Constructability: A guide to reducing temporary works - Temporary Works Forum

Page created by Barbara Payne
 
CONTINUE READING
Constructability: A guide to reducing temporary works - Temporary Works Forum
Constructability:
A guide to reducing
temporary works

                      Published – October 2020

                      This TWF Guidance is available
                      as a free download from
                      www.twforum.org.uk

                      Document: TWf2020: 02

                      NOTE: If you need to print this
                      document, be aware that the pages
                      are prepared with alternate (even)
                      pages offset for your duplex
                      (double sided) printing.
Constructability: A guide to reducing temporary works - Temporary Works Forum
Temporary Works forum                                Constructability: A guide to reducing temporary works – TWf2020: 02

Members of the Working Party
This guidance has been prepared by Working Group 25:
Convenor                                   Jim Tod                          Tony Gee and Partners LLP
Secretary                                  David Thomas                     Temporary Works Forum (TWf)
                                           Chris Bennion                    Chris Bennion Consultancy Ltd
                                           Paul Boddy                       Interserve Construction
                                           Tim Bowes                        Atkins
                                           Godfrey Bowring                  Retired
                                           Nick Boyle                       Balfour Beatty Civil Engineering Ltd
                                           Andrew Finch                     Jacobs UK Ltd
                                           Tim Lohmann                      Wentworth House Partnership
                                           Chris Maher                      Highways England
                                           Doug Potter                      Arcadis Consulting (UK) Ltd
                                           Jim Richings                     Vinci Construction UK
                                           Malachy Ryan                     Alan White Design Ltd
                                           Mike Webster                     MPW R&R Ltd
                                           Aleksander Widernik              Lendlease Construction (Europe) Ltd
                                           Rob Williams                     Murphy Group
                                           Steve Williams                   Network Rail
                                           John Winson                      Atkins
Contributors also included:                James Appleby                    Network Rail
                                           Natalie Cropp                    Tony Gee and Partners LLP
                                           Ray Filip                        RKF Consult
                                           Jon Hodgins                      Galliford Try
                                           Mathew Howells                   Tony Gee and Partners LLP
                                           Andrew Jarman                    Network Rail
                                           Sinead Lawlor                    Network Rail
                                           Andy Marshall                    Tony Gee and Partners LLP
                                           Kirsten Morris                   Hewson Consulting
                                           Neil Robinson                    Galliford Try
                                           Mike Southall                    Galliford Try
                                           Andrew Stotesbury                Lendlease
The Temporary Works Forum gratefully acknowledges the contribution made by the working group and contributors in
the preparation of this guidance.

Acknowledgement                                                  or type of project, from conception to decommissioning.
Some of the information (e.g. tables, etc.) was supplied by      The guide also contains suggested further reading
- and is the copyright of - Tony Gee and Partners LLP and        and examples where the principles have been applied
may appear elsewhere.                                            successfully.

Editorial note                                                   Disclaimer

The information provided in Chapters 6 to 8 is available         Although the Temporary Works Forum (TWf) does its
in ‘Word’ format on the Temporary Works Forum (TWf)              best to ensure that any advice, recommendations
website (www.twforum.org.uk . . . select . . . Resources/        or information it may give either in this publication or
Library Folders/TWfGuidance). These lists do not set             elsewhere is accurate, no liability or responsibility of any
out to be prescriptive and should be amended to suit             kind (including liability for negligence) howsoever and from
individual company operations and preferences. They              whatsoever cause arising, is accepted in this respect by
may be updated from time-to-time (and the Secretary              the Forum, its servants or agents.
invites contributions to them (secretary@twforum.org.uk).        Readers should note that the documents referenced in
Synopsis                                                         this TWf Guide are subject to revision from time to time
                                                                 and should therefore ensure that they are in possession of
This guide provides a definition of what is meant by             the latest version.
“constructability”; guidance on the legal requirements
on clients and designers; and suggests aspects of
constructability that should be considered throughout the
project lifecycle. The principles can be applied to any size

2                                                                                                    Return to the contents
Constructability: A guide to reducing temporary works - Temporary Works Forum
Constructability: A guide to reducing temporary works – TWf2020: 02                                                            Temporary Works forum

Contents
To navigate to page - hover over an item below and ‘click’. Return to contents by clicking on the
‘Return to the contents’ at the bottom of every page.

Section                                                                Page       Section                                                          Page
1.0   Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4                  8.4.1 Actions to be complete before
                                                                                                      holding constructability review  . . . . . . 19
2.0   Statutory legal aspects  . . . . . . . . . . . . . . . . . . . 4
                                                                                                8.4.2 Aim of the constructability review: . . . . 19
3.0   Construction process  . . . . . . . . . . . . . . . . . . . . 5                           8.4.3 Actions to be carried out after
4.0   Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6                          constructability review  . . . . . . . . . . . . 20
5.0   Procurement models (UK) . . . . . . . . . . . . . . . . . 6                 9.0     Summary and concluding remarks . . . . . . . . . 20
6.0   Constructability principles  . . . . . . . . . . . . . . . . 8              References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
      6.1 Lean construction . . . . . . . . . . . . . . . . . . . . . . 8         Further reading  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
      6.2 Low carbon design . . . . . . . . . . . . . . . . . . . . . 9           Bibliography . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
      6.3 Off-site fabrication – aspects of construction                          Appendix 1: Other definitions and terms  . . . . . . . . 24
          that can influence the design  . . . . . . . . . . . . 10               Appendix 2: Projects that benefited from early
      6.4 Reasons to consider off-site construction . . . 10                      contractor involvement . . . . . . . . . . . . . . . . . . . . . . . 25
      6.5 How the components get to and                                                   1.    Bar Hill bridge deck  . . . . . . . . . . . . . . . . . . . 25
          across site  . . . . . . . . . . . . . . . . . . . . . . . . . . 10             2.    Installation of bridge deck (A14)  . . . . . . . . . . 25
      6.6 The design of fabricated elements                                               3.    Pre-cast slabs form viaduct deck . . . . . . . . . 25
          required to be lifted or moved . . . . . . . . . . . . 11
                                                                                          4.    Dover Western Docks Revival –
      6.7 The handling and installation of                                                      New Marina Pier . . . . . . . . . . . . . . . . . . . . . . 26
          pre-fabricated elements on site . . . . . . . . . . . 13
                                                                                          5.    Dover Western Docks Revival –
7.0   When to consider constructability . . . . . . . . . 13                                    Wellington Dock Navigational Access . . . . . . 26
      7.1 Notes on the practical aspects of                                               6.    Blackfriars Thameslink Project  . . . . . . . . . . . 27
          carrying out constructability reviews . . . . . . . 15
                                                                                          7.    Landmark, Manchester . . . . . . . . . . . . . . . . . 27
      7.2 Who should undertake reviews . . . . . . . . . . . 15
                                                                                  Appendix 3: Good practice in BIM . . . . . . . . . . . . . . 29
      7.3 Information . . . . . . . . . . . . . . . . . . . . . . . . . . 15
                                                                                          Example 1 - Manchester Victoria Station . . . . . . 29
8.0   A methodological approach to
                                                                                          Example 2 - Birmingham New Street
      constructability reviews . . . . . . . . . . . . . . . . . . 15
                                                                                          Station . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
      8.1 Constructability at project initiation,
                                                                                  Appendix 4: Construction issues resulting
          option development and selection  . . . . . . . .                16
                                                                                  from aspects of the design . . . . . . . . . . . . . . . . . . . . 30
          8.1.1 Constructability at project initiation . . .               16
          8.1.2 Constructability at option                                                A4.1 Stability of reinforcement . . . . . . . . . . . . . . 30
                development and selection . . . . . . . . .                16             A4.2 Temporary piers  . . . . . . . . . . . . . . . . . . . . 30
          8.1.3 The importance of constructability at                                     A4.3 Stability of precast element . . . . . . . . . . . . 30
                project initiation, option development
                                                                                          A4.4 Precast concrete ceiling planks
                and selection  . . . . . . . . . . . . . . . . . . .       16
                                                                                               in a school . . . . . . . . . . . . . . . . . . . . . . . . . 31
          8.1.4 Actions to be complete before
                holding constructability review  . . . . . .               16             A4.5 Insitu cast earth retaining wall –
          8.1.5 Aim of the constructability review  . . . .                17                  concrete finish . . . . . . . . . . . . . . . . . . . . . . 31
          8.1.6 Actions to be carried out after                                           A4.6 Suspended ground floor slabs . . . . . . . . . . 32
                constructability review  . . . . . . . . . . . .           17             A4.7 Nearby buildings and party wall issues  . . . 32
      8.2 Constructability at preliminary and                                             A4.8 Composite decking . . . . . . . . . . . . . . . . . . 32
          detailed design . . . . . . . . . . . . . . . . . . . . . . .    17
                                                                                          A4.9 Reinforced concrete slab design/back
          8.2.1 Actions to be complete before
                                                                                               propping . . . . . . . . . . . . . . . . . . . . . . . . . . 32
                 holding constructability review  . . . . . .              17
          8.2.2 Aim of the constructability review: . . . .                17             A4.10 Limited soil investigations  . . . . . . . . . . . . . 33
          8.2.3 Actions to be carried out after                                           A4.11 Limited investigation of existing
                 constructability review  . . . . . . . . . . . .          18                   structures . . . . . . . . . . . . . . . . . . . . . . . . . 33
      8.3 Constructability at pre-construction cost                                       A4.12 Integrating permanent and temporary
          estimate build up (‘tender’) . . . . . . . . . . . . . . 18                           works design: needling and propping  . . . . 33
          8.3.1 Actions to be complete before holding                                     A4.13 Integrating permanent and temporary
                constructability review  . . . . . . . . . . . . 18                             works design: basements . . . . . . . . . . . . . 33
          8.3.2 Aim of the constructability review: . . . . 19
                                                                                  Appendix 5: Construction issues resulting
          8.3.3 Actions to be carried out after
                                                                                  from aspects of the site work  . . . . . . . . . . . . . . . . . 34
                constructability review  . . . . . . . . . . . . 19
                                                                                          A5.1 Stability of reinforcement . . . . . . . . . . . . . . 34
      8.4 Constructability at pre-construction stage (‘site
          work’) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19           A5.2 Precast concrete bridge fascia panels . . . . 34

Return to the contents                                                                                                                                              3
Constructability: A guide to reducing temporary works - Temporary Works Forum
Temporary Works forum                                        Constructability: A guide to reducing temporary works – TWf2020: 02

1.0          Introduction                                                          Regulation 4 - Client duties in relation to
             This document aims to provide guidance to all                         managing projects
             those in project teams on the consideration of                        4.—(1) A client must make suitable arrangements
             constructability.                                                     for managing a project, including the allocation of
1.1          The constructability of a project results from                        sufficient time and other resources.
             decisions made by the client, architect,                              (2) Arrangements are suitable if they ensure
             designer(s) and contractor(s) at the pre-project,                     that—
             options, development, construction and                                (a) the construction work can be carried out, so
             decommissioning/ demolition phases on aspects                         far as is reasonably practicable, without risks to
             such as location, land-take, form, programme                          the health or safety of any person affected by the
             and cost.                                                             project; ….
1.2          For the purpose of this guidance the following              2.2       In relation to designers:
             definition is adopted1:
                                                                                   Regulation 8 - General duties
             Constructability
                                                                                   8. - (1) A designer (including a principal designer)
             “the extent to which the design of a building                         or contractor (including a principal contractor)
             or construction project and its environment                           appointed to work on a project must have the
             facilitates ease of construction, subject to                          skills, knowledge and experience, and, if they
             the overall requirements of the building or                           are an organisation, the organisational capability,
             construction project and its environment.”                            necessary to fulfil the role that they are appointed
                    Source: Network Rail Safe by Design, Guidance                  to undertake, in a manner that secures the health
                             Note – Early Focus on Constructability                and safety of any person affected by the project.
                                 and Temporary Works (2019) [1.]
                                                                                   Regulation 9 Duties of designers
1.3          This guidance makes recommendations for                               9. - (2) When preparing or modifying a design
             the stages when it is sensible to consider the                        the designer must take into account the general
             constructability of the project. It also identifies                   principles of prevention and any pre-construction
             some of the factors that affect constructability                      information to eliminate, so far as is reasonably
             and which are common to many sites. Finally, it                       practicable, foreseeable risks to the health or
             gives examples of projects where constructability                     safety of any person ….
             has been considered early in the project
             development and incorporated into the design;               2.3       The role of the designer is recognised in HSE
             and other projects where details of the design                        Guidance:
             have left room for improvement.                                       “A designer has a strong influence during the
1.4          The practical result of considering constructability                  concept and feasibility stage of a project. The
             during the development and design stages is that                      earliest decisions can fundamentally affect the
             projects will be easier to build.                                     health and safety of those who will construct,
                                                                                   maintain, repair, clean, refurbish and eventually
             NOTE: A peer review may include some aspects                          demolish a building …”
             of a constructability review.
                                                                                                          Source: HSE, L153, Para 75 [3.]
2.0          Statutory legal aspects
                                                                         2.4       CIRIA has published Construction work
2.1          Constructability should be considered by the                          sector guidance for designers (C755) [4.].
             client, the designer(s) and the contractor(s). The                    The document has been produced to assist
             legal aspects of constructability are many and                        designers in complying with CDM2015,
             varied. The following extracts highlight key issues                   Regulations 8, 9 and 10. It provides a description
             in the Construction (Design and Management)                           of the risks typically associated with various
             Regulations 2015 (CDM2015) [2.]2 with which                           construction methods and how the designer can
             the reader should be familiar:                                        consider overcoming them.

1
    ‘Constructability’ isn’t new and other definitions and terms have been in use for many years. See Appendix 1.
2
 CDM came effect first on 31st March 1995 as the Construction (Design and Management) Regulations 1994, following the introduction
of European Directive 92/57/EEC on the minimum safety and health standards for temporary or mobile construction sites. The
Regulations were, and still are, aimed at improving the overall management and co-ordination of health, safety and welfare throughout
all stages of a construction project. They place duties on all those who can contribute to the health and safety of a construction project:
clients, designers and contractors.

4                                                                                                                   Return to the contents
Constructability: A guide to reducing temporary works – TWf2020: 02                                         Temporary Works forum

2.5       C755 states:                                                            f) replace the dangerous by the non-dangerous
          “Designers have to weigh many factors as they                              or the less dangerous
          prepare their designs. H&S considerations have                          g) develop a coherent overall prevention policy
          to be weighed alongside other considerations,                              which covers technology, organisation of
          including cost, fitness for purpose, aesthetics,                           work, working conditions, social relationships
          buildability, maintainability and environmental                            and the influence of factors relating to the
          impact. …”                                                                 working environment
          and provides a discourse3 on the issues that                            h) give collective protective measures priority
          should be taken into account.                                              over individual protective measures
2.6       It repeats the definition in L153 of what is meant                      i) give appropriate instructions to employees
          by the term reasonably practicable4 and contains              2.9       In summary6, the legal context to the need to
          some salutary advice 9 [emphasis added]:                                consider constructability has been around for
          “There is a feeling that after an accident,                             many years. The concept is not new.
          in retrospect, it is always obvious what                      3.0       Construction process
          more could have been done to prevent
          it occurring. Any decision in which cost                      3.1       The construction process is the delivery of the
          plays a major part will be likely to be (in                             whole permanent works. The permanent works
          retrospect) particularly criticised.”                                   are usually an assembly of component parts.
                                                                                  There is an interdependent relationship between
2.7       BS 5975: 2019 [5.], states:                                             the choice of component and method of
          8.1.2 Designers should address the buildability                         assembly.
                of permanent works, temporary works,                    3.2       Components are defined by their material,
                their interfaces, their proposed methods                          size, shape, weight and structural properties.
                of construction and any related design                            These may be dependent on the manufacturing
                assumptions.                                                      process, any post-processing assembly, the
          8.3.1 Permanent works designers should                                  weight that can be lifted, the position that they
                address the buildability of the permanent                         can be supported in during the temporary
                works and identify, and make provision                            stage(s), the stability of the component(s) under
                for, any temporary works and temporary                            their own self weight and environmental loads
                conditions required by their design and                           and the way in which they are incorporated into
                their assumed method of construction …                            the other permanent works.
2.8       The Management of Health and Safety at Work                   3.3       These are in turn affected by the availability of
          Regulations 1999 [6.] were the first to set out the                     raw materials, skilled workforce, manufacturing
          requirements for ‘risk assessment’ (Reg. 3) and                         facilities, transport, the type and size of plant
          introduced the ‘general principles of prevention’                       and any limitations on access and egress
          (Reg. 4). The latter are summarised in CDM2015                          arrangements. Where transport is problematic
          [3.] as an hierarchy5:                                                  the smallest transported components are - for
          a) avoid risks                                                          example - clay bricks, bagged cement, steel
                                                                                  reinforcing bars, locally won sand and aggregate,
          b) evaluate the risks which cannot be avoided                           locally sourced timber. It may also be feasible
          c) combat the risks at source                                           to set up on site pre-assembly manufacturing
                                                                                  facilities (e.g. from concrete batching plants
          d) adapt the work to the individual, especially
                                                                                  to production lines for match-cast segmental
             regarding the design of workplaces, the
                                                                                  concrete bridges).
             choice of work equipment and the choice of
             working and production methods, with a view,               3.4       Constructability exists on a varying scale
             in particular, to alleviating monotonous work,                       and every structure (or building) has overall
             work at a predetermined work rate and to                             requirements which may necessitate some
             reducing their effect on health                                      degree of compromise.
          e) adapt to technical progress

C755, Section 1.4.6
3

4
 The term ‘reasonably practicable’ has been defined as: “balancing the level of risk against the measures needed to control the real
risk in terms of money, time and trouble. However, you do not need to take action if it would be grossly disproportionate to the level of
risk. (See www.gov.uk/risk/faq.htm for the most up to date explanation of what ‘reasonably practicable’ means)” (Source: Glossary of
acronyms and terms, L153 (HSE, 2015) [3.])
This hierarchy is often referred to as ‘ERIC’ – Eliminate, Reduce, Inform and Control
5

There may be commercial and/or contractual aspects in the delivery of a project, not considered here
6

Return to the contents                                                                                                                      5
Temporary Works forum                                Constructability: A guide to reducing temporary works – TWf2020: 02

3.5     In some instances, a design which increases                     to input ideas at an earlier stage, enabling
        the material content of the permanent works                     more effective communication, improving
        but reduces the need for temporary works may                    design empathy for production and simplifying
        be safer, less disruptive, more cost-effective,                 construction techniques. In some cases the
        more carbon-efficient and cheaper. For example,                 Client enters into a contract with a single
        the overall combination of factors should be                    administrative party who then delivers the whole
        aggregated and where a more substantial                         project. In theory, the designer and constructor
        permanent works solution might significantly                    are an integrated team with the function of
        reduce the temporary works required then                        delivering the project (CIRIA C534 [9.]).
        this should be given due consideration as the          4.3      There remain some challenges in the UK of the
        preferred solution, particularly where it results in            resulting arrangements, which do not appear
        reduced construction time and risk exposure on                  to have delivered all the improvements sought8,
        site.                                                           but in respect of the consideration of temporary
3.6     Decisions made about the design of the                          works these forms of procurements have
        permanent works have a fundamental impact on                    advantages.
        the materials available, even at early stages.         5.0      Procurement models (UK)
3.7     The plant and techniques which are available to        5.1      There are now several programme management
        the constructor evolve constantly. For instance, in             models within the UK construction industry which
        the 25 years since the drafting of CIRIA R155 [7.]              define the progress of the project through the
        and CIRIA C543 [8.] there has been an increase                  stages from initial briefing to final completion,
        in the capacity of cranage, allowing larger parts               including:
        of the construction to be prefabricated/pre-
        assembled and lifted into position (so minimising               • Network Rail ‘Governance for Railway
        the need for insitu falsework and formwork and                    Investment Projects (GRIP)’ (2018) [10.]
        reducing the impact on the site) as well as self-               • Highways England ‘Project Controls
        propelled modular transporters (SPMTs).                           Framework’ v4 (2018) [11.]
4.0     Background                                                      • Royal Institute of British Architects (RIBA) ‘Plan
        Constructability; temporary works; safety;                        of Work’ (2013) [12.]
        construction methodology                                        • Office of Government Commerce ‘Gateway
4.1     For many years the typical form of procurement                    Review Process’ (2011) [13.]
        was for a Client to have separate contracts with                • Institution of Structural Engineers ‘The
        the Engineer and Contractor. The Contractor built                 Structural Plan of Work’ (2020) [14.]
        what the Engineer specified and there was little
                                                               5.2      All the procurement methods follow a similar
        opportunity to suggest improvements in design
                                                                        pattern (see Figure 1):
        which would increase buildability and reduce
        cost, risk and project duration. This contract                  • pre-project
        arrangement was also thought to lead to poor                    • options phase
        project delivery, quality of finished construction,
                                                                        • development phase
        delays, cost overruns and claims7.
                                                                        • construction phase (to ‘completion’ or
4.2     These issues led to a general change in the
                                                                          ‘hand back’)
        typical forms of procurement to the Early
        Contractor Involvement (ECI) and Design and                     • use phase (including operation and
        Build (D&B) contracts common today. The                           maintenance)
        intention is that the constructor is allowed                    • decommissioning / demolition phase

7
 UK: Emerson 1962; Banwell 1964; EDC 1967; Wood 1975; CIRIA 1983; CIRIA 1989; Latham 1994; Egan 1998; USA: ASCE 1974; CII
1986; CII 1987; Australia: Gyles 1992
8
 NAO 2001; RCTF 2001; SFC 2002; NAO 2005; Wolstenholme 2009; Laidlaw 2012; May 2013; CO 2013; HMSO 2013; Public
Accounts 2016

6                                                                                                   Return to the contents
End of
                                                                                                                                                      Construction
                                           Pre-project/ Initiation           Options phase                         Development phase                                       Use/operation        use and
                                                                                                                                                         phase
                                                                                                                                                                                               demolition

Return to the contents
                                                                                                                      Decision point:
                         HE Project      0                                                                                                           6
                                                                        1                2           3                4                 5
                         Control         Strategy                                                                                                    Construct,                     7
                                                                        Option           Option      Preliminary      Statutory         Construction
                         Framework       shaping and                                                                                                 commission                     Closeout
                                                                        identification   selection   design           procedures        preparation
                         (PCF) 2008      prioritisation                                                                                              and handover
                                                                                                                      and powers

                                                                                                                                                      6                  7
                                         1                                               3           4                5                                                             8
                         Network Rail                     2                                                                                           Construct,         Scheme
                                         Output                                          Option      Single option    Detailed                                                      Project
                         GRIP                             Feasibility                                                                                 test and           hand
                                         definition                                      selection   development      design                                                        closeout
                                                                                                                                                      commission         back

                                                                                                                                                                         6
                                         0                1                              2           3                4
                                                                                                                                                                                                                                                                                                                                                  Constructability: A guide to reducing temporary works – TWf2020: 02

                         RIBA Plan of                                                                                                                 5                  Handover   7
                                         Strategic        Preparation                    Concept     Developed        Technical
                         Work 2013                                                                                                                    Construction       and        In use
                                                                                                                                                                                                                                                                                    Figure 1 - Summary of some programme management models (UK)

                                         definition       and brief                      design      design           design
                                                                                                                                                                         closeout

                                                                                                                                                      Stage 5
                                                                                                                                                                         Stage 6
                         Construction                                                                Stage 3          Stage 4                         (Manufacture,
                                         Stage 1                                         Stage 2                                                                         (Handover Stage 7
                         Industry                                                                    (Design          (Production                     installation and
                                         (Preparation)                                   (Concept)                                                                       and       (In use)
                         Council (CIC)                                                               development)     information)                    construction
                                                                                                                                                                         closeout)
                                                                                                                                                      information)
                                                                                                                                                                                                            model for this stage (from pre-project to implementation)
                                                                                                                                                                                                     End of use, decommissioning and demolition may have such significant

                         The Structural                                                                                                               5
                                        0                                                2           3                4                 4.5
                         Plan of                                                                                                                      Manufacturing      6          7
                                        Strategic                                        Concept     Spacial          Technical         Production
                                                                                                                                                                                                consequences that it is appropriate to use the full project/ programme management

                         Work 2020                                                                                                                    and                Handover   In use
                                        definition                                       design      coordination     design            information
                         (IStructE)                                                                                                                   construction

7
                                                                                                                                                                                                                                                                                                                                                  Temporary Works forum
Temporary Works forum                                      Constructability: A guide to reducing temporary works – TWf2020: 02

5.3       The consequences of the end of use, i.e. the                             management; quality assurance; operational
          decommissioning and demolition phases, may                               research; and lean manufacturing.
          in themselves be significant enough that it would             6.1        Lean construction
          be appropriate to consider all these stages in this
          approach, e.g. from pre-project through to use                6.1.1      ‘Lean’ in its simplest form means eliminating
          (including operation and maintenance).                                   waste from everything we do.

5.4       Irrespective of the management model adopted,                 6.1.2      Essentially, ‘lean’ is a collection of ‘Work Study
          constructability reviews should be undertaken.                           and Operational Research’ techniques some
                                                                                   of which have been used for decades. These
6.0       Constructability principles                                              techniques have been used by contractors
          There have been many works published recently                            to gain a competitive edge. It has now been
          on the subject of “Lean Construction”. However,                          re-branded and is covered by a suite of CIRIA
          the application of science to manufacturing is not                       guides11. One of most valuable concepts is the
          new. To help achieve a sense of perspective, the                         definition of waste in CIRIA C730 [15.] (see
          following are offered:                                                   Figure 2):
          Charles Babbage (1791-1871)9                                  6.1.3      Applied simply to construction:
          Charles Babbage was credited as the inventor of                          Value adding (VA)         =    permanent works
          the digital (mechanical) computer and his ideas                          Essential non-value =          temporary works
          helped shape the “Industrial Revolution” as well                         adding (enVA)
          as the Victorian expansion in manufacturing.
                                                                                   Waste                     =    waste and inefficiency
          Fredrick Taylor (1856-1915)10
          Fredrick Taylor was one of the first Management
          Consultants. His legacy to us is: knowledge

                                                                                                     Any work activity will comprise
                                                                                                     all three elements of work. It

                                                                                                     adding (VA) content will be a
                                                                                                     lot less than other elements.

                                              Operator time
                                                                                                     When improving the way
                                                                                                     work is carried out:
                                                                                                     Step 1: aim to eliminate waste
                        Waste                                 EN VA                      VA          Step 2: improve the way
                                                                                                     ENVA is carried out

                                E liminate                        Reduce                             of VA

                                                                                                     Lean improvement reduces
                     Increased capacity                                                              the time taken to carry out
                       to do more work                                                               a particular task, releasing
                                                                                                     more capacity: ‘more for the
                                                                                                     same’ or ‘more for less’.

        Figure 1.1        Eliminating waste
                                                                                                                 Figure 2 – Defining waste

                                                                         Source: CIRIA C730, Lean tools and techniques – an introduction

9
 Babbage wrote, “On the Economics of Machinery and Manufactures” (1832). This book described differentiating task with skills, bonus
systems, “piece work” and profit sharing. His ideas are said to have influenced Marx.
 Taylor wrote the very influential book, “The Principles of Scientific Management” (1911). It is reported that his principles have been
10

adopted by everyone from Henry Ford to Lenin, Trotsky and Stalin.
 CIRIA: Implementing Lean in Construction (RP978); Build Lean (C696); Lean construction and BIM (C725); Lean and the sustainability
11

agenda (C726); Lean benefits realisation management (C727); A Lean guide for client organisations (C728); Selecting and working with
a Lean consultant (C729); Lean tools and techniques – an introduction (C730); Health and Safety Synergies of Lean (C769)

8                                                                                                                   Return to the contents
Constructability: A guide to reducing temporary works – TWf2020: 02                            Temporary Works forum

6.2     Low carbon design                                      6.2.4    The permanent works designer (PWD) needs
6.2.1   The term embodied carbon is used to describe                    to engage with the temporary works designer
        the greenhouse gas (GHG) emissions associated                   (TWD) to ensure greater consideration of
        with the production of materials or products                    constructability, e.g. through constructability
        to the factory gate. Carbon dioxide equivalent                  reviews.
        (CO2e) is used as a proxy for the impact of
        different greenhouse gases included in carbon
        assessments. In line with PAS 2080: 2016,
        Carbon management in infrastructure [16.],
        carbon assessments should consider the whole
        life of the asset from manufacture of materials,               VA                      enVA
        through construction, operation and end of life.
        To this end the trade-offs between more carbon
        intensive stages can be made with other lower             • Lowest VA – Design driven by lowest material
        carbon stages. However, often the scope is                  cost: low material cost, but may have high
        limited to embodied carbon assessments that are
                                                                    construction cost
        carried out without consideration of construction
        techniques or temporary works.
                                                                          VA                  enVA
6.2.2   Cost is also subject to the some of the same
        drivers as carbon (In general terms more
        embodied carbon equals more cost [17.]). This
                                                                  • Lowest enVA - Design driven by lowest
        can lead to designs which at first sight appear             construction cost: material costs may be higher,
        efficient because they have low “Value Adding”              but the construction costs are lower
        (VA) content but require more temporary works -           • The overall cost of the project is a combination
        “essential non-Value Adding” (enVA) - content to            of material and construction costs. A project
                                                                    with greater material content may be
        construct them.                                             sufficiently lower in construction cost for this
                                                                    to be the most economic solution
6.2.3   It may be cheaper overall - and therefore produce
        less embodied carbon - to construct permanent
        works with a higher material content and which                              Figure 3 – Consequences of different
        requires less temporary works, i.e. is easier to                                   approaches to constructability
        build (see Figure 3 and Figure 4).

                                                                                 In this instance the designer
                                                                                 aimed to make savings by
                                                                                 reducing the thickness of
                                                                                 the abutment wall below the
                                                                                 level of the bearing shelf.
                                                                                 While reducing the
                                                                                 concrete content of the
                 PROFILE FINISH

                                                                                 wall the complexity of the
                                                                                 reinforcement detailing and
                                                                                 the formwork costs were
                                                                                 increased.
                                                                                 A straight wall would have
                                                                                 resulted in simpler and
                                                                                 cheaper reinforcement,
                                                                                 reduced formwork costs,
                                                                                 exposure to less risk and
                                                                                 faster construction.

                                  Figure 4 – Example of a design driven by material reduction rather than constructability

Return to the contents                                                                                                    9
Temporary Works forum                               Constructability: A guide to reducing temporary works – TWf2020: 02

6.3     Off-site fabrication - aspects of construction                 • Presence of obstructions, e.g. something
        that can influence the design                                    already on site, especially if an existing
6.3.1   The plant available for construction is constantly               structure is being replaced.
        evolving.                                                      • Potential for an improvement in programme
6.3.2   Developments in fabrication facilities,                          delivery, e.g. working on several different parts
        transportation and means of placing (e.g.                        of the project concurrently.
        larger cranes, SPMTs) allow structures to be                   • Protection from the environment during
        constructed from components of greater size.                     fabrication.
        This can reduce the need for in-situ falsework                 • Potential reduction production costs.
        and formwork and so reduce the work on the
        site.                                                          • Improved quality control, e.g. concrete
                                                                         finishes, welding, etc.
6.3.3   Sections 6.4 to 6.7 list some of the aspects of
        the construction process that can influence the        6.5     How the components get to and across site
        design for off-site fabrication:                       6.5.1   There are many issues to be considered when
        • Reasons to consider off-site construction (see               assessing any access route(s), i.e. how the
          6.4)                                                         components get to and across site:

        • How the components get to and across site                    • Components and/or plant being delivered to
          (see 6.5)                                                      and across site:

        • The design of fabricated elements required to                   • weight
          be lifted or moved (see 6.6)                                    • dimensions including protrusions
        • The handling and installation of pre-fabricated                 • number of vehicles
          elements on site (see 6.7)
                                                                       • Restrictions on the existing route:
6.3.4   Similarly, some of the design choices will affect
                                                                          • width; height restrictions under, through
        the construction. They should be adapted by the
                                                                            bridges and/or tunnels; between buildings
        reader to suit their own project-specific needs.
                                                                          • length restrictions, e.g. tight bends, street
6.3.5   Designers should be aware of the problems
                                                                            furniture
        the Contractor will face. However, to obtain
        the best solution dialogue with the contractor                    • gradient of road route
        (a construction method specialist) should be                      • weight restrictions, e.g. bridges, roads
        arranged.
                                                                          • availability of railway (viz. route availability
6.4     Reasons to consider off-site construction                           (RA) rating)
6.4.1   There are many reasons to consider off-site                       • whether permits are required to use the
        construction:                                                       route (and how long they will take to obtain)
        • Enhance safety - e.g. to avoid building at                      • can bollards, etc. be removed temporarily
          height or over water; avoid live transport                        to assist the movement of Abnormal
          routes.                                                           Indivisible Loads, by agreement with the
        • Less interfaces to manage on site.                                relevant highway authority

        • Potential reduction in the amount of temporary               • Is the route affected by tides?
          works required on site (and the associated                      • This will affect the timing of operations
          reduction in risk exposure for site workers)
                                                                       • Is the route in the inter-tidal zone?
        • Absence of foundations and working space
                                                                          • This significantly restricts the access by
          available beneath the structure, e.g. in rivers,
                                                                            both land based and floating plant
          over valleys, on poor ground, or above roads,
          railways, sewers and tunnels.                                • How exposed is the route to weather (and will
                                                                         it flood or become blocked by snow)?
        • Potential disruption to adjacent sites, e.g.
          when working near or over railways and/or                    • Resilience of the route
          roads.                                                          • Will it deteriorate rapidly under adverse
        • Absence of or unsuitable working space                            weather? Will it take the traffic?
          adjacent to (or above) the structure, e.g. in                • Speed
          a congested city centre site, near airports,
                                                                          • Can the route accommodate the number of
          under overhead lines.
                                                                            vehicles in the required duration?
        • Limited period of access to the site, e.g. rail or
          road possession, tidal working.

10                                                                                                   Return to the contents
Constructability: A guide to reducing temporary works – TWf2020: 02                                Temporary Works forum

                                                                              • Do precast concrete elements have
          Example 1 – Bringing in material by rail                              protruding reinforcement?
          The Birmingham New Street Gateway                                • Does the load have to be tilted?
          programme was a £650m refurbishment
          of the old railway station into an iconic                           • Can the element be transported in its
                                                                                permanent orientation such that it does
          passenger Hub; completed whilst keeping the
                                                                                not have to be adjusted when lifted into
          operational railway working at all times in a
                                                                                position (e.g. a bridge beam for placing
          very congested city centre site.
                                                                                on abutments at different levels can be
          In order to maximise project efficiency and                           transported on temporary supports that
          minimise the effects on the neighbourhood                             have the same level difference as the
          an early decision was made to deliver most                            permanent supports)?
          materials/small plant - and remove most                          • What is the structural and material form of the
          waste products - by train. Only one of 12                          load to be moved?
          platforms could be closed at any time, so
                                                                              • What is its strength and rigidity?
          the closed platform was utilised to receive
          materials at the start of each shift and remove                        • If considering prefabricating or lifting
          waste at the end.                                                        reinforcement cages, remember that
                                                                                   reinforcement ties are poor structural
          Materials and plant were delivered to and
                                                                                   connections
          stored at the Bordesley sidings, just outside
          the city centre, minimising disruption                                 • If the element is made from concrete,
          throughout the project.                                                  what strength should have been
                                                                                   achieved before handling?
          This was a good example of thinking
                                                                              • How is it supported before moving?
          strategically at an early stage in order
          to facilitate efficient construction, whilst                        • Where are the attachment points?
          minimising the impact on others.                                    • What is the maximum reaction at each
                                                                                attachment point?
         • The proximity of being able to bring in material
                                                                              • Is relative movement between supports
           by rail (see Example 1)
                                                                                (temporary and permanent) important?
         • The need for haul roads and/or temporary
                                                                           • Will load be transmitted through two, three or
           bridges
                                                                             four points?
         • The impact on residents in the urban
                                                                              • Can it rock on just two supports (e.g. when
           environment
                                                                                considering 4 lifting points theoretically
         • Splice positions:                                                    equidistant from the centre of gravity,
            • Ensure that they are in the most                                  due to minor variations in setting out, all
              appropriate and optimal area                                      the load could be taken by only 2 lifting
                                                                                points)?
         • Contingency plans, e.g. redundancy;
           alternative delivery methods:                                   • Will the load need to be stored in a temporary
                                                                             position on site prior to be lifting into its
            • Ensuring that there is a robust approach to                    permanent position?
              minimise failed manoeuvres
                                                                              • What type of area is required for storage
6.6      The design of fabricated elements required                             purposes?
         to be lifted or moved
                                                                           • How will the load be supported after placing?
6.6.1    There are considerations for the design of
         fabricated elements required to be lifted or                         • Will it be supported immediately, without
         moved12:                                                               the need for grout to set?

         • What is the size, weight and position of the                       • It must be lined and levelled accurately.
           centre of gravity (CoG)?                                             Does the detailing allow for this? Temporary
                                                                                jacks can be used for fine adjustment
            • The point of application of the lift must pass
              through the CoG, or movement will take                          • The temporary supports and any
              place; the load will slew, twist or rotate (see                   permanent works they are attached
              Figure 5)                                                         to, must have adequate strength and
                                                                                stability for all ongoing environmental and
               NOTE: The position of the CofG varies                            construction loads (e.g. accidental impact,
               during the assembly of component parts                           wind and hydrostatic concrete loads), until
                                                                                incorporated into the permanent works.

 See also ‘Precast concrete: Good practice and common issues in temporary works’ (TWf2019: 01, TWf, 2019) (https://www.twforum.
12

org.uk/viewdocument/precast-concrete-good-practice-and)

Return to the contents                                                                                                        11
Temporary Works forum                             Constructability: A guide to reducing temporary works – TWf2020: 02

         • Can it be adequately supported about its                       • Have lifting checks been made in all temporary
           CoG? Is there any novelty in the design                          states (i.e. at all stages and not just off-site)?
           of the permanent works which makes the                         • Is off-line construction an option, e.g.
           temporary support particularly difficult (e.g.                   bridge slides, transportation by SMPT or
           inclined members, cantilever members)?                           bridge launches (where the road is diverted/
      • How is the member required to connect with                          constructed afterwards)
        the existing structure?                                               • Consider temporary states of the
         • Will protruding reinforcement clash with                             permanent works
           existing reinforcement?                                        • For multiple lifting operations, ensure the
      • How will the component be lifted?                                   attachments are designed to suit
         • Are screw-in loops (eyes) required? Has the                    • For complex lifts load compensating devices
           size and position been required, in order to                     may be required
           accommodate later construction?                                    • Consider the possibility of redundancy in
      • Consider the stability of modules                                       lifting equipment
         • Are braced beams required?
            NOTE: Beams in pairs are preferred to an
            odd number of beams
         • Have any splice positions been
           considered?

                                          Figure 5 - Example of eccentric lift. Centre of gravity is very close to lifting eye

                                                   NOTE: If the hook is not directly above the centre-of-gravity the load will rotate
                                                        (In this example, unequal chain lengths were used to achieve a level lift).

12                                                                                                        Return to the contents
Constructability: A guide to reducing temporary works – TWf2020: 02                                  Temporary Works forum

6.7      The handling and installation of pre-                               • Consider the stability of precast concrete
         fabricated elements on site                                           beams13 and steel girders
6.7.1    The considerations for handling and installing                         • These may be separate or combined
         fabricated elements on site include:                                • Are trial lift(s) and/or erection required?
         • Will pre-fabrication result in ‘locked-in’                        • When lifting, consider the access required at
           stresses in the permanent works?                                    any landing points to make connections and
            • Consider the effect of the construction                          remove lifting chains
              sequence on the final arrangement                              • Can cross-bracing of girders and similar
         • Have all the construction load cases been                           features required during the temporary state
           considered, e.g. prior to composite action                          be left permanently in place as sacrificial
           being achieved                                                      elements to reduce dismantling works?
            • Include horizontal loads                             7.0       When to consider constructability
         • What is the availability of plant?                                It is suggested that there is benefit in carrying
            • How does this affect the robustness of the                     out a formal constructability review at each of the
              programme to meet the installation date?                       four phases of the procurement management
                                                                             model (see Figure 6):
         • What size vehicle is required?
                                                                             • pre project/ initiation (see 8.1.1)
         • Consider:
                                                                             • options (see 8.1.2)
            • Dimensions including protrusions
                                                                             • development (see 8.2 and 8.3)
            • Weight
                                                                             • construction (see 8.4)
            • Applied ground bearing pressure
                                                                             These are considered in more detail in Sections
         • What space and/or additional cranage                              8.1 to 8.4. It may be appropriate to have a
           requirements are necessary for rigging and                        number of constructability reviews during the
           de-rigging large cranes                                           same phase. These can have the same goal (e.g.
            • Consider space for additional ballast,                         as an aid to the selection between alternatives
              delivery vehicles and turning circles                          during the initiation phase) or be different (e.g.
                                                                             as in the development phase when the design
         • What is the direction, distance and height to
                                                                             develops from preliminary design to a pre-
           be moved?
                                                                             construction cost estimate).
            • Are there changes in direction of travel and
                                                                             The design develops by a succession of choices
              slope or fall?
                                                                             between alternative solutions. As the alternatives
         • What are the site conditions?                                     are considered and preferences selected the
            • What are the ground conditions,                                design and detail become more defined. At each
              topography and foundation requirements?                        phase the choice of alternatives is limited by the
                                                                             preceding decisions. As the definition increases
            • Are there constraints from adjacent sites,                     the range of possibilities for future choices
              such as headroom near airports, over                           reduce, until eventually the design is completely
              railways or near nuclear facilities?                           defined.
            • What is the route of transportation (e.g.                      If, after considering constructability, a decision
              road, rail, river or sea) and what limitations                 on which the design has been based needs
              does this route impose?                                        to be changed, this may invalidate the design
            • Is on-site assembly of sub-assemblies                          work that had been based on it. The earlier
              constructed off site required?                                 the original decision was made, or the later
                                                                             the change is made, the more chance there is
         • How many items need to be moved, e.g. one-
                                                                             that it would affect other parts of the design;
           off move or multiple items?
                                                                             and the more re-working necessary. The earlier
         • Is speed critical (both programme duration                        that constructability is considered in design
           and velocity)?                                                    development, the more opportunity to influence
            • What site storage is required?                                 the design and the less need for reworking.

            • Is delivery ‘just in time’?                                    It should be noted, there is evidence from past
                                                                             projects that constructability was undertaken well
         • Are there environmental constraints, e.g.                         during some stages but was absent from others
           weather, tide and season?                                         (e.g. considered well at the design options stage
         • What provides the fail-safe in case of                            but undertaken poorly at the design stage).
           malfunction?
         • Is there any aspect in the design of the
           permanent works which makes its temporary
           support particularly difficult?

13
  Technical Advice Note: Handling of Bridge Beams on Site (PCA) (Now available at: https://www.twforum.org.uk/viewdocument/
technical-advice-note-handling-of)

Return to the contents                                                                                                        13
Temporary Works forum                                                                                  Constructability: A guide to reducing temporary works – TWf2020: 02

                                         High Influence                                                Low Influence                                   Results
                                         Low Cost                                                      High Cost

          100%                                                                                                                                                      100%

                            Decreasing                                                                                                                Increasing
                            influence                                                                                                                 cost

          0%                                                                                                                                                        0%

                                                                                                                                             Project Time

                    Pre project/                            Options                           Development                                     Construction         Use /                        End of use
                    initiation                              phase                             phase                                           phase                Operation                    and
                                                                                                                                                                                                demolition
     HE Project     0 Strategy,                             1 Option         2 Option         3               Decision       5                6 Construct,                        7 Closeout
     Control        shaping and                             identification   selection        Preliminary     point:         Construction     commission
     Framework      prioritisation                                                            design          4 Statutory    preparation      and
     PCF 2008                                                                                                 procedures                      handover
                                                                                                              and powers

     Network Rail   1 Output           2 Feasibility                         3 Option         4 Single        5 Detailed                      6 Construct,         7 Scheme       8 Project     End of use,
     GRIP           definition                                               selection        option          design                          test,                handback       closeout      decommis-
                                                                                              development                                     commission                                        -sioning and
                                                                                                                                                                                                demolition
                                                                                                                                                                                                may have
                                                                                                                                                                                                such
                                                                                                                                                                                                significant
     2013 RIBA      0 Strategic        1                                     2 Concept        3 Developed     4 Technical                     5                    6 Handover     7 In use      consequences
     Plan of Work   definition         Preparation                           design           design          design                          Construction         and closeout                 that it is
                                       and brief
                                                                                                                                                                                                appropriate
                                                                                                                                                                                                to use the
                                                                                                                                                                                                full Project /
                                                                                                                                                                                                programme
     Construction   Stage 1                                                  Stage 2          Stage 3         Stage 4                         Stage 5              Stage 6        Stage 7 (in   management
     Industry       (Preparation)                                            (Concept )       (Design         (Production                     (Manufacture,        (Handover      use)          model for
     Council                                                                                  Development)    Information)                    Installation &       and                          this stage
     (CIC)                                                                                                                                    Construction         closeout)                    (from pre
                                                                                                                                              Information)                                      project to
                                                                                                                                                                                                impementation)
     The            0 Strategic        1                                     2 Concept        3 Spatial       4 Technical    4.5              5                    6 Handover     7 In use
     Structural     definition         Preparation                           design           Cordination     design         Production       Manufacturing
     Plan of Work                      and brief                                                                             Information      and
     IStructE                                                                                                                                 Construction
     2020

                                 8.1.1         8.1.1                  8.1.2              8.2                8.2                  8.3        8.4
                                 Project       Project                Options            Preliminary        Detail               Tender     Project
                                 Initiation    Initiation             Selection          Design             Design                          Construction

                                                                       Figure 6 - How a constructability review can improve the design of permanent works

                                              NOTE: A diagram – based on figure 1 – showing the idealised change in the influence and cost of design and
                                                        constructability decisions on the project cost with respect to project duration, overlaid with project
                                                         procurement management model and suggested opportunities for formal constructability reviews

14                                                                                                                                                                              Return to the contents
Constructability: A guide to reducing temporary works – TWf2020: 02                                Temporary Works forum

7.1      Notes on the practical aspects of carrying              7.2       Who should undertake reviews
         out constructability reviews                            7.2.1     To be considered an effective way of ensuring
         There are a number of issues to consider:                         constructability, at any stage, constructability
         Positives:                                                        reviews should be undertaken by all parties to a
                                                                           project, bringing together different expertise from
7.1.1    Constructability reviews:                                         all duty-holders:
         • should be polite and inclusive;                                 • project manager;
         • can be a team-building exercise, when done                      • client;
           well;
                                                                           • permanent works designer (consultant);
         • will highlight issues which may affect safety,
           operations, temporary works requirements,                       • construction expert (temporary works);
           etc. and may inform ‘design change’;                            • principal designer;
         • should consider the likely impact on                            • specialist construction experts (e.g.
           neighbours and test whether the proposals                         proprietary suppliers);
           have the potential to disadvantage particular                   • stakeholder technical representative(s);
           groups in the community;
                                                                           • facility operator;
         • can enable efficiency for design and execution
           of the works, enable contingency plans to be                    • safety expert(s).
           developed and will troubleshoot issues before         7.2.2     Sometimes, the best constructability advice
           they get to site.                                               comes from the site team, e.g. foreman.
7.1.2    A constructability review can also:                     7.3 Information
         • ‘de-risk’ a project by ensuring that it can be        7.3.1     The project needs to be defined to a sufficient
           constructed and in what sequence (allowing a                    level of detail to be able to carry out a
           better focus on the most effective options);                    constructability review. This information may take
         • facilitate early identification of temporary works              the form of reports, surveys, archive information,
           requirements, to enable early procurement;                      calculations, drawings and models.

         • facilitate the production of temporary                7.3.2     Building Information Modelling (BIM) - see
           works solutions that suit chosen temporary                      Appendix 3 - can be an effective way of
           conditions and sequencing;                                      capturing, collating and presenting this
                                                                           information14.
         • enable early decisions to be made on whether
           the permanent works design can be amended             8.0       A methodological approach to
           to improve constructability;                                    constructability reviews

         • improve constructability to facilitate improved                 Sections 8.1 to 8.4 show a methodical approach
           safety, programme and cost.                                     to reviewing constructability. They identify the
                                                                           stages when a constructability review may be
         Hazards/pitfalls:                                                 useful and list some of the pre-requisites, aims
7.1.3    It should be remembered that:                                     and outputs of the review process.
         • There is more than one way to build                             The items listed and the topics covered should
           something and different construction experts                    be adapted and changed to suit the requirements
           may have preferred techniques;                                  of a particular project.
         • The people best at constructing are most                        More than one constructability review may be
           likely be on site constructing - the most                       required during each stage of the project delivery
           experienced or best construction expert(s)                      process. For example, it may be appropriate to
           may be not be available for the constructability                have a constructability review at the preliminary
           review;                                                         design stage and another at detailed design.
         • The continuity of construction experts                          It is expected that as the use of BIM develops
           at subsequent constructability reviews                          within the industry it will become a key tool
           may depend upon staff retention and the                         in carrying out and recording constructability
           contractor’s work commitments.                                  reviews.

14
  The TWf [September 2020] is preparing some advice, ‘An open standardized approach to the management of temporary works design
– digital collaboration’.

Return to the contents                                                                                                      15
Temporary Works forum                                Constructability: A guide to reducing temporary works – TWf2020: 02

                                                                        It is important to identify early on any technical
         NOTE: Engineering assurance and                                approval authorities, e.g. highways, rail. Large
         constructability reviews                                       clients may have their own technical approval
         Large infrastructure organisations such as                     process and should be engaged.
         Network Rail and Highways England have                8.1.2    Constructability at option development and
         engineering assurance processes that seek                      selection
         to de-risk designs against numerous criteria -
                                                                        Design development and options selection GRIP
         such as maintaining open railways and open
                                                                        1/2/3; RIBA 0/1/2; HE 0/1/2
         roads as far as is reasonably practicable – in
         order to minimise the effects of repairs and                   The brief (requirements) should be identified.
         enhancements on rail and road users.                           Consider the variety of options (forms)
                                                                        developed, e.g. location, number of spans,
         Undertaking constructability reviews will
                                                                        concrete or steel, practicalities, sequence of
         enable the project team to home in on the
                                                                        construction, aesthetics, etc.
         most appropriate, constructible solutions and
         ensure operations continue without undue                       The deliverability – in addition to
         disruption.                                                    constructability - should also be assessed. A
                                                                        project risk workshop may, for example, be
         Such procedures call for schedules of
                                                                        the way to do this. This process may repeat in
         temporary works to be developed, to include
                                                                        later stages.
         the following:
                                                               8.1.3    The importance of constructability at project
         • location/description of temporary works
                                                                        initiation, option development and selection
         • design check category
                                                                        If constructability and temporary works are not
         • high- or low-risk check category for work                    considered from the outset the structure may be
           package planning                                             very difficult (unsafe) and/or impossible (too risky)
         • confirmation and consideration of                            to build; as well as too expensive.
           coordination between all permanent and                       Decisions on land-take, programme and
           temporary works                                              aesthetics taken at the project initiation
         • dates for submission and acceptance for                      and option development stages will have a
           deliverables                                                 fundamental impact on the delivery of the
                                                                        scheme, e.g. space for site access and cranage,
         • details of temporary work design
                                                                        key possession dates and length of programme.
           organisation
                                                                        The designer may introduce risks that could be
         • details of interdisciplinary interfaces
                                                                        avoided or increase exposure. CIRIA C755 [4.]
         • requirements for inspections and testing                     advises:
         A constructability review will enable early                    • “Designers would be wise to stray on the
         determination of the need for such works.                        side of caution – especially when considering
                                                                          significant (‘life or death’) risks because after a
8.1     Constructability at project initiation, option                    death legal analysis of reasonableness will be
        development and selection                                         tinged by the reality and emotion of what has
                                                                          actually happened …
8.1.1   Constructability at project initiation
                                                               8.1.4    Actions to be complete before holding
        Grip 1, RIBA 0, HE 0
                                                                        constructability review
        It is never too early to consider constructability;
                                                                        The following actions should be completed:
        and as early as project initiation stage. A
        constructability review at this stage should be a               • Functional requirements established
        swift process, as there will be many unknowns                   • Alternative geographical locations identified
        and many options to home in on. Such a review
                                                                        • Stakeholders identified
        will enable appropriate conversations about how
        a proposal can be built; to test its feasibility for            • Value criteria established
        construction.                                                   • Outline solutions determined
        As early solutions are developed, the basics will               • Options preliminary design and feasibility
        then be better understood and key decisions can
        be made in principle, e.g. access arrangements,                 • Site investigation(s) carried out
        logistics, materials storage, cranage. This will                • Restrictions on timing and boundaries of
        enable key issues to be resolved, e.g. the need                   site possession identified, e.g. rail interface,
        to buy or hire land owned by others to facilitate                 airport/flightpath, tidal working, nearby power
        construction in good time.                                        transmission

16                                                                                                   Return to the contents
Constructability: A guide to reducing temporary works – TWf2020: 02                          Temporary Works forum

8.1.5   Aim of the constructability review                   8.2.1    Actions to be complete before holding
        The aim of the constructability review is to                  constructability review
        determine:                                                    The following actions should be completed:
        • whether the project can be built safely in the              • Form of structure established
          time allowed                                                • Geographical locations established
        • construction materials and methodology                      • Stakeholders engaged
        • what specialist plant and contractors are                   • Check that value criteria are being met
          required
                                                                      • Determine outline solutions
        • what geotechnical work has to be carried out
                                                                      • Advanced the options preliminary design
        • the obstacles that must be overcome
                                                                      • Identify interfaces between functions of works
        For example, site access and egress (e.g.
        timings: tides/possessions; environmental, site of            • Identify interfaces with other contracts
        special scientific interest); weather and seasonal            • Carry out further site investigation(s)
        conditions (e.g. monsoon season, school term
                                                                      • Draw up a schedule of site possessions
        times)
                                                             8.2.2    Aim of the constructability review
        • major items of temporary works; better
          still, what can be done to design them out                  The aim of the constructability review is to
          (elimination)                                               determine:

        • potential logistics problems                                • Method for choosing the location of
                                                                        construction joints
        For example: can the materials and resources be
        made available; where will they be coming from;               • Determine the size of pre-assembled
        does a mine, quarry or borrow-pit need to be                    components to be delivered to site
        established; do people need to be trained                     • Method of handling (craning) pre-assembled
        • potential transport problems                                  components.

        For example: can the materials and resources be                  NOTE: If reinforcement has to be pre-
        delivered to site at the correct time                            fabricated, how will the reinforcement cage
                                                                         temporary structure be designed?
        • any sources of uncertainty
                                                                      • Method of connecting pre-assembled
8.1.6   Actions to be carried out after
                                                                        components
        constructability review
                                                                      • Method of supporting pre-assembled
        The following actions should be completed:
                                                                        components before they become incorporated
        • best (compromise) solution chosen from                        into the works and are self-supporting
          options
                                                                         NOTE: This includes reinforcement, steelwork
        • safety case developed                                          and precast concrete
        • hazard identification carried out                           • Method of providing strength and stability
        • risks designed out or reduced                                 during early maturity (e.g. concrete strength
                                                                        for slip-forming)
        • risk register developed
                                                                      • Method of providing stability during early
8.2     Constructability at preliminary and detailed                    stages of construction
        design
                                                                         For example: additional bracing in composite
        Development phase: GRIP 4/5; RIBA 3/4; HE                        bridges where the steel beams would rely on
        3/4/5                                                            the deck to restrain the top flange; longitudinal
        Consider the form to be chosen: For example,                     restraint of continuous span bridges that are
        sequence of construction; bearing details (and                   constructed in incremental spans
        temporary fixity/restraint); thermal movements;               • Assess the stability of any existing structures
        residual stresses; temporary support to follow on               during the works, e.g. masonry walls upon
        construction (e.g. temporary support to precast;                removal of any adjacent walls, roof or floor
        precast acting as formwork resisting hydrostatic                support; the support of wet concrete on
        loads; precast acting as edge protection);                      masonry walls; wind loading on previously
        unsupported reinforcement; correct poor                         protected walls and/or structures
        buildability; eliminate unnecessary temporary
        works.

Return to the contents                                                                                                  17
You can also read