
Electricity Distribution Mandate                            New Generation Regulations
The Constitution of the Republic South Afri-                Over and above the energy reticulation mandate,
ca (No. 108 of 1996) assigns to municipalities              there are also a number of regulations and rules
the responsibility for administering services to            that provide guidance on how municipalities can
communities in a sustainable way, including                 deal with new generation in their areas of control.
electricity reticulation and street lights.                 Some of these are summarised below:

The Municipal Systems Act (No. 32 of 1998)                  Electricity Regulation Act, 2006. New Gener-
defines the roles of municipalities as service              ation Regulations of 2011 (published as GNR.
authorities and assigns to municipalities the               399 in Government Gazette No. 34262 dated
right to determine the service provider that will           4 May 2011) provides regulations targeted spe-
distribute electricity within their boundaries.             cifically at government structures and outlines
                                                            the rules for the procurement and new gener-
The Municipal Finance Management Act (No. 56                ation capacity of electricity by organs of state.
of 2003) outlines the requirements for municipal-           The regulations state that the Minister of Energy
ities to set tariffs for service provision, including       may make a determination as to whether any
electricity tariffs. Section 33 of the MFMA stip-           new generation capacity shall be established
ulates that a municipality can only enter into a            by Eskom, another organ of state or an Inde-
contract imposing financial obligations on the              pendent Power Producer (IPP). If the new gen-
municipality beyond a three-year period if:                 eration capacity is established by an IPP then
•     A draft of the contract is publicly adver-            the Minister may also determine the identity
       tised for comment 60 days prior to the               of the buyer or, where applicable, the procur-
       municipal council meeting at which the               er and the buyer. The REIPPP is a programme
      contract will be considered for approval.             managed through such determination.
•     The municipal council has considered the
       financial implications of the contract and           The New Generation Regulations are important
      any comments received on the proposed                 for municipalities to take into account, particu-
      contract.                                             larly if they are intending to procure electricity
•     The municipal council has adopted a reso-             from an IPP. The potential impact of the New

                                                        4
Renewable Energy Scenarios - for Municipalities in South Africa January 2018 - CITY ENERGY
Renewable Energy Scenarios for Municipalities in South Africa

Generation Regulations for municipalities is             tricity is supplied either directly, through wheel-
discussed under sections 3 and 4.                        ing or to a facility on the same property, does
                                                         not need a generation licence but is required
Electricity Regulation Act, 2006. Schedule 2             to be registered with NERSA. These types of
Licensing Exemption And Registration Notice              systems also have to enter into a connection
(2018) defines which energy generation activi-           and use-of-the-system agreement with the lo-
ties are exempt from the requirement to apply            cal electricity distributor. These examples are
for and hold a licence. However, these activities        covered in more detail in the scenarios overleaf.
must be registered with the National Energy
Regulator of South Africa (NERSA).

There are many different types of exemptions
that are potentially relevant for municipalities.
For example, one of the new exemptions is that
a system with installed capacity of no more
than one megawatt (1MW), and where the elec-

                                                     5
Renewable Energy Scenarios - for Municipalities in South Africa January 2018 - CITY ENERGY
Renewable Energy Scenarios for Municipalities in South Africa

3. Procuring Renewable Electricity

The first broad area of transition linked to re-               What are the Key Challenges?
newable electricity is where the municipality is              If there is no system in place to accommodate
presented with the option of procuring elec-                  SSEGs (such as an application form), it is like-
tricity from generators other than Eskom. This                ly they will proceed to connect to the distribu-
could be from embedded small-scale genera-                    tion grid in an uncontrolled manner. This could
tors (SSEGs) which have excess electricity that               cause safety risks when there is a need for grid
they wish to sell to the municipality or projects             maintenance and it is not clear whether or not
run by Independent Power Producers (IPPs)                     there are SSEGs feeding into the grid.
set up specifically to sell electricity.
                                                              There is also a risk of loss of income to mu-
3.1 Scenario One: Procuring                                   nicipalities that distribute electricity, as a result
Electricity from a SSEG                                       of increasing numbers of SSEGs purchasing
What is the Scenario?                                         less electricity from municipalities once they
One of the most common scenarios a municipal-                 have invested in their own RE systems. This
ity is presented with is when a small-scale em-               migration of customers could be motivated by
bedded generator (SSEG) has excess electricity                security of supply, cheaper electricity or envi-
that can be fed back into a municipal grid. In                ronmental concerns.
this scenario, an existing customer who is con-
nected to the municipal grid installs an electricity          The loss of customers could be further inten-
generation system, such as solar photovoltaic                 sified if tariffs are increased to try and com-
panels or mini wind turbines. The customer is                 pensate for a decrease in revenue, pushing
not able to use all the electricity generated by              up prices further. This creates an additional in-
the SSEG system and would therefore like to sell              centive for customers to migrate to renewable
the excess electricity to the municipality.                   energy. It is, therefore, important to ensure that
                                                              the municipality establishes the correct pricing
                                                              structure to ensure that all customers, including
                                                              customers with SSEG, contribute to the cost of
                                                              maintaining the grid.

                                                               SSEGs intending to sell electricity to munici-
                                                               palities could fall into one of the categories for
                                                               exemption from licensing in terms of the new
                                                              “Schedule 2 Licensing Exemption And Regis-
                                                               tration Notice (2018)”. For example, a solar PV
                                                               rooftop installation that is 1MW or smaller in-
                                                               stalled on a property that is connected directly
                                                               to the municipal grid will not need a generation
                                                               licence. However, they will still be required to
                                                               be registered with NERSA and sign a connec-
                                                               tion and use-of-the-system agreement with the
                                                               municipality.
Credit: GIZ/Glenn McCreath

                                                          6
Renewable Energy Scenarios - for Municipalities in South Africa January 2018 - CITY ENERGY
Renewable Energy Scenarios for Municipalities in South Africa

 Resource Tip
                                                              What Should You Not Do?
 See the Small-Scale Embedded Generation                      Municipalities should not ignore SSEGs. There
 Impact Model to assess the potential impacts of              is a risk that uncontrolled grid connection will
 SSEGs on municipal revenue:                                  cause safety risks on the grid. Not responding
 http://www.cityenergy.org.za/uploads/resource_437.xlsx
                                                              to requests from SSEGs will also cause cus-
 http://www.cityenergy.org.za/uploads/resource_436.pdf
                                                              tomer frustration and may force them to relo-
                                                              cate or withdraw from the grid entirely.
What Should You Do?
Municipalities need to ensure there is a holistic             What is the Way Forward?
system in place to accommodate SSEGs con-                     These are some of the requirements:
necting to the local grid. The components of                  •   Finalisation of the NERSA regulatory rules
this system should include:                                       for SSEG to clarify the regulatory frame-
•     Revision of the metering and billing sys-                   work.
      tem (to allow for bi-directional flows of               •   Finalisation of technical standards or
      electricity).                                               guidelines, for example, for wiring code or
•     Definition of the requirements for a gener-                 metering requirements.
      ator to connect to the municipal grid and               •   National registry and reporting systems for
      the adoption of a clear application pro-                    SSEGs.
      cess for SSEGs.                                         •   Support for municipalities in electricity tar-
•     Design of embedded generation tariffs                       iff design.
      and an assessment of their implications                 •   Additional capacity (human resources) to
      for the municipality and for customers.                     be allocated by electricity departments to
•     Establishment of an embedded genera-                        this new area of work.
      tion tariff that is approved by NERSA.                  •   Electricity distribution departments to in-
•     Setting up a system for monitoring and re-                  clude new approaches into their work to
      porting on SSEG installations, as required                  retain customers and develop new reve-
      by NERSA.                                                   nue streams.
•     A communications campaign highlighting
      the new SSEG system and how the tariff                  3.2 Scenario Two: Procuring
      was designed.                                           Electricity from an IPP
                                                              What is the Scenario?
 Resource Tip                                                 There are Independent Power Producers (IPP)
 The AMEU SALGA SSEG Resource Pack
 provides templates for municipalities to establish
                                                              that would like to set up an electricity gener-
 sound SSEG permitting procedures. More documents             ation facility for the primary purpose of gener-
 are under development and will be added to the pack,         ating electricity and selling it to a municipality
 which currently contains the following five documents:       at a rate that is competitive when compared to
  •   Technical Requirements for Embedded                     the Eskom bulk tariff. In this scenario, a munic-
      Generation: http://www.cityenergy.org.za/               ipality is considering purchasing electricity from
      uploads/resource_410.pdf                                these IPPs.
  •   Application Form: http://www.cityenergy.org.
      za/uploads/resource_412.pdf                             What are the Key Challenges?
  •   Commissioning Report: http://www.cityenergy.            For IPPs to have a viable business model they
      org.za/uploads/resource_415.pdf                         will often require a long-term power purchase
  •   Customer Service Contract: http://www.                  agreement (PPA) with a municipality at a particu-
      cityenergy.org.za/uploads/resource_413.pdf              lar tariff. It is widespread practice for PPAs to in-
  •   Decommissioning Report: http://www.cityenergy.          clude tariff escalation over time. A key risk is that
      org.za/getfile.php?id=411&category=5                    the tariff escalation may result in the municipality

                                                          7
Renewable Energy Scenarios - for Municipalities in South Africa January 2018 - CITY ENERGY
Renewable Energy Scenarios for Municipalities in South Africa

paying in the long term for renewable electricity
at a higher rate than the bulk electricity price.                 Case Study: City of Cape Town
                                                            The City of Cape Town (CoCT) initiated a
There are also challenges related to capacity               process to purchase electricity from IPPs
within municipalities to adequately manage                  to meet its renewable energy and climate
the technical and financial complexity intro-               change commitments. From the outset the
duced by projects of this nature. For example,              CoCT acknowledged that the IPP would
the intermittent supply of renewable energy                 need to obtain a generation licence from
projects (only when the wind blows or the sun               NERSA. However, NERSA indicated that
shines) requires high levels of electricity de-             there was a requirement for a ministerial
mand-and-supply planning and tariff modelling.              determination for it to grant generation
                                                            licences, as per Section 34 of the Electricity
There are also risks related to the current regula-         Regulation Act (No 4 of 2006). Following two
tions in South Africa regarding the procurement             years of unsuccessful discussions between
of electricity by municipalities. The key regula-           the CoCT, NERSA and the Department of
tions that impact licensing of IPPs are the Elec-           Energy, the Minister of Energy refused to
tricity Regulation Act 4 of 2006 (ERA), and the             gazette the determination.
New Generation Regulations of 2011 (NGR). The
ERA states that ‘no person may operate a gen-               In 2017 the CoCT initiated legal proceed-
eration facility without a licence issued by NER-           ings against NERSA and the Minister re-
SA, unless exempt by the ERA as per Schedule                questing the court to allow the municipality
2’. The NGR states that the Minister of Energy              to buy electricity directly from the IPP. The
may make a ‘Section 34 Ministerial Determina-               basis of the court application is to test
tion’, which allows for new generation to take              whether a ministerial determination is in
place and determines to whom this electricity               fact needed (or is just a possibility) and,
can be sold. In effect, a Section 34 determina-             if the determination is needed, to test the
tion from the Minister of Energy may be needed              constitutionality of Section 34 of the Elec-
for a municipality to purchase electricity from an          tricity Regulation Act and the ministerial
IPP. This could be a very lengthy process with              determination process.
no guarantee of a positive outcome. This read-
ing of the regulations is, however, currently being
challenged in the courts (see case study below).

                                                      8
Renewable Energy Scenarios for Municipalities in South Africa

What Should You Do?                                         Resource Tip
The following steps outline a possible starting            Ekurhuleni Metropolitan Municipality is currently
                                                           following the process as described above. The
point for a municipality intending to explore the
                                                           eThekwini Municipality has a draft PPA that can be
possibility of procuring electricity from IPPs.            used as a template for other PPAs. See:
These steps have been developed based on                   www.cityenergy.org.za/uploads/resource_384.docx
lessons from municipalities that have started to
experiment with RE procurement.                           What Should You Not Do?
ŦŦ Step1 – Assess the need and set targets                Many municipalities are approached by pro-
     for alternative electricity procurement              spective IPPs with unsolicited bids requesting
     and generation. This assessment should               municipalities to sign memoranda of under-
     take into account costs not necessarily              standing (MoU) or PPAs that will allow them to
     reflected in the tariff, such as additional          generate electricity for the municipality. A PPA
     grid management costs. This assessment               without a formal procurement process should
     could lead to a general energy procure-              NOT be entered into with an IPP.
     ment strategy for the municipality which
     would analyse all scenarios and options              What Is the Way Forward?
     and their respective costs.                          These are some of the requirements:
ŦŦ Step 2 – Develop a local energy supply                 •   Secure policy clarity from the Department
     plan to define the best mix for a diversified            of Energy and other national departments
     energy supply portfolio.                                 around the scope for municipalities to procure
ŦŦ Step 3 – Ensure that NERSA and Treasury                    their own electricity. This could include the fol-
     (national and provincial) are aware of the               lowing, or a combination of the following:
     municipality’s intention to investigate pro-             •      Specific allocation for municipal RE
     curement from IPPs.                                             projects within the IRP with determi-
ŦŦ Step 4 – Develop a standard PPA that can                          nations from the Minister.
     be used for IPPs.                                        •      An implementation programme un-
ŦŦ Step 5 – Draft terms of reference for the                         der the IRP, which could be managed
     procurement of electricity from IPPs, out-                      in partnership with with IPP Office,
     lining the size and technology limitations.                     for example, where a municipal IPP
ŦŦ Step 6 – Conduct a procurement process                            procurement programme could be
     and assess the offers made by different                         developed and managed.
     IPPs.                                                    •      Dedicated support from NERSA for
ŦŦ Step 7 – Award preferred IPPs, subject to                         assisting the IPPs through the licens-
     the Section 33 process of the Municipal                         ing process.
     Finance Management Act (MFMA) of 2003                    •      Municipalities developing their own
     being concluded (i.e. approval to commit                        individual programmes.
     the city budget for a period exceeding               •   Conduct evidence-based research to
     three years) and the necessary electricity               quantify the costs and benefits of such
     generation licences being obtained by the                programmes to strengthen the municipal
     IPP from NERSA.                                          and SALGA lobbying position.
ŦŦ Step 8 – Conclude a final agreement on a               •   Undertake pilot projects (once policy clari-
     PPA between the municipality and the IPP,                ty and evidence-based research is in place)
     based on conclusion of the licensing and                 through the most capacitated municipalities.
     section 33 processes.                                •   Share lessons learnt and tools, such as
ŦŦ Step 9 – Conduct a grid connection as-                     standardised PPAs, terms of reference
     sessment.                                                and technical specifications, from these
                                                              pilot projects with other municipalities.

                                                      9
Renewable Energy Scenarios for Municipalities in South Africa

4. Generating Renewable Electricity

The second broad area of transition linked to re-            proves the handover and long-term functional-
newable electricity is where a municipality gen-             ity of the system.
erates its own electricity from renewable sourc-
es. This could be through the installation of a              The steps that can be followed include:
solar photovoltaic system, biogas digester or a              ŦŦ Step 1 – Assessment of the renewable en-
range of other renewable energy technologies.                     ergy resources available in the municipal-
                                                                  ity to help determine which technologies
4.1 Scenario Three: Generating                                    to focus on. This assessment could lead
RE for Own Use                                                    to a general energy procurement strategy
What is the Scenario?                                             for the municipality which would analyse
The municipality may decide to install a renew-                   all scenarios and options and their respec-
able energy system on existing infrastructure or                  tive costs.
buildings. This size of installation is designed to          ŦŦ Step 2 - Assess the need and set targets
supplement the electricity use of the infrastruc-                 for alternative electricity generation and
ture, but may also have excess energy to feed                     procurement.
into the grid during less-busy periods.                      ŦŦ Step 3 – Assessment of infrastructure (e.g.
                                                                  wastewater treatment works, building roofs,
What are the Key Challenges?                                      parking lots, etc.) for possible integration of
The primary risk with these types of smaller in-                  alternative electricity technologies.
stallations is the upfront capital cost associated           ŦŦ Step 4 – Conduct a feasibility study of po-
with the technology. For example, a one mega-                     tential installations.
watt (1MW) solar photovoltaic roof-top system                ŦŦ Step 5 – Ensure a budget allocation for the
may cost R15 million. As a result, there needs                    installation in the Medium-Term Expendi-
to be careful assessment of the financial impact                  ture Framework (MTEF).
of the installation over a long-term period.                 ŦŦ Step 6 – Issue a terms of reference for
                                                                  installations and conduct a procurement
 Resource Tip
                                                                  process.
 See the CSIR’s “A Guideline for Public Entities on
 Cost-efficient Procurement of PV assets”: https://
 researchspace.csir.co.za/dspace/handle/10204/9738           What Should You Not Do?
                                                             Municipalities should not install small-scale
What Should You Do?                                          systems that have very long payback periods
The installation of renewable energy systems                 (e.g. longer than 15 years) as this could be con-
will typically follow a standard supply chain                sidered wasteful expenditure. Municipalities
management process. It is also common                        should also not install systems that are inap-
practice to finance an installation of this size             propriate to the available resources. The design
from the municipal budget rather than sourc-                 and size of the installations should match the
ing finance from an external agency. It is good              available resources (wind, sunshine) and the
practice to include at least a three-year main-              potential use for the electricity.
tenance component in the installation contract,
or even longer for more complex installations.               What is the Way Forward?
Lessons learnt from pilot projects have shown                These are some of the requirements:
that having a maintenance contract greatly im-               •   Easily accessible renewable energy re-

                                                        10
Renewable Energy Scenarios for Municipalities in South Africa

        source information at a municipal level                  There are also various legislative and licensing
        (e.g. fine-scale wind and solar maps).                   requirements. The municipality will need to ap-
•       Support in identifying funding for pilot                 ply for an electricity generation licence and reg-
        projects.                                                ister the plant with NERSA (if it is above 1MW).
•       Standardised procurement documents and                   The municipality may also need a determination
        technical specifications for installations.              from the Minister of Energy to go ahead with
                                                                 the installation (refer to Scenario Two for more
    Resource Tip
                                                                 information on this).
    There are a number of case studies on municipal
    RE projects available on http://www.cityenergy.
    org.za/category.php?id=3#13                                  What Should You Do?
                                                                 Installations of this nature should be treated part-
4.2 Scenario Four: Generating                                    ly as infrastructure investment projects and partly
RE for Sale                                                      as potential income-generation projects (resulting
What is the Scenario?                                            from the generation and sale of electricity).
A municipality may decide to install a renewable
energy plant for the specific purpose of gener-                  The following steps should be considered when
ating electricity and feeding into the electricity               embarking on a project of this nature:
grid. This could be in the form of a waste-to-en-                ŦŦ Step 1 – Assess the renewable energy
ergy project, solar farm, wind farm or other type                     resources available in the municipality to
of renewable energy installation.                                     determine which technologies to focus on.
                                                                 ŦŦ Step 2 – Assess the need and set targets
What are the Key Challenges?                                          for alternative electricity generation and
Medium and large-scale electricity generation                         procurement. This assessment could lead
facilities can be very expensive. They require                        to a general energy procurement strategy
advanced technical, financial, contractual and                        for the municipality which would analyse
project skills. Careful financial planning will be                    all scenarios and options and their respec-
needed during the planning process.                                   tive costs.

                                                            11
Renewable Energy Scenarios for Municipalities in South Africa

Credit: GIZ/Glenn McCreath

ŦŦ Step 3 – Assess infrastructure (e.g. waste-                 It is current best practice to include an opera-
   water treatment works, building roofs,                      tional and maintenance component in the scope
   parking lots, etc.) for the possible integra-               of work or the terms of reference, where the
   tion of alternative electricity technologies.               external service provider will initially ensure the
ŦŦ Step 4 – Calculate a levelised cost of elec-                operation and maintenance of the facility, as well
   tricity (LCOE) for the potential installation.              as the transfer of knowledge to the municipality.
ŦŦ Step 5 – Conduct a feasibility study of po-
   tential installations.                                      What Is the Way Forward?
ŦŦ Step 6 – Investigate financing options,                     These are some of the requirements:
   which could include different types of                      •   Ensure there is a clear framework for mu-
   ownership and investment options.                               nicipal energy generation projects, for
ŦŦ Step 7 – Issue a terms of reference for in-                     example, through an implementation pro-
   stallations and conduct the procurement                         gramme under the IRP, in partnership with
   process.                                                        the IPP office, where municipal RE projects
                                                                   could be supported (refer to Scenario Two).
 A LCOE is recommended as it takes into account                •   Dedicated support from NERSA to assist
 the financing, operational and maintenance                        municipal RE projects through the licens-
 costs, as well as other costs, over the entire lifes-             ing process.
 pan of the project. This will provide an accurate             •   Work with National Treasury and other finan-
‘best value’ assessment with comparison to oth-                    cial institutions to unlock funding support and/
 er sources of electricity, such as Eskom. It will                 or surety for the investment in RE projects.
 also assist in securing financing for the project if
 required. There is currently a debate about how
 to include the co-benefits of renewable energy
 installations in LCOE assessments.

                                                          12
Renewable Energy Scenarios for Municipalities in South Africa

5. Facilitating Additional Electricity Services

The third broad area of transition linked to re-
newable electricity is where the municipality
plays a facilitator role in the sector. The munici-
pality could grant non-discriminatory third-par-
ty access to the grid to create an enabling envi-
ronment for new generation capacity, promote
alternative uses of energy as a service delivery
option or even develop electricity storage ca-
pacity as an economic driver.

5.1 Scenario Five: Wheeling of
Private Sector Electricity
Wheeling refers to the transport of electricity on
a grid. To better understand wheeling electricity,
it is useful to think of a road network analogy. If
a road network is well run and allows for several
types of vehicles, there is increased potential for
economic development and social upliftment                  Credit: GIZ/Glenn McCreath
opportunities. However, it is also important that
there is budget for the maintenance of the road             by stating there should be ‘non-discriminatory
network.                                                    network access to all users of the transmission
                                                            or distribution system’. NERSA has developed
If this analogy is applied to the electricity grid          guidelines and ‘Rules on network charges for
it would make sense to allow other entities to              third-party transportation of energy’, which out-
make use of the grid. This would stimulate eco-             line the process for calculating ‘use-of-system
nomic opportunities and social development by               charges’. Significant issues have been raised
allowing for new users of the network. However,             by municipalities and the sector regarding
users help to pay for the ongoing maintenance               these rules and, as a result, NERSA is current-
of the grid.                                                ly undergoing a consultation process to review
                                                            the rules and regulations.
What is the Scenario?
 An opportunity may arise where an IPP wants                Another risk with wheeling is that the munici-
 to sell electricity to a customer who is connect-          pality may lose the customer who is buying
 ed to the municipal grid. In this scenario, the            electricity through a wheeling process. This
 IPP requests access from the municipality to               can be partly managed if the tariff for grid
‘wheel’, or transport, electricity through the grid         usage is properly set, which should enable
 to another entity or customer.                             the municipality to recover a large portion of
                                                            the costs of managing the grid. However, the
What are the Key Challenges?                                loss of cross-subsidisation from this customer
The main risk with wheeling is that it is difficult         would require a revision of the municipal reve-
to determine how much to charge users of the                nue model to identify other areas of income for
grid. The ERA makes provision for wheeling                  cross-subsidisation.

                                                       13
Renewable Energy Scenarios for Municipalities in South Africa

A final challenge with wheeling is the increased                          grid, and support and capacity building to
administration burden associated with new                                 develop and analyse the cost-of-supply
types of customers. For example, the billing                              studies in municipalities.
system would need to be revised to accom-                         •       Finalisation of NERSA rules and guide-
modate wheeling charges and to differentiate                              lines and ‘Rules on network charges for
between electricity provided as municipal elec-                           third-party transportation of energy’.
tricity and electricity provided by a third party.                •       Greater understanding of the impact on
                                                                          municipal revenue (through the cost-of-
                                                                          supply study) and on the municipality’s ca-
  Resource Tip
 Nelson Mandela Bay Metropolitan Municipality                             pacity to cross-subsidise electricity from
 (NMBM) has initiated a wheeling agreement                                other revenue streams.
 process for green power trading. The Metro initially set
 a grid usage charge of 7% of the value of the electricity        5.2 Scenario Six: Increasing
 sold. This was later revised to 20% following a detailed
 cost-of-supply study. See: http://www.cityenergy.org.
                                                                  Energy Access and Reducing
 za/uploads/resource_341.pdf                                      Energy Poverty
                                                                  The final scenario relates to additional elec-
                                                                  tricity services where municipalities provide
What Should You Do?                                               alternative energy services to households to in-
Currently, there is uncertainty over estimating                   crease energy access and fight energy poverty.
costs for the grid ‘system charges’. It is critical
for municipalities to ensure that a cost-reflec-                  What is the Scenario?
tive tariff for wheeling is charged so that the                   Opportunities exist for municipalities to provide
municipality can recover all the costs associat-                  a basket of renewable and alternative energy
ed with the grid.                                                 services to households that do not have access
                                                                  to grid-connected electricity. This could be
The steps that a municipality could follow to fa-                 mainly in areas, such as informal settlements,
cilitate wheeling include the following:                          where this is no grid infrastructure. It could
•      Conduct a detailed cost-of-supply study                    also be relevant in grid-connected areas where
       to determine the cost of the grid usage,                   supply is constrained, or where households are
       following the methodology from NERSA.                      energy-poor.
•      Establish an overall strategy for wheeling,
       including the aims and long-term implica-                  The basket of energy services may include a
       tions of wheeling.                                         combination of gas stoves, solar water heat-
•      Draft a generic connection and use-of-                     ers, solar chargers and energy efficient light-
       system agreement.                                          ing. These can be used instead of fuel sources,
•      Revise the billing system to accommodate                   such as paraffin, that contribute to the risk of
       wheeling charges and third-party sales.                    fires and air pollution.

What Should You Not Do?                                           Other benefits include reduced peak electricity
Municipalities should not allow service provid-                   consumption, reduced theft of electricity, and
ers to use the grid for wheeling without paying                   opportunities for small business development.
for this usage.
                                                                      Resource Tip
What Is the Way Forward?                                              For information on effective solar water heating
These are some of the requirements:                                   programs see ‘Review of best practise solar
                                                                      water heating implementation by local government’.
•   A clear methodology and process for de-
                                                                      http://www.cityenergy.org.za/uploads/resource_351.pdf
    termining cost of supply for the electricity

                                                             14
Renewable Energy Scenarios for Municipalities in South Africa

Municipalities could also consider setting up                  ipality and the user. These include operational
micro- or mini-grids. Mini-grids are smaller, de-              and maintenance costs, as well as other factors
centralised grids that often have renewable en-                such as safety, levels of services and practica-
ergy components and provide basic electricity                  bility for the users.
needs to communities. A mini-grid pilot project
is under development in Raymond Mhlaba Lo-                     What should you do?
cal Municipality in the Eastern Cape.                          An appropriate basket of alternative energy
                                                               technologies depends on the existing energy
 Resource Tip                                                  requirements of beneficiaries and communities.
 For more information on mini-grids, see ‘Energy               Typically, this varies from community to com-
 Access in South Africa a toolkit for developing               munity. Planning and research are, therefore,
 successful green mini-grids’:
                                                               important parts of the process. The steps to
 http://www.cityenergy.org.za/uploads/resource_426.pdf
 For more information on alternative household energy          follow could include:
 access, see the chapter on household energy access            ŦŦ Step 1 – Conduct community surveys to
 in the ‘Sustainable energy solutions for South African             gain an understanding of existing energy
 local government – A practical guide’: http://www.                 behaviour and financial affordability within
 sustainable.org.za/userfiles/household%20energy.pdf
                                                                    a particular community.
                                                               ŦŦ Step 2 – Select a sub-set of alternative
What are the Key Challenges?                                        technologies that are appropriate for the
The key risk with offering alternative energy ser-                  community.
vices is push-back from community members                      ŦŦ Step 3 – Conduct stakeholder consulta-
who see it as a sub-standard service. It is import-                 tion processes that clearly communicate
ant to manage the stakeholder consultation pro-                     the intention of the programme and ex-
cess when initiating programmes of this nature.                     plain the technology.
                                                               ŦŦ Step 4 - Pilot different combinations of the
There also needs to be careful consideration of                     alternative technology in different areas.
the long-term implications, for both the munic-

                                                          15
Renewable Energy Scenarios for Municipalities in South Africa

What is the way forward?                                   required to ensure investment is made in appro-
These are some of the requirements:                        priate technology.
•   Assistance with assessing and developing
    baskets of alternative energy options.                 What should you do?
•   Assistance with communicating the via-                 The steps to follow with storage facilities are
    bility of alternative energy technologies,             the same as those for generation facilities (see
    particularly in communities that cannot be             Section 4.2). It should be re-emphasised that
    electrified.                                           storage options are currently very expensive for
•   Share learnings from the mini-grid pilot               municipalities, despite this being a rapidly de-
    project in Raymond Mhlaba Local Munici-                veloping field. Implementing time-of-use tariffs
    pality to enable further development if and            could assist in making these storage options
    where found feasible.                                  slightly more feasible.

5.3 Scenario Seven: Operating                              What should you not do?
a Storage Facility                                         Municipalities should be cautious about invest-
Energy storage facilities store excess electricity         ing in storage facilities as some technologies
generated in times of lower demand for use at a            can be prohibitively expensive. However, it is
later stage when demand is high. In South Africa           also worth noting that there is currently signif-
the most common storage facilities are hydro-              icant international investment and local studies
electric pumped-storage schemes that make                  in electricity storage technologies. In future
use of potential energy, and solar water heaters           these technologies may be a much more viable
and concentrated solar power plants that store             option for consideration.
heat energy. Batteries are another way to store
electricity for later use, and could be used to
provide storage where renewable energy instal-
lations produce electricity intermittently.

What is the Scenario?
A municipality may consider investing in elec-
tricity storage facilities, such as large-scale
batteries and pump-storage schemes, to store
excess electricity for use at times of peak de-
mand or in the event of load shedding. In some
instances, storage technologies can also be
used in place of grid upgrades.

At this stage, storage technology is a very
expensive option for municipalities. However,
electricity storage is seen as a key component
of long-term renewable energy base load op-
tions. The field is evolving rapidly, with contin-
uous technological innovation and investment.

What are the Key Challenges?
As with electricity generation systems, the key
risk is the capital cost associated with installa-
tions of this nature. Careful planning is therefore

                                                      16
Renewable Energy Scenarios for Municipalities in South Africa

Notes

                                     17
For further information please contact
                                  SALGA energy unit
                           Nhlanhla Ngidi: nngidi@salga.org.za
                       Lungile Manzini: lmanzini@salga.org.za
                                     012 369 8000

                       For additional resources see:
                                 www.cityenergy.org.za

Head Office                              Physical Address: Menlyn Corporate Park,
Telephone: (012) 369 8000                Block B, 175 Corobay Avenue, Cnr Garsfontein
Fax: (012) 369 8001                      and Corobay, Waterkloof Glen ext11, Pretoria

     In Partnership with
You can also read