ENGINEERING POLICY 305 - FACILITIES CONNECTION REQUIREMENTS APPLICABLE STANDARD(S)

Page created by Karl Cohen
 
CONTINUE READING
ENGINEERING POLICY 305 - FACILITIES CONNECTION REQUIREMENTS APPLICABLE STANDARD(S)
ENGINEERING

 POLICY 305 - FACILITIES CONNECTION REQUIREMENTS

  APPLICABLE STANDARD(S):                 NERC FAC-001-0

DOCUMENT OWNER: TOM KING

   APPROVED BY: DAN WILKINSON

          TITLE: MANAGER OF ENGINEERING

   APPROVED BY: DANNY JANWAY

          TITLE: VP OF ENGINEERING & OPERATIONS

                        Version Number: 5.0
                              Page 1
Table of Contents
1. DEFINITIONS ..............................................................................................................................6
2. INTRODUCTION ..........................................................................................................................7
3. MISO’S FEASIBILITY STUDY .....................................................................................................8
4. SYSTEM IMPACT STUDIES .......................................................................................................8
5. GENERATION CONNECTIONS REQUIREMENTS ..................................................................10
   5.1 General Requirements .............................................................................. 10
       5.1.1 Backfeed ............................................................................................. 10
       5.1.2 Generator Frequency .......................................................................... 10
       5.1.3 Interrupting Device .............................................................................. 10
       5.1.4 System Protection ............................................................................... 11
       5.1.5 Synchronizing ..................................................................................... 11
       5.1.6 System Grounding .............................................................................. 11
       5.1.7 Voice Communication Circuit .............................................................. 11
       5.1.8 Disconnecting Devices........................................................................ 12
       5.1.9 Disturbance Monitoring ....................................................................... 12
       5.1.10 Transient Stability Performance ........................................................ 12
       5.1.11 Excitation Control .............................................................................. 12
       5.1.12 Speed Governing .............................................................................. 13
       5.1.13 Dynamic Performance Data .............................................................. 13
       5.1.14 Automatic Generation Control (AGC)................................................ 13
       5.1.15 Black Start Capability ........................................................................ 13
       5.1.16 Sub-Synchronous Torsional Interactions or Resonances ................. 13
       5.1.17 Unbalanced Electric Conditions ........................................................ 14
       5.1.18 Harmonics and Flicker ...................................................................... 14
   5.2 Operating Requirements ........................................................................... 14
       5.2.1 Synchronization .................................................................................. 15
       5.2.2 Generator Step-up and Auxiliary Transformer Tap Settings ............... 15
       5.2.3 Voltage Schedule/Power Factor ......................................................... 15
       5.2.4 Voltage Range .................................................................................... 16
       5.2.5 Frequency Range ............................................................................... 16
       5.2.6 Net Demonstrated Real and Reactive Capabilities ............................. 16
       5.2.7 Other Applicable Operating Requirements ......................................... 16
       5.2.8 Operating Restrictions ........................................................................ 17

                                                            Version Number: 5.0
                                                                      Page 2
5.3 Relay Protection Requirements ................................................................. 17
     5.3.1 Customer Facilities ............................................................................. 17
     5.3.2 WPSC Facilities .................................................................................. 18
  5.4 Other Protection Requirements ................................................................. 19
     5.4.1 Generator Control ............................................................................... 19
     5.4.2 Transformer Surge Protection (Lightning Arresters) ........................... 19
     5.4.3 Breakers ............................................................................................. 19
     5.4.4 Equipment Basic Insulation Levels ..................................................... 19
     5.4.5 Insulators for Station ........................................................................... 19
  5.5 Costs Incurred ........................................................................................... 19
  5.6 Design Review .......................................................................................... 20
  5.7 Facility Data............................................................................................... 20
     5.7.1 Data on Equipment to be Installed ...................................................... 20
     5.7.2 Generator Data ................................................................................... 21
  5.8 Final Documentation ................................................................................. 21
  5.9 Approval .................................................................................................... 21
6 WPSC NON GENERATION CONNECTIONS TECHNICAL REQUIREMENTS ........................22
  6.1 Distribution Interconnection Guidelines ..................................................... 22
     6.1.1 Procedure for Distribution Interconnections ........................................ 22
     6.1.2 Distribution Interconnection Configuration .......................................... 23
     6.1.3 Extraordinary Services Requests ........................................................ 24
     6.1.4 Extension of WPSC System to Remote Locations .............................. 25
     6.1.5 Facility Ownership .............................................................................. 25
  6.2 Tap Connection Definition and Requirements ........................................... 25
  6.3 Looped Connection Definition and Requirements ..................................... 26
  6.4 Network Connection Definition and Requirements .................................... 26
  6.5 Voltage Levels ........................................................................................... 26
  6.6 Power Factor Requirements ...................................................................... 26
  6.7 Frequency Range ...................................................................................... 27
  6.8 Power Quality ............................................................................................ 27
     6.8.1 Harmonics and Flicker ........................................................................ 27
     6.8.2 Sensitive Electrical Equipment............................................................ 27
     6.8.3 Transformer Protective Devices .......................................................... 28
  6.9 Unbalanced Electric Conditions................................................................. 28

                                                 Version Number: 5.0
                                                          Page 3
6.9.1 Voltage Balance .................................................................................. 28
      6.9.2 Current Balance .................................................................................. 28
   6.10 Subsynchronous Torsional Interaction .................................................... 28
   6.11 Information Required ............................................................................... 29
   6.12 Other Design Criteria ............................................................................... 31
      6.12.1 Equipment Basic Insulation Levels ................................................... 31
      6.12.2 Transformer Surge Protection (Lightning Arresters) ......................... 31
      6.12.3 Ratings of Current Carrying Equipment ............................................ 31
      6.12.4 Electrical Clearances (Outdoor) ........................................................ 32
      6.12.5 Insulators for Station ......................................................................... 32
      6.12.6 Air Break Switch(es) and Disconnect Switch(es) .............................. 32
      6.12.7 Facility Fence Safety Clearances ..................................................... 33
      6.12.8 Ground System Resistance .............................................................. 33
      6.12.9 Breaker Duty ..................................................................................... 33
   6.13 System Protection ................................................................................... 33
      6.13.1 Transmission Protection ................................................................... 33
      6.13.2 End-User Protection.......................................................................... 33
   6.14 Automatic Under-frequency Load Shedding ............................................ 33
   6.15 Remote Relay Access ............................................................................. 34
      6.15.1 Loop or Network Connected Facilities .............................................. 34
7 METERING AND TELEMETRY ..................................................................................................34
   7.1 Metering .................................................................................................... 34
   7.2 Telemetry .................................................................................................. 35
8 VOICE COMMUNICATIONS.......................................................................................................36
   8.1 Normal ....................................................................................................... 36
   8.2 Emergency ................................................................................................ 36
      8.2.1 Generation Owner .............................................................................. 36
      8.2.2 Transmission/End-User ...................................................................... 36
      8.2.3 Interruptible Contracts......................................................................... 37
   8.3 Communication Protocol ........................................................................... 37
9 INSPECTION REQUIREMENTS ................................................................................................37
10 TESTING AND MAINTENANCE REQUIREMENTS ................................................................37
   10.1 Generation Owners ................................................................................. 37
   10.2 Transmission/End Users ......................................................................... 38

                                                     Version Number: 5.0
                                                               Page 4
10.3 Maintenance and Testing Schedule ........................................................ 38
       10.3.1 Transmission Substation Protective Relaying Testing ...................... 38
       10.3.2 Generation Protective Relay Testing ................................................ 38
       10.3.4 Breaker and Transmission Substation Functional Testing ................ 39
       10.3.5 Inspection and Testing of Distribution Substations ........................... 39
11 SPECIAL PROVISIONS............................................................................................................39
12 COORDINATION WITH OTHER CODES, STANDARDS, AND AGENCIES ..........................39
13 INDEMNIFICATION ..................................................................................................................40
APPENDIX A ..................................................................................................................................41

                                                            Version Number: 5.0
                                                                       Page 5
1. Definitions

  1.1. Customer shall mean the person or entity requesting an interconnection with
       the Wolverine transmission grid.

  1.2. WPSC stands for Wolverine Power Supply Cooperative, Inc. and is synonymous
       with the Transmission Owner (TO) for this document.

  1.3. LGIA or “Interconnection Agreement” shall mean that Large Generator
       Interconnection Agreement between the Transmission Provider, the
       Transmission Owner, and the Interconnection Customer and filed with and
       approved or accepted by FERC.

  1.4. Loss shall mean any and all losses relating to injury to or death of any person or
       damage to property, demand, suits, recoveries, costs and expenses, court
       costs, attorney fees, and all other obligations by or to third parties, arising out of
       or resulting from the other Party’s performance, or non-performance of its
       obligations under this Agreement.

  1.5. NERC shall mean the North American Electric Reliability Council, or its
       successor agency assuming or charged with similar responsibilities related to
       the operation and reliability of the North American electric interconnected
       transmission grid.

  1.6. Network Upgrade shall mean the necessary upgrades to the Transmission
       Owner Transmission System that would not have been required but for the
       interconnection of the Facility to the WPSC transmission system, including
       (i) upgrades necessary to remove overloads and voltage criteria violations and
       (ii) upgrades necessary to remedy short circuit and/or stability problems
       resulting from the interconnection of the Facility to the WPSC transmission
       system.

  1.7. RFC stands for ReliabilityFirst Corporation. ReliabilityFirst is a not-for-profit
       company incorporated in the State of Delaware whose goal is to preserve and
       enhance electric service reliability and security for the interconnected electric
       systems within its territory. ReliabilityFirst was approved by the NERC to
       become one of eight Regional Reliability Councils in North America and began
       operations on January 1, 2006.

  1.8. MISO stands for the Midwest Independent Transmission System
       Operators. As a fully integrated regional transmission organization, the non-
       profit Midwest ISO assures industry consumers of unbiased regional grid
       management and open access to the transmission facilities under Midwest ISO's
       functional supervision. Midwest ISO optimizes the efficiency of the
       interconnected system, provides regional solutions to regional planning needs
       and continually minimizes any risk to reliability.

                                      Version Number: 5.0
                                             Page 6
2. Introduction
This document provides minimum connection requirements for all entities seeking facility
connections to WPSC’s system. It is the intent of this document to satisfy the NERC
Planning Standard FAC-001 by identifying requirements for connections. Although
NERC and RFC requirements refer to the Bulk Transmission System and voltages of
100 kV and above, this document also applies to connections to WPSC’s systems rated
lower than 100 kV. This document does not address how or what entity will pay for
studies and system upgrades.

Transmission Interconnections refer to transmission connections between WPSC and
other utilities. Connections other than generation are considered End-Users or Load
Serving Entities (LSE). Requests for connections to WPSC’s system will follow the
procedures outlined by MISO and, in general, will require an application, Feasibility
Study, System Impact Study (SIS), and a Facility Study or Generator Interconnection
Study. All expenses associated with these studies are the responsibility of the party
requesting the interconnection. These studies will be performed to determine the
detailed impact on WPSC’s system. These studies are directed by the MISO and
required to meet their format. More details of MISO’s requirements to initiate a study
can be obtained by contacting MISO. Any upgrades, additions, enhancements, or
changes of any kind to an existing connected facility are subject to WPSC and MISO’s
review to ensure continued compliance with these requirements

WPSC operates its transmission system in compliance with NERC Reliability Standards,
RFC standards, and WPSC’s own planning criteria and facility connection requirements.
All facilities involved in the generation, transmission, and distribution of electricity must
be properly connected to the interconnected transmission system to avoid degrading its
reliability and ensure continued compliance to the applicable reliability standards. The
procedures outlined by MISO and described above are meant to ensure WPSC’s
transmission system continues to meet these reliability standards.

The scope of this document is limited to the technical requirements for connected facility
design and operation and does not address transmission service. Parties requiring
transmission service should refer to the WPSC Open Access Transmission Tariff.

The objective of this document is to:
 Satisfy compliance with NERC Planning Standard FAC-001 pertaining to
   documentation of facility connection requirements by those entities responsible for
   system reliability.
 Inform those entities seeking facility connections to the WPSC System of the various
   requirements for system reliability, personnel and equipment safety, and quality of
   service.
 Ensure consistent requirements are imposed on the various entities seeking to
   connect facilities to the network.
 Maintain system reliability, personnel and equipment safety, and quality of service as
   new facilities are added to the network and existing facilities are modified.
 Ensure continued compliance with NERC Reliability Standards, RFC standards,
   MISO standards, and WPSC’s own planning criteria and facility connection
   requirements.

                                       Version Number: 5.0
                                              Page 7
   Provide uniform equipment specifications, designs, engineering, and installation
    practices to promote safety and uniformity of service.

3. MISO’s Feasibility Study
Any entity proposing new or materially changed generation or load serving connection
points for transmission service from WPSC’s system must initiate a Feasibility Study.
The Feasibility Study is initiated through MISO and is performed or supervised by
WPSC. The Feasibility Study is performed to determine and evaluate the electrical
configuration and physical connections/locations between the transmission system and a
proposed connected facility. The electrical configuration determines the connection
equipment including transformers, switchgear and other station equipment, and required
transmission line sections. The MISO will notify any interconnected utility that could be
impacted by the proposed facility and coordinate the studies to determine their impact as
necessary.

For the proposed interconnection modeled, the Study shall determine:
              1) The cause of any electric system capability and reliability limitations;

               2) A list of electric system components that must either be upgraded or
                  constructed to accommodate the proposed interconnection;

               3) The amount of generation/load that can be accommodated without
                  violating facility ratings and/or reliability standards if the full
                  generator/load cannot be accommodated without exceeding such
                  facility ratings and/or reliability standards.

The Study shall consider the locational effects of the generator/load. This analysis shall
be a quick screening process used to identify required interconnection upgrades. This
study is just meant to identify local constraints on the neighboring transmission system
and is not a delivery study.

4. System Impact Studies
After the Feasibility Study a SIS must be performed, if the interconnection customer
chooses to continue with the process. The SIS is used to determine the proposed
connection facility’s impact on system reliability. The proposed generation will be tested
covering a range of probable operating conditions and system responses to probable
disturbances. The transient stability affect of the new generation/load on the existing
system and the behavior of the additional generation/load following system faults are
studied. For new generation, the ability to meet WPSC’s reactive power requirements
will be analyzed. The dynamic fault clearing simulation tests for connection to the Bulk
Electric System (BES) will include:
     1. bolted 1-phase to ground faults at most critical location cleared by primary
        relaying.
     2. bolted 3-phase to ground faults at most critical location cleared by primary
        relaying.
     3. bolted 2-phase to ground faults at most critical location resulting with delayed
        clearing due to a breaker failure.
     4. bolted 3-phase to ground faults with critical element out-of-service prior to the
        fault event cleared by primary relaying.

                                      Version Number: 5.0
                                             Page 8
The dynamic fault clearing simulation tests for connection to the non-BES include:
   1. bolted 1-phase to ground faults at most critical location cleared by primary
      relaying.
   2. bolted 3-phase to ground faults at most critical location cleared by primary
      relaying.
   3. bolted 2-phase to ground faults at most critical location resulting with delayed
      clearing due to a breaker failure.

Total clearing time to be studied will be 4 cycles local and 34 cycles for faults cleared by
primary relaying and 19 cycles local and 49 cycles remote for breaker failure clearing.
This will be reviewed on a case-by-case basis prior to performing the study.

All requested study transfers will be analyzed without the proposed generation/load
interconnection and with the proposed generation/load interconnection to determine any
adverse impacts on the transfer capability caused by the proposed generation/load. The
Study shall identify any reductions in transfer capability and the associated system
conditions. No delivery rights will be granted based on this study.

The SIS will determine the impact of the proposed facility for a range of expected
seasonal loading and power transfer conditions on the transmission line and transformer
loading, voltage profiles and schedules, minimum reactive requirements, and power
quality. The effect of the proposed facility on short circuit duties is examined for all
proposed generation facilities and transmission connections. Stability performance is
also assessed for all proposed generation facilities. A multi-step approach to the
proposed facility may be considered when the impact of each step is assessed
separately.

The scope of the above SIS is determined by WPSC and/or MISO based on the type,
location, and power level of the proposed facility. WPSC or a consultant to WPSC will
perform the system impact studies at the expense of the requesting party. A report
documenting the assumptions, results, and conclusions of the SIS is made available to
the requesting party. WPSC must be notified in writing of new facilities, upgrades, or
additions. This includes an increase in load or added generating units to existing
facilities connected to the transmission system within the WPSC Control Area.

WPSC approval of a proposed facility or facility change is contingent upon a design
review of the proposed connected facility. Operation of a connected facility is also
subject to continuing compliance with all applicable construction, maintenance, testing,
protection, monitoring, and documentation requirements of WPSC, MISO, RFC and the
applicable NERC Planning Standards.

                                       Version Number: 5.0
                                              Page 9
5. Generation Connections Requirements
    5.1 General Requirements
    Applications for generator interconnection within WPSC's system should be
    directed to the Midwest ISO. The request will be entered into the Midwest ISO's
    study queue for generator interconnection. The Midwest ISO will contact WPSC
    as the direct-connect Transmission Owner in order to inform WPSC that the
    application has been received. An Ad Hoc Working Group will be formed
    consisting of WPSC personnel, other affected transmission owners or parties and
    Midwest ISO personnel. The Midwest ISO contact for generator interconnection
    studies is as follows:

    Mr. Diwakar Tewari
    Midwest ISO
    720 City Center Drive
    Carmel, IN 46032
    DTewari@midwestiso.org
    (317) 249-5715

    Attachment R to the tariff, Generator Interconnection Procedures and
    Agreement, prescribes the procedures for small generators (defined as
    generation interconnection requests equal to or less than 20 MW). Attachment X
    to the tariff, Standard Large Generator Interconnection Procedures, prescribes
    the procedures applicable to generating facilities that exceed 20 MW. The
    attachments may all be found at www.midwestiso.org.

    The customer must take responsibility to specify appropriate equipment and
    ancillary operating facilities so that the parallel generation facility is compatible
    with the WPSC transmission system. The applicant’s installation must conform
    to National Electrical Safety Code (NESC) and National Electrical Code (NEC)
    requirements.

           5.1.1 Backfeed
                   A customer’s generation facility should not backfeed power into
                   the WPSC system unless a specific agreement has been made to
                   supply power to the WPSC system. Under no circumstances
                   should a customer energize a disconnected WPSC circuit.

           5.1.2 Generator Frequency
                   All generation shall be nominal 60 Hz, balanced, positive
                   sequence, three-phase generation.

           5.1.3 Interrupting Device
                   The customer must provide a three phase interrupting device to
                   isolate the generation from the WPSC system for any faults or
                   abnormal operating conditions. This device shall be capable of
                   interrupting the maximum available fault current at that location,
                   regardless of the source, and clear the fault in less than one cycle
                   once initiated. The three-phase device shall interrupt all three

                                    Version Number: 5.0
                                          Page 10
phases simultaneously. The interruption control shall have
      automatic (relay), WPSC SCADA, and manual initiation. The
      tripping control of the circuit interrupting device shall be powered
      by a battery backed DC source that is independent of the AC
      source. This is required in order to ensure operation upon loss of
      the WPSC transmission voltage source under abnormal or fault
      conditions.

5.1.4 System Protection
      The customer will have responsibility for providing adequate
      system protection to WPSC facilities for the generation including
      system protection for any WPSC operating conditions, whether or
      not their generation is in operation. WPSC has standardized on
      Schweitzer Engineering Laboratory (SEL) relays for its
      transmission lines and requires these relays to be used to ensure
      coordination. The Customer is responsible to provide Primary and
      Backup relaying in sufficient quantity to produce a redundant trip
      scheme capable of interrupting under all conditions listed above.

             Short Circuit: phase-to-phase, phase-to-phase-to-ground,
             three phase, three phase-to-ground, or phase-to-ground.
             Abnormal voltage or frequency.
             Lightning and switching surges.
             Excessive harmonic voltages and/or currents.
             Excessive negative sequence voltages.
             Separation from WPSC.

5.1.5 Synchronizing
      The customer shall assume all responsibility for synchronizing the
      generator with the WPSC system. The initial synchronization of
      the generator to WPSC’s system shall require monitoring to
      ensure that all three phases are synchronized and have the
      correct sequence. After the first successful synchronization, only
      the A phase voltage is required to be synchronized before
      connecting to the WPSC system. Upon loss of the WPSC supply,
      the customer must immediately separate from the WPSC system.

5.1.6 System Grounding
      Grounding requirements for connections to WPSC transmission
      systems must meet all NESC and NEC requirements. WPSC will
      review all interconnection grounding designs and reserves the
      right to require the customer to add additional grounding.

5.1.7 Voice Communication Circuit
      The customer will be required to establish a voice communication
      circuit capable of reliably interfacing with WPSC’s Control Center.
      The intent is to facilitate communication for maintenance and
      system configuration modifications as required.

                      Version Number: 5.0
                            Page 11
5.1.8 Disconnecting Devices
      A three-phase air break switch or a three-pole single-throw
      disconnect switch accessible at all times shall be installed on each
      transmission line supply entrance to the connecting facility in
      addition to the interrupting device described above. The
      disconnecting device is to provide a visible isolation point between
      the connecting facility and WPSC’s transmission system and shall
      have a mechanical interlock in the open position suitable for a
      WPSC padlock. The disconnecting device shall be identified with
      a WPSC designated equipment number.

5.1.9 Disturbance Monitoring
      The Customer’s system must have disturbance monitoring
      equipment per PRC-002-RFC-01 (Found at www.RFirst.org).

5.1.10 Transient Stability Performance
      Transient stability performance of the generator is the
      responsibility of the Customer. Transient stability performance
      should be in accordance with WPSC Transient Stability Criteria
      and outlined in the SIS. WPSC will perform the necessary studies
      to evaluate transient stability performance. The cost of these
      studies will be the responsibility of the Customer as part of the
      SIS.

5.1.11 Excitation Control
      In addition to the normal excitation system and automatic voltage
      regulation equipment, the following controls are also required for
      each synchronous generator:

             Reactive Compensation - Reactive line drop compensation
             shall be provided in the automatic voltage regulator (AVR)
             to permit the control of voltage beyond the generator
             terminals. The point of control shall be adjustable over a
             range of 0 to 0.15 per unit reactance (on the generator
             base).

             Over-current Limiter - The excitation system shall be
             provided with a current limiting device that will supersede
             or act in unison with the AVR to automatically reduce
             excitation so the generator field current is maintained at
             the allowable limit in the event of sustained under-voltages
             on the transmission system. The over-current limiter
             device must not prevent the exciter from going to and
             remaining at the positive limit for 0.1 seconds following the
             inception of a fault on the power system.

             Under-excitation Limiter - An under-excitation limiter to
             prevent instability resulting from generator under-excitation
             is required.

                     Version Number: 5.0
                           Page 12
Power System Stabilizer – Power System Stabilizers
             (PSS) which is installed in the Automatic Voltage Regulator
             of the generator can improve the power system stability.
             Though the output power is determined by the generator
             mechanical torque, a generator output value can also be
             changed by changing excitation values transiently. A PSS
             detects changing of the generator output power, controls
             the excitation, and reduces the power swing. WPSC
             studies may identify the need for the use of power system
             stabilizers, depending on the plant size, excitation system
             type and settings, facility location, area transmission
             system configuration and other factors. This will be
             determined on a case-by-case basis.

5.1.12 Speed Governing
      All synchronous generators shall be equipped with speed
      governing capability. This governing capability shall be unhindered
      in its operation consistent with overall economic operation of the
      generation facility. See NERC Reliability Standard VAR-002.
      Over-speed protection in the event of load rejection is the
      responsibility of the Customer.

5.1.13 Dynamic Performance Data
      Dynamic performance data shall be made available to WPSC as
      part of the facility specifications and plans for evaluation by
      WPSC. This data is required to evaluate the system dynamic
      performance of the generation facility that includes but is not
      limited to transient stability.

5.1.14 Automatic Generation Control (AGC)
      Depending upon various control area factors applicable to tie line
      and frequency regulation, provision for dispatch control of the
      generation facility by the MISO Control Center AGC system may
      be required. This will be considered on a case-by-case basis and
      any provision for control by AGC should be included in a Facility
      Connection Agreement between the Customer and WPSC/MISO.

5.1.15 Black Start Capability
      Depending upon the geographic location and other
      considerations, black start capability may be required.
      Recommendations for black start requirements will be made in the
      SIS. The Facility Connection Agreement shall address the black
      start requirements.

5.1.16 Sub-Synchronous Torsional Interactions or Resonances
      High speed reclosing and sub-synchronous currents may result in
      excessive torsional stress on the generator. The Customer must
      provide WPSC with protection from damaging torsional
      oscillations resulting from all WPSC transmission system

                     Version Number: 5.0
                           Page 13
operations, and ensure the turbine-generator is not excited into
            resonance by normal system operations. The Facility Connection
            Agreement shall address these matters.

     5.1.17 Unbalanced Electric Conditions
            5.1.17.1 Voltage Balance
                    All three-phase generation shall produce balanced 60 Hz
                    voltages. Voltage unbalance attributable to the Customer
                    combined generation and load shall not exceed 1.0%
                    measured at the point-of-service. Voltage unbalance is
                    defined as the maximum phase deviation from average as
                    specified in ANSI C84.1, American National Standard for
                    Electric Power Systems and Equipment – Voltage Ratings,
                    60 Hertz.

            5.1.17.2 Current Balance
                    Phase current unbalance attributable to the Customer
                    combined generation and load shall not exceed that which
                    would exist with balanced equipment in service, measured
                    at the point-of-common coupling. Situations where high
                    unbalance in voltage and/or current originates from the
                    transmission system are to be addressed in the Facility
                    Connection Agreement.

     5.1.18 Harmonics and Flicker
            The Customer shall take responsibility for limiting harmonic
            voltage and current distortion and/or voltage flicker caused by
            their generation equipment. Limits for harmonic distortion
            (including inductive telephone influence factors) are consistent
            with those published in the latest ANSI/IEEE 519, Recommended
            Practices and Requirements for Harmonic Control in Electrical
            Power Systems. WPSC criteria requires that flicker occurring at
            the point of compliance shall remain below the “Border Line of
            Visibility” curve on the IEEE 1453/GE curve for fluctuations less
            than 1 per second or greater than 10 per second. However, in the
            range of 1 to 10 fluctuations per second, voltage flicker shall
            remain below 0.4%. Depending upon the nature of the generation
            and its location, WPSC may require the installation of a monitoring
            system to permit ongoing assessment of compliance with these
            criteria. The monitoring system, if required, will be installed at the
            Customer’s expense. Situations where high harmonic voltages
            and/or currents originate from the transmission system are to be
            addressed in the Facility Connection Agreement.

5.2 Operating Requirements
     The Customer is responsible for operating their generation with full regard
     for the safe practices of, and with full cooperation under the supervision
     of, the WPSC/MISO Operation Center. A Customer’s generation shall not
     supply power into the WPSC transmission system unless a specific
     written agreement has been made to supply power to the WPSC

                            Version Number: 5.0
                                  Page 14
transmission system. Under no circumstances shall a Customer energize
WPSC transmission facilities that have been de-energized. Circuits that
are electrically disconnected from the WPSC transmission system and
are energized by a Customer constitute a potential safety hazard for both
WPSC transmission personnel and the general public. Also, the
energizing of such circuits at abnormal voltage or frequency could cause
damage to electrical equipment of both the WPSC transmission system
and the Customer’s generation. WPSC reserves the right to disconnect
service to any generating facility if, for any reason, WPSC deems the
continuation of the service is, or may be, a detriment to the operation of
the WPSC Transmission System. The minimum requirements for
operation of a generation facility on the WPSC Transmission System are
contained herein.

5.2.1 Synchronization
       The Customer shall assume all responsibility for properly
       synchronizing their generation for operation with the WPSC
       Transmission System. Upon loss of the WPSC supply, the
       Customer shall immediately and positively cause the generation to
       be separated from the WPSC system. Synchronizing of
       generation to the WPSC Transmission System may be, at
       WPSC’s discretion, performed under the direction of the
       WPSC/MISO Control Center.

5.2.2 Generator Step-up and Auxiliary Transformer Tap
Settings
       The Customer must provide to WPSC the tap settings, available
       tap ranges, and impedance data for generator step-up and
       auxiliary transformers. WPSC may require changes to the tap
       settings for voltage control purposes. If tap setting changes are
       necessary, WPSC will provide the Customer with a report that
       specifies the required tap changes and technical justification for
       these changes.

5.2.3 Voltage Schedule/Power Factor
       Specification of the generator voltage schedule will be determined
       under the direction of the WPSC/MISO Control Center. This
       requirement is listed on the MISO website. See also NERC
       Reliability Standard VAR-002. A steady-state deviation between
       +0.5% to –0.5% of the nominal voltage will be permissible.
       WPSC’s voltage schedule is determined by WPSC’s Energy
       Control Center and can be obtained by calling 800-283-1260. In
       certain unusual situations where a voltage schedule is
       inappropriate, WPSC/MISO, initially and in the future, may
       substitute adherence to a specified voltage schedule with a
       specified power factor. A steady state deviation from this power
       factor of less than +/-1% is required.

                       Version Number: 5.0
                            Page 15
5.2.4 Voltage Range
      The generation facility must be capable of continuous non-
      interrupted operation within a steady-state voltage range during
      system normal and single facility outage conditions. This voltage
      range is from 95% to 105% of the nominal transmission voltage.
      During emergency and/or transient system conditions, as voltage
      may temporarily be outside the 95% to 105% range, all
      reasonable measures should be taken to avoid tripping of the
      generation facility due to high or low voltage.

5.2.5 Frequency Range
      The generation facility must be capable of continuous, non-
      interrupted operation in the frequency range of 59.5 to 60.5 Hz.
      Limited time, non-interrupted operation is also expected outside
      this frequency range in accordance with the generator
      manufacturer’s recommendations.

5.2.6 Net Demonstrated Real and Reactive Capabilities
      The Net Demonstrated real capability in accordance with ECAR
      (RFC) Document 4 and NERC Reliability Standards MOD-024 and
      MOD-025 must be provided to WPSC annually. In addition,
      individual generators in the generation facility must make available
      the full steady-state over and under-excited reactive capability
      given by the manufacturer’s generator capability curve at any MW
      dispatch level. Tests that demonstrate this capability must be
      conducted and documented at not more than five-year intervals in
      accordance with ECAR (RFC) Document 4 and NERC Reliability
      Standards MOD-024 and MOD-025. Such documentation shall be
      provided to WPSC. WPSC reserves the right to witness these
      tests.

5.2.7 Other Applicable Operating Requirements
      In order to assure the continued reliability of the WPSC
      Transmission System, the Customer may be requested to adhere
      to other operating requirements and/or encouraged to adopt
      common operating practices. These operating requirements and
      practices include the coordination of maintenance scheduling,
      performance not to exceed a specified forced outage rate,
      operations procedures during system emergencies, participation
      in control area operating reserves, provisions for backup fuel
      supply or storage, and provisions for emergency availability
      identified by the North American Electric Reliability Council.
      WPSC, as the Transmission Provider, may require the Customer
      to provide Interconnected Operation Services defined by NERC
      under Policy 10. Such requirements shall be addressed in the
      Connection Agreement with the Customer. Conformance with
      applicable requirements in ECAR (RFC) Documents, particularly
      Document 4, “Criteria and Methods for the Uniform Rating of
      Generation Equipment, RFC Reliability Standard PRC-002-RFC-

                     Version Number: 5.0
                           Page 16
01, “Disturbance Monitoring and Reporting Requirements”, and
           NERC Reliability Standard VAR-002, “Generator Operation for
           Maintaining Network Voltage Schedules”, are required. All data
           reportable to RFC and/or NERC shall also be made available to
           WPSC.

     5.2.8 Operating Restrictions
           Situations necessitating generation curtailments or forced outages
           as the result of unavailability of transmission facilities owned
           and/or operated by WPSC are to be addressed in a Facility
           Connection Agreement with the Customer.

5.3 Relay Protection Requirements
      5.3.1 Customer Facilities
           The customer is responsible for determining the generation and
           transformer protective equipment required to meet all applicable
           standards that it is properly installed, and coordinates with WPSC
           relaying. WPSC reserves the right to specify relay settings
           deemed necessary to ensure coordination, avoid safety hazards,
           or to prevent any impairment of WPSC’s ability to serve other
           customers. The customer is liable for failure of the protective
           relays to meet standards and operate effectively.

           The relay protection system may be part of a self-contained
           generation control package. Additional relay protection may be
           required if testing or operational problems are encountered with
           this self contained generation control package. WPSC shall
           review the interface protection and/or the self-contained protection
           schemes included with the generation before the unit will be
           permitted to connect to the WPSC system.

           The following relay functions are required by the customer for
           protection of the WPSC system. The use of the transfer trip
           receiver is conditional as set forth below.

           Relay                         Purpose
           Frequency                     To detect under and over-frequency
                                         operation and separate the customer
                                         parallel generation.

           Under/Over-Voltage            To detect under and over-voltage
                                         operation and cause separation of
                                         the customer parallel generation.

           Transfer Trip Receiver        To receive a trip signal from a

                          Version Number: 5.0
                                Page 17
WPSC transfer trip transmitter and
                                     separate the customer parallel
                                     generation.

      Ground Fault Detector          To detect a ground fault on the
                                     WPSC or customer system and
                                     separate the customer’s generation.

      Over-Current                   To detect an over-current condition
                                     and separate the customer’s
                                     generation.

      Directional Power              To detect a reverse power flow
                                     condition and separate the customer
                                     parallel generation.

      Output contacts of these relays shall directly energize the trip
      coil(s) of the generation breaker or an intermediate auxiliary
      tripping relay that directly energizes the breaker trip coil(s). The
      relaying system shall have a power source independent from the
      ac system and immune to ac system loss or disturbances (e.g., dc
      battery and charger) to ensure proper operation of the protection
      scheme. The loss of this source shall cause removal of the
      generation from the WPSC system. The protective relays
      required by WPSC and any auxiliary tripping relay associated with
      those relays shall be utility-grade devices.
      Utility grade relays are defined as follows:

                Meet ANSI/IEEE Standard C37.90, Relays and Relay
                 Systems Associated with Electric Power Apparatus.
                Have relay test facilities to allow testing without
                 unwiring or disassembling the relay.
                Have appropriate test plugs/switches for testing the
                 operation of the relay.
                Have targets to indicate relay operation.

      It is the Customer’s responsibility to determine that their protective
      equipment is adequate to meet all applicable standards.

5.3.2 WPSC Facilities
      A transfer trip relaying system must be installed at the Customer’s
      expense if WPSC determines it is necessary to protect WPSC
      facilities at this level. The transfer trip relaying system shall
      consist of all transfer trip transmitters located at WPSC facilities,
      transfer trip receivers at the Generation Facility, and the
      communication channels between the WPSC location(s) and the
      Generation Facility.

                      Version Number: 5.0
                            Page 18
5.4 Other Protection Requirements
      5.4.1 Generator Control
       The following items shall be coordinated with each other:

                  Ground Time Over-Current elements at adjacent facilities.
                  Volts/Hz and over-excitation protection/limiting.
                  Loss-of-excitation and under-excitation limiting.

       See also NERC Reliability Standard VAR-002.

       5.4.2 Transformer Surge Protection (Lightning Arresters)
           Lightning arresters protecting transformers are generally mounted on
           the transformer. However, since lightning arresters can adequately
           protect equipment some distance from the arresters, the overall
           number of lightning arresters required in each design can be reduced.
           Allowable lightning arrester separation distance from the equipment
           being protected shall be determined by the latest edition of IEEE Std.
           C62.22 IEEE Guide for the Application of Metal-Oxide Surge Arresters
           for Alternating –Current Systems. The Transmission/End-User should
           consult the manufacturer’s catalog for details concerning arrester
           protective characteristics, ratings, and application.

       5.4.3 Breakers
           The minimum breaker duty ratings, in regards to the interrupting
           capabilities, will be provided by WPSC.

           The minimum breaker ratings, in regards to continuous and short
           circuit capabilities, will be provided by WPSC.

       5.4.4 Equipment Basic Insulation Levels
           The minimum required Basic Insulation Levels (BIL) for stations will
           be provided by WPSC. Facilities in areas with significant air pollution
           may require a higher insulation level.

       5.4.5 Insulators for Station
           WPSC will determine the required station post insulator types.
           Facilities in areas with significant air pollution may require a higher
           insulation level. Higher strength insulators are available and should
           be used if needed to meet bus momentary fault circuit withstand
           values.

5.5 Costs Incurred
The customer must take responsibility for all costs incurred by WPSC to provide
parallel operation of the generation facility. This includes, but is not limited to:
         Each review of the engineering and engineering drawings associated
            with the generation.
         All metering not covered under the transmission tariff of general
            applicability.

                               Version Number: 5.0
                                     Page 19
   The necessary facility modifications on the WPSC transmission
           system to adequately accommodate the operation of the Customer’s
           facility
          WPSC facility replacements, modifications, and/or enhancements due
           to exceeded ratings directly caused by or which could potentially be
           caused by the power flow attributed to the generation.
          All communications circuits required for telemetering, protective
           relaying, and/or voice communications with the generation.
          All protective devices to be provided by the Customer for the
           protection of the WPSC transmission system.
          All protective relaying, including any transfer trip transmitter(s),
           receiver(s), and associated equipment, not on the Customer's
           premises required by WPSC due to the addition of the generation.
          All protective relaying required to protect the generation from faults
           and abnormal system operating conditions.
          All additional regulating and control devices required. This would
           include any equipment necessary for suppression of harmonic current
           and/or voltages.
          WPSC equipment replacements or modifications caused by the
           increase in available fault current associated with the installation of
           the Generation Facility.
          Calibration, testing, and maintenance of relays and protective devices
           provided by the Customer for the protection of the WPSC
           transmission system.
          All telemetering equipment to provide necessary telemetry to the
           WPSC/MISO Control Centers.
          Future changes associated with the generation due to changing
           conditions on the WPSC system.
          All studies performed by WPSC/MISO pertaining to the Generation
           Facility.

5.6 Design Review
The Customer is responsible for submitting all specifications and detailed plans
to WPSC for review and approval prior to receiving permission to connect to the
WPSC transmission system. WPSC requires a review of the Customer’s plans
for the generation to determine the compatibility of design and operation with the
WPSC system. This design review does not relieve the Customer of any
responsibility identified in this document or determine in other contracts.

5.7 Facility Data
At least nine (9) months prior to the in-service date, WPSC shall receive the
following data. The purpose of generation facility data to be provided to WPSC
by the Customer is to ensure proper coordination to protect against equipment or
facility damage, to mitigate safety hazards to utility personnel and the public, and
to minimize interference with WPSC’s ability to serve other transmission system
users.

       5.7.1 Data on Equipment to be Installed
          Interrupting Devices and Relays

                               Version Number: 5.0
                                     Page 20
Complete manufacturer's data for interrupting devices and relays
              used for the protection of the WPSC system and the generation.
         Power Transformers
              Complete nameplate and test sheet data.
         Power Capacitors
              Voltage and VAR rating of capacitor banks, number of units, bank
              configuration, and detailed drawings of capacitor interconnect.
         Data on the generation protection equipment. including transfer
          switches, fuses, breakers, relays, relay settings, and detailed
          schematic diagrams.
         Complete manufacturer's data and specifications for transfer
          switches, testing procedures, equipment schematics, and backup
          protection.
         Information on characteristics of load, such as initial and near future
          expected load, power factor of such load, and dynamic (flicker,
          harmonics, etc.) character of such load.
         Required minimum and maximum low-side operating voltages.

      5.7.2 Generator Data
         Type (synchronous, induction, dc with solid-state inverter, etc.);
         Nameplate data and ratings, including any rectifying, regulating, or
          inverting equipment;
         Harmonic content at full rated output;
         Detailed dynamic performance data.
         Real and reactive capabilities at scheduled voltages.
         Electric one-lines and schematic diagrams showing the generation,
          the interconnecting facility with the WPSC transmission system, and
          the protective relaying.

5.8 Final Documentation
      WPSC shall receive final documentation of the generation facility that
      replaces the above specifications and data submitted for the design
      review once the facility is ready for operation. Prior to operation of a
      generation facility, the Customer shall supply to WPSC three copies of all-
      final electric one-line, equipment data, and schematic diagrams.
      Subsequent revisions affecting the generation facility shall be
      documented with three copies of the revised electric one-line and
      schematic diagrams.

5.9 Approval
      The construction, testing, and maintenance of the protective relaying
      equipment provided by the Customer for protection of the WPSC
      transmission system shall be subject to review and approval by WPSC.
      Prior to establishing service for operation, the Customer shall obtain
      approval from WPSC for the generation, electrical equipment
      specifications, and operating procedures. WPSC will issue final approval
      for operation of a Customer’s generation. Failure to meet any of the
      requirements stated herein to the satisfaction of WPSC may result in a
      refusal to permit operation of the generation facility. Review and approval

                             Version Number: 5.0
                                   Page 21
by WPSC of the proposed generation facility specifications and plans
          shall not be construed as confirming or endorsing the design or
          warranting the safety, durability, reliability, adequacy, or otherwise of the
          generation facility.

6 WPSC Non Generation Connections Technical Requirements
    6.1 Distribution Interconnection Guidelines
           6.1.1 Procedure for Distribution Interconnections
              6.1.1.1 Introduction
                 This procedure describes the process for a Distribution Utility
                 ["DU"] to establish a new or modify an existing Distribution
                 Interconnection with WPSC. The process requires a formal
                 Transmission Service Request that meets WPSC and Midwest
                 ISO requirements. The procedure provides for regular, on-going,
                 well coordinated planning, design and construction processes so
                 that new interconnection facilities can be completed within a
                 normal project schedule time frame. It also provides for an
                 expedited application process when unanticipated needs occur.

             6.1.1.2 Transmission Access and Annual Load & Resource
             Update
                 A DU requesting an interconnection from WPSC for service from
                 MISO, including any DU interconnected to WPSC under a
                 grandfathered coordination or transmission ownership agreement,
                 must request transmission access for each individual distribution
                 interconnection. In addition, any DU connected to the WPSC
                 transmission system must submit an annual Network Integration
                 Transmission Service [NITS] application update to the Midwest
                 ISO.

             6.1.1.3 Transmission Service Request
                 For each new distribution interconnection project or modification to
                 an existing interconnection, the applicant must submit a
                 Transmission Service Request to the MISO. The MISO, in
                 accordance with Attachment D in the MISO tariff, will process the
                 request and complete a System Impact Study. This includes an
                 analysis of the alternatives to satisfy the request and a preliminary
                 estimate of any direct assignment facilities and network upgrades
                 required.

             6.1.1.4 Annual Network Integration Transmission Service [NITS]
             Application Update
                 Any DU interconnected to WPSC must file an annual NITS
                 application update with MISO by November 1 each year. The
                 application provides a forecast of the DU load and resources,
                 plans for distribution system expansion, and a forecast of all new
                 and expanded distribution interconnections.

                                  Version Number: 5.0
                                        Page 22
WPSC will perform on-going planning studies taking into
      consideration the DU forecast growth and expansion plans.
      WPSC will work with the DUs on its system to develop optimized
      solutions for new and expanded distribution interconnections.

   6.1.1.5 Expedited Application Process
      When unanticipated needs occur requiring expedited application
      processing, such actions as temporary facilities, shortened
      schedules and special letter agreements to support parallel work
      activities may be used to attempt to meet the requested service
      date. Each requirement for expedited service will be handled
      individually under the Midwest ISO Tariff provisions. The
      requesting DU will be responsible for any costs for providing
      expedited service over and above those normally incurred by
      WPSC.

6.1.2 Distribution Interconnection Configuration
   6.1.2.1 Introduction
      A radial distribution interconnection is the standard service for DU
      interconnections. Special distribution system needs requiring
      services beyond the standard will be handled in accordance with
      Section C, Extraordinary Service Requests.

   6.1.2.2 Standard Connection to WPSC System
      Radial supply connections will be implemented for all types of DU
      interconnections including but not limited to interconnections for
      distribution substations (load service substation), dedicated
      customer substations and bulk power substations (substation
      feeding a sub-transmission system).

      The cost of the radial portion of each interconnection from the
      WPSC tap point to the DU substation and any associated
      switching will be direct assignment costs and the financial
      responsibility of the requesting DU.

   6.1.2.3 Dedicated Customer Substation Distribution
   Interconnection with Parallel Generation
      Where a dedicated Distribution Interconnection is required to
      serve a large retail load with parallel generation that can be
      offered for sale to third parties across the grid, the greater of the
      maximum retail load served or maximum power delivered to the
      grid will dictate the interconnection design. The DU must request a
      dual purpose interconnection, since the customer is both a DU
      retail customer and a Transmission Service customer.

      Full open access to the transmission grid will be available via this
      dual purpose interconnection. Service needed to meet the retail
      service requirements will be determined first, with additional
      capacity and facilities, if any, to allow full open access to the
      transmission grid added.

                      Version Number: 5.0
                            Page 23
You can also read